Questions and Answers regarding MEAG Power s Vogtle 3 & 4 Project after the crisis in Japan

Similar documents
UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF NUCLEAR MATERIAL SAFETY AND SAFEGUARDS WASHINGTON, DC IN FUEL CYCLE FACILITIES

Information Regarding Status of Construction of Plant Vogtle Units 3 and 4 June 12, 2017

Regulatory Implications of Fukushima for Nuclear Power Plants in the U.S.

Vogtle. Eighth Semi-Annual Construction Monitoring Report. units 3 & 4. February Docket No

Vogtle 3&4. Buzz Miller Executive VP Nuclear Development

FITCH RATES OGLETHORPE POWER CORP., GA 'A-' & REMOVES NEGATIVE WATCH; OUTLOOK STABLE

mew Doc 371 Filed 04/26/17 Entered 04/26/17 19:07:57 Main Document Pg 1 of 9 : :

DIRECT TESTIMONY OF STEVEN D. ROETGER, WILLIAM R. JACOBS, JR PH.D, MARK D. RAUCKHORST AND DAVID P. POROCH,

Information Regarding Status of Construction of Plant Vogtle Units 3 and 4 September 1, 2017

Regulations on Severe Accident in Korea

México D.F., 7 Mayo 2013 NRILTD NUCLEAR RISK INSURERS LIMITED

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Washington, D. C FORM 8-K CURRENT REPORT

Regardless of the ownership model, however, the costs of providing service, with only a few exceptions, are covered by the customer.

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Washington, D. C FORM 8-K CURRENT REPORT

Making Victims Whole: Compensation of Nuclear Incident Victims in Japan and the United States

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Washington, D. C FORM 8-K CURRENT REPORT

Responses to Investor Questions - September 24, 2018

Outline. Introduction FLEX strategy in Taiwan Methodology Failure Probability of FLEX Case Study and Results Conclusion 核能研究所

Fiscal Year 2013 Budget and Long Range Plan Columbia Generating Station. Brad Sawatzke VP, Nuclear Generation/CNO March 20, 2012

UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C FORM 10-Q

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Washington, D. C FORM 8-K CURRENT REPORT

UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 8-K

Methods and Applications of Risk Assessment

Uranium Participation Corporation Annual Management Report of Fund Performance February 28, 2011

Southern Company Conference Call. May 21, 2018

UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 8-K

Detailed Resilience Pledge

mew Doc 770 Filed 06/23/17 Entered 06/23/17 22:22:36 Main Document Pg 1 of 9

NIPPON EXPORT AND INVESTMENT INSURANCE GUIDELINES FOR INFORMATION DISCLOSURE CONSIDERATIONS FOR NUCLEAR SECTOR PROJECTS IN TRADE INSURANCE

Pre-Earthquake, Emergency and Contingency Planning August 2015

Insights. Japan Earthquake. Insurance Industry Impact and Risk Management Lessons. Background

Fiscal 2011 has been a year of growth in our uranium holdings and strengthening in the spot price of uranium.

SCANA Nuclear Strategy Presentation

SUPPLEMENTAL/COMPLÉMENTAIRE CMD: 12-M23.B

Analysis of the Macroeconomic Impact of the Tohoku-Pacific Ocean Earthquake

One Month after the Great East Japan Earthquake: Critical Role of Financial Infrastructure

Social Safety Nets Adaptive to Natural Disasters

INTRODUCTION TO NATURAL HAZARD ANALYSIS

David Landry, P.Eng, Cameco Corporation. Nuclear Energy: Industry update and the implications for fluorspar

PREDICTING EARTHQUAKE PREPARATION: SMALL BUSINESS RESPONSES TO NISQUALLY

The Impacts of Construction and Operation of Three Generation Alternatives on the Economy of the Commonwealth of Virginia

Legal Challenges in US New Reactor Licensing

Plant Vogtle Additional Units 3 and 4 (Project) Amended and Restated Power Purchase Agreement Between MEAG and JEA (PPA)

Disaster, Social Fairness, and Social Status: Damage and Social Consciousness after the Great East Japan Earthquake

Commissioner Baran s Comments on SECY , Draft Final Rule Mitigation of Beyond-Design-Bases Events

Entergy s Spent Fuel Storage. What is the Litigation All About? How to Store Pilgrim s Spent Nuclear Fuel?

REINSURANCE FOCUS: SPECIAL FOCUS

(Act No. 48 of June 27, 2012)

Tokyo Electric Power Company Holdings, Incorporated

Financial Contents. Southern Company 2017 Annual Report

Financial and Corporate Information

Consolidated Five-Year Summary

PG&E CORPORATION REPORTS FIRST QUARTER PERFORMANCE; ADJUSTS OUTLOOK FOR FULL-YEAR 2011 RESULTS; FORGOES DIVIDEND INCREASE IN 2011

Financial Report. CHUBU ELECTRIC POWER COMPANY, INCORPORATED (April 28, 2015) Stock Code: 9502

Financial Report. CHUBU ELECTRIC POWER COMPANY, INCORPORATED (April 26, 2013) Stock Code: 9502

Japanese Aftershocks. Summary

First Quarter 2018 Earnings Conference Call. May 2, 2018

the Great East Japan earthquake

Having regard to the Treaty establishing the European Atomic Energy Community, and in particular Articles 31 and 32 thereof,

NUCLEAR NEW BUILD: INSIGHTS INTO FINANCING AND PROJECT MANAGEMENT. Dr. Jan Horst Keppler, Senior Economic Advisor NEA Nuclear Development Division

FY2017 Financial Results (April 1, 2017 March 31, 2018)

S P E C I A L C I R C U L A R

h-;f(t- Belton T. Zeie{al \-/ Partner

Quantitative Risk Assessment Process of Fuel Assembly Retrieval from Spent Fuel Pool in Fukushima Daiichi Nuclear Power Plant Decommissioning

NB Power Licence Renewal Intervention CNSC Hearing Notice No H-02

South Carolina Public Service Authority September 27, 2017 Investor Communication

By Lynne Holt, Paul Sotkiewicz, and Sanford Berg 1. April 8, Abstract. I. Background

South Carolina Electric & Gas Company ("SCE&G" or the "Company") hereby

An Insurance Perspective on Recent Earthquakes

MUPSA Methodology: Future Developments & Safety Goals

Equity Market Commentary 14 March 2011

Meeting Transcript (Presentation) Event Date/Time: April 30, 2014 Event Name: TEPCO Investor Meeting for FY2013 Earnings Results

STRATEGIC PLAN, Rev. 0 Nov. 2009

CAPITAL EXPENDITURES NUCLEAR OPERATIONS

Notice Concerning Issuance of New Shares, Disposition of Treasury Shares. and Secondary Offering of Shares

BEFORE THE GEORGIA PUBLIC SERVICE COMMISSION STATE OF GEORGIA

COLUMBUS, Georgia February 5, 2013 Aflac Incorporated today reported its fourth quarter results.

2018 General Rate Case. Power Supply (PS) Volume 01 Nuclear (Palo Verde)

TiPEEZ System for Information management against earthquake, tsunami and nuclear disaster, considering nuclear communication

Lessons from the Great East Japan Earthquake: Impacts on Payment and Settlement Systems

Presentation Notes for the Raymond James 37th Annual Institutional Investors Conference

a GAO GAO NUCLEAR REGULATION NRC Needs More Effective Analysis to Ensure Accumulation of Funds to Decommission Nuclear Power Plants

mew Doc 4 Filed 03/29/17 Entered 03/29/17 09:07:49 Main Document Pg 1 of 109

SOUTHERN CO FORM 8-K. (Current report filing) Filed 01/29/15 for the Period Ending 01/29/15

The Licensees identified in Attachment 1 to this Order hold licenses issued by the

COUNCIL OF THE EUROPEAN UNION. Brussels, 4 June /14 Interinstitutional File: 2013/0340 (NLE) ATO 45

AFLAC INCORPORATED ANNOUNCES THIRD QUARTER RESULTS, INCREASES QUARTERLY CASH DIVIDEND, AFFIRMS 2011 AND 2012 OPERATING EPS TARGETS

Fiscal Year 2017 Columbia Generating Station Annual Operating Budget

Fourth Quarter 2018 Earnings Conference Call. February 20, 2019

Getting ahead of the next Big One The future of disaster insurance in New Zealand

Southern Company. 2nd Quarter 2018 Earnings. June 30, 2018

Recent Changes of Safety Regulation in Korea

Guide. Commission Recommendation

Hazard Mitigation FAQ

mew Doc 1172 Filed 08/17/17 Entered 08/17/17 15:11:35 Main Document Pg 1 of 11

Fiscal Year 2018 Columbia Generating Station Annual Operating Budget

Exhibit No.: Witnesses: SCE-06 Paul Hunt 338-E) Before the. July 22, 2013

Tohoku Pacific earthquake and Economic Indicators: a

Accounting for the effects of natural disasters under IFRS Japan

Cautionary Statement Regarding Forward-Looking Statements

Transcription:

Questions and Answers regarding MEAG Power s Vogtle 3 & 4 Project after the crisis in Japan March 15, 2011 (Source MEAG Power) 1. How do MEAG Power, Georgia Power, Oglethorpe Power, and the City of Dalton (the co-owners) feel about Plant Vogtle Units 3 & 4? Do all co-owners remain committed? We are deeply saddened by the impact of the natural disaster on the Japanese people. We also have been following the events transpiring around the nuclear facilities. MEAG Power and the co-owners take very seriously our commitment to safe operation of nuclear energy facilities and we will incorporate lessons learned based on this experience into our safety and operating procedures. Based on what we know now, we do not expect the events unfolding in Japan to have significant impacts on our Vogtle 3 and 4 construction and licensing effort. Targeted commercial operating dates for Units 3 and 4 remain 2016 and 2017 respectively. The owners remain committed to the project. 2. Are the Vogtle units (current and planned) located near a fault line? If so, what magnitude earthquake was assumed in the plant designs? How strong of an earthquake could MEAG Power s plants withstand? Plant Vogtle is located in an area deemed to be low activity zones for seismic activity but is still designed for earthquake ground motions of 0.3 g (g = the force of gravity) and evaluated for earthquakes up to 0.5 g. The seismic evaluation encompassed the most severe earthquake for the site that might occur once in 10,000 years. In comparison, the Fukushima Daichii facility is believed to be designed for 0.18g ground motion and the earthquake created maximum acceleration estimated at 0.35g. 3. Will this delay the COL? Today s NRC licensing processes, including those for the Vogtle AP1000, fully evaluates such issues as severe earthquakes, tsunamis, station blackouts, and long-term core cooling capability. The AP1000 design provides significant advances in many of these areas. The safety of this design applied at the Vogtle site has been fully evaluated and meets or exceeds requirements. The AP1000 enhanced design and the rigorous regulatory reviews already performed give us confidence that the licensing process can remain on schedule. Southern Company and the Plant Owners recognize that significant NRC resources may be required to monitor and evaluate this event and to address any lessons learned. Fortunately, the NRC has a separate division, the Office of New Reactors, dedicated to supporting the new licensing process for Vogtle 3 & 4. 4. What impact will the Japanese nuclear situation have on the Vogtle 3 & 4 projects? Any additional costs and delays anticipated? Based on what we know now, we do not expect the events unfolding in Japan to have significant impacts on our Vogtle 3 & 4 construction and licensing effort. Targeted commercial operating dates for Vogtle 3 & 4 remain 2016 and 2017 respectively.

5. What is the current status of licensing for Plant Vogtle Units 3 & 4? On December 2, 2010, Westinghouse submitted an AP1000 Design Certification Amendment (DCA) to the NRC. On February 10, 2011, the NRC announced that it was seeking public comment on a proposed rule to approve the DCA and amend the certified AP1000 reactor design for use in the U.S. The Advisory Committee on Reactor Safeguards also issued a letter on January 24, 2011 endorsing the issuance of the COL for Vogtle Units 3 & 4. MEAG Power currently expects to receive the COL for Vogtle Units 3&4 from the NRC in late 2011 based on the NRC s February 16, 2011 release of its COL schedule framework. 6. Could what happened in Japan happen at Vogtle Units 3 & 4 too? Our facilities have been designed in accordance with NRC requirements related to natural events such as earthquakes, tornadoes, flooding (including tsunamis) and hurricanes. These requirements ensure that the plants can be safely shutdown and maintained in shutdown status after these events. The NRC requirements provide a design margin above historical event levels. Fukushima Daichii suffered damage from the tsunami primarily due to flooding of its power systems. The location of MEAG Power s plants would result in the dissipation of any tsunami that reached the Atlantic coast of the United States before it reached the site. The Japanese tsunami traveled 6 miles inland. Plant Vogtle is approximately 130 miles from the coast at an elevation of approximately 220 feet above sea level. The distance inland and elevation of the Vogtle site would protect the facilities from tsunamis substantially larger than the maximum probable used in the design. The AP1000 design includes passive safety systems that rely on gravity, natural circulation, convection, compressed gas and condensation to maintain safe operation and shut down safety. Many of the enhanced features of the AP1000 design are specifically intended to eliminate the dependence upon mechanical and electrical support systems to keep the fuel cool during an event. 7. How is the NRC reacting to the news regarding the Fukushima Daiichi Nuclear Plant in Japan? There has been no indication from the NRC that the events involving the nuclear units in Japan will adversely impact the current licensing schedule for Vogtle Units 3 & 4. The NRC has confirmed that although significant resources may be required to monitor and evaluate the events in Japan, it has a separate division, The Office of New Reactors, dedicated to support the licensing process for the new Vogtle Units. 8. What is the current status of completion of Vogtle 3 & 4 based on percentage of the EPC contract that has been fulfilled to nearest date? At the end of 2010, the project was approximately 30% complete based on payments versus the spending curve. Equipment Procurement is the major effort at this stage of the project.

9. What would be the impact of a substantial delay (1 to 2 years?) of receiving the COL for Vogtle Units 3 & 4? What is the impact of a commercial operation date delay? A delay in the issuance of the COL would likely extend the construction timeline by a timeframe equal to the delay and therefore result in an equivalent delay in the commercial operation date, as well as result in additional capital needs to fund any cost increases and capitalized interest on the bonds issued to finance the project through the revised commercial operation dates. 10. What would be the impact of a potential cancellation of Vogtle Units 3 & 4 in terms of construction cost expended and adequacy of MEAG Power's power supply? As previously set forth in the Official Statements related to the Vogtle Projects M, J and P, MEAG Power has examined certain risk scenarios to determine the impact of cancellation of Vogtle Units 3 & 4 on the projected cost of power in 2026, the year when MEAG Power would have to place in service another generating resource in the event Vogtle Units 3 & 4 are cancelled. Such examination involved projections by MEAG Power of the cost of power in 2026 in each of the following circumstances: - Vogtle Units 3 & 4 are placed in service on time and budget (the Base Case Projection ); - Vogtle Units 3 & 4 are cancelled at the end of 2011 due to the failure to receive the COL by such time and a 300 MW combined cycle generating unit has been financed and placed in service by MEAG Power by 2026, the year when its full output is needed (the First Risk Scenario Projection ); and - Vogtle Units 3 & 4 are cancelled at the end of the construction period due to the failure of the units to achieve commercial operation and a 300 MW combined cycle generating unit has been financed and placed in service by MEAG Power by 2026, the year when its full output is needed (the Second Risk Scenario Projection ). In the preparation of its projections of the cost of power in 2026, MEAG Power has made certain assumptions with respect to conditions that may occur in the future. See COMPETITION Certain Responses of MEAG Power to Competition Planned Resources: Vogtle Units 3&4 Projects Impact of Certain Risk Scenarios on Projected Cost of Power in 2026 in the Updated Annual Information Statement dated February 17, 2010 and available on MEAG Power s website. While MEAG Power believes the assumptions were reasonable at the time for the purpose of such projections, the assumptions are subject to a number of risks and uncertainties, some of which are beyond MEAG Power s control, and therefore actual conditions may differ substantially from those assumed. In addition, MEAG Power has relied upon certain information and assumptions provided to it by others. While MEAG Power believes the sources to be reliable, it has not independently verified the information and offers no assurances with respect thereto. Based on the considerations and assumptions referred to above: - under the Base Case Projection, (a) the projected average unit cost of power purchased from MEAG Power and SEPA by the Participants is 7.62 cents/kwh and (b) at the retail level, the projected average unit cost of power purchased from the Participants by all customers is 11.1 cents/kwh;

- under the First Risk Scenario Projection, (a) the projected average unit cost of power purchased from MEAG Power and SEPA by the Participants is 8.82 cents/kwh and (b) at the retail level, the projected average unit cost of power purchased from the Participants by all customers is 12.3 cents/kwh; and - under the Second Risk Scenario Projection, (a) the projected average unit cost of power purchased from MEAG Power and SEPA by the Participants is 9.12 cents/kwh and (b) at the retail level, the projected average unit cost of power purchased from the Participants by all customers is 12.6 cents/kwh. These projections of average unit cost of power purchased from the Participants compare favorably to the 2026 national All Sectors Average End-Use Price of 12.9 cents/kwh as projected by the U.S. Energy Information Administration Annual Energy Outlook 2010 Early Release Overview dated December 14, 2009. In summary, given the sensitivities which were run and based on the assumptions used, in the unlikely event the Project were cancelled the result show that MEAG Power would still remain competitive. MEAG Power and the Co Owners expect that the Project will move forward as planned and we are committed to the Project. 11. What would be the cost responsibilities of MEAG Power versus JEA and MEAG Power versus PowerSouth pursuant to the respective PPAs for Project J and Project P if Vogtle Units 3 & 4 were cancelled? If the plant is cancelled all together, then JEA and Power South continue to be responsible for the first 240 months of payment of both interest and principal components of Debt Service of projects J and P, respectively, subsequent to the commencement of billing by MEAG Power. Thereafter, the MEAG Power Participants assume responsibility for payment of the Debt Service until 2058 or until the bonds are paid in full, whichever event first occurs. Any cost of acquisition and construction not financed through bond proceeds will be allocated between JEA and the MEAG Power Project J Participants on a 50/50 basis. The same allocation applies to Power South and the MEAG Power Project P Participants as to cost of acquisition and construction not financed through bond proceeds. The obligations of the MEAG Power Participants, JEA and Power South supporting Project M, Project J and Project P are supported by take or pay, court validated contracts, which are unconditional obligations to pay regardless of the status of the Vogtle Unit 3 & 4. In addition, MEAG Power Participants obligations include a general obligation pledge of the Participants supporting their respective responsibilities under the contracts. 12. Does this make MEAG Power contemplate accessing the Federal guarantees sooner than anticipated? The events in Japan do not affect our planning with regards to the planned timing of accessing the DOE Loan Guarantee Program. 13. Can unspent proceeds from the 2010 Vogtle 3 & 4 transactions be used for other purposes (i.e. to build a gas plant)? No, the proceeds may only be used for Vogtle 3 & 4 expenditures

14. How much of the BABs proceeds have been spent? Approximately $550 million of bond proceeds have been spent through February 28, 2011. 15. How are the unspent proceeds invested? Asset Type Market Value Account Market Value US Federal Agency $ 1,789,348,158.34 Construction $ 1,238,217,035.44 US Treasury 11,533,500.66 Nuclear Fuel 69,163,274.26 Government Backed Money Market Mutual Funds 31,480,944.38 Temporary Liquidity Guarantee Program Bonds 270,266,695.97 Capitalized Interest 654,682,161.38 Debt Service Reserve 140,566,828.27 TOTAL $ 2,102,629,299.35 TOTAL $ 2,102,629,299.35 Projects Market Value Maturities Market Value Project M $ 808,096,682.79 Less than 1 Year $ 561,285,418.81 Project J 978,743,572.44 1 to 3 Years 946,428,829.72 Project P 315,789,044.12 3 to 5 Years 477,627,927.57 TOTAL $ 2,102,629,299.35 5 to 7 Years 111,747,873.25 7 to 10 Years 5,539,250.00 TOTAL $ 2,102,629,299.35 16. Has MEAG Power spoken to JEA and PowerSouth since the situation in Japan began to unfold? What are the feelings from JEA and PowerSouth about Plant Vogtle Units 3 & 4? We have provided continuing updates to both JEA and PowerSouth regarding the situation in Japan on an ongoing basis. MEAG Power, JEA and PowerSouth remain fully committed to the project.