Agenda. Enel: Introduction Auctions: Enel experience and key factors Case study: India Closing remarks

Similar documents
June 08, 2017 Ratings

Second Quarter 2018 Ended September 30, 2017 Earnings Presentation

First Quarter 2018 Ended June 30, 2017 Earnings Presentation

Capital Markets Day. Global Renewable Energies. Antonio Cammisecra

Earnings Call 22 nd November 2016 Q2 FY 17

Fourth Quarter & Full Year Ended March 31, 2018 Earnings Presentation

We guide companies leading the electricity transformation

Competitive bidding set to transform wind power market

INOX WIND LIMITED Q2FY18 INVESTOR UPDATE

Solar development & rooftop solutions BOO/BOOT

Perspective on Financing Wind Energy Projects. June 16, 2016

SOLAR ENERGY CORPORATION OF INDIA LIMITED DRAFT 1000 MW GRID CONNECTED ROOF TOP SOLAR PV SCHEME FOR GOVERNMENT BUILDINGS UNDER CAPEX AND RESCO MODELS

Anti-dumping duty on PV cells and modules November 2017

Fiscal Third Quarter 2019 Ended December 31, 2018 Earnings Presentation

Solar Energy Corporation of India Limited भ रत य स र ऊर न गम न नमट ड (A Government of India Enterprise)

JAWAHARLAL NEHRU NATIONAL SOLAR MISSION (JNNSM) Phase-II

Enel Green Power 9M 2015 consolidated results

Minutes of Pre-bid meeting held on 29th June 2017 at GETRI, Vadodara with prospective bidders for Solar and Wind power tenders floated by GUVNL.

Enel Green Power business plan. Rome - April 3 rd 2014

Draft Guidelines. for. Tariff Based Competitive Bidding Process. for. Grid Connected Solar PV Power Projects

@5}; i i,, DeeffiflE anga Comp ny Secretary. 07thAugust, 2018

Leading Diversified Renewable Energy Generation Company

Capital Markets Day. Strategic Plan Alberto De Paoli CFO

Ratings. August 2, Synopsis

COMPANY OVERVIEW. US$812mn. Largest Energy Generator in Chile 5,063MW 531 MW 100% 11 Years. US$2.2bn. BBB-/Baa3 66.7% of installed capacity

REQUEST FOR SELECTION (RfS) DOCUMENT FOR SETTING UP OF 2500 MW ISTS-CONNECTED WIND-SOLAR HYBRID POWER PROJECTS (TRANCHE-I)

Investor Presentation May 2018

Renewable Energy in Mexico - update on the auctions and investment opportunities. Santiago Ross Associate Norton Rose Fulbright LLP 22 November 2017

RATING METHODOLOGY June Rating Methodology for Solar Power Producers. ICRA Rating Feature. Overview

Suzlon Energy Limited Q1 FY August 2017

F. No. 53/15/2016 -WE Ministry of New & Renewable Energy. Evaluation of Generation Based Incentives Scheme for Wind Power Projects

DRAFT PRE BID (MoU) (Rev-1) Memorandum of Understanding

Conference Call. Encavis AG Bold move into the PPA market. October 9, 2018

IN THE JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION AT RANCHI. Case No. 12 of 2018, 13 of 2018, 14 of 2018 & 15 of 2018

Suzlon Energy Limited Q1 FY August 2018

GMR Chhattisgarh Energy Limited

IWL: NOI: 37: oa= September, The Secretary BSE Limited Phiroze Jeejeebhoy Towers Limited Dalal Street, Mumbai

RfS & Rs with compare to other states, there is no such charge

1200kV AC Sub-station at Bina. Delivering Smart Grid/ Distribution Solutions `

GOVERNMENT OF MADHYA PRADESH

Solar Energy Corporation of India Limited (A Government of India Enterprise)

WALK-THROUGH THE LEGAL STRUCTURE OF PPA S عرض الهيكل القانوني التفاقيا شراء الطاق

FY 2015 consolidated results. March 23, 2016

न और नव करण य ऊर म त र लय

Capital Stage AG: Strategic Partnership with Solarcentury. November 2, 2017, 11:00 CET

INOX WIND LIMITED QUARTERLY INVESTOR UPDATE Q4 & FY16

9M 2016 consolidated results. November 10, 2016

POWER PURCHASE AGREEMENT

Renewable Energy Certificates: Inches Away From Implementation

Private Sector Participation in Highways Some Insights

9M FY16 Results. Leading Diversified Renewable Energy Generation Company

Suzlon Energy Limited H1 FY November 2017

Designing Energy Markets for the Future

1H 2018 consolidated results. July 31, 2018

Basics of PPA Negotiations. Eng. David M. Mwangi, Individual Energy Consultant Nairobi, Kenya

Implementation of Solar Based Projects in MP Dated 20 July, 2012

Leading Renewable Energy Generation Company

How to get a CfD: Allocation Process and the Transition from the RO 11/06/14

Jawaharlal Nehru National Solar Mission

LARGE SCALE SOLAR INNOVATION SHOWCASE

Competitive Bidding Guidelines for procurement of Electricity

GROWING OUR INDUSTRY-LEADING POSITION

India's Solar Leap: Financing a Mature Market

Leading Diversified Renewable Energy Generation Company

Renewable Energy in India: Getting to Targets

Power Procurement Strategy

Auctions to support renewable energy deployment overview and design elements Reverse Auctions to Scale Renewable Energy 6 June 2017

Gabriel Zeitouni, COWI A/S

TELANGANA STATE POWER COORDINATION COMMITTEE Request for Proposal (RfP) NOTICE No. TSPCC (Commercial)/02/15-16

Mending Power Sector Finances PPP as the Way Forward. Energy Market Forum

Company Secretary; Obligations and Disclosure Requirements) Regulations, 2015 e Earnings Presentation

Solar Energy Corporation of India Limited (A Government of India Enterprise)

Clarification for the queries received from the Bidders, dated 30 May Clarification on RFP. Clarification by KREDL

MP URJA VIKAS NIGAM LTD.

Consultant report on EBITDA projections prepared by Greenko

Renewable Energy and Mining Summit. Toronto, September 25th, 2013

Azure Power Global Limited (AZRE)

Interim relief for stranded gas based plants though long term viability hinges on improved domestic gas avaliability:care Ratings

Investor presentation. H results September 26, 2017

Renewable Energy Auctions Analysing IRENA Energy Community Workshop on Renewable Energy Auctions 8 March 2017

Strategic Partnership with Tenaga Nasional Berhad. 09 May 2016

Scanned by CamScanner

Economic and financial feasibility of PV projects

Peter Wright. Renewable Energy Projects in Africa Comparing Procurement Models for Renewable Generation Capacity. Simmons & Simmons March 2015

CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3rd & 4th Floor, Chandralok Building, 36, Janpath, New Delhi : /

Key lessons from South Africa s Renewable Energy IPP Programme

Amendment No. 2. (iii) Clarification No. 2 dated vide Ref No.: NTPC/ /NSM/TI/RAJ/03/CLR02

2015 Investor day Strategic Plan New foundations for growth

By Director of Various New and Renewable Energy T

Past, Present & Future

Clarifications Sought No. 1 In what format the Bank Guarantee will be accepted if Bank Guarantee is from outside India.

Enel Green Power 1Q 2014 consolidated results

FY 2016 results. April 4, 2017

Preparing Renewable Energy Power Purchase Agreements in the Middle East and North Africa: Questions to Ask

The Role of Commercial Banks and Private Sector in NAMA Design and Implementation. Rodrigo Violic Head of Project Finance, Banco BICE

K.P. ENERGY LIMITED CIN: L40100GJ2010PLC059169

THE MOROCCAN RENEWABLE ENERGY MARKET OPPORTUNITIES FOR INVESTORS IN MOROCCO. - May 5th,

Latin America PV Playbook

Investor presentation

KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM. PRESENT: Sri.T.M. Manoharan, Chairman

Transcription:

Agenda Enel: Introduction Auctions: Enel experience and key factors Case study: India Closing remarks 1

Enel today 1 Global and diversified operator 40 bn Regulated Asset Base 62 mn distribution end users #1 in Italy, Spain, Chile, Peru #2 in Argentina, Colombia 38 GW renewable capacity 2 Global leadership in renewables 18.3 mn free retail customers #1 in Italy and Spain 47 GW thermal capacity Highly flexible and efficient generation fleet 1. As of 2016 2. Consolidated (35.9 GW) and managed (1.9 GW) capacity including 24.9 GW of large hydro. 3. Presence with operating assets Countries of presence 3 2

Operational data Leadership along the various segments of the value chain Key indicators 1 Enel and European peers 2 Infrastructure & Networks 62 mn end users 41.2 mn smart meters 1.9 mn km grids Retail 56.4 mn power customers 5.5 mn gas customers Renewables generation 35.9 GW of installed capacity 5 Customers (mn) Installed capacity (GW) 3 4 9 42 45 27 23 22 70 38 35 83 132 62 Thermal generation 46.8 GW of installed capacity Grid Length (mn km) - 0.7 0.8 1.0 1.3 1.9 1. Data as of December 31 st 2016; 2. Data as of December 31 st 2016; 3. Retail Customer: Free + Regulated; 4. Figure refers to the European perimeter (Engie does not disclosure total number of customers); 5. It doesn t include 1.9 GW of managed capacity 3

3 2.5 2 1.5 1 0.5 0 Enel Group 2016-2019 strategic plan update 2017-19 growth capex by business 2017-19 cumulated growth EBITDA Growth EBITDA by year ( bn) 42% 6% 5% 27% 1.9 2.6 12.4 bn 47% 55% 4 bn 15% 3% 0.8 1.4 0.8 1.3 1.9 Networks Renewables Networks Renewables 2016 2017 2018 2019 Thermal generation Retail Thermal generation Retail COD 2015-16 EBITDA COD 2017-19 EBITDA EBITDA secured 4

5 Enel Green Power Renewable energy division Key figures 2016 Capacity 1 (GW) 35.7 Production (TWh) 92.4 Key financials ( bn) 2016 EBITDA 4.2 Opex 1.4 Countries with operations Maintenance capex 0.4 Countries with development Growth capex 1 2.8 Wind Solar Hydro Geo Biomass Large hydro Net installed capacity 1 (GW) 6.4 1.2 2.5 0.8 0.1 24.8

Agenda Enel: Introduction Auctions: Enel experience and key factors Case study: India Closing remarks 6

Strictly confidential Enel Green Power Recent achievements (2015 - Present) USA Cimarron Bend: biggest EGP Wind Plant under construction (400 MW) Germany Acquisition of a geothermal project and started drilling exploration activities India In 2015 BLP acquisition. Competitive participation in recent 750 MW PV auction Mexico In 2016 1 GW PV awarded in a tender + 200 MW Wind Morocco EGP Consortium awarded 850 MW Wind tender Indonesia Awarded the right for exploration and development of 55 MW Peru 326 MW awarded in 3 technologies: PV, wind and hydro Brazil Nova Olinda: biggest EGP PV Plant under construction (292 MW) Zambia In 2016 Awarded 34 MW of PV Australia Acquired 275 MW of PV, the largest solar plant in the continent Operational presence Advanced development Growth 7

Key Elements in Auction Design From the perspective of IPP Recognize Long-term nature of Investment Clear, long-term regulation and targets Guard against short-term opportunistic players Not just the $, also the contract (PPA) Ensure bankability of terms e.g. clear provisions on curtailment, dispute settlement, force majeure, termination, payment guarantee Clarify risk allocation Off-taker credit risk? Foreign currency risk? Align with reinforcement of Grid Infrastructure Consistency with TSO planning, adjust auction mechanism (e.g. per region, differentiated tariffs, separate auction for interconnection)

Potential investors need stable regulation, especially on four high priority factors Factors: remuneration, electricity sales, project risk & scheme accessibility Equity investors can be affected in their project business plan by multiple factors......each with a different potential severity of impact Illustrative analysis Sale of electr. Factor Description Impact 1 Time-to-COD Scheme access Remuneration Sale of Certainty that production will be electricity 2 fed into the grid (thus sold) CapEx Remunerat. 2 Level of remuneration received by RES plant Project risk / discount rate 4 Discount rate of cash flows (thus embedding perceived risk) Time-to-COD 3 Time between project award and COD (start of revenues) Revenues OpEx Financial costs Tax Debt repayment Equity OpEx Prj. risk / disc. rate Tax Debt CapEx 2 Plant cost, in terms of equipment and installation OpEx & Tax 2 Operation and Maintenance expenditure Tax rate & new taxes Scheme access Factor impacts the chance investors have to actually "win" a project Way to filter access to RES scheme 1. Measured as sensitivity of IRR to modifications to the listed factors (see factor-specific footnotes for detail); severity ranking based on the following thresholds (highest to lowest IRR impact): 3.0p.p. / 2 p.p. / 1 p.p. 2. Assumed change of: +/- 10% 3. Assumed delay of 1 year in project EPC (4 years vs. 3) 4. Assumed +200 basis points on interest rate Source: BCG analysis

Tender Agreements Key points for a bankable PPA Energy charge currency: Energy charge paid in US $ or in local currency equivalent of the amount payable in US $ (based on the relevant date of payment as notified by the Central Bank on the day before such payment is made). Energy charge Indexation: adjusted annually to US or local CPI. Deemed energy payment: payments of deemed energy to be guaranteed in case of COD delays due to the Buyer, Curtailment and post COD Grid Unavailability (both planned and forced). Liquidity Guarantee: provide a liquidity support mechanism, such as an escrow account or an on-demand guarantee issued by acceptable bank, based on foreign currency, to be used in case of Buyer's insolvency or any other Buyer's event of default. Compensation on termination in case of Buyer s default: in case of termination for a Buyer s event of default, the Buyer shall provide a termination payment to compensate the Seller s debt, equity and taking into account the expected return on investment. The amount to be valued by a reputable Independent Third-party Evaluator agreed by the Parties. Change in Law and economical contest: include provisions of price adjustment in the case of law, tax regime or economical contest changing after the date of the effective date of the PPA, adversely affecting the expected return on investment. Arbitration: any dispute (not resolved thought an Expert determination) to be solved under rules generally acceptable to the International Community (e.g. UNCITRAL or ICC) Force Majeure: to excuse the Seller from performing its obligations if a Force Majeure Event (an event beyond the reasonable control of such Party) prevents such performance. Term: the duration of the PPA shall be 25 years, extendible

Auctions Best practices and lessons learnt Structured pre-qualification helps to assign remuneration to solid projects and investors Filter out speculators, high upfront commitments (bid bond), penalties in case of delays, constraints on project property before COD Important to predict unfair competitive behaviors (e.g. ways to by-pass pre-qualification criteria) Guarantees on energy offtake are a critical aspect, in particular for project bankability Long term PPAs (either with regulator or private) a key requirement from financial institutions Critical to boost RES PPA market, either via quota obligations or auctions, with capacity targets aligned with available project pipeline Clear Timeline to extract the best value from the auction Avoid frequent postponements is very important to have the most solid investors in the game Local content constraints should be set consistent with local ability to provide service High local content target implies buying locally equipment with strong effect on performance Local content requirements can be balanced-off by incentivizing other items of the investors' cost structure (e.g. financing, fiscal) Communication with players when setting rules and during implementation a success factor Frequent consultations when designing auctions, direct channels during auctions Q&A session and pre-bid meeting are crucial to have a well structured bidding process

Agenda Enel: Introduction Auctions: Enel experience and key factors Case study: India Closing remarks 12

Central Government Tenders NSM Batch 1 Dec 2010 NSM Batch 1 Dec 2011 Karnataka Apr 2012 Andhra Pradesh, NTPC 500 MW AP, NTPC 150 DCR, 150 MW Rajasthan, NTPC, 420 MW Maharashtra, SECI, 450MW Uttar Pradesh, NTPC, 100 MW Karnataka State, 1170 MW Uttar Pradesh, SECI, 125 MW Karnataka NSM, 500 MW Telangana, NSM 350 MW Andhra Pradesh, SECI 400 MW Chhattisgarh, SECI, 100 MW Gujarat, SECI, 250 MW Karnataka, SECI, 950 MW Rajasthan, NTPC, 130 MW Rewa State, 750 MW Kadapa, NTPC, 250 MW Bhadla, SECI, 250 MW Tariff (INR/kWh) India Renewables Scenario Capacities, Targets, Mechanisms & Tariffs RES: Installed capacity vs 2020 target (in GW) High and low winning tariff for recent tenders 70 60 50 40 30 20 10 0 12.3 60 1 40 *Source: CERC, data Utility as of Scale 31st Solar March Rooftop Solar Wind Biomass Small Hydro 2017 Installed Capacity (GW) Target (GW) 32.3 These targets are divided in phases and batches that use different incentive mechanism such as tenders on tariffs, tenders on Capex grants or EPC tenders through government utilities. The main implementing agencies are: 60 8.2 10 4.4 5 10.95 7.49 VGF tender results converted to equivalent tariff for plotting purposes 7.94 4.63 5.12 5.04 4.69 4.34 4.41 4.78 4.66 4.73 4.82 4.94 4.94 4.35 3.3 NTPC SECI STATE EGP Participated Highest Winning Tariff Lowest Winning Tariff 3.15 2.62 NTPC SECI Techno commercial submission and online auction on tariff or capex grant. Solar Park and non-solar Park Model 25 year PPA with NTPC/SECI + PSA with State Discom State Govts/ Utilities/Discoms Techno commercial submission and online auction Generally Non Solar Park Model 25 year PPA with state discoms/renewable agency *NTPC National Thermal Power Corporation Limited SECI Solar Energy Corporation of India; VGF: Viability Gap Funding 2010-12 2015 2016 Most recent RA in 2017 were Rewa 3.30 INR/kWh (levellised), Kadapa (AP) 3.15 INR/kWh & Bhadla 2.62 INR/kWh SECI was the implementing agency for first wind tender. Tender closed at INR 3.46 which was ~17% lower than the lowest prevailing Feed in Tariff 2017

Tender Summary India Rewa 750 MW PV Tender at record low tariff of INR 2.98/kWh Description 750 MW (3 Units x 250MW) PV Tender in Rewa, Madhya Pradesh by RUMSL (Rewa Ultra Mega Solar Limited) Implementation Agency RUMSL 50:50 JV between SECI (Solar Energy Corporation of India) & MPUVNL (Madhya Pradesh Urja Vikas Nigam Limited) - State Renewable Nodal Agency Solar Park Model with Reverse Auction process Land, Evacuation and other Infrastructure being developed by RUMSL Tariff based competitive bidding Timelines PPA Connection Submission January 2017 Reverse Auction February 2017 PPA Signing March-April 2017 COD 18 Months from PPA MPPMCL (Madhya Pradesh Power Management Company Limited) - Capacity based PPA (200 MW) DMRC (Delhi Metro Rail Corporation) Energy Based PPA equivalent to 50 MW (Long term Inter State Open Access Agreement) Pooling Substations (220/33 kv) 3 nos. 1 dedicated for each 250 MW unit. Developed and owned by RUMSL. Design and Contracting by MPPMTCL MP State Transmission Company Main Substation (400/220 kv) Single unit being developed by PGCIL (Power Grid Corporation of India Limited) as part of Inter State Transmission System Main Highlights Funded by World Bank Transaction Advisory by International Finance Corporation Power Evacuation into central transmission network part of National Green Energy Corridor PPA with an escalation of INR 0.05/kWh/Year till 15 years. PPA backed by State Payment Guarantee.

Bidders exposure after Bid Submission India Rewa 750 MW PV Tender Guarantee Set-up day Amount/MW (For 250 MW bid) Duration Bid bond Bid Submission 0.016 MUSD/MW (4 million USD) Validity 90 Days (Returned after Reverse Auction in case of Bidder does not win) Performance Bond Awarding date/ppa Signing Awarding date/ppa Signing 0.028 MUSD/MW (7 million USD) 0.018 MUSD/MW (4,5 million USD) Up till COD Up till COD + 1 Year Tariff based competitive Bidding 23/01/2017 9/02/2017 25/03/2017 18 Months Bid Submission Reverse Auction Return of Bid Bond by Authorities PPA Signing with Successful Bidders COD COD + 1Year Guarantees to be provided Bid Bond (4 MUSD) Performance Bond (7 MUSD) Performance Bond (4,5 MUSD)

Project Selection Preselected site and connection Site specific information are provided to the Bidders by the authority in the RFP: boundary coordinates of the site area including CAD files; grid connection solution including details on connection works, costs and responsible party; geotechnical, hydrological and topographical reports; site specific road map of permits, including timeline and responsible party; Bidders are allowed to perform site visit Bid Submission is usually 1.5 months after RFP issuing

India First Wind Tender 1 GW capacity auctioned at record low tariff of INR 3.46/kWh Capacity Bid submission COD PPA Tender Details Tender Results 1000 MW, single player can bid minimum 50 to maximum 250 MW First Round: 9 th Jan. Reverse Auction: 23 rd Feb 2018-2019 (18 months from signing of Letter of Intent) PPA for 25 years at levelized tariff (no inflation or indexation) with Power Trading Co (PTC, Govt. of India undertaking). PTC to sign back to back PSA (Power Sale agreement) with DISCOM. No deemed power, no compensation for grid problems Interconnection at Central Transmission Utility (CTU) while 95% of projects in India have been developed for State Transmission. STU connection possible but bearing relevant transmission charges (which are different for each state) First round submission on Jan 9 th (70 days from RfQ). 95% of bids around just two CTU substations in Gujarat and Tamil Nadu. Total MW bid : 2600 MW (2,6X oversubscribed) Preferred States : Tamil Nadu (1750 MW) and Gujarat (750 MW) due to high EOH (3300-3500) and CTU availability New tenders expected at central and state level in H1 2017 Aggressive bidding by OEM s and IPP s resulted in record low tariff of INR 3.46; 16% lower than the lowest Feed in Tariff (INR 4.15 per unit) prevailing at that time Tariff discovery resulted in all state governments stopping signing of new PPA s and coming up with guidelines for procurement of RE through competitive bidding route

Bidders exposure after Bid Submission India First Wind Tender 1000 MW Guarantee Set-up day Amount/MW (for 250 MW bid) Duration Earnest Money Deposit (Bid bond) Bid Submission 0.016 MUSD/MW (4 million USD) 9 months (returned after completion of Reverse Auction) Performance Bank Guarantee On issue of Letter of Intent to winner of RA 0.032 MUSD/MW (8 million USD) 2 years: returned post commissioning of the project Draft Guidelines Issued Final Guidelines Issued Request for selection (RfS) Issued Deadline for Tender Submission Deadline for Tender Submission Technical Qualification & Reverse Auction same day with 3hrs notice Issue of LOI to winners of RA, COD within 18 months from LOI COD 14 th June 2016 22 nd Oct 2016 28 th Oct 2016 15 th Dec 2016 Postponement 9 th Jan 2017 23 Feb 2017 By April 2017 Oct 2018 70 Days 18 months Bid Bond (4 MUSD) Performance Bond (8 MUSD) *Exchange Rate USD=INR 65

Project Selection Site and inter-connection to be selected by Bidders Bidders are required to develop their own projects: Focus on high wind areas, most of the projects bid were in 2 states of India (Gujarat and Tamil Nadu) obtain relevant permits and approvals from state nodal agencies Projects to be connected to CTU, getting the approvals for evacuation and wheeling of power (Long Term Open Access) was the responsibility of bidder IPP s bidding using own site IPP s having existing pipeline and close to CTU sub-station used their own sites for bidding This gave them a competitive edge in terms of preparedness and negotiation with OEM s However as most of the existing pipeline was designed to connect to State Transmission Utility sub-station; hence many IPP s were not ready with their sites OEM s bidding directly or with IPP s OEM s (Gamesa and Inox) bid without tying up with IPP s. Inox won 250 MW; Gamesa stopped short of the winning tariff Some OEM s entered into pre-bid agreement with IPP s As the margins are very thin, there is an inclination to tie up before with IPP s

Agenda Enel: Introduction Auctions: Enel experience and key factors Case study: India Closing remarks 20

Closing Remarks Competitive auction is an effective and efficient mechanism to attract private investment in large-scale renewable generation (However, auctions cannot start from scratch..) Long-term planning as well as a consistent long-term signals is important from the government Competitive pricing depends not only on the level of competition but also on the terms of the PPA and other contractural terms Alignment with grid infrastructure buildout is a key factor

Thank You