PJM & MISO Assumptions and Criteria for Testing of New Resources

Similar documents
Generation Retirement Scenario Special Assessment Update

EIPC Roll-Up Report & Scenarios

Year Assessment Preliminary Study Design

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS

TRANSMISSION OWNER ZONAL PLACEMENT PROCESS

1. Title: Qualified Transfer Path Unscheduled Flow (USF) Relief

NPCC 2017 MARITIMES AREA INTERIM REVIEW OF RESOURCE ADEQUACY

FAC Facility Interconnection Studies

Risk Assessment & Mitigation. FRCC Fall Compliance Workshop November 10 12, 2015

Appendix C-2. Entergy Arkansas, Inc. May 26, 2016

Long-Term Reliability Assessment

Generation Retirement Scenario

Appendix C-2 DRAFT. Entergy Services, Inc. May 6July 13, 2016

Cost Allocation Reform Update

Cost Allocation Principles for Seams Transmission Expansion Projects

Injection / Withdrawal CARP

SPP s Operating Region

Standard FAC Facility Ratings. A. Introduction

FTR Credit Requirements Prevailing Flow Paths Affected by Transmission System Upgrades

NTTG REGIONAL TRANSMISSION PLAN. December 30, 2015

Reliability Pricing Model

Transmission System Expansion Cost Allocation Alternatives for Renewable Resources. Cost Allocation Working Group March 26, 2008 OG&E Ver 2 3/20/8

Effective for SERC Region applicable Registered Entities on the first day of the first calendar quarter after approved by FERC.

Comparison of Performance-Based Capacity Models in ISO-NE and PJM June 2, 2016

2017 OMS MISO Survey Results June 2017

BAL Disturbance Control Standard Contingency Reserve for Recovery from a Balancing Contingency Event

MVP Postage Stamp Cost Allocation and Portfolio Requirement Regional Expansion Criteria and Benefits Working Group. September 28, 2017

TNUoS Tariffs in 10 minutes March 2018

BAL-002-2(i) Disturbance Control Standard Contingency Reserve for Recovery from a Balancing Contingency Event

Available To owners of Qualifying Facilities ( QF ) making sales of electricity to the Company in the State of Oregon.

MISO Planning Process. May 31, 2013

BAL Frequency Response & Frequency Bias Setting Standard

SPP PLANNING AND COST ALLOCATION OVERVIEW

Stakeholder Comments Template

APS/SRP Stakeholder Meeting For Transmission Planning

Defining Generator Outage States DRAFT Tariff Proposed Amendments. Shaded material in blue text is updated since the 2/12/14 BIC.

MISO Cost Allocation Response. RECBWG February 15, 2018

Financial Incentives for Deploying Carbon Capture and Storage: Tom Wilson Sr. Program Manager CSLF Financing Roundtable 2010 April 6, 2010

SCHEDULE 19 LARGE POWER SERVICE

APS/SRP Stakeholder Meeting For Transmission Planning

Valuation of Transmission Assets and Projects. Transmission Investment: Opportunities in Asset Sales, Recapitalization and Enhancements

History of Cost Allocation within MISO RECB TF. January 29, 2015

Impacts of Marginal Loss Implementation in ERCOT

Filed with the Iowa Utilities Board on May 31, 2017, E STATE OF IOWA DEPARTMENT OF COMMERCE UTILITIES BOARD

Rate Schedules and Seams Agreements Tariff

SPP New Member Communication and Integration Process. Mountain West Transmission Group. Background Information October 2017

Amendment to extend exceptional dispatch mitigated energy settlement rules and modify residual imbalance energy settlement rules

2017 Metrics with Historical Data

PJM/MISO Cost Allocation For Economic Upgrades

Stakeholder Comments Template

STATE OF NORTH CAROLINA UTILITIES COMMISSION RALEIGH DOCKET NO. E-100, SUB 84

Appendix B-2. Term Sheet for Tolling Agreements. for For

OREGON STANDARD AVOIDED COST RATES AVOIDED COST PURCHASES FROM ELIGIBLE QUALIFYING FACILITIES Page 1

SUMMARY OF CAPITAL EXPENDITURES

A. Introduction. Standard MOD Flowgate Methodology

Flexible Capacity Procurement. Market and Infrastructure Policy Issue Paper

Attachment A. BAL Frequency Response & Frequency Bias Setting Standard. Supporting Document

10-day Formal Comment Period with a 5-day Additional Ballot (if necessary), pursuant to a Standards Committee authorized waiver.

Costs and Revenue Offsets Item # Description

Southern Companies Attachment J (LGIP), Page 2 Standard Large Generator Interconnection Procedures (LGIP) (Applicable to Generating Facilities that ex

Constellation Energy Comments on Proposed OTC Reforms

MTEP16 Futures Development Workshop 1/15/15

MISO PJM IPSAC. August 26, PJM IPSAC Meeting, August 26,

Transmission Planning Standards Industry Webinar: Footnote b. January 8, 2012 John Odom, FRCC, Standard Drafting Team Chair

Implementation of BAL Dede Subakti

Gaps in Current Reserve Pricing Methodology

Real-Time Reserves. Vince Stefanowicz Sr. Lead Engineer, Generation Operating Committee May 1, PJM 2018

April 6, 2018 VIA OVERNIGHT MAIL. Sheri Young, Secretary of the Board National Energy Board th Avenue SW Calgary, Alberta T2R 0A8

T-D Interconnections: Best Value Planning White Paper January 2016

Public Service Enterprise Group. NYC Investor Meeting February 14, 2007

NYISO 2018 BUDGET OVERVIEW

TABLE OF CONTENTS ARTICLE ONE: RECITALS... 5 ARTICLE TWO: ABBREVIATIONS, ACRONYMS, AND DEFINITIONS... 6 ARTICLE THREE: OPERATING COMMITTEE...

WECC Process for Risk-Based Compliance Oversight Inherent Risk Assessment and Compliance Oversight Plan

A. Introduction. B. Requirements and Measures

Price Effects of Real-Time Market Pricing Run Parameters

Licensing of activities in energy sector of Latvia

5 Minute Settlements. Ray Fernandez Manager, Market Settlements Development Market Settlements Subcommittee November 10,

2018 Interconnection Process Enhancements (IPE) Stakeholder Call May 21, :00 a.m. 4:00 p.m. (Pacific Time)

1. Balancing Authority (BA) 2. Generator Owners (GO) 3. Generator Operators (GOP)

Participant Funding: The SeTrans Proposal. Bruce Edelston Director, Policy and Planning Southern Company

New Member Cost Allocation Review Process. Prepared by: COST ALLOCATION WORKING GROUP

Minutes Board of Trustees

Business Overview. Jim Scilacci Senior VP and CFO, Edison Mission Group. Lehman Brothers High Yield Bond and Syndicated Loan Conference

Information Document Available Transfer Capability and Transfer Path Management ID # R

FERC Order 890 APS Attachment E SRP Attachment K

Draft Proposal for the Allocation of Congestion Revenue Rights to Merchant Transmission

IN THE MATTER OF THE BOARD S INVESTIGATION OF CAPACITY PROCUREMENT AND TRANSMISSION PLANNING BPU - Docket No. EO

Stakeholder Survey I Cross Border Cost Allocation for Economic Transmission Projects For Discussion September 24, 2008

1st Qua u r a ter e M e M e e t e in i g 2nd Qua u r a ter e M e M e e t e in i g

2018 Interconnection Process Enhancements (IPE) Issue Paper

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE

2018 ERO Enterprise Metrics

Newfoundland. Brunswick R1 NA NA NA NA NA NA NA NA NA

MISO PJM IPSAC. December 2, Revised December 22, PJM IPSAC Meeting, December 2,

SCHEDULE 72 INTERCONNECTIONS TO NON-UTILITY GENERATION

Technical Conference. August 3, 2009

ITC Midwest 2014 Attachment O True-Up Presentation. Presenter: David Grover Manager, Transmission Pricing July 8, 2015

Organized Regional Wholesale Markets

Business Practice Manual For. Generator Management. Version Revision Date: August 7September 8, Page i

Renewable Generation, Transmission and the Energy Marketplace

Transcription:

& Assumptions and Criteria for Testing of New Resources 1

Introduction These slides provide a description and comparison of the assumptions and criteria used by and during the study of customer proposed projects 2

Basic Overview So what s the Impact? Study Horizon ERIS Analysis Uses 3 and 10 year cases Summer Peak and Summer off-peak Uses 5 year case 1. Two different sets of results? 2. Different transmission assumptions? 3. Different generation assumptions? Summer Peak and Light Load TRUE BUT NRIS Analysis Summer Peak only Summer Peak and Light Load Projects near the RTO seams are studied under both RTOs criteria which will bridge the study gap and fix identified issues above. 3

Types of Resources studied by and Generation Interconnection Merchant Interconnection Service Requests Upgrade Requests (IARR) No No 4

Case Case year Typically a 3 year and a 10 year case Typically a 5 year case Base line reliability Upgrades Using upgrades not contained in the base case (potential future base line upgrades) 1. Only Board approved, MTEP A projects, are added to our study base cases 2. If an IC wants to advance an MTEP project, that option is available to the IC but they must bear the advancement costs. Test MTEP B projects, in addition to other TO recommended projects, for constraint mitigation. If MTEP B projects fix the constraint, then they are included in the GIA with the caveat that they must: i. move to MTEP A by the next MTEP cycle or ii. move to MTEP A within 1 year of execution of the GIA Otherwise, the IC either funds 100% of that MTEP B project or funds an alternative (if identified during the SIS phase) Model upgrades which have been approved as needed in all years leading up to and including the year on which the study is to be performed Test upgrades for future base case years. If upgrades can fix a violation and the upgrade is chosen as the appropriate reinforcement the customer must pay for advancement costs associated with the upgrade 5

Case Deactivations Previously queued requests If the unit retirement is public information, then that information is incorporated in all Planning study cases 1. All previously queued, active DPP projects, are modeled online in the base case at their expected seasonal output. 2. All projects with executed Interconnection agreements are modeled online in the base case at their expected seasonal output. 3. Projects under suspension are modeled online in the base case at their expected seasonal output. Generators removed as required based on deactivation date & transfer of rights and then any upgrades are modeled 1. All previously queued requests still active (under study) are modeled off line. This results in the projects aggravating a constraint, but not having the ability to back off a constraint. 2. All projects with signed ISAs are modeled on-line. This allows projects to both aggravate and back off constraints 3. Projects under suspension (in the construction phase) are turned off so they do not back off constraints 6

Summer Peak Reinforcement Capacity (Firm) / Network Resource Requests Load Category A (System intact) Category B NERC Category B (loss of 1 element): Category C NERC category C1, 2, 4, 5: (loss of 2+ elements) Owner Criteria (FERC 715) Capacity Resource / Firm merchant transmission / Long Term Firm Service 100% of requested Capacity Interconnection Rights Summer peak 1. <500kV: 5% DF or 5% impact on 2. >500kV: 10% DF or 5% impact on facility rating 1. <500kV: 5% DF or 5% impact on 2. >500kV: 10% DF or 5% impact on facility rating 1. <500kV: 10% DF or 5% impact on facility rating 2. >500kV: 10% DF or 5% impact on facility rating As Required NRIS All Units at 100% of capacity rights Summer Peak Study Gen has >= 5% DF or MW Impact >= 20% of Applicable Line Rating Study Gen has >= 5% DF or MW Impact >= 20% of Applicable Line Rating Only when requested by a Owner As Required 7

Summer Peak Reinforcement Energy (Non-Firm) / Energy Resource Requests Load Category A (System intact) Category B NERC Category B (loss of 1 element): Category C NERC category C1, 2, 4, 5: (loss of 2+ elements) Owner Criteria (FERC 715) Energy Resource / Non-Firm merchant transmission Summer peak N/A N/A All fuel types at 100% of Summer Energy Output 1. <500kV: 10% DF or 5% impact on 2. >500kV: 10% DF or 5% impact on As Required ERIS Wind at 20% nameplate Gas at 100% of Nameplate Coal & Nuclear at 100% of Nameplate Summer Peak 1. Study Gen has >=5% DF 2. MW Impact >= 20% of Applicable Line Rating 3. Overloaded element is at generator s outlet 1. Study Gen has >=20% DF 2. MW Impact >= 20% of Applicable Line Rating 3. Overloaded element is at generator s outlet Based on Local TO Criteria Based on Local 8

Light Load () / Shoulder Peak () Reinforcement Resource modeling Load Category A (System intact) Category B NERC Category B (loss of 1 element): Category C NERC category C1, 2, 4, 5: (loss of 2+ elements) Owner Criteria (FERC 715) Load at 50% of summer peak Wind 40% ramp to 80% energy Oil & Gas off Coal (<500MW) at 45% initial Coal (> 500MW) at 60% initial Nuclear at 100% Pumped Storage Full Pump Other resources at 0% 50% of summer peak 1. <500kV: 5% DF or 5% impact on 2. >500kV: 10% DF or 5% impact on 1. <500kV: 5% DF or 5% impact on 2. >500kV: 10% DF or 5% impact on 1. <500kV: 10% DF or 5% impact on 2. >500kV: 10% DF or 5% impact on As Required ERIS Load at 70% of summer peak Wind at 100% nameplate All other units are modeled at their expected seasonal output. Coal, Nuclear are at 100% Oil and Gas off 70% of summer peak 1. Study Gen with >= 5% DF 2. Study gen MW Impact >= 20% of Applicable Line Rating 3. Overloaded element is at generator s outlet 1. Study Gen with >= 20% DF 2. Study gen MW Impact >=20% of Applicable Line Rating, or 3. Overloaded element is at generator s outlet Based on Local Based on Local 9