Washington Metropolitan Area Transit Authority Board Action/Information Summary

Similar documents
FY2018 Second Quarter Financial Update

FY2018 Third Quarter Financial Update

FY2017 Year-End Financial Update

State of Good Repair Review

Capital & Strategic Planning Committee. Item III - A. January 25, FY2019 Capital Budget Work Session

Quarterly Capital Progress Update

Keeping Metro Safe, Reliable and Affordable

FY2020 Budget Outlook

Jul Aug Sept Oct Nov Dec Jan Feb Mar Apr May Jun

Operating Budget Report

OPERATING BUDGET REPORT

Report by Finance and Administration Committee (A) Washington Metropolitan Area Transit Authority Board Action/Information Summary

Operating Budget Report

Operating Budget Report

Arlington County, Virginia

2 nd Quarter Capital and Operating Reports

FY2017 Budget Discussion

PROPOSED CAPITAL IMPROVEMENT PLAN

FY2014 Capital and Operating Budget Discussion

TESTIMONY OF RICHARD SARLES

Approval to Submit TIFIA Loan Application

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY TRANSPORTATION IMPROVEMENT PROGRAM CAPITAL COSTS (in $1,000)

FY2011 Budget Forum. District of Columbia. October 19, 2009

Notice of Public Hearing Washington Metropolitan Area Transit Authority

Approval of FY2017 Capital Budget and FY Capital Improvement Program

GM/CEO s Proposed FY2020 Budget

Operating Budget Report

METRO. Metro Funding. Associated Master Plan: Comprehensive Master Transportation Plan (MTP) for Arlington. Neighborhood(s):

Report by Finance and Administration Committee (B) Washington Metropolitan Area Transit Authority Board Action/Information Summary

FY2017 Budget Guidance

Metro 2025 Alternative Funding and Financing

- II OPERATING BUDGET REPORT ^ H FY2013 ^^ H. ««-ms. I ~?j i... \6.3 j^^^^^^ YTD OVERTIME BUDGET VS ACTUAL ($ in Millions) 1

The following items were handed out at the November 2, 2017 NVTC Meeting.

Responses to Committee Requests

Safety and Operations Committee. Information Item III-B. January 24, 2019

Next Capital Funding Agreement

Metro. Board Report. Fare revenue projections, based on preliminary assumptions for ridership

Washington Metropolitan Area Transit Authority Metro Budget Overview

RAC Capital Presentatition May 5, 2010

Amend FY 2006 Infrastructure Renewal Program

Review of Capital Needs Inventory and Preliminary Capital Improvement Program

Proposed Capital Improvement Plan (CIP)

Capital Improvement Program Update

Quarterly Status Report

FY2014 Operating Budget Performance Report

Finance & Administration Committee Information Item IV-A October 9, 2014 Momentum Update

FY2017 Third Quarter Financial Update and CIP Amendment

Quarterly Financial Report FY2015 Q3 January March 2015

PROPOSED FISCAL YEAR 2011 BUDGET. Testimony of. Richard Sarles, General Manager. Washington Metropolitan Area Transit Authority.

Proposed Capital Improvement Plan (CIP)

Cash & Liquidity The chart below highlights CTA s cash position at June 2014 compared to June 2013.

Financial Report - FY 2017 Year to Date May 31, 2017

CITY OF LOS ANGELES INTER-DEPARTMENTAL CORRESPONDENCE

Customer Service and Operations Committee. Board Action Item III-A. July 10, 2014

SUBJECT: October Monthly Financial Reports ^ DATE: December 22, 2011

Quarterly Status Report

Quarterly Status Report

Operating Budget. Second Quarter Financial Report

Approval of Reimbursable Project for Purchase of Buses for DC Circulator

Washington Metropolitan Area Transit Authority

Quarterly Status Report

Toronto Transit Commission

Capital Metropolitan Transportation Authority Monthly Financial Report For Period Ending November 30, 2013

Public Hearing on Peak Fares for Peak Service

Huntington Parking Garage Budget Adjustments

May 31, 2016 Financial Report

Report by Finance and Administration Committee (B) Washington Metropolitan Area Transit Authority Board Action/Information Summary

CENTRAL CITY LINE PROJECT UPDATE AND SMALL STARTS EVALUATION & RATINGS APPLICATION UPDATED & REVISED 4/20/17

2007 Legislative Program Northern Virginia Transportation Authority Approved: November 10, 2006

Management Committee Meeting date: March 8, 2017 For the Metropolitan Council meeting of March 22, 2017

Table Of Contents Chapter 9: Vehicle, Facility and Other Equipment Inventory and Disposition

Quarterly Financial Report FY2015 Q4 April June 2015

Quarterly Financial Performance Report Q1 2017

TRANSIT SYSTEM MAINTENANCE AND RENOVATION. VEHICLES - Caltrain

SUBJECT: APPROVAL OF FISCAL CAPITAL IMPROVEMENT PROGRAM

Approval of FY2013 Budget

FY2016 Year-End Financial Update

Cash & Liquidity The chart below highlights CTA s cash position at August 2018 compared to August 2017.

STAFF REPORT INFORMATION ONLY

TEX Rail Fort Worth, Texas Project Development (Rating Assigned November 2012)

Financial Report Fiscal Year 2018

Financial Report Fiscal Year 2018

Potomac Yard Metrorail Station TIIF Allocation

Financial Update for the Period Ended April 7, 2018

Chairman Skinner and the VRE Operations Board. Authorization to Issue a Request for Proposals for Federal Legislative Services

CHAPTER 7: Financial Plan

M Aug sept OCt Nov Dec ~ FtIb ~ ~ ~

Part I. Capital Programs Office Report: Capital Spending Update Part II. Transforming Capital Delivery September 12, 2016

August 31, 2016 Financial Report

SEPTA s State of Good Repair Funding Crisis

New York City Transit Authority Consolidated Financial Statements Management s Discussion and Analysis December 31, 2004 and 2003

FAP Agenda Number 4. Attachment 2. Central Arizona Project Capital Project Program Review

Financial Report Fiscal Year 2018

FY2011 Monthly Financial Report (October 2010)

Operating Budget Report

Transit Subsidy. Mission Statement. Mandates

CHAPTER 9 FINANCIAL CONSIDERATIONS

Consent Item (A) Washington Metropolitan Area Transit Authority Board Action/Information Summary

MARTA 2009 Budget Summary Review

Metropolitan Transportation Authority Proposed Capital Program

Transcription:

Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number: 201958 Resolution: Yes No TITLE: Second Quarter Capital Program Update PRESENTATION SUMMARY: This presentation provides an overview of Metro s performance in executing the Capital Program from both a project delivery and financial perspective. The presentation highlights several key projects that were delivered or progressed significantly during. PURPOSE: Management will update the Capital and Strategic Planning Committee on the status, delivery and success of the Capital Program. DESCRIPTION: Key Highlights: $505 million of capital investments were made through the second quarter. Full year capital investment is forecasted between $1.1 and $1.2 billion, compared to a budget of $1.25 billion. Background and History: Metro s original capital budget of $1.25 billion includes funding to repair, rehabilitate, and replace Metro's capital assets, including vehicles, stations, track and structures, power, yards and garages and business support. Discussion: Capital Investment Program Metro invested $505 million in its capital program thru December 2017, compared to a budget of $578 million. Full year capital investment is forecasted between $1.1 and $1.2 billion, compared to a budget of $1.25 billion. Capital projects fall into one of the following phases: development and evaluation (D&E), design, or construction or implementation. We will highlight

projects in each phase. D&E Phase D&E phase provides funding for evaluation, planning, and development for potential capital projects. The D&E process helps to ensure that projects have clearly defined scopes, schedules, and cost estimates with appropriate consideration for risks and alternative solutions. Project funding is allocated when initiatives are sufficiently developed to advance to the next stage. The 27 projects in the D&E phase include rail yard phase II, bridges, red tag switching, Gallery Place station capacity improvement, and knowledge management repository. Design Phase The design phase develops scopes of works into biddable documents. There are 16 projects in the design phase, including Potomac Yard, 8000 series railcars, and Foggy Bottom and Farragut West station enhancements. Construction and Implementation Phase The construction and implementation phase is the project delivery process. Highlights of the 75 projects in construction and implementation include: 7000 Series Railcars: An investment of $144.3 million was realized for the 7000 series railcars by the end of second quarter. The overall project was 63% complete with a total of 472 new railcars accepted through December 2017. Conditional acceptance of 100 replacement cars is expected to be completed by March 31, 2018. Railcar Rehabilitation: Railcar rehabilitation investment reached $23.1 million year-to-date and the project is forecasting slightly below budget due to lower than expect spare parts costs. The project replaced railcar components, such as heating, ventilation, and air conditioning systems on the 2000/3000 series railcars, brake pads on the 2000/3000 series railcars, and battery assemblies on the 6000 series railcars. Track Rehabilitation: The Authority financed $37.2 million in track rehabilitation year-to-date. Highlights include: crosstie renewal (12,227); fastener renewal (10,977); third rail rehab (1.1 miles); running rail (4.7 miles); switch rehabilitation (six); insulator renewal (3,573). Radio Infrastructure Replacement T-band Relocation: Project implementation activities produced a $12.1 million investment year-todate. Major milestones include: College Park to Gallery Place cellular will be ready by June 2018; factory acceptance test for fixed network equipment, subscriber order and 95% of radio system design work will be completed by June 2018. Bus Replacement: The bus replacement project expended $0.3 million year-to-date. Acceptance testing is expected to be completed in January

2018 and full scale of production to begin in February 2018. Bus Rehabilitation: Bus Rehabilitation investment year-to-date was $22.3 million. Highlights include rehabilitation of 50 buses, replacement of 50 energy storage systems and the rebuilding of 60 transmission assemblies. Andrews Federal Center Bus Garage: Metro invested $42.4 million in Andrews Federal Center Bus Garage through the second quarter. Retaining walls, membrane roofing installation and the precast concrete envelope have been completed. FUNDING IMPACT: This is an information item to present a progress report on the Capital Program. No specific action with a budget impact is requested at this time. TIMELINE: Anticipated actions after presentation May 2018 third quarter capital progress report delivered to the Committee

Capital and Strategic Planning Committee Item III - A February 8, 2018 Second Quarter Capital Program Update

Washington Metropolitan Area Transit Authority FY2017 Budget: Second Quarter Ridership and Revenue Capital Program Update Finance & Administration Committee October 8, 2015 Capital and Strategic Planning Committee February 8, 2018

Purpose Provide Second Quarter Capital Program update and highlight key capital projects 2

Capital Investment Forecast Range $1.1-$1.2B YTD Actuals $504.8M 3

Project Phases Development and Evaluation 27 Projects Design 16 Projects Construction and Implementation 75 Projects 4

Development & Evaluation (D&E) Evaluation, planning and development for potential capital projects Development of scopes, schedules and cost estimates with appropriate consideration for risks and alternative solutions Current initiatives include rail yard phase 2 and bridges 5

Rail Yard Phase II Budget ($M): % Expended 1% $0.9 $0.0 $0.9 $0.0 $0.9 Project Completion: 34% 10/1/17 10/1/17 3/2/18 Milestones Review and prioritize rehabilitation needs at the yards to be completed January 2018 Advertise Design/Build Procurement Package by March 2018 6

Bridge Structures Budget ($M): % Expended 0% $0.6 $0.0 $0.6 $0.0 $0.6 Project Completion: 1% 10/1/17 12/1/17 6/15/18 Milestones Review and evaluate expansion joint replacement January 2018 Final evaluation review June 2018 7

Major Projects in Design Scopes of works are progressed through design phase and developed into biddable documents Potomac Yard Station Foggy Bottom and Farragut West Station Enhancements 8000 Series Railcars 8

Potomac Yard Budget ($M): % Expended 12% $16.3 $9.2 $5.3 $0.8 $2.3 Project Completion: 90% 9/1/2010 9/1/2010 2/28/2018 Budget will be adjusted to meet contract award amount and memorandum of understanding (MOU) Milestones Value engineering options complete January 2018 Technical Proposals due February 2018 9

Foggy Bottom and Farragut West Station Enhancements Budget ($M): % Expended 12% $0.8 $0.1 $0.6 $0.1 $0.6 Project Completion: 9% 10/1/17 10/18/17 9/18/18 Milestones Alternatives Development complete by February 2018 Egress Analysis and Evaluation Scan complete by April 2018 Engineering Feasibility and Constructability Analysis complete by July 2018 Farragut West Station AM Peak Period Order of Magnitude Cost Estimates complete by September 2018 10

8000 Series Railcars Budget ($M): % Expended 19% $2.0 $0.4 $1.7 $0.4 $1.5 Budget will be adjusted to meet forecast. Project Completion: 2% 7/1/16 1/1/17 6/30/18 Milestones 2K/3K cars approaching 40 years. Timing of potential purchase and determination of quantity will be informed by fleet plan. Work with internal and external stakeholders to develop requirements for 8000 technical specification. Complete industry review to determine latest available technology. Develop specification for engineering support service. 11

Construction and Implementation Projects Projects delivering planned scope of work 7000 Series Railcars Railcar Rehabilitation Track Rehabilitation Radio Infrastructure Replacement T-Band Relocation Bus Replacement Bus Rehabilitation Andrews Federal Center Bus Garage 12

7000 Series Railcars Budget ($M): % Expended 42% $1,709 $978 $326 $144.3 $325 Project Completion: 63% 12/15/05 12/15/05 3/31/2024 Railcars Accepted Railcars to be Accepted Total Railcars to be Delivered 472 276 748 Milestones Date 100 cars to replace 4000 series 3/2018 30 cars to partially replace 5000 series Remaining 146 cars to be delivered 12/2018 7/2019 13

Railcar Rehabilitation Budget ($M): % Expended - 41% $55.9 $23.1 $55.9 $23.1 $52 Project Completion: 41% 7/1/17 7/1/17 6/30/18 Forecast reflects lower than budgeted costs for spare parts Components 2/3K HVAC Overhaul 2/3K Brake Pads 6K Railcar Battery Assemblies Railcar Exterior Vinyl Wrap Project Truck Repair 14

Track Rehabilitation Budget ($M): % Expended - 45% $81.8 $37.2 $81.8 $37.2 $69.5 Project Completion: 45% 7/1/17 7/1/17 6/30/18 Forecast reflects low bid savings for new contracts and rescheduling of work due to manufacturing issues. Budget will be adjusted to meet forecast. Component Planned Forecast Q1&2 Actuals Crosstie Renewal 13,000 15,000 12,227 Fastener Renewal 23,500 23,500 10,977 Third Rail Rehab. 2.5 miles 2.5 miles 1.1 miles Running Rail 13.0 miles 13.0 miles 4.7 miles Switch Rehabilitation 12 14 6 Insulator Renewal 14,000 14,000 3,573 15

Radio Infrastructure Replacement T-Band Relocation Budget ($M): % Expended - 25% $333.4 $47.3 $47.6 $12.1 $73 Project was able to achieve a major milestone sooner than previously forecasted. Budget will be adjusted to meet forecast. Project Completion: 15% 4/1/15 4/1/15 12/23/22 Milestones College Park to Gallery Place cellular ready - June 2018 Factory Acceptance Test for fixed network equipment (Contract Milestone) June 2018 Subscriber Order (all mobiles and high-end portables) June 2018 Radio system design 95% complete June 2018 16

Bus Replacement Budget ($M): % Expended 1% $63 $0.3 $63 $0.3 $39.7 Project Completion: 1% 7/1/17 7/1/17 9/30/18 Forecast reflects delay in the delivery of buses due to EFA regulation to procure clean fuel technologies to reduce emissions and lower fuel costs Milestones Acceptance testing expected to be completed January 2018 Full scale production to begin February 2018 Deliver of 66 40ft CNG buses by June 2018 Deliver of 100 40ft CNG buses by September 2018 17

Bus Rehabilitation Budget ($M): % Expended - 43% $51.8 $22.3 $51.5 $22.3 $47.4 Project Completion: 43% 7/1/17 7/1/17 6/30/18 Forecast reflects procurement delivery delay of bus component parts Component Planned Forecast Quarter 1 & 2 Deliverables Buses Rehabilitated 100 100 50 Energy Storage Systems Replaced (ESS) 100 100 50 Engine Assemblies Rebuilt 100 100 50 Transmission Assemblies Rebuilt 120 120 60 18

Andrews Federal Center Bus Garage Budget ($M): % Expended - 79% $185 $127 $54 $42.4 $68.7 Project Completion: 72% 9/15/14 9/15/14 2/14/19 Forecast reflects project acceleration in Milestones Retaining walls completed Membrane roofing installation completed Precast concrete envelope completed Complete Interior Slab on grade 19