For personal use only

Similar documents
PALADIN ENERGY LTD ACN

Annual General Meeting 19 November 2015 Alexander Molyneux Interim Chief Executive Officer

For personal use only

September Quarter Results Conference Call and Investor Update

PALADIN ENERGY LTD ACN

Paladin Energy Ltd. The New Energy In The Market. May 2010 V

Paladin Energy Ltd. The New Energy in the Market

Langer Heinrich Mining Operation URANIUM MINING - AN INDUSTRY IN CRISIS. John Borshoff, Managing Director/CEO

For personal use only

PALADIN ENERGY LTD The New Energy In The Market John Borshoff, Managing Director Investor CB Presentation February 2008

For personal use only

For personal use only

For personal use only

PALADIN RESOURCES LTD. John Borshoff, Managing Director/CEO Ron Chamberlain, CFO

PALADIN ENERGY LTD ACN

Etango Uranium Project

John Borshoff Managing Director/CEO

PALADIN RESOURCES LTD THE NEW ENERGY IN THE MARKET

Etango Uranium Project

Constructing the Salamanca uranium mine in Western Spain. 121, Cape Town, February 2017

RNI INCREASES GROSVENOR GOLD ORE RESERVES TO 523,000oz

NOT FOR DISSEMINATION IN THE UNITED STATES OF AMERICA

TIRIS URANIUM PROJECT EXPLOITATION LICENCE GRANTED KEY MILESTONE ACHIEVED FOR PROJECT MOMENTUM FOR DEVELOPMENT BUILDING

Toro Energy Limited. Wiluna Uranium Project Western Australia. Australia s Leading Development Stage Uranium Company. PDAC Canada March 2014

As the uranium market tips into the biggest supply deficit in its history, Salamanca is the only major uranium mine being built in the world today

Glencore Finances Matrix into Copper Production Summary

Sourcing the raw materials of the future. Authier Lithium Project JORC Resource Overview ASX: SYA JULY 2016

ANNUAL REPORT. Paladin Energy Ltd

For personal use only

Australian Uranium Conference Fremantle July Weidong Xiang Managing Director

For personal use only

September 2014 Quarterly Results

Graynic Completes Joint Venture for Central American Nickel Assets

For personal use only

INVESTOR PRESENTATION

For personal use only

MEDUSA MINING LIMITED

For personal use only

Goldman Sachs Australia Gold Day 30 May 2013, Sydney. Spencer Cole Manager Investor Relations

For personal use only

For personal use only

GOLD RESERVES INCREASED BY 155% TO 2.15 MILLION OUNCES AT SIMBERI GOLD PROJECT

URANIUM RESOURCES, INC. ENERGY METALS: LITHIUM AND URANIUM

For personal use only

For personal use only

For personal use only

QUARTERLY ACTIVITY REPORT FOR THE PERIOD ENDING 31 MARCH 2014

Nickel West Reimagining the future. Eduard Haegel, 20 October 2016

Company Announcements Office. PNG Chamber of Mines and Petroleum Mining Seminar Wafi-Golpu Joint Venture

Mine Gold. Create Value. Full Year Results for the year ending 30 June 2017

For personal use only

June 2014 Quarterly Results. Sandeep Biswas Managing Director & Chief Executive Officer

For personal use only

For personal use only

AGM PRESENTATION (ASX: MML)

2018 Half Year Financial Results. 22 February 2018

2018 Q1 Conference Call. April 27, 2018

MOROBE EXPLORATION JV UPDATE PNG Mining Conference. Exploration across the Morobe Province

Arafura Resources Limited

Macusani Project Uranium & Lithium in Peru Moving Towards 2020 Production TSX-V:PLU FSE:QG1 OTC:PLUUF

For personal use only

Piauí Nickel-Cobalt Royalty Acquisition

For personal use only

For personal use only

Quarterly Results. June 2015

For personal use only

For personal use only

Please find attached an Open Briefing interview between Perilya Limited and Corporatefile.com.au.

VULCAN RESOURCES AND UNIVERSAL RESOURCES MERGER TO CREATE SIGNIFICANT COPPER-FOCUSSED GLOBAL DEVELOPMENT COMPANY

For personal use only

31 December 2008 Half Year Financial Report

SOUTH AUSTRALIA EXPLORATION AND MINING CONFERENCE STEVEN MCCLARE IIIII GENERAL MANAGER 28 NOVEMBER 2013

Investor Presentation. Jindalee Resources Limited (ASX:JRL) 3 August 2018

Creating a Globally Diversified Uranium Producer. January 2012

For personal use only

Emerging Producer in the. Murchison Goldfields

OTCQX:CROCF. February. completed % U 3 O 8 Cut Off Grade. contained. repetitions. significant the aim of. Gold retains

Hot Chili Raises A$8.1m via Placement

20% Increase in T3 Feasibility Study Plant Throughput to 3Mtpa

Strategies for Evolving Market Conditions Mines and Money Conference & Exhibition March 2013, Hong Kong

June 2013 Quarterly Results. Greg Robinson Managing Director and Chief Executive Officer

14 May 2013 ASX Code: AGS COMPANY PRESENTATION

For personal use only

April NYSE American: URG TSX: URE

For personal use only

Appointment of Mr. Andre Liebenberg to Danakali Board

Australian Nickel Conference 14 October Heron Resources Limited ASX: HRR

For personal use only. Mines and Money London December 2015

CONSOLIDATED ZINC LIMITED ACN INTERIM FINANCIAL REPORT FOR THE HALF YEAR ENDED 31 DECEMBER 2017

Rusina Mining NL ABN Interim financial report for the half-year ended 31 December 2008

ANNUAL GENERAL PRESENTATION

RESOURCES ROUND UP CONFERENCE SYDNEY 10 MAY Trangie Johnston. Managing Director. Broken Hill Prospecting (ASX: BPL) Booth #45

For personal use only

Combination to create the premier ASX mid-tier gold producer

For personal use only

For personal use only

Thackaringa Cobalt Project Pre Feasibility Study

VITAL METALS ANNUAL GENERAL MEETING

HIGHLIGHTS. For the period ended March 2013

Kingsgate Consolidated Limited

Transcription:

PALADIN ENERGY LTD ACN 061 681 098 Ref: 399272 27 August 2015 ASX Market Announcements Australian Securities Exchange 20 Bridge Street SYDNEY NSW 2000 By Electronic Lodgement Dear Sir/Madam June 2015 Full Year Conference Call Presentation Attached please find the presentation in relation to the year end and June quarter results conference call and investor update to be held tomorrow morning at 6.30am Perth time. Full details in relation to the call were announced on 24 August 2015. Yours faithfully ALEXANDER MOLYNEUX Interim CEO Level 4, 502 Hay Street, Subiaco, Western Australia 6008 Postal: PO Box 201, Subiaco, Western Australia 6904 Tel: +61 (8) 9381 4366 Fax: +61 (8) 9381 4978 Email: paladin@paladinenergy.com.au Website: www.paladinenergy.com.au

Annual Results Conference Call and Investor Update 28 August 2015 Alexander Molyneux Chief Executive Officer Craig Barnes Chief Financial Officer Darryl Butcher EGM Technical and Project Development Andrew Mirco GM Corporate Development and Investor Relations

Disclaimer and Notes for JORC and NI 43-101 Mineral Resources and Ore Reserves This presentation includes certain statements that may be deemed forward-looking statements. All statements in this presentation, other than statements of historical facts, that address future production, reserve or resource potential, exploration drilling, exploitation activities and events or developments that (the Company ) expects to occur, are forward-looking statements. Although the Company believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward looking statements include market prices, exploitation and exploration successes, and continued availability of capital and financing and general economic, market or business conditions. Investors are cautioned that any such statements are not guarantees of future performance and actual results or developments may differ materially from those projected in the forward-looking statements. Readers should not place undue reliance on forward-looking information. The Company does not assume any obligation to update or revise its forward-looking statements, whether as a result of new information, future events or otherwise. In the following presentation, for those deposits that are reported as conforming to the Joint Ore Reserves Committee (JORC) 2004 or 2012 code, the terms Inferred Mineral Resources, Indicated Mineral Resources, Measured Mineral Resources, Ore Reserves, Proved Ore Reserves, Probable Ore Reserves and Competent Person are equivalent to the terms Inferred Mineral Resources, Indicated Mineral Resources, Measured Mineral Resources, Mineral Reserves, Proven Mineral Reserves, Probable Mineral Reserves and Qualified Person, respectively, used in Canadian National Instrument 43-101 (NI 43-101). The technical information in this presentation that relates to Exploration Results, Mineral Resources and Ore Reserves is based on information compiled by David Princep B.Sc. and Stephanie Raiseborough B.E., both of whom are Fellows of the Australasian Institute of Mining and Metallurgy. Mr. Princep and Ms. Raiseborough each have sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity that they are undertaking to qualify as Competent Persons as defined in the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves, and as Qualified Persons as defined in NI 43-101. Mr. Princep and Ms. Raiseborough are full-time employees of the Company and consent to the inclusion of the relevant information in this announcement in the form and context in which it appears. Previous tonnages, grades, assays and other technical data relating to the Oobagooma deposit are taken from historical records prior to the implementation of the current NI 43-101. While the data is believed to have been acquired, processed and disclosed by persons believed to be technically competent, they were estimated prior to the implementation of NI 43-101 and are therefore regarded as historical estimates for the purposes of NI 43-101 and as an exploration target for the purposes of JORC disclosure. A Qualified Person as defined in NI 43-101 has not done sufficient work to classify the historical estimate as current Mineral Resources. The Company is not treating the historical estimates as current Mineral Resources as defined in NI 43-101 and for this reason the historical estimates should not be relied upon. At present, the Company considers that these resources have no equivalent classification under NI 43-101 and should therefore be considered as unclassified. The historical information is presented on the basis that it may be of interest to investors. Some of the information in this presentation, in relation to the mineral resources and ore reserves for all deposits except Manyingee and Michelin, was prepared and first disclosed under the JORC Code 2004. It has not been updated since to comply with JORC Code 2012 on the basis that the information that the estimates are derived from has not materially changed since it was last reported. 1

Paladin. A GLOBAL URANIUM LEADER OWNS LANGER HEINRICH, A STRATEGIC TIER ONE MINE HAS OPTIMISATION AS A CORE COMPETENCY PROVIDES BEST SENIOR LEVERAGE TO URANIUM UPSIDE 2

Global Uranium Leader Paladin is the world s only independent pure play uranium miner 27.4 KazAtomProm Annual Capacity 24.5 Mlb Areva 23.5 Cameco 23.5 ARMZ/Uranium One 21.4 Rio Tinto 11.8 BHP Billiton 8.8 Paladin 8.0 Navoi 6.2 Government owned Divisions of diversified companies Integrated with non-mining 3

Langer Heinrich A Strategic Tier One Mine Lowest cost open pit uranium mine in the world US$1.4Bn Cumulative sales revenue +20 Year Mine Life 1 31.6Mlbs Cumulative production 1 At current processing rates 4

Key Achievements for FY2015 Production 5.037Mlbs US$37.0/lb ASP 3.4% above average spot Recovery 87.6% C1 Cash Cost US$29/lb US$26.03/lb June Quarter 2015 US$1.8M Gross Profit US$94.9M increase in cash on hand to US$183.7M Bicarbonate Recovery Plant (BRP) implemented and operating 118% of design 1 Completion of 25% equity sale in LHM to CNNC for US$190M 15% strategic investment by HOPU 2020 CB Issue and repayment of 2015 CB 1 Based on Q4, the first full quarter of production 5

FY2015 Profit & Loss Down 38% Sales revenue US$198.6M 5.367Mlb sold at average realised price of US$37.0/lb Impairments of US$193.1M (after tax) US$180.8M write down of Queensland exploration assets Down 5% Gross Profit US$1.8M Turnaround from FY2014 Gross Loss of US$65.1M Finance costs US$57.0M Down 12% Admin, marketing and non-production costs of US$19.3M Down 30% Exploration expenditure US$5.7M 6

FY2015 Cash Flow US$M Cash and cash equivalents of US$183.7M Cash outflow from operating activities of US$24.7M Cash outflow from investing activities of US$15.6M Cash inflow from financing activities of US$137.6M Operating Activities Investing Activities Financing Activities 7

US$M Capital Management Debt Reduction FY2012 to FY2015 Total debt reduction 1 US$429.6M since June 2012 US$189.9M during FY2015 Next maturity is Q4 FY2017 Outlook for improved operating cash flows Strategic initiatives to be considered Breakdown of Key Debt Instruments 1 US$M LHM Syndicated Facility Agreement 61 Convertible Bonds due April 2017 274 Convertible Bonds due March 2020 150 Total Debt 485 1 Reductions based on face value of debt 8

Optimisation a Core Competency Paladin maintains a world class technical services team focused on cash flow optimisation FY2015 key project delivered was BRP Capital Cost of US$6.8M 93% utilisation in first full quarter of operation likely to achieve >95% Recovery of sodium bicarbonate 118% of design by end of first quarter Total direct cost saving projected to be >US$3/lb (>US$15Mpa) Additional secondary benefits 9

Optimisation a Core Competency FY2016 Cash Flow Optimisation Initiatives All in total expenditure including annualised impact and optimisation initiatives 1 Assumed USD/NAD of 12.60 Vs 11.48 for FY2015 9.6% reduced grade to 694ppm offset by volume increase Mining and processing optimisation: Full-year impact of BRP plus increase in expected performance to over 200% of design Alliance style mining contract Other Controllable costs: Reduction of head office staff and admin costs Exploration on care and maintenance (i.e., minimal spend to meet licence commitments) 1 Includes: Operating cash flows; investing cash flows; and debt servicing (including principal and interest payments on the LHM syndicated facility agreement) 10

Best Leverage to Uranium Upside Uranium is not affected by recent commodity rout 11

Best Leverage to Uranium Upside Uranium has a positive outlook and Paladin has leverage US$/lb Analysts forecast Source: TradeTech for historical spot. Analysts forecast is based on average of 16 analyst forecasts as shown in latest available reports (analysts include: BAML; BMO; Cantor; CIBC; CIMB; Comark; CS; Dundee; JPM; Raymond James; RBC; RFC Ambrian; Salman; Scotiabank; TD; and UBS). 39 48 55 68 Current situation is positive Japan restart commenced 10 August 2017 will see record nuclear power generation 65 reactors under construction 59% in Asia Mined supply reduced 10% in 2014 Higher prices are needed Paladin is leveraged Publicly-listed uranium pure play exposure FY2016 85% spot-related exposure FY2017 & FY2018 almost 100% spot related 12

Strategy 1. Maximise LHM operating cash flows through optimisation initiatives that preserve the integrity of the long-term life of mine plan 2. Maintain KM and exploration on a minimal expenditure, care and maintenance basis 3. Minimise corporate and administrative costs 4. Consider strategic initiatives with respect to partnerships, strategic investment, funding and corporate transactions 13

FY2016 Guidance 5.0-5.4Mlbs Production US$4/lb ASP Premium to spot LHM C1 US$25-27/lb 7-14% lower than FY2015 US$19M Corporate costs, KM care and maintenance and exploration US$14M lower than FY2015 US$6M One-off Restructuring Charges In Q1 FY2016 Sales delivery timing, mine plan and restructuring costs forecast group cash balance US$120-130M 30 September 2015 before rebuilding to finish neutral for FY2016 14

Appendix 15

Langer Heinrich Project Update Production FY2015 5.037Mlb recovery 87.6% Bicarbonate Recovery Project (BRP) commenced April 2015 operating 120% of design positive change to plant performance immediate significant reduction in reagent usage positive impacts in other areas of the plant provide consequential benefits C1 Cost US$29.0/lb Actual FY2015 Actual Jun 15 Qtr Ore processed 3.4Mt 0.89Mt Ore feed grade 768ppm 778ppm Recovery 87.6% 87.8% U 3 O 8 production 5.04Mlb 1.34Mlb C1 Cost being reduced in FY2016 C1 cash cost $25-27/lb Optimisation and innovation for further unit cost reduction further benefits from the BRP project expected other focal areas: process recovery operator training and operating systems process plant utilisation Guidance FY2016 of 5.0-5.4Mlb 16

Pipeline Projects Kayelekera Mine C&M routines established and costs coming down restart feasibility study near completion discharge of water continued successfully during the year Michelin Deposit Canada successfully upgraded Michelin deposit Measured & Indicated mineral resource by 25% to 84Mlb U 3 O 8, with 23Mlb U 3 O 8 remaining in Inferred historic NROP (Non Resident Ownership Policy) exemption granted to Paladin to majority own and develop operation at Michelin Manyingee WA advancing toward Field Leach Trial (FLT) significant project enhancement with new acquisition of Carley Bore 17

Contact Details Head Office Level 4, 502 Hay Street Subiaco Western Australia 6008 PO Box 201, Subiaco Western Australia 6904 Telephone: +61 (0) 8 9381 4366 Facsimile: +61 (0) 8 9381 4978 Email: paladin@paladinenergy.com.au Website: www.paladinenergy.com.au Investor Relations Andrew Mirco Telephone: +61 (0) 8 9423 8162 Mobile: +61-409-087-171 18