For personal use only

Similar documents
For personal use only

For personal use only LARGE FLAKE GRAPHITE PRODUCTION & MARKETS AUSTRALIAN ENERGY & BATTERY MINERALS INVESTOR CONFERENCE MARCH 2018

Large-Flake Graphite Production and developing Expandable Graphite Manufacturing

For personal use only. Opera&ng, op&mising and expanding the Graphmada large flake graphite mine in Madagascar. Investor Presenta,on March 2017

For personal use only

The challenge of bringing a new mine into production stratminglobal.com

Achmmach Tin Project, Morocco DFS complete, Funding Underway. Melbourne Mining Club, 17 July 2018 Russell Clark, CEO

ANNUAL GENERAL PRESENTATION

TERRAMIN AUSTRALIA LIMITED. Annual General Meeting

SOUTH AUSTRALIA EXPLORATION AND MINING CONFERENCE STEVEN MCCLARE IIIII GENERAL MANAGER 28 NOVEMBER 2013

Sourcing the raw materials of the future. Authier Lithium Project JORC Resource Overview ASX: SYA JULY 2016

For personal use only

September Quarterly Report

For personal use only

For personal use only

ALTURA MINING LIMITED ANNUAL GENERAL MEETING

Achmmach Tin Project, Morocco DFS complete, Funding Underway. IMARC, 31 October 2018 Russell Clark, CEO

VITAL METALS ANNUAL GENERAL MEETING

Pathway to Production

MAHENGE BEST IN CLASS GRAPHITE PROJECT. 121 Mining Investment Cape Town

Panda Hill Niobium Project. January 2014

NOT FOR DISSEMINATION IN THE UNITED STATES OF AMERICA

Wetar Development Update - Mobilisation HIGHLIGHTS

Valence Industries Australia s Only Graphite Producer

For personal use only

HALF YEAR 2017 RESULTS PRESENTATION 16 FEBRUARY 2017

Half Yearly Update. February 2016

TERRAMIN AUSTRALIA LIMITED. Annual General Meeting

Syrah Resources and Graphite Market JP Morgan Clean Energy Conference 17 May Shaun Verner, Managing Director & CEO

WODGINA ORE RESERVE COMMENTARY

For personal use only

Investing in Tin Seminar London 5 th December 2011

Strong progress on construction at Montepuez

Glencore Finances Matrix into Copper Production Summary

MEDIA RELEASE. OCEANAGOLD HAILE OPTIMISATION STUDY DELIVERS ENHANCED VALUE (All financial figures in US Dollars unless otherwise stated)

Strong progress on construction and supply contracts puts Battery Minerals on track for commissioning in November

An alternative coal developer in 2012 & producer in 2013

AZUMAH MINING LEASES GRANTED

ALLIANCE RESOURCES L I M I T E D

Kilmain Project Collaborative opportunities in Queensland for exploration, resource development and investment with JOGMEC Presentation Colin

For personal use only

QUARTERLY REPORT OCTOBER TO DECEMBER 2014

For personal use only

QUARTERLY REPORT APRIL TO JUNE 2014

Broadening Base Creating a unique mineral sands company. Africa Down Under Conference 30 August 2018

CINOVEC a globally significant previously mined lithium deposit in the heart of Europe

INVESTOR PRESENTATION. August 2018

PRODUCING AND EXPLORING Q WEBCAST

Summary of information Not Financial Product Advice Disclaimer Forward-Looking Statements Not an Offer No Distribution in the US

For personal use only

MEDIA RELEASE OCEANAGOLD UPDATES DIDIPIO NI TECHNICAL REPORT

TIRIS URANIUM PROJECT EXPLOITATION LICENCE GRANTED KEY MILESTONE ACHIEVED FOR PROJECT MOMENTUM FOR DEVELOPMENT BUILDING

For personal use only

For personal use only

For personal use only

For personal use only

Developing an Advanced Lithium Project in Quebec, Canada

FUNDING TO COMMENCE PHASE II EXPANSION

Westgold Resources Limited Australia s Newest Gold pure-play. Denver Gold - September 2016

For personal use only

For personal use only. ASX Code: GMM

6 September 2017 AFRICA DOWN UNDER AMENDED PRESENTATION

20% Increase in T3 Feasibility Study Plant Throughput to 3Mtpa

Authier Lithium Project Advances to the Definitive Feasibility Stage

Dragon Mining A Decade of Nordic Gold Production

For personal use only

Offtake and Mining FINNISS LITHIUM PROJECT

DRAGON MINING LIMITED An Established Nordic Gold Producer with an Exciting Future RIU Melbourne Resources Round-up 29 September 2011

Quarterly Activities Report For The Period Ending 30 September 2018

For personal use only

Kasbah Resources. Russell Clark Chief Executive Officer. Achmmach: One of the few build ready tin projects in a secure location

Dragon Energy Limited

The Yamarna Gold Belt: Exploration Upside To Be Funded From Production

QUARTERLY ACTIVITIES REPORT September 2017

US$335,000, % Senior Secured Notes Due 2018 (Issued February 2011) Nomura Fixed Income Corporate Day 15 November 2012

For personal use only

Bass Metals (BSM) COMPANY REPORT INITIATION OF COVERAGE. Starting small in graphite

For personal use only

RAMELIUS APPROVES VIVIEN GOLD MINE

Developing NT s First Lithium Resource

Paulsens Project resource soars 41% to 318,000oz as 2012 surplus cashflow forecast hits $35m

DRAGON MINING LIMITED An Established Nordic Gold Producer with an Exciting Future Fennoscandian Exploration and Mining Conference 3 November 2011

For personal use only. AGM Presentation. November 2016

Developing First Lithium Resource in NT

An Australian gold miner for global investors WA Mining Club - May 2018

MERGER PRESENTATION JULY 2018

Company Announcements Office. Subject: Australia Papua New Guinea Business Forum Golpu Project Update

For personal use only

Mine Gold. Create Value. Full Year Results for the year ending 30 June 2017

PERFORMANCE UPDATE FROM HILLGROVE'S KANMANTOO OPERATION GREG HALL IIIII CEO & MANAGING DIRECTOR 1 MAY 2013

Emerging Producer in the. Murchison Goldfields

Presentation Annual General Meeting 29 October 2014

Minerals for a sustainable future

For personal use only

Wetar Copper Project Expansion Update - Commencement

MALINGUNDE GRAPHITE PROJECT

JUNE 2018 QUARTERLY ACTIVITIES REPORT

For personal use only

SYDNEY MINING CLUB FEBRUARY 2019 DUNCAN GIBBS MANAGING DIRECTOR & CEO

An Australian gold miner for global investors BMO Conference - February 2018

Transcription:

GRAPHMADA GRAPHITE MINE OPERATIONAL UPDATE HIGHLIGHTS Bass Metals Ltd nearing completion of Stage 1 of the optimisation program: the establishment of 6000 tonnes per annum (tpa) production of premium graphite concentrates at its 100% owned Graphmada Large Flake Graphite Mine. Major processing equipment items have now arrived in Madagascar. Process Plant civil works are nearing completion, to time with the release from customs of the major equipment items. Modular Dryer System (MDS) construction has commenced and is on time and budget, with expected commissioning in November 2017. Prices for graphite concentrates in Bass intended end markets have improved materially over the last 2 quarters. Figure 1: The commencement of MDS installation; laying out of frames, completion of structural footing, and control room construction nearing completion.

Bass Metals Limited (ASX: BSM ) (the Company ) is pleased to provide an update on its optimization and refurbishment of the Graphmada Graphite Mine, located in Madagascar. MINE HEALTH AND SAFETY UPDATE The Company is pleased to report that whilst the optimization and refurbishment of the mine has been in progress no Lost Time Injuries have been reported. The Company continues its focus of applying sound safety management practices to its activities and maintains its strategy of engineering a safe operating environment into the refurbishment of the mine. OPTIMISATION & REFURBISHMENT PROGRAM UPDATE Refurbishment works continue as planned with the program on budget and on schedule. Significant actions undertaken since the last Operational Update include: ü Processing plant equipment shipped and in Madagascar awaiting customs clearance; ü Manufacture of new pumps complete and shipped to Madagascar; ü All procedures for heavy load transport of equipment to site arranged; ü On site off-loading safety procedures finalised; ü Plans for refurbishing electrical control room and plant offices finalised; ü Manufacturing of all electrical control boards and cables in progress; ü Final plan for electrical cabling routing confirmed; ü Extension of the existing generator shed to accommodate electrical distribution boards in progress; ü Process Plant civil works nearing completion in time for the arrival onsite of major processing equipment items; ü Integration between old and new floatation cells complete and water fill test successful; ü Floatation cells piping and material flow connection work underway; ü Refurbishing of previously used plant pumps underway;

ü Surge bins, pumps and piping installation underway. ü All civil work to accommodate Modular Dryer System (MDS) complete; ü Assembly and erection of MDS components in progress; ü MDS electrical control room nearing completion; ü Manufacturing of dry sorting and screening equipment complete; ü Graphite size fraction storage bins complete; ü Mahefadok mine planning underway; ü Planning for extended stockpile area revised and confirmed. Figure 2: Completed flotation recycle bins installed.

Figure 3: MDS installation underway. SALES & MARKET UPDATE The mine currently has 298 tonnes of graphite concentrates in stock. The Company is negotiating the sale ofthis stock as part of maintaining regular supplies to Graphmada s main customers. Small samples have also been dispatched from existing stock to potential new customers who are enquiring as to Graphmada s plans to supply natural flake graphite in 2018. Most interest is centred on the large to very large flake size concentrates as the market continues to see a significant decrease in supply in these flake sizes. Table 1: Current Stock GRADE FC% Mesh Size +50-50+80-80 -100 <85 1 85-90 45 78 10 90-94 13 43 69 36 >94 1 TOTAL 14 88 150 46 A total of 298 tonnes product.

Prices for graphite concentrates in Bass intended end markets have improved materially over the last 2 quarters due to weakening supply out of China from the continued environmental crack downs, particularly in the use of coal in drying closing many factories in Shandong. Reports also indicate that Expandable Graphite usage is increasing significantly in China due to recent legislative changes in the use of fire retardants. Prices are expected to continue to rise in the coming months particularly for large flake sizes with FC > 94%, the target of optimized production activities at Graphmada. Figure 4: 6 month flake graphite prices. BASS METALS CEO, MR TIM MCMANUS: We are nearing completion of Stage 1 of our optimization and refurbishment of the Graphmada Mine and aim to ramp up production from late 2017 through to early 2018 to reach 500 tonnes a month of high-value graphite concentrates (Stage 1: 6000 tpa run-rate). As the only industrial minerals company on the ASX capable of entering all graphite market segments at premium pricing levels, and with pricing continuing to grow by double figures month on month, the Company is experiencing significant enquires for its future production, particularly in the larger flake sizes.

As such the team at Bass remains encouraged that our strategic timing to re-commission the Graphmada Mine will prove to add significant value to all shareholders and provide an excellent base to implement a Stage 2 expansion to 20,000 tpa. For more information, please contact: Tim McManus Chief Executive Officer Phone: (07) 3203 5894 Email: admin@bassmetals.com.au Peter Wright Director Phone: (07) 3203 5894 Email: admin@bassmetals.com.au Please visit us at: www.bassmetals.com.au

ASX ANNOUNCEMENT 19 JUNE 2017 ABOUT THE GRAPHMADA JUMBO FLAKE GRAPHITE MINE Bass Metals Ltd. is one of only three publicly listed graphite producers in the world. The Company 100% owns and operates the Graphmada large flake graphite mine, Bass flagship project, located in eastern Madagascar. Madagascar has been a recognized producer and exporter of premium graphite for over 100 years and sets the world standard for product quality and flake size. The Graphmada mine has 40-year mining permits in place, containing four premium quality, large flake, graphite deposits hosted in weathered graphitic gneiss, a soft, easily minable rock that incurs low mining costs. With all associated mining infrastructure and logistics in place, the mine currently produces and sells a range of graphite concentrates into multiple market segments, to customers in India, the United States and Europe. With the aim of generating revenue through lowest quartile cost production, the mine is currently being optimized by an experienced management team to 6000 tonnes per annum (Stage 1) with improved final graphite concentrate grades, in order to grow cash margins. Graphmada also has significant potential for low capital intensity expansion. Bass plans to invest capital to expand production to greater than 20,000 tonnes per annum (Stage 2) of graphite concentrate sales by 2019. In addition to exploring the greater mineralization potential of Madagascar, the Company has also made the strategic decision, in parallel with the optimization of Graphmada, to actively explore and develop deposits in the immediate proximity to the mine, to materially expand its resource inventories. The Loharano deposit has provided the bulk of the feed to the Graphmada processing plant and has total JORC compliant Indicated and Inferred resources of 5.7Mt @ 4.1% Grade with a 2% cut-off 1. This mineralization is known to go to depth with increasing grade, and is open in all directions. With the Company having a strong community engagement program and being well down the path in achieving its optimisation plans and growing its resource inventory, the team at Bass is confident of its plans for expansion and its future value creation for shareholders. 1 These estimates were prepared and first disclosed by Stratmin Global Resource PLC under the JORC Code 2004. The estimates have not been updated to JORC Code 2012 on the basis that the information has not materially changed since it was last reported. Reference is made to the Company's announcement of 2 September 2015, which provides further detail regarding this information.

ASX ANNOUNCEMENT 19 JUNE 2017 DISCLAIMER & CAUTIONARY STATEMENTS DISCLAIMER This document has been prepared by Bass Metals Limited (the Company ). It should not be considered as an invitation or offer to subscribe for or purchase any securities in the Company or as an inducement to make an invitation or offer with respect to those securities. No agreement to subscribe for securities in the Company will be entered into on the basis of this document. This document is provided on the basis that neither the Company nor its officers, shareholders, related bodies corporate, partners, affiliates, employees, representatives and advisers make any representation or warranty (express or implied) as to the accuracy, reliability, relevance or completeness of the material contained in the document and nothing contained in the document is, or may be relied upon as a promise, representation or warranty, whether as to the past or the future. The Company hereby excludes all warranties that can be excluded by law. FORWARD LOOKING STATEMENTS This document may contain certain forward-looking statements. Such statements are only predictions, based on certain assumptions and involve known and unknown risks, uncertainties and other factors, many of which are beyond the Company s control. Actual events or results may differ materially from the events or results expected or implied in any forward-looking statement. The inclusion of such statements should not be regarded as a representation, warranty or prediction with respect to the accuracy of the underlying assumptions or that any forward looking statements will be or are likely to be fulfilled. The Company undertakes no obligation to update any forward-looking statement to reflect events or circumstances after the date of this document (subject to securities exchange disclosure requirements). The information in this document does not take into account the objectives, financial situation or particular needs of any person. Nothing contained in this document constitutes investment, legal, tax or other advice. COMPETENT PERSON STATEMENT The information in this document that relates to Exploration Results is based on information compiled by Tim McManus, a Competent Person who is a member of the Australasian Institute of Mining and Metallurgy and a full-time employee of the Company. Tim McManus has sufficient experience that is relevant to the style of mineralisation and type of deposit under consideration and to the activity being undertaken to qualify as a Competent Person as defined in the 2012 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Tim McManus consents to the inclusion of the information in this document in the form and context in which it appears.