NYISO Capital Budgeting Process. Draft 01/13/03

Similar documents
BS&P Guidelines for NYISO Budget Preparation/ Financing and for Project Monitoring. Draft 07/1423/03

Review Criteria. Robotics Program. Reviewer SCORE SUMMARY. Extent of Need 25 Goals Objectives and Milestones

Proposed Change to Unsecured Credit Scoring Model

LCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP

Treasury and Policy Board Office Accountability Report

Office of Audit and Evaluation. Audit of Major Capital Project Management

FASB/IASB Update Part I

Audit Planning Process 2004 July Audit Department. Leaders in building public trust in civic government

Managing Project Risk DHY

Prince2 Foundation.exam.160q

Intro Public-Private Partnership (P3) Finance Course

Terms of Reference (ToR)

Crowe, Dana, et al "EvaluatingProduct Risks" Design For Reliability Edited by Crowe, Dana et al Boca Raton: CRC Press LLC,2001

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

CCAC Comprehensive Planning, Budgeting & Assessment Process

1890 Project Management

Project Risk Management

Budget Analyst GS Career Path Guide

Understanding Business Borrowers $150 COURSE DESCRIPTIONS

GAO INFORMATION TECHNOLOGY. Treasury Needs to Strengthen Its Investment Board Operations and Oversight. Report to Congressional Requesters

POWERLINE SAFETY FY2014 ACHIEVEMENTS FY2013-FY2015 PLANS

CHAPTER 2 FROM THE IDEA TO THE BUSINESS PLAN

Department of Defense INSTRUCTION

Enterprise Risk Management

JORDAN. Terms of Reference

NERC 2013 Business Plan and Budget Overview. May 3, 2012

Resource Allocation, Management, and Planning Presentation for Board of Regents

PEFA Handbook. Volume III: Preparing the PEFA Report FINAL VERSION

ก ก Tools and Techniques for Enterprise Risk Management (ERM)

Township of Perry Strategic Asset Management Policy

Version 2.0- Project. Q: What is the current status of your project? A: Completed

Introduction. The Assessment consists of: A checklist of best, good and leading practices A rating system to rank your company s current practices.

Armenia: Infrastructure Sustainability Support Program

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

MEMORANDUM. To: From: Metrolinx Board of Directors Robert Siddall Chief Financial Officer Date: September 14, 2017 ERM Policy and Framework

All organisational units

Faster Payments Task Force Decision-Making Framework August 26, 2015

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

The UNOPS Budget Estimates, Executive Board September 2013

Managing tax administration reforms

BERGRIVIER MUNICIPALITY. Risk Management Risk Appetite Framework

Phase 1: Written Qualifications. Phase 2: Client Reference Checks. Phase 3: Evaluation: Oral Interviews

Conference Paper A New Cost Management Policy for Your Organization: An Integrated Approach Woomi Chase Ken Odom Tom Dauber

EAN.UCC Project Management Framework Handbook. Issue Version 3.0

Pacific Islands Regional Oceanscape Program (PROP) Project Number: P151780

TRAINING CATALOGUE ON IMPACT INSURANCE Building practitioner skills in providing valuable and viable insurance products

TAC 216 Companion Guide

Department of Homeland Security Office of Inspector General

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

PEFA Training. Dakar, Senegal January & February 1, #PEFA. PEFA Secretariat

Global Environment Facility

Chapter 33 Coordinating the Use of Lean Across Ministries and Certain Other Agencies

Phase 1: Water Budget Based Rate Structure Feasibility Analysis

Morgan Asset Projection System (MAPS)

Morningstar Investment Management Manager Selection

Whitman County, Washington

ENTERPRISE RISK MANAGEMENT (ERM) POLICY

Risk Management Plan PURPOSE: SCOPE:

Final Preliminary Survey Report Audit of Budgeting and Forecasting. June 19, Office of Audit and Evaluation

0470_022817_03_chap01.fm Page 11 Wednesday, September 8, :29 PM. Part I The basics of project risk management

Risk Assessment Mitigation Phase Risk Mitigation Plan Lessons Learned (RAMP B) November 30, 2016

Institutional Strengthening for Aviation Regulation

Project Selection Risk

A n n u a l P e r f o r m a n c e A p p r a i s a l P r o c e s s F Y P r i n c i p l e & W o r k f l o w

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP

PRINCE2-PRINCE2-Foundation.150q

University of Virginia Debt Policy Dated February 22, 2013

Terms of Reference for an Individual National Consultant to conduct the testing of the TrackFin Methodology in Uganda.

1. Introduction 1.1. BACKGROUND

PEFA Handbook. Volume I: The PEFA Assessment Process Planning, Managing and Using PEFA

EFFECTIVE TECHNIQUES IN RISK MANAGEMENT. Joseph W. Mayo, PMP, RMP, CRISC September 27, 2011

MERCER SENTINEL SERVICES

Chapter-8 Risk Management

District of Columbia Public Schools Budget Development and Execution Processes Were Not Sufficient to Avoid Divisional Over- and Under-Spending

B.29[17d] Medium-term planning in government departments: Four-year plans

Master Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards

SLT Budget Subcommittee. Presentation to SLT September 23, 2011 Lisa Freiburger & Laurie Chesley

Finance and Budget Modeling Town Hall. March 27 & 28, 2018

Environmental, Social and Governance Policy Statement

Project Management Certificate Program

SERC Reliability Corporation Business Plan and Budget

LIFE CYCLE ASSET MANAGEMENT. Project Management Overview. Good Practice Guide GPG-FM-001. March 1996

RESERVE BANK OF MALAWI

OFFICE OF INSPECTOR GENERALoFF

Project Integration Management

ENVIRONMENTAL SOCIAL GOVERNANCE (ESG) POLICY INTRODUCTION

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

REQUEST FOR PROPOSALS

RECOMMENDED PRINCIPLES AND BEST PRACTICES FOR STATE RENEWABLE PORTFOLIO STANDARDS

MISSION VALUES. This Framework has been printed by:

Advanced Operational Risk Modelling

A Project Management Guide for Researchers

Security Risk Management

SOA STRATEGIC PLAN EXPOSURE DRAFT

Morningstar Analyst Rating TM for Funds Methodology Document

VANUATU NATIONAL INFRASTRUCTURE MASTERPLAN. Terms of Reference for Consultants

Braindumps.PRINCE2-Foundation.150.QA

AN INTRODUCTION TO RISK CONSIDERATION

IDENTIFICATION AR II /15/06 THE PLANNING, BUDGETING, AND ASSESSMENT CYCLE. Part 1. THE PLANNING, BUDGETING, AND ASSESSMENT CYCLE

SERC Reliability Corporation Business Plan and Budget

Transcription:

NYISO Capital Budgeting Process Draft 01/13/03 1

1.0 INTRODUCTION An effective, capital budgeting process is essential to ensure sound capital investment decisions. This report details a recommended approach to identify, rank, fund, and manage capital investments. The capital budgeting process described herein can be applied to the selection, control, and evaluation of capital projects. The recommended approach has three phases, as described below. 1.1 Selection The selection process identifies all new and recurring capital investment projects for inclusion into the capital budget portfolio based on an overall targeted budget cap. Within the selection phase, capital investments are screened, ranked, and selected. 1.2 Control An ongoing monitoring process that manages selected capital investment projects to ensure that each investment continues to be required and, as such, is delivered on schedule and within budget. 1.3 Evaluation The review process used will determine if a capital investment has realized its expected mission and business performance goals. During the evaluation phase, the overall effectiveness of the capital planning process will be reviewed. Lessons learned during the evaluation phase should be geared towards modifying future project selection decisions. 2

2.0 INITIAL SCREENING OF PROJECT INVESTMENTS All proposed capital projects must go through the screening stage, to determine whether an investment should be considered for additional review. If so, the ISO will determine the appropriate level of investment analysis (as suggested by the type, size, and risk associated with the proposed project), review, and decision-making. Specific roles and responsibilities of the key participants in the screening stage of the Capital Planning and Investment process are described in Table 1. Table 1. Screen Stage Roles and Responsibilities Party ISO BS&P Roles & Responsibilities Develop project proposal Provide additional screening information Review project proposal against screening criteria Determine project viability Review screening of projects and provide input Review preliminary results Approve or disapprove project funding 2.1 Develop Project Proposal The first stage of the capital budgeting process centers on developing and screening a preliminary project proposal, which is prepared by the ISO. At this stage the proposal should include the minimum set of information. The following information should be included in the preliminary project proposal. Project Name Project Description Project Category (economics, replacement, regulatory, etc.) Alternatives Expected Benefits Expected Returns Expected Costs Expected Schedule Expected Risks Definition of Performance Measures 2.2 Review Project Proposal Against Screening Criteria 3

The principal objectives during the screening stage are to determine whether the project is viable and decide if it should be analyzed through the evaluation process. Apply Screening Criteria The ISO will use the following criteria to screen the preliminary initiative proposal. Does the project support core business functions? Is it critical to the performance of these functions? Does the project support operational or work processes that have been simplified or otherwise redesigned? Does the project improve service reliability? What are the expected benefits of the proposed initiative? Is the project required by regulation? Are there major risks involved that will reduce the likelihood of the project performing as expected? Do the project s performance measures adequately reflect the benefits to the appropriate business objectives? What are the alternatives? How do the alternatives compare with the recommended proposal? 2.3 Determine Project Viability BS&P will use information from the preliminary project proposals and associated reviews to provide feedback to the ISO regarding further consideration of the proposed project 2.4 Recommend Evaluation Process If a project is considered viable, BS&P recommends to the ISO that the project proposal be supplemented with additional detail to continue through the evaluation process. 4

3.0 SCORE PROJECT PROPOSAL The ISO will employ a uniform methodology to assign a set of numeric values to a proposed project on the basis of expected returns, costs, and risks. The methodology should rely on the application of explicitly defined and weighted selection criteria in accordance with well-defined scoring rules. Scores assigned to proposed projects would be used in the ranking process. 3.1 Apply the Evaluation Process to Assign a Project Score Score Project To score a proposed project the ISO will provide results of the initial screening evaluation to BS&P for review. Applying uniform and consistent decision criteria will provide BS&P with the necessary input to rank the various capital investments. The Scoring stage is not intended to be the sole basis for decision-making. Rather, it will serve as one factor in the overall selection process. The weighting of multiple decision criteria will allow decision-makers to determine the relative importance of selection factors. The ability to develop and refine specific rules is crucial to the success of this approach. The weighting and scoring rules can be adjusted, as experience with the model and process is gained. Although the scoring approach accommodates the creation of a rankordered list of projects, final investment decisions should be influenced by additional information, including input derived from collaborative forums, as appropriate. Present Project Scores Scoring results can be presented in a variety of ways to provide a visual means to compare the strengths and the weaknesses of alternative projects. 3.2 Analyze Evaluation and Scoring Results For each proposed project, the ISO will review results and findings of the evaluation process and decide whether to recommend and refer the project to BS&P for further consideration. The numeric value is used in ranking and prioritization of proposals with respect to selection for funding and approval for implementation. 3.3 Recommend Project for Selection After completing the review, the ISO will submit those proposed projects to BS&P for consideration. The recommendation should highlight significant issues that are likely to 5

affect the success of the project, such as cost, technical complexity, and dependence on other capital projects. 4.0 SELECT INITIATIVES FOR CAPITAL INVESTMENT PORTFOLIO The selection of projects by the ISO will be based on information gathered and analyzed during the screening and scoring stages of the capital budgeting process. 4.1 Analyze and Compare Projects The ISO analyzes and compares projects. 4.2 Recommend Project Selection The ISO, upon analysis of proposed capital projects, provides recommended projects to BS&P for funding. The recommendations also inform BS&P of the relative operational, technical, financial, and institutional strengths and weaknesses of each project. 4.3 Rank Projects Using the fundamental concepts of portfolio management, such as return, cost, and risk, as well as other decision factors, the ISO ranks projects still under consideration. The ranking decision will also be influenced by the results and findings of on-going and completed evaluation activities and project scoring and re-scoring efforts. 4.4 Recommend an Overall Capital Investment Portfolio The factors that the ISO considers when creating a Capital Investment Portfolio (CIP) are discussed below. Overall Risk Capital projects are likely to possess some level of technical, operational, financial, or organizational risk. 4.5 Approve or Disapprove Corporate Investment Portfolio After the ISO ranks the different capital projects, BS&P will review and, as appropriate, approves the capital project. Following the approval by BS&P, the ISO will prepare the final funding proposal for the Capital Budget. 6

5.0 CONTROL PROJECTS The control phase of the capital budgeting process requires continuous monitoring of ongoing projects through development or acquisition life cycle and deployment, up to point of operation. At that point, the evaluation phase of the process begins. The objective of the control phase is to ensure timely oversight, quality control, and executive in a disciplined, well-managed, and consistent manner. This will promote delivery of quality projects and results in projects that are completed within scope, on time, and within budget. The ability to monitor capital projects adequately relies on effective project management activities. Automated project cost and schedule control systems should be utilized to manage, maintain, and provide shared access to project baselines, monitor changing requirements, and track resource allocations. The frequency of the control review should be established in the selection phase based on factors including strategic alignment, criticality, scope, cost, and risk associated with the project. 5.1 Establish and Maintain Initiative Cost, Schedule, and Technical Baselines The ISO is responsible for establishing project management and execution plans, procedures, and practices to support project-monitoring activities. The ISO should provide periodic updates to BS&P on the status of the project s cost, schedule, and technical baselines. Baselines provide both the framework and sufficient detail to assess the status of the project s major milestones, decisions, activities, and work products and deliverables. 5.2 Maintain Current Project Cost, Schedule, Technical, and General Status Information The ISO collects information on resources allocated and expended throughout the preoperational stage of the project. The ISO also maintains a record of changes to the technical components of on-going project. Changes may later be reviewed for continued funding. 5.3 Assess Project Progress Against Performance Measures During the pre-operational stage of a project, the ISO will determine whether additional project evaluation is warranted. If so, the ISO will perform a more detailed review of the project to assess progress against its planned cost, schedule, and technical baselines. The primary purpose of assessments is to ensure that projects remain on schedule and budget by identifying issues or deficiencies that require corrective action. 5.4 Prepare Project Control Status Reports 7

With a project's control review schedule established during the selection phase, the ISO should prepare a Control Status report for review by BS&P. The status report will be used to determine whether to continue, modify, or cancel the project. 6.0 EVALUATE INITIATIVES The evaluation phase of the capital budgeting process begins after an investment becomes operational, suggested within six months of deployment. The Evaluation Phase closes the loop of the capital budgeting process by comparing actual cost and performance criteria against estimates. This will not only allow performance to be assessed, but also helps identify areas where decision-making can be improved. The evaluation phase focuses on two primary steps. 1. Determining if the specific capital investment met performance, cost, and schedule objectives. 2. Determining the extent to which the capital budgeting process improved the outcome of the capital investment. The two steps of the evaluation phase include conducting a Post Implementation Review (PIR) and applying lessons learned, both at project and process levels. Results of the PIR are reported to the BS&P to offer a better understanding of project performance and assist the ISO in directing any adjustments to the project. The committee will also work internally to revise the process as necessary. The timing of the PIR would be initially determined during the selection phase. The PIR for a new project generally should take place about six months after the project is in service. If a project is cancelled, the PIR should take place immediately. Review of a cancelled project defines lessons learned for future capital investment decisions and activities. 6.1 Conduct Post-Implementation Reviews The central objective of the PIR is the capital investment evaluation, in which the ISO assesses the impact the capital program has had on reliability, customer satisfaction and system capability. The capital investment evaluation focuses on three primary areas described below. 1. Impact to Stakeholders The impact a project has on stakeholders is typically measured by the ISO with surveys (formal or informal), interviews, and feedback studies. 2. Ability to Deliver Capital Performance Measures (Quantitative and Qualitative) 8

The Project s impact should be carefully evaluated to determine whether it met its original and possible modified performance goals 3. Ability to Meet Performance Goals Cost: Return: Schedule: Risk Analysis: A management report should also be submitted to the BS&P for all projects to document lessons learned, including project management and technical insights. A high-level assessment of management techniques, including organizational approaches, budgeting, acquisition and contracting strategies, tools and techniques, and testing methodologies is essential to establish realistic baselines and ensure the future success of other capital projects. To capture management lessons learned the project manager should develop a summary report after completion of the PIR. 7.0 APPLY LESSONS LEARNED 7.1 Evaluate Capital Planning and Investment Process Through regular use and practical experience, the ISO and BS&P should expect the capital budgeting process to mature and evolve. 7.2 Identify Lessons Learned and Recommend Process Improvements Having identified the strengths and the weaknesses of the current process, the ISO and BS&P will work together to develop, recommend, and modify the budget process as appropriate. 7.3 Endorse Process Improvements The BS&P and ISO will implement modifications to improve the capital budgeting process. 9