What is Earned Value Analysis?

Similar documents
EARNED VALUE MANAGEMENT. Is it worth the effort?

Project Monitoring and Control Project Closure. Week 8

Cumulative trends Problems and issues since last report

Earned Value Management Guide

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

Earned Value Management - EVM

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7

INSE 6230 Total Quality Project Management

Earned Value Management An Overview March 2014

Performance measurement

Project Management -- Monitoring the progress

IP-CIS : CIS Project Management

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

THE VALUE OF EARNED VALUE MANAGEMENT

Earned Value Formulae

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

PROJECT MANAGEMENT BODY OF KNOWLEDGE

2. Briefly discuss the factors that contribute to the improvement of the contractor s cash flow?

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

Learning Legacy Document

Quantifying Damages in Construction Claims. James L McGovern

Earned Value Management Handbook. arne. alu

Performance Analyzer Formulas. Assumptions. Current Month Adjustments

Project Controls Professional? We need the facts ma am, just the facts. Alex Davis PMC SIG 17 th September 2013

Application of Earned Value Management (EVM) for Effective Project Control

Estimating Cost-To-Go Without Stable EVM Data

THE PMP EXAM PREP COURSE

Project Performance Evaluation By Earned Value Method

Workshop II Project Management

MMZG 523 PROJECT MANAGEMENT

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado

GPE engineering project management. Project Management in an Engineering Context

CE303 Introduction to Construction Engineering. Importance of Cost Control System. Project Cost Control System

Department of Industrial Engineering

Earned Value Management

Project Management: Cost

The Mystery of Earned Value - An Oil & Gas Owner s Perspective

5-D Integrated Earned Value Analysis

Running head: VALUE ANALYSIS REPORTING 1

Slides copyright 1996, 2001, 2005, 2009, 2014 by Roger S. Pressman. For non-profit educational use only

Objectives of Project Cost Control System

Homework 6 Questions and Answers

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

Administration. Course Aim. Introductions

Professional Development Seminar Series

Three Numbers to Measure Project Performance

Level of Effort (LOE) Replanning

Earned Value Management (EVM) and the Acquisition Program

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities

ENGINEERING MANAGEMENT (GE

!" #Resource) *"* $ $ $&& $ $+$ (+& $ $ !"( /3 "'(!", &"!"-1 "'('') (+. %& $') Data Type Entry Type. % Complete Percentage Calculated or Entered

PROJECT COST MANAGEMENT

PMP Exam Prep Coaching Program

1/7/2015. Sharif University of Technology. Session#12. Instructor. Class time. Course evaluation. International Campus Kish

Earning Value From Risk

EARNED VALUE AS A RISK ASSESSMENT TOOL

Reporting and Analysis

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management

The Value of EVM. Earned Value Management

Humphreys &Associates, Inc.

Project Management: A Systems Approach to Planning, Scheduling, and Controlling Twelfth Edition

Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT. Number: DI-FNCL Approval Date:

Basic Project Management

Lecture 18: Chapter 27!

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

Earned Value Management System. a system to

PERCEPTION Tracking Progress & EAC

Components of a Project Portfolio Management Process: Part Two Managing the Pipeline

Earned Value Performance Management (EVPM) Then, Now and the Future

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?

Capital Acquisition Under The President s Management Agenda. David Muzio Office of Federal Procurement Policy

[Project Name] Monthly Performance Report for mmm/yyyy. [Sub-Project, phase, etc.] [Company] [Company Address] Marc Arnecke, PMP

Project Controls Expo

Earned Value Management System. a system to

Overview of Today s Discussion. Don t Let EVM Data Mislead You. Steve Sheamer. Brief Overview of EVM Concepts. Why you can t trust BACs or EACs

Project Controls Expo 16 th Nov 2016

Project health monitoring by Earned Value Analysis

Earned Value Management. Danielle Kellogg. Hodges University

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

Pass PMP in 21 Days - ITTO Toolbox PROCESS MAP

EV in a War Zone: Understanding Earned Value & How to apply it.

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

Earned Schedule in Action

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.

Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis

Lecture 3: Project Management, Part 2: Verification and Validation, Project Tracking, and Post Performance Analysis

Roberta Tomasini Defense Acquisition University DSN

Software Process and Management

Application of Earned Value Analysis in Analysing Project Performance

CHAPTER 10 PROJECT CONTROL

Predicting Project Completion Date Using Earned Value Management

Final: Total 200 points (3-hour exam)

Transcription:

What is Earned Value Analysis? 1

Earned Value Performance Measurement Time now Budget Cost Actual Good News or Bad? Time 2

Starting point Recording Progress The Plan is in place and work has started, so we need to record progress of how we are doing i.e. What have we achieved so far? We derive the Earned Value by multiplying the progress as a percentage against the overall budget whether this be monies, hours or quantities 3

Measuring using Manhours - example Construct concrete walls (300m3) 1000hrs, 20d After 10 days; 150m3 completed i.e. 50% complete 500 of 1000 budget hours earned 4

What have we achieved on the Plan? Schedule What work has been started/completed? Real and measurable % progress Good examples: Have you built as many rooms as you planned to at this stage? Have you plumbed/wired as many rooms as expected? Milestones achieved we moved in on time!! A bad example of progress is the double glazing company is coming next week 5

Progress Underpinning Information (Quantity Tracking) We should use/provide underpinning information to support our % progress complete figure e.g. Drawings and documents produced Numbers of cables, pipes, bricks, bottles of wine Metres of Pipe types Metres cubed of concrete Items of equipment to install, i.e. kitchen cupboards, dishwasher Contractor programmes Underpinning information removes any confusion, doubt, or conflict when scrutinising performance 6

Types of progress: Staged Milestones Actual % Complete use of Quantity Tracking Equivalent Units Operational Performance via MPS i.e. tonnes produced Level of Effort No Measurable Deliverables, i.e. departmental personnel Apportioned Effort support to doing tasks, i.e. Project Management Steps/Underpinning Schedule Further detail to enable progress to be ascertained 7

How is Earned Value measured? How much work should be done? How much work is done? How much did it cost? What is the total job supposed to cost in the execution year? Budgeted Cost for Work Scheduled (BCWS) plan schedule budget Budgeted Cost for Work Performed (BCWP) accomplishment value of plan that has been earned Actual Cost of Work Performed (ACWP) Actuals Accruals Current Baseline Budget At Completion (CB BAC) Baseline scope plus approved and implemented changes 8

Earned Value Performance Measurement Time now BCWS CB BAC Cost BCWP ACWP The value of the planned work you have actually done is less than your original estimate i.e. you have done less work than you anticipated Time The costs of doing the work is less than your original estimate You are under budget for the work you have performed 9

Earned Value Performance Metrics CPI & SPI Under and over performance can be quantified using: Cost Performance Index, CPI Schedule Performance Index, SPI The CPI is calculated as: BCWP / ACWP The SPI is calculated as: BCWP / BCWS 10

CPI & SPI A CPI or SPI value greater than 1 indicates overperformance i.e. ahead of schedule, below planned cost A CPI or SPI value less than 1 indicates underperformance i.e. behind schedule, above planned cost CPI and SPI values of 1 indicates a good performance i.e. We are delivering what we said, when we said 11

Earned Value Performance Metrics CV & SV Under and over performance can be quantified using: Cost Variance, CV Schedule Variance, SV The CV is calculated as:bcwp minus ACWP The SV is calculated as: BCWP minus BCWS 12

CV & SV A positive CV or SV value indicates over-performance i.e. ahead of schedule, below planned cost A negative CV or SV value indicates under-performance i.e. behind schedule, above planned cost A CV or SV value of 0 indicates a good performance there is no variance between planned and actual costs or work i.e. We are delivering what we said, when we said 13

Good News or Bad News? Project 1 ACWP Actual Cost BCWP Earned BCWS Planned Cost Are the SPI and CPI less than or greater than 1 SPI? >1 <1 CPI? >1 <1 What action would you take? 14

Good News or Bad News? Project 2 ACWP Actual Cost BCWS Planned Cost Are the SPI and CPI less than or greater than 1 SPI? >1 <1 CPI? >1 <1 What action would you take? BCWP Earned 15

Good News or Bad News? Project 3 ACWP Actual Cost BCWP Earned BCWS Planned Cost Are the SPI and CPI less than or greater than 1 SPI? >1 <1 CPI? >1 <1 What action would you take? 16

Good News or Bad News? Project 4 BCWP Earned BCWS Planned Cost Are the SPI and CPI less than or greater than 1 SPI? >1 <1 CPI? >1 <1 What action would you take? ACWP Actual Cost 17

In Summary Earned Value is a simple process if applied in the correct manner There are individuals who perpetuate the myth that Earned Value is a complex process in order to create a niche market Earned Value is best performed at the project detail level and if necessary rolled up Avoid applying Earned Value in non Project environments i.e. Level of Effort tasks, it adds no value Other applications of the process can cause the corruption of the practice, unnecessary manipulation and the proliferation of complex equations and rules as illustrated on the next slide 18

Execution Year End Metrics Year End EAC YE SV EAC (Baseline Carryover) Cost ACWP Current Baseline BAC Current Baseline EAC Forecast Year End SV BCWS BCWP Slippage Forecast Year End BCWP Time Now Time Year End Forecast Completion Date 19

and finally If you are relying on Earned Value to highlight the big project issues then you are not really engaged with the delivery of the project 20