Economic Analysis Concepts
Questions & Decisions (1) Is the project justified?- Are benefits greater than costs? Which is the best investment if we have a set of mutually exclusive alternatives? If funds are limited, how should different schemes be ranked? When should the road be built or upgraded? 2
Questions & Decisions (2) What standard of construction should be used? What standard and frequency of road maintenance is optimal? Should staged construction be used? Are complementary investments required? 3
Appraisal Framework All appraisals need a framework or model for: a) Forecasting changes b) Evaluating those changes 4
Components of Economic Analysis (1) Costs and benefits are measured in money terms Road construction and maintenance costs are compared with estimates of the direct primary benefits going to road users and road agency Secondary benefits are usually ignored Economic prices are used in constant terms 5
Components of Economic Analysis (2) Costs and Benefits are forecast over the planning time horizon (usually between 10 and 20 years) Future Benefits are valued less as time progresses using the planning discount rate Costs and Benefits are compared using decision criteria such as NPV, IRR, etc. 6
Economic and Financial Prices The cost to the economy of road rehabilitation and maintenance may differ from the financial cost because of : taxes and duties shortage of foreign exchange under-employment The Government will usually be concerned with ECONOMIC costs. Contractors will usually be concerned with FINANCIAL costs. 7
Use of Economic Prices In an Economic Appraisal we use ECONOMIC (or SHADOW) prices NOT FINANCIAL prices Adjust financial prices as follows: Exclude all taxes and duties and subsidies Use the planning discount rate not financial market rate If overvalued exchange rate then value imports and exports more highly Use the opportunity cost of labor Standard Conversion Factors are now widely used for road construction costs 8
Benefits from Road Investment Changes in transport costs occur because of : Lower road roughness Shorter trip distance Faster speeds Reduced chance of impassability Reduced traffickability problems Change in mode 9
Project Costs Management (including design and supervision) Labor Equipment Materials Land, Resettlement, Environment 10
Primary Effects (1) Reduced vehicle operating costs (VOC) fuel and lubricants vehicle maintenance depreciation and interest Tire wear Crew time overheads Reduced journey time drivers, passengers and goods 11
Primary Effects (2) Changes in road maintenance costs Changes in accident rates Increased travel Environmental effects Change in value of goods moved 12
Secondary Effects Changes in agricultural output Changes in services Changes in industrial output Changes in consumers behavior Changes in land values Changes in income 13
Consumers Surplus Approach Captures primary benefits Advantages: Simple, cost based, traffic approach dependent on predicting changes in traffic Disadvantages: May not address critical factors promoting either rural development or social access 14
Normal and Generated Traffic Benefits Total Benefits = Transport cost savings to Normal traffic and growth Cost C1 + Additional benefits to Generated traffic C2 Demand Curve (Price Elasticity of Demand) T1 T2 Traffic Normal Generated 15
Generated Traffic Benefits Traffic induced by the road investment are traditionally valued at: Half the difference in transport costs Hence total generated transport cost benefits = Generated Traffic Volume x Change in Transport Costs per km x Distance x 1/2 16
Producers Surplus Approach Captures secondary benefits Advantages: Draws attention to changes in agricultural output (key economic activity in rural areas) Disadvantages: No reliable way of predicting response - impact studies give widely different answers - it could be based on agricultural supply price elasticities but this is almost never done; it requires very careful examination to use. For most projects benefits are just invented! 17
Producers Surplus P2 P1 Price & Costs per Unit of Output Increased Farmgate Price Lower Input Costs Output O1 O2 18
Coverage and Double Counting Any economic analysis should be designed to give maximum coverage of benefits But we must avoid double counting. Do not add primary and secondary benefits (e.g. changes in land values added to changes in transport costs) In a competitive economy the consumers surplus approach (used in HDM) should be adequate 19
Economic Comparisons Economic analysis involves a comparison of With and Without project cases Forecasts are made of traffic, road condition, VOC and road maintenance effects for BOTH scenarios An unrealistic Without case (i.e. with little maintenance) can give a false result A range of With investment cases should be analyzed to find the best solution 20
Traffic Categories Normal traffic: Existing traffic and growth that would occur on road, with and without the investment Diverted traffic: Traffic diverted from another road with same origin and destination to as the project road as a result of the investment Generated traffic: Traffic associated with existing users of the road driving more frequently or driving further than before Induced traffic: Traffic attracted to the project road due to increased economic activity in the road s zone of influence brought about by the project 21
Benefits from Road Investment Transport cost savings for existing (or normal) traffic = Normal Traffic Volume x Change in Transport Costs per km x Distance Main changes in cost from: a) change in transport MODE b) reduced journey TIME c) reduced VOCs 22
Benefits of Upgrading to a Motorable Track Headloading C1 Costs Track Improved road C2 C3 T1 T2 T3 Traffic 23
Cost Effectiveness Against Standard of Road 95% of year, access established Marginal productivity 99% of year, access established Maintenance for roughness reduction 0 Maintenance expenditure $/km 24
Development Benefits Development benefits arise from a combination of increased traffic and reduced transport costs. Benefits may also include : Increased agricultural production Increased service provision Increased industrial activity 25
Estimating Benefits Normal traffic benefits: trips N * d 1 * (VOC 1 -VOC 2 ) Diverted traffic benefits: trips D * ((d 1 * VOC 1 )-(d 2 *VOC 2 )) Generated and Induced traffic benefits: trips G * d 2 * (VOC 1 -VOC 2 )/2 d 1 = existing road length d 2 new road length VOC 1 = vehicle operating costs per km without investment VOC 2 = vehicle operating costs per km with investment VOC data relates to each road section and its condition at the time 26
Economic Decision Criteria (1) Net Present Value NPV = (B 1 -C 1 )/(1 + r) + (B 2 -C 2 )/ (1 + r) 2 + + (B n -C n )/(1 + r ) n Internal Rate of Return To calculate IRR, solve for r, such that NPV = 0 B 1, B 2 Bn = Benefits in years 1, 2 n C 1, C 2 Cn = Costs in years 1, 2. n r = Planning discount rate n = Planning time horizon 27
Economic Decision Criteria (2) Net Present Value/ Investment Cost NPV/ C = NPV/C i First Year Rate of Return FYRR B 1, C 1 C i = (B 1 -C 1 ) / C i = Benefits and Costs in year 1 after construction = Road investment costs Payback Period 28
Economic Decision Criteria (3) NPV IRR 3 NPV/C FYRR Project economic validity V.Good V.Good V.Good Poor Mutually exclusive projects V.Good Poor Good Poor Project timing Fair Poor Poor Good Project screening 1 Poor V.Good Good Poor Under budget constraint 2 Fair Poor V.Good Poor Notes: 1. check for robustness to changes in key variables (sensitivity analysis) 2. with incremental analysis 3. IRR may be indeterminate with NONE or MANY solutions. 29
Present Value Calculation Period Flow 0 1 2 3 4 5 6 7 A0 A5 PV(A0) = A0 PV(A5) = A5 / (1 + i ) ^ 5 PV(Aj) = Aj / (1+ i ) ^ j PV(Aj) = Present Value of Aj Aj = Amount at year j i = Discount rate j = Year 30
Present Value at 12.0% Discount Rate 1.00 in Year 1 = Year 2 Year 3 Year 4 1.00 in Year 5 = Year 6 Year 7 Year 8 Year 9 1.00 in Year 1 0 = 1.00 0.89 0.80 0.71 0.64 0.57 0.51 0.45 0.40 0.36 in Year 1 in Year 1 in Year 1 1.00 in Year 15 = 0.20 in Year 1 1.00 in Year 20 = 0.12 in Year 1 31
Discount Rate The discount rate is opportunity cost of capital in the public sector, ie the rate of return on marginal public sector investments The discount rate to be used will be given by the planning authority responsible for the project The World Bank traditionally has not calculated a discount rate for each project but has used 10 to 15 percent as a notional opportunity cost of capital in developing countries 32
Discount Rate Versus Interest Rate US discount rate around 4% 33
NPV and IRR The Net Present Value (NPV) of a project alternative relative to the without project alternative is the sum of the discounted annual net benefits. The Internal Rate of Return (IRR) is the discount rate at which the NPV is zero. 34
NPV Decision Rule 1. If the NPV is positive, for the chosen discount rate, then the alternative is acceptable. 2. If the NPV is negative, for the chosen discount rate, then the alternative is unacceptable. 3. If the NPV is zero, for the chosen discount rate, then the alternative is indifferent to the without project alternative. 35
NPV and IRR Calculation (1) Discount Net Rate (i) Discount Present 12.0% Rate (i) Present Investments Profits Present 0.0% 7500 or or Net Value Present 3.0% 6326 Year Costs Benefits Benefits Factor Value 6.0% 5281 a b c d = c-b e = 1/(1+i)^a f = d*e 9.0% 4347 12.0% 3508 0 10000 0-10000 1.0000-10000 15.0% 2752 1 0 6500 6500 0.8929 5804 18.0% 2068 2 0 3000 3000 0.7972 2392 21.0% 1447 3 0 3000 3000 0.7118 2135 24.0% 881 4 0 5000 5000 0.6355 3178 27.0% 365 30.0% -109 33.0% -544 Total 10000 17500 7500 3508 36.0% -944 39.0% -1315 NPV = 3508 42.0% -1657 45.0% -1975 IRR = 29.3% 48.0% -2271 36
NPV and IRR Calculation (2) 8000 6000 NPV at 12% Discount Rate Net Present Value (M$) 4000 2000 0 Internal Rate of Return 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% -2000-4000 Discount Rate (%) 37
NPV Versus IRR 10000 Net Present Value (M$) 8000 6000 4000 2000 0 NPV at 12% Discount Rate Internal Rate of Return 0.0% 10.0% 20.0% 30.0% 40.0% 50.0% 60.0% -2000-4000 Discount Rate (%) - The IRR and NPV will not necessarily rank the alternatives by the same order - Always use NPV to compare project alternatives 38
Multiples Rates of Return Net Year Benefits 0-500 1 1150 2-660 NPV at 12% 0.64 IRR #1 10% IRR #2 20% Discount Rate NPV 0% -10.0 2% -6.9 4% -4.4 6% -2.5 8% -1.0 10% -0.0 12% 0.6 14% 0.9 16% 0.9 18% 0.6 20% 0.0 22% -0.8 24% -1.8 26% -3.0 28% -4.4 30% -5.9 Net Present Value (M$) Multiple Rates of Return 2.00 0.00 0% 5% 10% 15% 20% 25% 30% 35% -2.00-4.00-6.00-8.00-10.00-12.00 Discount Rate (%) 39
No Rate of Return Year Net Benefits 0 200 1 300 2 350 NPV at 12% 747 IRR #NUM! 900 800 No Rate of Return Discount Rate NPV 0% 850.0 2% 830.5 4% 812.1 6% 794.5 8% 777.8 10% 762.0 12% 746.9 14% 732.5 16% 718.7 18% 705.6 20% 693.1 22% 681.1 24% 669.6 26% 658.6 28% 648.0 30% 637.9 Net Present Value (M$) 700 600 500 400 300 200 100 0 0% 5% 10% 15% 20% 25% 30% 35% Discount Rate (%) 40
Same Rate of Return Net Benefits Project Project Year 1 2 0-1000 1000 1 1250-1250 NPV at 12% 116-116 IRR (%) 25% 25% Discount Project Project Rate 1 2 1% 238-238 3% 214-214 5% 190-190 7% 168-168 9% 147-147 11% 126-126 13% 106-106 15% 87-87 17% 68-68 19% 50-50 21% 33-33 23% 16-16 25% 0 0 27% -16 16 29% -31 31 31% -46 46 Net Present Value (M$) Same Rate of Return 300 200 100 0 0% 5% 10% 15% 20% 25% 30% 35% -100-200 -300 Discount Rate (%) Project 1 Project 2 41
Incremental Rate of Return Alternative A - Base Investments Profits Present or or Net Value Present Year Costs Benefits Benefits Factor Value NPV = 6.3 0 8 0-8 1.00-8.0 IRR = 100.0% 1 0 16 16 0.89 14.3 MIRR = 100.0% B/C = 1.79 Alternative B - Base Investments Profits Present or or Net Value Present Year Costs Benefits Benefits Factor Value NPV = 7.1 0 100 0-100 1.0000-100.0 IRR = 20% 1 0 120 120 0.8929 107.1 MIRR = 20% B/C = 1.07 Alternative B - Alternative A Investments Profits Present or or Net Value Present Year Costs Benefits Benefits Factor Value NPV = 0.86 0 92 0-92 1.0000-92 IRR = 13% 1 0 104 104 0.8929 93 MIRR = 13% B/C = 1.01 42
IRR Reinvestment Assumption IRR IMPLICIT ASSUMPTION: ALL CASH FLOW VALUES WILL EARN THE IRR INTEREST RATE Discount Rate (i) 12.0% Future Value in Year 4 Investments Profits If You If You Receive or or Net Invest at and Invest at Year Costs Benefits Benefits 29.3% 29.3% a b c d = c-b Interest Interest 0 10000 0-10000 10000 1 0 6500 6500 12929 6500 2 0 3000 3000 16715 = 8404 3000 3 0 3000 3000 21611 10865 3879 3000 4 0 5000 5000 27940 14047 5015 3879 5000 NPV= 3508 IRR= 29.3% Total 27940 43
Modified Internal Rate of Return Modified Internal Rate of Return Calculation Financing Reinvestment Rate (i) Rate (i) 12.0% 12.0% Present Future Modified Net Value Value Cash Year Benefits of Costs of Benefits Flow a d = c-b Costs at Year 0 Benefits at Year 4 0-10000 10000 10000 0 0-10000 1 6500 0 0 6500 9132 0 2 3000 0 0 3000 3763 0 3 3000 0 0 3000 3360 0 4 5000 0 0 5000 5000 21255 TOTAL 7500 10000 21255 NPV = 3508 3508 IRR = 29.3% 20.7% MIRR = 20.7% 44
Benefits X Cost 120 100 Alternative B 80 Benefits 60 40 20 0 Alternative A 0 20 40 60 80 100 120 Costs 45
Net Benefits X Costs (Efficiency Frontier) 8 7 6 Alternative B Net Benefits (NPV) 5 4 3 2 Alternative A 1 0 0 20 40 60 80 100 120 Costs 46
Comparison of Alternatives When comparing project-alternatives, the Net Present Value (NPV) is used to select the optimal project-alternative (alternative with highest NPV) The Internal Rate of Return (IRR) or the B/C ratio are not recommended to compare alternatives of a given project Project Alternatives NPV 0.0 3.7 6.7 5.5 47 Optimal Alternative: Highest NPV
Projects Ranking Projects When comparing the economic priority of different projects, a recommended economic indicator is the NPV per Investment ratio Selected Alternative Overlay Reseal Overlay 48 NPV/Investment 8.4 5.2 2.1 P R I O R I T Y
Budget Constraints Simple Methodology Projects Selected Alternative NPV Investment NPV per Investment Available Budget Overlay Reseal Overlay 16.8 15.6 20.0 2.0 3.0 5.0 8.4 5.2 4.0 P R I O R I T Y Reseal 3.0 2.0 1.5 Budget Constraint Cut Off Overlay 5.0 49 10.0 0.5
Budget Constraints Optimization Projects Alternatives Available Budget NPV 0.0 3.7 6.7 5.5 0.0 2.0 1.0 3.5 0.0 5.4 2.1 3.2 50 Evaluates all possible combinations of projectalternatives to find the combination that maximizes the NPV of the overall network for the given budget constraint. P = Number of projects A = Number of alternatives C = Number of possible combinations C= A ^P
HDM-4 Optimization Example (1) Section 1 Option Cost NPV A 2 4 B 5 7 C 7 8 Section 2 Option Cost NPV A 1 3 B 3 6 C 5 8 What is the recommended program for a budget of 5? 51
HDM-4 Optimization Example (2) 9 8 7 6 B C B C 5 4 3 A A dnpv/dcost 2 1 0 0 1 2 3 4 5 6 7 8 Cost Section 1 Section 2 52
HDM-4 Optimization Example (3) 18 16 14 12 10 8 1-A, 2-B 1-A, 2-C 1-B, 2-C 1-C, 2-C 6 4 1-A, 2-A 2 0 0 2 4 6 8 10 12 14 Combination of project alternatives that maximizes the NPV of the network 53 Cost Network
Appraisals & Post Evaluations (1) An Appraisal is carried out before an investment is made. Everything is uncertain. A Post evaluation may be made say 5 years after the investment. The investment is known and 5yrs of with case are known. The without case is unknown as is the remainder of the with case. 54
Appraisals & Post Evaluations (2) In Both Cases forecasting and evaluation models are required to come to an answer. Hence we can never be certain about the viability of an investment! 55
Sensitivity Analysis Consequences of changes on inputs Investment Costs (e.g. +15%) Traffic Growth Rate (e.g. = zero) Generate Traffic (e.g. = zero) Value of Time (e.g. = zero) A = Investment Costs Increase (e.g. +15%) B = Road User Benefits Decrease (e.g. - 15%) C = A and B together 56
Switching Values Analysis Inputs that yield a NPV equal to zero Investments Costs Normal Traffic Traffic Growth Rate Generate Traffic Investment Cost Road User Benefits 57
Risk Analysis Inputs vary at the same time following some defined distributions Normal Traffic Frequency Distribution 35% 30% 25% 20% 15% 10% 5% Country Africa Region Project Road Management Initiative Road Road from Point A to Point B Option 2 Upgrade to ST Internal Rate of Return Upgrade Road to Surface Treatment Standard Minimum 4.2% Maximum 22.7% Average 11.9% Standard Deviation 3.5% Median 11.7% Percentile 25% 9.4% Percentile 50% 11.7% Percentile 75% 14.1% Probability that IRR is less than 12% 50% Probability that IRR is greater than 12% 50% 0% 0.50 0.58 0.65 0.73 0.81 0.88 0.96 1.04 1.12 1.19 1.27 1.35 1.42 1.50 Multiplier Factor 1.58 1.65 1.73 1.81 1.88 1.96 Upgrade Road to Surface Treatment Standard 8% 7% Frequency Distribution 14% 12% 10% 8% 6% 4% Project Investment Costs Frequency Distribution 6% 5% 4% 3% 2% 1% 2% 0% 0% 0.50 0.58 0.65 0.73 0.81 0.88 0.96 1.04 1.12 1.19 1.27 1.35 1.42 1.50 Multiplier Factor 1.58 1.65 1.73 1.81 1.88 1.96 58 5.0% 6.0% 7.1% 8.1% 9.1% 10.1% 11.2% 12.2% 13.2% 14.2% 15.3% 16.3% 17.3% 18.3% Internal Rate of Return 19.4% 20.4% 21.4% 22.4% 23.5% 24.5%
Rural Transport Infrastructure Farm Household/ Village Sub-village Typical Transport Infrastructure Path Path/Track Track/ Earth Road Market Center Earth Road/ Gravel Road District Headquarters 1-2 lane Gravel / ST Road Regional Headquarters 2 lane AC** Road Capital/ Port Typical Traffic Porterage NMT NMT 0-5VPD 5-50VPD 1-5 km 1-10 km 5-20 km Share of Asset Value Share of Network Length 40% 20% 0% NMT >100VPD >1500VPD 20-200VPD 10-50 km 20-100 km 50-200 km 40% 20% 0% Responsability Type of Network Community Local Government Rural Transport Infrastructure Provincial/Central Government Trunk or Provincial Road Tracks Roads Highways 59
Rural Transport Infrastructure Rural Transport Infrastructure Primary, Secondary and Municipal Roads Road Network Tertiary Secondary Primary Functional Classification Access Collector Arterial Responsibility Community Local Government Regional & National Municipal % of Road Network N.A. +- 70% +- 10% +- 10% 1 to 2 earth or gravel 1.5 to 2 gravel or paved Physical Characteristics tracks lanes lanes 2 or more paved lanes Normally sections with 1 to 5 kms Normally sections with 5 to 20 kms Normally sections with 20 to 100 kms Normally sections with 50 to 200 kms Traffic Characteristics Mostly NMT < 50 AADT + NMT 50-500 AADT > 500 AADT Economic Evaluation No No Yes Yes Social Evaluation Yes Yes Complimentary No Financial Evaluation No No No Tolls Technical Evaluation No Yes Yes Yes Environmental Evaluation No Yes Yes Yes Safety Evaluation No Yes Yes Yes Focus on social evaluation (cost effectiveness indices, community priorities and multi-criteria analysis) 60
Social Benefits: Why the Concern? There is unease with conventional appraisal based primarily on transport cost savings to traffic There is a strong desire at community and national levels for better access and mobility which is frequently not matched by standard measured economic benefits The rich world governments subsidise rural transport. Should the same happen for developing countries? Isolation is a recognised characteristic of poverty There is a feeling that a minimum degree of access and mobility is a basic human right Development has moved away from a narrow definition of economic development towards concern with livelihoods and meeting Millennium Development Goals The issue is particularly important when roads are impassable to motor traffic 61
Economic & Social Benefits Consumers and producers surplus approaches are very economic in orientation. Yet roads provide social benefits including improved access to health and education facilities and improved social mobility that cannot be easily translated into conventional economic benefits. Although they may have important long term economic consequences. Improved health and education and more secure social networks increase long term earning capabilities but so far the economic forecasting framework does not include this. When roads are impassable to motorized traffic we know that the quality of health care and schooling falls. Drug supply and supervision drops. Likewise no NGO, government agency or commercial enterprise will establish or support a service which cannot guarantee all year round access. 62
Indices and Ranking Widely used for feeder road planning; there are many different approaches e.g. i) cost of improvement / population ii) estimated trips / cost Advantages: Speed, simplicity, transparency, many factors can be incorporated Disadvantages: How do we value widely different factors? (adding up apples and pears); weightings are not stable ; cannot easily address questions of road standards, timing etc, ; possible double counting 63
Example of Two Indices i) Andhra Pradesh (India) cost effectiveness = cost of upgrading/ population served But no measure of condition change and no importance to traffic ii) Airey & Taylor 1st for impassable roads rank = cost per head of establishing basic access 2nd when access is there: estimated trips x access change prioritization index = -------------------------------------------- rehabilitation cost per km 64
Community Priorities Community priorities now often form an important part of feeder road appraisal. It is possible just to ask communities to rank the investments they prefer- both within the road sector or between roads and other investments. Advantages: Community acceptability, use of community knowledge Disadvantages: Sectional interest groups may dominate voting, community knowledge of area or road impact may be poor 65
Cost Effectiveness Analysis (CEA) Compares the cost of interventions with its predicted impacts and it is used where the benefits cannot be measured in monetary terms, or where the measurement is difficult It includes provisions that (a) the objectives of the intervention are indicated and are clearly part of a ampler program of objectives (such as reduction of the poverty); and (b) the intervention represents the smaller cost alternative of obtaining the indicated objectives It produces effectiveness indicators, such as Total Beneficiary Population per Investment or Investment per Beneficiary Population 66
CEA Comparison of Alternatives To compare project-alternatives, the investment cost is used to select the optimal alternative The selected alternative is the one with the lowest investment cost that will achieve the objective of the program Project Alternatives Investment 2.0 3.7 1.7 5.5 Optimal Alternative: Lower Investment 67
Projects Eligibility with CEA To assess if a project is eligible, an acceptable effectiveness indicator threshold is defined Projects Investment per Population (U$/person) 50 Effectiveness Indicator Threshold Example 150 Eligible 500 68 Not Eligible
Effectiveness Indicator Threshold Frequency of Projects 40 35 30 25 20 15 10 5 0 0 50 Reasonable 100 150 200 250? 300 350 400 450 Investment per Population (US$/person) 69 Non Reasonable? Evaluate Universe of Projects and Available Budget 500 550 600 650 700 750 800 850 900 950
Possible CEA Indicators Investment Cost per Total Beneficiary Population 100 US$ per person Total Beneficiary Population per Investment Cost 0.01 persons per US$ Total Beneficiary Population per Investment Cost in thousands of dollars 10 persons per 1,000 US$ Etc. 70
Options for Beneficiary Population Rural beneficiary population o Effectiveness = (rural beneficiary population) / Investment Poor beneficiary population o Effectiveness = (poor beneficiary population) / Investment Mixed beneficiary population Etc. o Effectiveness = (poor persons + 0.3 non poor persons) / Investment 71
Total Beneficiary Population (1) Total Beneficiary Population = Directly Benefited Population + Indirectly Benefited Population The Directly Benefited Population is the one that lives next on the road, defined for example to 2.0 km at each side of the road, and the population in the ends of the road, depending on its characteristics and the use of the road The Indirectly Benefited Population is the population that lives in other roads near the road in consideration, who use the project road to arrive at the main population center of the region or at a main road 72
Total Beneficiary Population (2) D Main Population Center B C E F A Village For example, for the road section B-C: Directly Benefited Population = Population along section B-C plus on towns B and C Indirectly Benefited Population = Population along section A-B plus on town A 73
Multi Criteria Analysis (MCA) (1) It adopts criteria such as traffic, proximity to educative, health, and economic centers, etc. To each section, a number of the points is assigned to each criteria that correspond to the fulfillment of the criteria The added number of the points that each section receives is computed simply adding the points assigned for each criteria, or with the use of a more complex formula, for example, weighting the criteria by their perceived importance 74
Multi Criteria Analysis (2) It produces a priority indicator The indicators used in a MCA reflect implicit economic and subjective evaluations If the weights and the points are decided and assigned on a participative way, the MCA has the potential to be a good participative method for planning based on implicit a socioeconomic estimates Nevertheless, it tends to be applied by planning consultants or in isolation without the consultation with the users and communities affected by the project 75
Multi Criteria Analysis (3) The result of the MCA, is often, unfortunately, not transparent, specially if many factors are considered and a complicated formula is also applied Therefore, if it is adopted, this method must be used very carefully and to be maintained simple, transparent, and participative 76
Multi Criteria Analysis Example (1) Level of poverty of the influence area (Low, Medium, High) Potential for economic development of the influence area (Low, Medium, High) Importance of the road given by local consultation process (Low, Medium, High) Provision of access of social services of the road (Low, Medium, High) Problems of transitability of the road (Low, Medium, High) Functional classification level of the road (Low, Medium, High) Existence of public transport (Low, Medium, High) 77
Multi Criteria Analysis Example (2) Population Poverty Agricultural Area Traffic Functional Classification Priority Index Location on Basic Network Beneficiary Population per km Factor Poverty Percent Factor Percent of Area of Influence Factor Daily Traffic (AADT) Factor A=4 B=3 C=2 D=1 Factor Yes = 1 No = 0 Factor 9,889 1.00 99% 1.00 0% - 20 0.25 1 0.33 1 1.00 520 0.05 99% 1.00 0% - 20 0.25 2 0.67 1 1.00 1,237 0.13 99% 1.00 0% - 15 0.19 2 0.67 1 1.00 564 0.06 97% 0.98 14% 0.25 80 1.00 3 1.00 1 1.00 344 0.03 97% 0.98 36% 0.64 15 0.19 3 1.00 1 1.00 503 0.05 97% 0.98 18% 0.32 35 0.44 3 1.00 1 1.00 Health Centers Schools Public Transport Environment Feasibility Yes = 1 No = 0 Factor Yes = 1 No = 0 Factor Yes = 1 No = 0 Factor Yes = 1 No = 0 Factor Priority Index 0-0 - 1 1.00 1 1.00 5.6 0-0 - 1 1.00 1 1.00 5.0 0-0 - 1 1.00 1 1.00 5.0 0-1 1.00 1 1.00 1 1.00 7.3 0-1 1.00 1 1.00 1 1.00 6.8 0-1 1.00 1 1.00 1 1.00 6.8 Factor = Value / Maximum Value 78