The World Bank. Key Dates. Project Development Objectives. Component(s) Public Disclosure Copy. Overall Ratings

Similar documents
Implementation Status & Results Burkina Faso Local Government Support Project (P120517)

Implementation Status & Results Central African Republic Support to Vulnerable Groups Community Development Project (P111679)

Implementation Status & Results Azerbaijan Corporate and Public Sector Accountivility Project (P099924)

Implementation Status & Results Tajikistan Tax Administration (P127807)

Implementation Status & Results Haiti Strengthening the Management of Agriculture Public Services (GFRP) (P113623)

Implementation Status & Results Chad Public Financial Management Capacity Building (P090265)

Public Disclosure Copy

Implementation Status & Results Nigeria Nigeria Edo State First Development Policy Operation (P123353)

Implementation Status & Results Tanzania Tax Modernization Project (P100314)

Implementation Status & Results Afghanistan Afghanistan Capacity Building for Results Facility (CBR) (P123845)

Implementation Status & Results India India: Bihar Integrated Social Protection Strengthening Project (P118826)

Implementation Status & Results Senegal SENEGAL: TRANSPORT & URBAN MOBILITY PROJECT (P101415)

Implementation Status & Results Kosovo Public Sector Modernization Project (P101614)

Implementation Status & Results Ukraine Public Finance Modernization Project (P090389)

Implementation Status & Results Brazil Second National Environmental Project - Phase II (P099469)

Implementation Status & Results Croatia Revenue Administration Modernization Project (P102778)

Implementation Status & Results Indonesia Local Government and Decentralization Project (P111577)

Implementation Status & Results India Assam State Roads Project (P096018)

Implementation Status & Results Ghana Health Insurance Project (P101852)

Implementation Status & Results Mozambique Health Commodity Security Project (P121060)

Implementation Status & Results Ghana Ghana - Micro,Small and Medium Enterprise Project (P085006)

The World Bank Albania-Enhancing Quality of Financial Reporting (EQ-FINREP) (P152567)

The World Bank. losure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized. Public Disclosure Copy

Implementation Status & Results Ghana Health Insurance Project (P101852)

Implementation Status & Results Senegal SENEGAL: TRANSPORT & URBAN MOBILITY PROJECT (P101415)

Implementation Status & Results Colombia Disaster Vulnerability Reduction First Phase APL (P082429)

Implementation Status & Results Indonesia Government Financial Management and Revenue Administration Project (P085133)

Implementation Status & Results Niger Niger Reform Management and TA (P108253)

Implementation Status & Results Brazil Sao Paulo Feeder Roads Project (P106663)

MicroSmall&Medium Enterprise and Large Enterprise Supply Chain Finance (P157691)

Implementation Status & Results India Strengthening India's Rural Credit Cooperatives (P102768)

Implementation Status & Results Indonesia Sustainable Management of Agricultural Research and Technology Dissemination (SMARTD) (P117243)

Implementation Status & Results Indonesia Project for Indonesian Tax Administration Reform (PINTAR) (P100740)

Implementation Status & Results Sri Lanka Public Sector Capacity Building (P097329)

Implementation Status & Results Philippines National Program Support for Tax Administration Reform. (P101964)

Public Disclosure Copy. Implementation Status & Results Report Federally Administered Tribal Areas (FATA) Governance and Policy Program (P156412)

Implementation Status & Results Samoa SAMOA HEALTH SECTOR MANAGEMENT PROGRAM SUPPORT PROJECT (P086313)

Public Disclosure Copy. Implementation Status & Results Report Revenue Mobilization Program for Results: VAT Improvement Program (VIP) (P129770)

Public Disclosure Copy

Public Disclosure Copy

The World Bank Kenya Cash Transfer for Orphans and Vulnerable Children (P111545)

The World Bank Integrated Disaster Risk Management and Resilience Program (P144539)

Implementation Status & Results Serbia Transport Rehabilitation Project (Serbia) (P075207)

Implementation Status & Results Ethiopia Urban Local Govt Development Project (P101474)

Implementation Status & Results Argentina AR Cordoba Road Infrastructure (P099585)

Public Disclosure Copy. Implementation Status & Results Report Revenue Mobilization Program for Results: VAT Improvement Program (VIP) (P129770)

Public Disclosure Copy

The World Bank. Key Dates. Project Development Objectives. Components. Overall Ratings. Public Disclosure Authorized

Public Disclosure Copy

The World Bank Mozambique Public Financial Management for Results Program (P124615)

Public Disclosure Copy

TR Third Access to Finance for SMEs (SME III) (P130864)

Key Dates. Project Development Objectives. Components. Overall Ratings

Public Disclosure Copy

Implementation Status & Results Liberia LR-Public Financial Management - IFMIS (P109775)

Public Disclosure Copy

Public Disclosure Copy

West Bengal PRI (P105990)

Implementation Status & Results Indonesia National Community Empowerment Program In Urban Areas For (P125405)

Implementation Status & Results Vietnam Second Northern Mountains Poverty Reduction Project (P113493)

Implementation Status & Results China China Wuhan Second Urban Transport (P112838)

The World Bank Pastoral Community Development Project III (P130276)

The World Bank. Ghana: Energy Development and Access Project (P074191) Key Dates. Project Development Objectives. Components

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

Public Disclosure Copy

West Bengal Institutional Strengthening of Gram Panchayats Program II (P159427)

The World Bank Bangladesh Ghorashal Unit 4 Repowering Project (P128012)

Public Disclosure Copy

Implementation Status & Results Bosnia and Herzegovina Agriculture and Rural Development Project (P101213)

Public Disclosure Copy. Implementation Status & Results Report Uganda Reproductive, Maternal and Child Health Services Improvement Project (P155186)

Implementation Status & Results Indonesia FOURTH NATIONAL PROGRAM FOR COMMUNITY EMPOWERMENT IN RURAL AREA (PNPM IV) (P122810)

Implementation Status & Results Yemen, Republic Fisheries Resource Management and Conservation (P086886)

The World Bank Building a Modern Fiscal System Technical Assistance (P154694)

The World Bank. Ghana: Energy Development and Access Project (P074191) Key Dates. Project Development Objectives. Components

State Owned Financial Institutions Reform Project (P156837)

The World Bank Public Financial Management Capacity Building (P090265)

Bangladesh Insurance Sector Development Project (P156823)

The World Bank Burkina Faso Donsin Transport Infrastructure Project (P120960)

Implementation Status & Results Brazil BR APL 1 Para Integrated Rural Dev (P082651)

The World Bank Municipal Services Improvement (P096481)

The World Bank Mauritania Public Sector Governance Project (P146804)

The World Bank Revenue Administration Modernization Project (P130202)

Implementation Status & Results Africa Central African Backbone - APL4 - Gabon (P122776)

PNG - Small and Medium Enterprise Access to Finance Project (P120707)

Implementation Status & Results Argentina AR Cordoba Road Infrastructure (P099585)

Implementation Status & Results Indonesia ID-Urban Water Supply and Sanitation (P090991)

Implementation Status & Results Peru PERU Participatory intervention model to improve child nutrition (P120888)

The World Bank Nigeria - Public/Private Partnership Program (P115386)

Implementation Status & Results Mongolia Governance Assistance Project (P098426)

The World Bank Kenya Infrastructure Finance/PPP project (P121019)

The World Bank CG Rep. Skills Development for Employability Project (P128628)

Public Disclosure Copy. Implementation Status & Results Report Revenue Mobilization Program for Results: VAT Improvement Program (VIP) (P129770)

Implementation Status & Results Indonesia Aceh Infrastructure Reconstruction Financing Facility (IRFF) (P101785)

Implementation Status & Results Lebanon LB-EMERGENCY POWER SECTOR REFORM CAPACITY REINFORCEMENT (P104774)

The World Bank. Key Dates. Project Development Objectives. Components. Public Disclosure Authorized. Implementation Status & Results Report

Public Disclosure Copy

Implementation Status & Results Kazakhstan SOUTH-WEST ROADS: WESTERN EUROPE-WESTERN CHINA INTERNATIONAL TRANSIT CORRIDOR (CAREC 1B & 6B) (P099270)

Public Disclosure Copy. Implementation Status & Results Report CAPE VERDE - Recovery and Reform of the Electricity Sector Project (P115464)

Zambia Kafue Town - Muzuma - Victoria Falls Regional Transmission Line Reinforcement Project

The World Bank Indonesia Infrastructure Guarantee Fund Project (P118916)

Transcription:

Implementation Status & Results Burkina Faso Local Government Support Project (P120517) Operation Name: Local Government Support Project (P120517) Project Stage: Implementation Seq.No: 5 Status: ARCHIVED Archive : 22-Mar-2014 Country: Burkina Faso Approval FY: 2012 Product Line: IBRD/IDA Region: AFRICA Lending Instrument: Specific Investment Loan Implementing Agency(ies): MATDS Key s Board Approval Original Closing Planned Mid Term Review 10-Nov-2014 Last Archived ISR 03-Aug-2013 Effectiveness 06-Jun-2012 Revised Closing Actual Mid Term Review Project Development Objectives Project Development Objective (from Project Appraisal Document) The proposed project seeks to harness emerging government commitment to local government reforms by supporting the implementation of critical aspects of fiscal and administrative decentralization in six of the 13 regions of Burkina Faso. The primary objective of the project is to strengthen the central government#s capacity for administrative and fiscal decentralization and the institutional capacities of communes in six regions, and to improve accountability linkages between local policy makers and citizens in the six regions. Has the Project Development Objective been changed since Board Approval of the Project? Yes No Component(s) Component Name Component Cost Component 1 - Establishing the foundations of robust administrative and fiscal intergovernmental 9.80 institutions Component 2 - Strengthening capacity of municipalities to manage local development 37.98 Component 3 - Improving accountability linkages between local level policy makers and citizens 5.94 Component 4: Project management and evaluation 10.00 Overall Ratings Previous Rating Current Rating Progress towards achievement of PDO Satisfactory Satisfactory Overall Implementation Progress (IP) Satisfactory Satisfactory Overall Risk Rating Moderate Moderate Implementation Status Overview The project was approved by the Board on November 1, 2011 and the financing agreement was signed on December 8, 2011.The effectiveness date was June 6, 2012. Page 1 of 6

The project has the following components: Component 1 - Establishing the foundations of robust administrative and fiscal intergovernmental institutions ($9.8 million). This component will support the central government agencies to further develop a transparent and rule-based intergovernmental fiscal framework and robust intergovernmental administrative systems. It will support the government in making a gradual shift from existing ex ante controls to ex post monitoring, as the capacity of communes increases to exercise their discretion. It will provide support to a high level policy making process (Vision Prospective de la Decentralisation-VPD) and assist the Ministries of Economy and Finance and Territorial Administration, Decentralization and Security to develop their coordination and managerial capacity. Component 2 - Strengthening capacity of municipalities to manage local development ($37.98 million). To address capacity constraints at the local government level, the project will provide support to local communes to address their core institutional development requirements for socio-economic development through institutional development grants. Annual grant allocations to each commune will, in part, be based upon the commune s performance in establishing their institutions. Component 3 - Improving accountability linkages between local level policy makers and citizens ($5.94 million). This component aims to empower local councils and populations by strengthening their capacity to participate in local decision making processes related to their socio-economic development and monitor local authority performance. At the same time, it aims to support local councilors in their oversight and representative function and to strengthen the capacity of local communes to communicate with local populations and account for their performance. The component will also reward communes in all 13 regions that demonstrate excellence in engaging communities in local development decision-making processes, through the provision of small grants on a competitive basis, and will ensure that the practices are disseminated as a motivation to other communes. Component 4 - Project management and evaluation ($9.65 million). This component will provide project management support to the Ministry of Territorial Administration, Decentralization and Security (MATDS) in project implementation and support regular project evaluations as well as procurement and safeguards reviews, and financial reporting and auditing. An implementation team for the project visited Burkina Faso over the period of January 18-31, 2014. The objectives of the mission were to discuss the implementation of the 2013 annual work plan (see attached 2013 Work Plan Realization report) and to attend the steering committee meeting. Overall the implementation of the project is progressing satisfactorily. The implementation of the first component activities is on track. The component supports the central government agencies to establish a transparent and rule-based intergovernmental fiscal framework and robust intergovernmental administrative systems. It engages with the government to make intergovernmental transfers more transparent and formula based. The component has ensured that the grant amounts available to communes are communicated to the communes in a timely fashion in order to give them an opportunity to make proper budget planning. In 2014, the Government has substantially increased the level of budgetary allocations to local communes to 5 percent of budgetary resources. There has been a change in the institutional context of the project in 2013. After the separation of MATDS into MATD (Ministere de l'amenagement du Territoire et de la Decentralization) and MATS (Ministere de l'administration Territoriale et de la Securite) earlier in 2013, the project coordination unit has been moved from MATDS to MATD. The PCU will be headed by the Secretary General of the MATD as the National Coordinator and the existing Associate Coordinator will continue working under him. The component supports a high level policy making process (Vision Prospective de la Décentralisation--VPD) and assists the MEF, MATS and MATD in developing their capacity. The second component provides institutional development support to communes. The second component of the project has been officially launched in June 2013. It finances the implementation of the institutional development plan of communes. The third component promotes accountability. It strives to achieve better accountability of communes towards citizens. Working through local and regional NGOs, the component strengthens accountability linkages between citizens and communes. Under this component six NGOs (one per region) have been hired to work with local governance stakeholders in their respective regions. The component has facilitates the organization of a national competition for excellence in local governance (COPEGOL). The competition awards communes for innovative practices in good governance and participation. As of February 2014, the disbursement rate of the project stands at 33%. Locations Page 2 of 6

Country First Administrative Division Location Planned Actual Burkina-Faso Cascades Region Cascades Region Burkina-Faso Centre-Est Centre-Est Burkina-Faso Centre-Nord Centre-Nord Burkina-Faso Centre-Sud Centre-Sud Burkina-Faso Plateau-Central Plateau-Central Burkina-Faso Sahel Sahel Results Project Development Objective Indicators Indicator Name Core Unit of Measure Baseline Current End Target Direct project beneficiaries Number Value 0.00 4000.00 4000.00 Female beneficiaries Percentage Increase in the execution rate of annual commune procurement plan Increase in local taxes collected for the commune governments Deviation of commune level budget implementation from initially approved annual communal budget Sub Type Supplemental 02-Jan-2012 02-Jan-2012 Value 0.00 2000.00 2000.00 4000 (of which 50% female) Percentage Value 83.13 0.00 5.00 Taux d'execution du plan de passation des marches de la commune The targeted increase is annual, this column will be updated after the mission in december. Percentage Value 41.62 0.00 15.00 Taux d'accoissement des value recettes propes de la commune Percentage Value 40.00 40.00 4.00 Measures local government s institutional capacity. Based Page 3 of 6

Actual availability of funds to communes committed by the central government earlier in the budget cycle Notification of indicative allocation of transfer amounts by central government to each commune government by November of preceding fiscal year Increase in percentage of citizens rating commune government s performance satisfactory on the difference between the budget primitif and the compte administratif records. Text Value April 30, 2011 February 1, 2014 No later than February 28, 2016 03-Feb-2014 Measures the actual availability of all funds by the central government to local governments. Funds are allocated to communes Text Value No Yes Yes Information will be taken from the projet arretés. Notification to include indicative allocations for all general dotations and sectoral transfers (according to the sectoral competencies actually delegated to each commune). The communes are notified Percentage Value 47.30 0.00 70.00 Pourcentage de citoyens N/A evaluant la performance du conseil municipal comme etant satisfaisante Intermediate Results Indicators Indicator Name Core Unit of Measure Baseline Current End Target Intergovernmental fiscal framework policy Text Value No Yes statement issued by the government The government is working on teh text. Sectoral decentralization reviews/service Text Value 0 8 delivery guidelines completed The work is ongoing. Cumulative number Page 4 of 6

Number of government officials who participated in decentralization training courses and study tours Communes that established local budget committees Commune officials find MEF ordinateur function for revenue collection carried out effectively at a regional level Communes that comply to 70 percent with organigramme for territorial collectivities in terms of responsibilities and functions implemented on regional and commune level Number of communes with council-validated Institutional Development Plans (IDP) Communes that were awarded the consecutive budget allocations Increase in the number of people who state that they have received announcements of the cadre de concertation meetings and who can recall through which channel Communes submitting their candidacy documents to the annual regional competition Data on Financial Performance (as of 07-Jan-2014) Number Value 0.00 15.00 70.00 31-Dec-2012 Percentage Value 39.30 0.00 100.00 Communes qui ont mis en The work is ongoing. place des comites de suivi budgetaire et de tresorerie Percentage Value 20.00 0.00 70.00 The updated figure will be available after a survey of local government officials. Percentage Value 5.00 0.00 30.00 The figure will be available after the annual survey. Percentage Value 0.00 100.00 100.00 Percentage Value 0.00 0.00 70.00 2013 was the first year of implementation. The updated figure will be available in January 2015. Percentage Value 38.00 0.00 80.00 The work has started, the figure will be available in November 2014. Percentage Value 10.00 100.00 60.00 Financial Agreement(s) Key s Page 5 of 6

Project Ln/Cr/Tf Status Approval Signing Effectiveness Original Closing Revised Closing P120517 IDA-H7360 Effective 08-Dec-2011 06-Jun-2012 Disbursements (in Millions) Project Ln/Cr/Tf Status Currency Original Revised Cancelled Disbursed Undisbursed % Disbursed P120517 IDA-H7360 Effective XDR 37.30 37.30 0.00 12.49 24.81 33.00 Disbursement Graph Key Decisions Regarding Implementation Disclosure of the PAD after board approval. Restructuring History There has been no restructuring to date. Related Projects P120844-Mainstreaming Governance and Institutional Development in Burkina Faso Page 6 of 6