CHAPTER 6: COST ESTIMATES

Similar documents
Capital Cost Estimation Methodology

4 Cost Estimation Assumptions

8. FINANCIAL ANALYSIS

CHAPTER 9 FINANCIAL CONSIDERATIONS

This chapter describes the initial financial analysis and planning for the construction and operations of the Locally Preferred Alternative (LPA).

Honolulu High-Capacity Transit Corridor Project Alternatives Analysis

READINESS REVIEW ENTRY INTO PROJECT DEVELOPMENT. Columbia Pike Streetcar Arlington County, Virginia FTA Region 3

Forecasting Asset Conditions with Decay Curves April 16, 2012 Keith Gates, PE Senior Analyst, Strategic Planning & Analysis

WESTSIDE SUBWAY EXTENSION

Executive Change Control Board. March 30, 2016

Budget Discussion. July 2009 Citizens Advisory Committee

Executive Change Control Board. January 15, 2016

Total Operating Activities for FY17 are $56.9 million, an increase of $5.1M or 9.8% from FY16.

Tech Memo #4: Capital Costs

Washington Metropolitan Area Transit Authority Metro Budget Overview

10 Financial Analysis

8.0 FINANCIAL ANALYSIS

CHAPTER 9 FINANCIAL CONSIDERATIONS

University Link LRT Extension

Executive Change Control Board. August 3, 2016

VALLEY METRO RAIL FY18 Budget EXECUTIVE SUMMARY

Adopted Five Year Operating Forecast and Capital Program

Corridor Management Committee. May 6, 2015

Executive Summary - Fiscal Year 2016 Valley Metro Rail Preliminary Annual Operating and Capital Budget

Valley Metro Rail Preliminary Annual Operating & Capital Budget Fiscal Year 2018

TEX Rail Fort Worth, Texas Project Development (Rating Assigned November 2012)

Honolulu High-Capacity Transit Corridor Project

The DRAFT Bus and Rail Investment Plan in Orange County


Regional Connector Transit Corridor Draft Environmental Impact Statement/ Draft Environmental Impact Report APPENDIX HH FINANCIAL ANALYSIS REPORT

ADOPTED FY 2013 OPERATING AND CAPITAL BUDGET FIVE-YEAR OPERATING FORECAST AND CAPITAL PROGRAM FY 2013 FY May 17, 2012

Notice of Public Hearing Washington Metropolitan Area Transit Authority

Financial Plan. Section 8 STATUS QUO PLAN STATUS QUO PLAN ASSUMPTIONS STATUS QUO PLAN BUDGET ITEMS

Chapter 9 Financial Considerations. 9.1 Introduction

FIVE-YEAR OPERATING FORECAST AND CAPITAL PROGRAM

FY2017 Budget Discussion

2.0 PROJECT FINANCIAL PLAN...

Amend FY07 System Access Program for Artwork

Cancelled. Final Action

Route Route Z Intersection Realignment

CENTRAL CITY LINE PROJECT UPDATE AND SMALL STARTS EVALUATION & RATINGS APPLICATION UPDATED & REVISED 4/20/17

ADOPTED FY 2012 OPERATING AND CAPITAL BUDGET FIVE-YEAR OPERATING FORECAST AND CAPITAL PROGRAM FY FY 2016

Keeping Metro Safe, Reliable and Affordable

Contents. Appendix. Cost Model Structure. Tables

MEMORANDUM. Santa Clara Valley Transportation Authority Board of Directors. Michael T. Burns General Manager. DATE: August 4, 2008

PRELIMINARY FY 2015 OPERATING AND CAPITAL BUDGET FIVE-YEAR OPERATING FORECAST AND CAPITAL PROGRAM FY 2015 FY April 15, 2014

Cincinnati Streetcar: Options & Recommendations for Funding Operations

RESOLUTION NO. R Tacoma Link Expansion Baseline Budget, Schedule, Phase Gate 5, and Project Naming

FIVE-YEAR CAPITAL PROGRAM AND OPERATING FORECAST

2040 Long Range Transportation Plan. Financial Summary

RESOLUTION NO. R Baseline Budget and Schedule, and Approve Gates 5 and 6 for the East Link Extension

The Bus and Rail Investment Plan in Orange County

Arlington County, Virginia

FEDERAL TRANSIT ADMINISTRATION PROJECT MANAGEMENT OVERSIGHT PROGRAM

Travel Forecasting for Corridor Alternatives Analysis

I-64 Capacity Improvements Segment III Initial Financial Plan

Review and Update of Year 2035 Regional Transportation Plan

FY2018 Second Quarter Financial Update

Chapter 5: Cost and Revenues Assumptions

Adopted Five Year Operating Forecast and Capital Program

Providers of Public Transportation Individual Targets

JP Morgan Public Finance Transportation Utility Conference

INVESTING STRATEGICALLY

METRO. Metro Funding. Associated Master Plan: Comprehensive Master Transportation Plan (MTP) for Arlington. Neighborhood(s):

BOARD OF DIRECTORS JOINT MEETING MONDAY, JULY 19, :00 AM 1201 EAST 7 TH AVENUE, 3RD FLOOR FLORIDA CONFERENCE ROOM AGENDA

OPERATING BUDGET REPORT

Recommend to Board. Final Action

Dulles Corridor Metrorail Project

Portal North Bridge Project Hudson County, New Jersey Core Capacity Project Development (Rating Assigned February 2017)

Chapter 6: Financial Resources

Operating Budget. Third Quarter Financial Report (July 2005 March 2006)

Final Interim Policy Guidance Federal Transit Administration Capital Investment Grant Program

TSCC Budget Review TriMet

MOTION NO. M Tacoma Link Expansion CMC Phase 1 Preconstruction Services PROPOSED ACTION

INVESTMENT STRATEGIES

Northern Virginia District State of the District. Helen L. Cuervo, P.E. District Engineer March 15, 2016

Audit and Finance Subcommittee

Financial Forecasting Assumptions for Plan 2040 (DRAFT)

Freight Rail Improvements Oklahoma City to Shawnee TIGER Grant Application Benefit Cost Analysis Technical Memo October 2009

MOTION NO. M Funding and Cooperative Agreement with the City of Shoreline related to the Lynnwood Link Extension

PROPOSED CAPITAL IMPROVEMENT PLAN

FY2018 Third Quarter Financial Update

Draft Environmental Impact Statement. Appendix G Economic Analysis Report

May 31, 2016 Financial Report

Dulles Corridor Metrorail Project

FY2017 Year-End Financial Update

1/31/2019. January 31, Item #1 CITIZENS PARTICIPATION

Valley Metro Rail FY18 Preliminary Budget Overview

Safety and Operations Committee. Information Item III-B. January 24, 2019

2040 Transit System Plan

DULLES CORRIDOR METRORAIL PROJECT MONTHLY COST SUMMARY AS OF FEBRUARY 28, 2013 APRIL 2013

Financial Analysis Working Paper 1 Existing Funding Sources Draft: April 2007

For Action. TTC 15-Year Capital Investment Plan & Capital Budget & Plan. Summary

CHERRIOTS 2018 SERVICE PLAN APPENDIX A EQUITY ANALYSIS

Title VI Approval of Major Service Change, Disparate Impact and Disproportionate Burden

Operating Budget Report

Metropolitan Transportation Authority: East Side Access Cost Overruns

Overview of the Final New Starts / Small Starts Regulation and Frequently Asked Questions

Toronto Transit Commission

Transit Life Cycle Program 2013 Update

Transcription:

CHAPTER 6: COST ESTIMATES 115

116 UNION STATION GEORGETOWN: ALTERNATIVES ANALYSIS for PREMIUM TRANSIT SERVICE

The Recommended Alternative could be designed and constructed under a number of financing options. Chapter 6 Cost Estimates A. CAPITAL COSTS 1. Introduction This chapter of the AA Report describes the organization and format for capital costs, the methodology and assumptions, and results. Capital costs for the three final alternatives have been developed based upon previous work performed for the K Street Transitway Study and the DC s Transit Future System Plan by DDOT. In the case of the K Street Transitway, the capital costs were developed based upon a greater level of conceptual engineering than has been developed for the Union Station to Georgetown AA Study. In the case of the DC s Transit Future System Plan, the work in this AA Study represents a greater level of detail than the system wide planning work. Costs in the K Street Transitway Study, were developed in 2009 dollars, while cost data for streetcars from the system wide planning work was obtained in 2012 dollars. All of these cost numbers have been escalated to current year, 2013 dollars, by applying 3% annual escalation. A projected year-of-expenditure (YOE) cost for the three final alternatives was also developed by escalating 3% per year to 2016, the estimated mid-point of construction for the project. [Note: If the next phase of project development results in a NEPA action for a Build Alternative, then DDOT may accelerate the design and construction of the recommended alternative using expedited delivery methods (perhaps a P3).] For vehicles, a 5% contingency was applied due to the lack of variability with purchasing versus construction. 2. Organization and Format The capital costs are presented in FTA Standard Cost Category (SCC) Format. This format includes nine standard cost categories as follows: > Category 10 Guideways and track elements > Category 20 Stations > Category 30 Yard and Shop (maintenance facilities) > Category 40 Sitework and special conditions > Category 50 Systems > Category 60 Right-of-way > Category 70 Vehicles > Category 80 Professional Services > Category 90 Unallocated Contingency CHAPTER 6: COST ESTIMATES 117

3. Methodology and Assumptions Additional detail on the FTA SCC sub-categories is provided in this section. > Category 10 This category includes the trackwork and slab for the streetcar and generally no value for the premium bus alternative as it primarily operates on existing roadway. Values were used per linear foot based on the system wide streetcar studies. > Category 20 A lump sum value of $450,000 per station for both bus and streetcar was used in 2012 dollars and escalated to 2013 for base year and 2016 for YOE dollars. > Category 30 A lump sum of $12,500,00 in 2012 dollars was used to be consistent with values in the system wide streetcar studies, then escalated to 2013 and 2016 dollars. For buses, the assumption was made that the 12 buses required could be maintained in existing bus facilities and no capital costs were incurred. > Category 40 This category includes utility relocations, civil/roadway work needed to prepare the roadway for inclusion of track and new slab. It also includes traffic maintenance. For the portion in the three final alternatives along K Street, costs from the K Street Transitway project were used. The K Street reconstruction between Washington Circle and Mount Vernon Square was assumed to be re-constructed for three final alternatives. The K Street Transitway costs were $139 Million in 2009 dollars, which equate to $171 Million in 2016 year of expenditure dollars. The $171 Million is incorporated into all of the three final alternatives, reformatted into appropriate FTA SCC categories. For the portions of the alternatives outside the K Street area, costs per linear foot were used consistent with the system wide streetcar studies. Construction costs for reconstruction of the Hopscotch Bridge are not included in this cost estimate. > Category 50 For Alternatives 1 and 2, this category includes a per linear foot cost for traffic signal and crossing protection, traction power supply and distribution, and communications, consistent with values used for the system wide streetcar studies. For Alternative 3, costs were only used for traffic signals and crossing protection. No additional values have been added for alternative/non-catenary propulsion alternatives as these could vary greatly in costs. For both streetcar and premium bus, a lump sum of $2 MIllion in 2013 dollars was used for fare collection, although the specific fare collection methods have not yet been determined. > Category 60 At the level of analyses completed for this AA Study, no additional right-of-way beyond that already owned by the public would be required for the three alternatives. Therefore, no costs have been included for right-of-way. In the next phase of project development, small areas of right-of-way may be required. > Category 70 For streetcars, a lump sum of $5 Million per vehicle in 2012 was used, and then escalated to 2013 and 2016, consistent with system wide streetcar values. For buses, a lump sum of $1.25 Million per vehicle was used and then escalated to 2013 and 2016 dollars. > Category 80 The following percentages of Category 10-50 costs (including contingencies) are used: PE and Planning 8% Final Design 7% Program Management 4% Construction Administration and Management 12% Other soft costs 4% This totals 35%; the percentage being used in the system wide streetcar studies. > Category 90 An unallocated contingency of 4% is used for Categories 10-80. 4. Results Table 6-1 below provides a summary of capital costs for each of the three final alternatives. For additional detail on the capital costs by alternative refer to Appendix H of this AA Report. Table 6-1: Summary of Total Capital Cost Estimates by Alternative in Year-of-Expenditure Dollar Totals FTA Standard Cost Categories (SCC) Alternative 1 Alternative 2 10 GUIDEWAY & TRACK ELEMENTS $32,722,803 $38,574,160 N/A Alternative 3 20 STREETCAR/ BUS STATIONS $5,900,726 $6,638,317 $6,638,317 30 STREETCAR, YARD, SHOP $14,068,860 $14,068,860 N/A 118 UNION STATION GEORGETOWN: ALTERNATIVES ANALYSIS for PREMIUM TRANSIT SERVICE

FTA Standard Cost Categories (SCC) 40 SITEWORK & SPECIAL CONDITIONS ( Utilities, Civil/ Roadwork, Temporary Facilities during Construction) Alternative 1 Alternative 2 Alternative 3 $138,876,860 $153,570,313 $128,219,641 50 SYSTEMS $12,288,808 $17,181,796 $4,085,443 50.02 Traffic signals and crossing protection $1,779,397 $2,641,147 $1,899,989 50.03-50.04 Traction power supply & distribution $7,931,887 $11,773,248 N/A 50.03-50.04 Alternative Propulsion --- --- N/A 50.05 Communications $392,070 $581,948 N/A 50.06 Fare collection system and equipment $2,185,454 $2,185,454 $2,185,454 Construction Subtotal (10-50) $203,858,056 $230,033,445 $138,943,401 70 VEHICLE (EA) $59,089,213 $64,998,134 $17,726,764 80 PROFESSIONAL SERVICES $71,350,320 $80,511,706 $48,630,190 80.01 Preliminary Engineering $16,308,645 $18,402,676 $11,115,472 80.02 Final Design $14,270,064 $16,102,341 $9,726,038 80.03 Project Management for Design and Construction 80.04 Construction Administration & Management $8,154,322 $9,201,338 $5,557,736 $24,462,967 $27,604,013 $16,673,208 80.05-80.08 Other Soft Costs $8,154,322 $9,201,338 $5,557,736 Subtotal (10-80) $334,297,589 $375,543,285 $205,300,355 90 UNALLOCATED CONTINGENCY $13,371,904 $15,021,731 $8,212,014 TOTAL PROJECT COST (10-90) $347,669,492 $390,565,017 $213,512,369 5. Financing Options The Recommended Alternative could be designed and constructed under a number of financing options. A final financing package could include some combination of the financing options listed below. > Local Government Financing Under most financing options some level of local funding from DC government will likely be required. This may range from a majority of project funds to a local match for some form of federal funds, to some share of costs in a public-private partnership arrangement. > USDOT Tiger Grant Funds The USDOT assists with transportation projects through Tiger Fund Grants. These grants are extremely competitive and would likely only assist with a small portion of total project funds. > FTA Grants FTA assists in the funding of rail projects nationwide through various programs, including the Section 5309 New Starts Program. This program has historically contributed 50% of capital costs for approved projects, within a limited national funding cap. > FHWA Funding DDOT utilizes FHWA funds for transportation projects and could look to use FHWA funds for a portion of the costs for the Recommended Alternative. > Public-Private Partnership Funding DDOT could partner with private sector design/construction teams for design, construction, and potentially operation of the Recommended Alternative. D. OPERATING COSTS The inputs to the calculation of Operating Costs for both the Streetcar and Premium Bus alternatives are described below. For the Streetcar Alternatives, these assumptions are consistent with Streetcar planning work performed to date, both from system wide streetcar studies and this AA Study. For the Premium Bus Alternative, data was utilized from actual operating costs for the DC Circulator bus. CHAPTER 6: COST ESTIMATES 119

1. Streeetcar Assumptions Consistent with DC s Transit Future System Plan Final Report, April 2010, the following are used as input to calculate operating costs for Streetcar Alternatives 1 and 2: > Service at 10 minute headways during all hours of streetcar operation. > Hours of Operation: Monday-Thursday 6 AM to 12 AM Friday 6 AM to 2 AM Saturday 8 AM to 2 AM Sunday 8 AM to 10 PM > Operating Costs from the April 2010 DC s Transit Future System Plan Final Report at $216.81 per revenue hour plus $5.23 per revenue mile (in 2009 dollars). These costs combine those items which are hourly based such as operator wages, maintenance staff, and administrative support staff with those costs that are mileage based such as track and station maintenance and electricity. > Operating Costs for this AA Study are escalated to 2013 dollars using 3% rate per year from 2009 to 2013. > Travel times and mileage consistent with those provided in other sections of this AA Study, as follows: Alternative 1 3.41 miles, 23.9 minute one way travel time, which is an average of EB AM peak, EB PM peak, WB AM peak and WB PM peak travel times. No reduction in off-peak travel times was assumed although it is expected that travel times could be slightly less. Alternative 2 3.60 miles, 28.9 minute average one way travel time, computed as above. 2. Premium Bus Assumptions For Premium Bus Alternative 3, the following inputs were used: > Service at 10 minute headways during all hours of premium bus operations. > Hours of Operation same as for the Streetcar Alternatives 1 and 2 > Operating Costs are based on system wide Circulator operating costs for calendar year 2012. These costs average to $95 per revenue hour and are all-inclusive system wide numbers and do not need a per revenue mile component added. > Travel times and mileage consistent with those provided in other sections of this AA Study report, as follows: 3.67 miles, 26.2 minute one way travel time, which is an average of EB AM peak, EB PM peak, WB AM peak, WB PM peak travel times. No reduction in off-peak travel times was assumed although it is expected that travel times could be slightly less. > Operating costs for the premium bus were escalated one year at 3% from 2012 to 2013 dollars. 3. Operations and Maintenance Costs The Table 6-2 summarizes the Operations costs for each of the three build alternatives. Table 6-2: Operating Costs Alternative 1 Streetcar Alternative 2 Streetcar Alternative 3 Premium Bus Miles Unit Cost per Mile Mileage Based Cost Hours Unit Cost per Hour Hourly Based Cost Total O&M Costs 2009 dollars Total O&M Costs 2012 dollars Total O&M Costs 2013 dollars 263,852 $5.23 $1,379,946 30,821 $216.81 $6,683,013 $8,062,959 - $9,074,860 278,554 $5.23 $1,456,835 37,269 $216.81 $8,081,133 $9,537,968 - $10,734,982 N/A N/A N/A 33,788 $95.00 $3,209,814 - $3,209,814 $3,306,108 120 UNION STATION GEORGETOWN: ALTERNATIVES ANALYSIS for PREMIUM TRANSIT SERVICE