BCE Guidance. Advanced Wastewater Treatment Plant. Version 1.0

Similar documents
Project Selection Risk

METHODOLOGY For Risk Assessment and Management of PPP Projects

Draft Environmental Impact Statement. Appendix G Economic Analysis Report

Opportunity Paper Template

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Table of Contents Advantages Disadvantages/Limitations Sources of additional information. Standards, textbooks & web-sites.

PROJECT FEASIBILITY REPORT CHECKLIST

Using Tolerable Risk to Drive Asset Management Decision Making

Chapter 8: Lifecycle Planning

The Capital Expenditure Decision

Construction Mitigation Management

Technical Line Financial reporting development

Department of Defense INSTRUCTION

Methodology for Quantitative Procurement Options Analysis Discussion Paper. Partnerships British Columbia Updated April 2014

CAPITAL BUDGET NUCLEAR

Fundamentals of Project Risk Management

1. Define risk. Which are the various types of risk?

Department of Defense INSTRUCTION

Risk Management Guideline July, 2017

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

Managing Project Risk DHY

MONETIZING RISKS A PRIORITIZATION & OPTIMIZATION SOLUTION JASON DE STIGTER, P.E. 13 October 2014

ENTERPRISE RISK MANAGEMENT (ERM) GOVERNANCE POLICY PEDERNALES ELECTRIC COOPERATIVE, INC.

RISK EVALUATIONS FOR THE CLASSIFICATION OF MARINE-RELATED FACILITIES

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

Managing Project Risks. Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways

City Council Report 915 I Street, 1 st Floor

UCISA TOOLKIT. Major Project Governance Assessment. version 1.0

Kidsafe NSW Risk Management Plan. August 2014

City and Borough of Juneau, AK WATER UTILITY AND WASTEWATER UTILITY RATE STUDY

Risk Management Policy and Framework

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

RISK MANAGEMENT STANDARDS FOR P5M

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

Risk Management Policy

Project Management Certificate Program

YORK COUNTY, SOUTH CAROLINA

Cost-benefit analysis in the context of EU Cohesion funding - tools, methodology and available support

Risk Management at Central Bank of Nepal

Cost Benefit Analysis (CBA) Economic Analysis (EA)

Financing for Energy & Sustainability

RISK MANAGEMENT FRAMEWORK

YACHTING AUSTRALIA. Club Risk Management Template. A Practical Resource for Clubs and Centres

Accounting for the effects of natural disasters under IFRS Japan

Chapter-8 Risk Management

Alternatives Development, Project Justification, and Financial Realities Financial Considerations

WHAT IS CAPITAL BUDGETING?

Project Risk Management

Updated Financial Analysis Final Draft

AREAWIDE WATER QUALITY MANAGEMENT PLAN AMENDMENT PROCESS

Use of Internal Models for Determining Required Capital for Segregated Fund Risks (LICAT)

Weber State University Information Technology Division. Policy Guide

Introduction to Risk for Project Controls

RISK MANAGEMENT LECTURE 5. Ahmed Elyamany

Procedure: Risk management

Practical Water Utility Asset Management Plans

Zurich Hazard Analysis (ZHA) Introducing ZHA

Capital Project Approval Request

Portfolio Rebalancing:

Ahsan Jamal. Case Study IDENTIFYING AND MANAGING KEY RISKS IN CONSTRUCTION PROJECTS

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP

NASA Business Case Guide for Real Property and Facilities Project Investments

DFARS Procedures, Guidance, and Information

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. cover_test.indd 1-2 4/24/09 11:55:22

Topic RISK MANAGEMENT Procedure Category Risk Management Updated 07/2011

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

4.1 Risk Assessment and Treatment Assessing Security Risks

Appendix C: Economic Analysis of Natural Hazard Mitigation Projects

Certificate IV in Project Management Practice

Scouting Ireland Risk Management Framework

Risk Management Plan for the Ocean Observatories Initiative

PROGRAMMED MAINTENANCE Planned Maintenance Program

Integrated Capital Planning Manual

CEQA ENVIRONMENTAL REVIEW GUIDELINES

Business Auditing - Enterprise Risk Management. October, 2018

RESERVE BANK OF MALAWI

Chapter 7: Risk. Incorporating risk management. What is risk and risk management?

CAPITAL BUDGETING AND THE INVESTMENT DECISION

Planning and Urban Management (Environmental Impact Assessment) Regulations 2007 SAMOA

SEC Comments and Trends

Wastewater Asset Management Unique Perspectives from the Engineer & Municipality

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Solvency Assessment and Management: Stress Testing Task Group Discussion Document 96 (v 3) General Stress Testing Guidance for Insurance Companies

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS

2. 5 of the 75 questions are under trial and will not contribute to your overall score. There is no indication of which questions are under trial.

BURNET COUNTY ACCIDENT PREVENTION PLAN & SAFETY POLICY

COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS

Project Management. A Practitioner s Guide. Steven M. Bragg

5000 Public Personal Injury Compensation Plans

Mn/DOT Scoping Process Narrative

IPP TRANSACTION ADVISOR TERMS OF REFERENCE

INTERNATIONAL AUDITING PRACTICE STATEMENT 1010 THE CONSIDERATION OF ENVIRONMENTAL MATTERS IN THE AUDIT OF FINANCIAL STATEMENTS

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

Economic and Technical Evaluations for Engineering and Maintenance Projects. Germany, Munich, relexa hotel München.

T. ROWE PRICE STATEMENT OF COMPLIANCE: UK STEWARDSHIP CODE

DRAFT COMPREHENSIVE COST OF SERVICE AND RATE DESIGN ANALYSIS. San Antonio Water System. San Antonio Water System 21 MAY 2015 PREPARED FOR

Possibility of Using Value Engineering in Highway Projects

Master Development Plan for the TxDOT North Tarrant Express Project, Segments 2-4. Chapter 6: Preliminary Cost Estimates.

Overview of Standards for Fire Risk Assessment

Grinder Pump Policy Approved by County Council May 11, 2011

Transcription:

Sacramento Regional County Sanitation District Version 1.0 September 2012

Contents 1.0 Introduction... 1 1.1 Purpose... 1 1.2 Context... 1 1.3 BCE Overview... 1 1.4 Program Procedures for BCE... 2 2.0 BCE Initiation... 2 2.1 Problem Statements and Drivers... 2 2.2 Stakeholder Identification... 2 2.3 Project Constraints... 3 3.0 Alternatives... 3 3.1 Step 1 - Brainstorming... 3 3.2 Step 2 Alternative Screening... 4 3.2.1 Fatal Flaw Analysis... 4 3.2.2 Additional Screening (Optional)... 5 3.3 Step 3 Final Alternatives... 5 3.3.1 Alternative Design... 5 3.3.2 Capital Costs... 6 3.3.3 Operation & Maintenance... 6 3.3.4 Salvage Value and End of Life Disposal Cost... 7 3.3.5 Indirect Costs... 8 3.4 Public Impact Costs... 10 3.5 Non-Quantifiable Factors... 10 4.0 Analysis... 10 4.1 Calculating Life Cycle Costs... 10 4.2 Sensitivity (Uncertainty) Analysis... 11 4.3 Recommendation of a Preferred Alternative... 11 5.0 BCE Documentation... 12 6.0 Reviews and Approvals... 12 Sacramento Regional County Sanitation District i

1.0 Introduction 1.1 Purpose The purpose of this guidance is to standardize the development and presentation of Business Case Evaluations (BCEs) for the AWTP Program. BCEs are a comprehensive approach to identifying and evaluating alternatives at all stages of the AWTP Program. They will be integral parts of the engineering evaluations performed by the Program Management Team and Design Consultants and will be the primary documentation of critical technical decisions that affect the design, construction and operation of the advanced wastewater treatment facilities. The goals of this BCE guidance are to standardize BCE development to meet the Program requirements and to ensure alternatives are fully and appropriately evaluated. Specific objectives for meeting these goals include: Modifying relevant SRCSD procedures for application to this Program Providing guidance to consultants who are not familiar with SRCSD procedures or BCE templates Being a reference for standard factors and costs for use in the BCEs 1.2 Context SRCSD has well developed BCE procedures that are used for developing balanced, business case- based, decisions on a variety of projects and alternative evaluations. Depending on the nature and dollar magnitude of the solutions under considerations, existing procedures require the development of a BCE or a Project Development Plan (PDP). For the purposes of all evaluations related to this Program, this guidance consolidates all relevant procedures under a single set of procedures, to be referenced as BCE process or procedures. The BCE guidance in this document will be used to guide the development and analysis of all Program alternatives expected to result in significant financial outlays. 1.3 BCE Overview A BCE is a rigorous methodology for evaluating alternatives. It is applied at most levels of alternative analysis: from decisions between major treatment process alternatives, to selection of the types and numbers of assets used on a preferred alternative. In most cases, BCE considers all aspects of asset ownership, including levels of service, capital costs, operations and maintenance costs, and risks. It also incorporates non-cost factors to ensure the most appropriate alternatives are selected and the selection process is well documented. The AWTP Program is primarily focused on upgrading the SRWTP to meet the District s new discharge requirements. Consequently, this BCE guidance is focused on developing and evaluating alternatives for modifying the existing facilities and constructing new facilities to meet the new discharge requirements. Sacramento Regional County Sanitation District 1

Historically, the District has used BCEs to address a wide range of problems, including operational issues. The existing District BCE procedures identify four failure modes and each problem is associated with one or more failure mode. The failure modes are levels of service, capacity, mortality and efficiency. For the AWTP Program, BCEs will primarily focus on selecting the most appropriate unit processes and equipment for meeting the new discharge requirements. To help stay focused on these needs, BCE guidance requires the PMO staff and subsequent design teams to identify specific drivers, which may include one or more of these failure modes for each analysis. 1.4 Program Procedures for BCE All BCEs will follow the same basic process. The level of detail and amount of effort for each BCE will depend on its potential impact on the AWTP, Program, and alternatives. The BCE process has three phases: BCE Initiation Alternatives Development Alternatives Evaluation 2.0 BCE Initiation Problem initiation is the critical step that forms the basis for the remainder of the BCE process. During problem initiation, the problem drivers are identified and the problem statement is developed. Other initial steps in the BCE process are also performed. 2.1 Problem Statements and Drivers The problem statement is based on the drivers for the problem in question. The principle driver for the AWTP Program is meeting the new level of service for the effluent discharged from the SRWTP and this driver is critical in evaluating major unit processes for the Program. However, more detailed drivers need to be identified when considering ancillary systems or subsystem. The drivers for these analyses will be based on the requirements of unit processes they are serving. For example, a unit process may need to have a 150 mgd pumping system. The driver for the BCE for the pumping system is a capacity of 150 mgd. The problem statement should concisely describe the drivers for the facilities under consideration. It should focus on the function that the asset(s) will perform rather than the physical asset. A specific solution should not be identified in the problem statement. The problem statement should narrow the focus of the work and allow for a wide range of possible solutions. 2.2 Stakeholder Identification Identify all stakeholders early in the process. Stakeholders may be involved in development of the problem statement and at other times during the process where their input is needed. Stakeholders will always include operations and maintenance staff representatives. Other Sacramento Regional County Sanitation District 2

stakeholders could include other design teams working on potentially impacted designs, Program Management team for schedule or budget, and external stakeholders. External stakeholders can include community workgroups and other governmental agencies. Since the new facilities will be located at the existing SRWTP, most projects will not have external stakeholders. The Bufferlands group may be used as a resource for environmental impact and mitigation at SRWTP. 2.3 Functional Requirements Clearly identify functional requirements for the project. The functional requirements should include the range of operating conditions and requirements. 2.3 Project Constraints Specific constraints that could affect the development of alternatives should be identified and discussed to ensure that the evaluated alternatives meet the project requirements. The identified constraints could be used in the fatal flaw analysis and could determine whether an alternative is further analyzed. Typical project constraints include, but are not limited to: Physical conditions Existing site conditions Concurrent and future construction in the project area Codes, regulatory standards, and relevant permits Scheduling/timing- regulatory deadlines, seasonal construction windows, other construction at SRWTP Potential future changes to discharge requirements 3.0 Alternatives Alternative development is a three step process that identifies potential alternatives, screens potential alternatives, and develops alternatives for the BCE analysis. The goal of the alternatives development is to have 3 to 5 alternatives for the BCE. Limiting the number of alternatives that are considered in the BCE saves time and budget and allows the alternatives to be more fully developed which should minimize the need to reconsider the BCE as the design advances. If at the end of the fatal flaw analysis too many alternatives are still under consideration, a preliminary cost effectiveness analysis is performed to select the most viable. 3.1 Step 1 - Brainstorming It is important to consider the full range of potential alternatives to the problem. A good approach for identifying potential alternatives is brainstorming by the Design Team and stakeholders. The brainstorming should be based on the problem statement, drivers, and functional requirements. Sacramento Regional County Sanitation District 3

There is no precise number of brainstormed initial alternatives. The number can be as few or as many as necessary. When alternatives are generated, engineering judgment should be used to look for major redundancies and eliminate those alternatives that perform similar functions. In many cases, the alternatives will be self-evident. It may be useful, however, to think outside the box and consider types of alternatives which may help unearth an interesting candidate. Some project goals can be accomplished either with major capital facilities that require relatively little operating effort and expense, or alternatively with smaller or less costly facilities that require greater ongoing operating or maintenance effort. Consideration should be given to the base No Project alternative. In some cases, this would lead immediately to not meeting a level of service such as the District s discharge requirements. In other cases, a No Project alternative can be useful in determining if the system or subsystem is really critical to the Program. Alternative descriptions should be brief but have sufficient information to show how each alternative would solve the problem; fundamental differences between the alternatives; and key components (physical and functional features, sizing, etc.), phasing (to accommodate future increases in wastewater flows), advantages or disadvantages with respect to compliance with potential constraints relevant to the project. Redundant alternatives should be consolidated. 3.2 Step 2 Alternative Screening Potential alternatives identified during brainstorming are subjected to a fatal flaw analysis. 3.2.1 Fatal Flaw Analysis Fatal flaw analysis should consider that ability of potential alternatives to meet the project drivers and the project constraints. The alternatives are considered to be fatally flawed if they do not resolve the problem statement or if they meet any of the fatal flaw criteria. The failing alternatives are then removed from further evaluation. Examples of fatal flaw criteria are: Level of service: Creates a discharge that does not meet NPDES permit limits Project components are in conflict with District s established Levels of Service Schedule: Project cannot be completed by the required delivery date Project would delay other aspects of AWTP Program Sacramento Regional County Sanitation District 4

3.2.2 Additional Screening (Optional) If the fatal flaw analysis did not reduce the number of alternatives to about 5 or less, additional screening should be performed. The design team should develop suitable criteria for the additional analysis. The additional analysis can be performed on qualitative and/or quantitative basis. The criteria should be selected to identify significant differences between alternatives that would render some alternatives inferior to the others. The level of detail required for potential alternatives is based on planning level information. The descriptions and sketches could include process and instrumentation diagrams, flow schematics, site plans, and basic drawings. Site plans should be based on Program base mapping. Major existing underground pipelines and conduit that would need to be relocated should be identified. 3.2.2.1 Qualitative Analysis A qualitative analysis may allow for a fast screening and elimination of potential alternatives that have significant drawbacks but not fatal flaws. Example criteria could include process reliability, size of facilities (if related to construction costs), power requirements for major equipment, and construction schedule. Qualitative analysis can be performed using a 1 to 5 rating scale where 1 and 2 are considered low impact, 3 is considered moderate impact, and 4 and 5 are considered high impact. 3.2.2.2 Quantitative Analysis A preliminary cost effectiveness analysis can be performed on the potential alternatives. The cost effectiveness analysis is similar to the analysis discussed in Section 4 below but with less detail. The BCE Template discussed in Section 7 should be used to determine the net present value (NPV) of the potential alternatives. Direct costs could include probable construction, engineering, and operation and maintenance (O&M). O&M costs should be calculated based on a 60-year life cycle. The SRCSD has standards for the frequency of facility inspections, cleaning and regularly scheduled maintenance activities. Estimates for power and chemical consumption should be estimated. Other factors such as risks and environmental impacts and mitigations can be considered on a qualitatively on a non-economic basis. 3.3 Step 3 Final Alternatives The alternatives from Step 2 are subjected to a more detailed development. This evaluation employs Basis of Design Reports (BODRs) or preliminary designs of each alternative to prepare costs estimates and other information for the BCE. 3.3.1 Alternative Design Alternatives need to be adequately developed to allow estimates of capital, O&M and risk costs. Costs for expansions of new or existing facilities that may be needed in the future to handle increased flows will not be included in the BCE analysis. Costs for potential Sacramento Regional County Sanitation District 5

modifications or additional new facilities that may be needed if discharge requirements change in the future will be considered as risk costs. 3.3.2 Capital Costs Capital costs are required for the BCE. Capital costs are the actual anticipated costs to SRCSD for the implementation of each alternative and include: Construction This includes the probable cost for construction of the project, startup and testing, and spare parts. Planning level construction cost estimates have been prepared as part of the PMO Program Validation effort. These costs will be updated routinely as the projects move through their various phases and increasingly accurate information becomes available. Refer to Program and project level cost estimating procedures for additional information, including the contingency allowances to be used during various Program and project phases. Construction cost markups - See section A 1.3.2, construction cost estimating methodology for all markups to be included. Environmental Mitigation Cost - This cost includes only mitigation of environmental features required for the construction of the project. It is anticipated that mitigation costs will be either negligible or similar between alternatives. In these cases, environmental mitigation costs can be ignored for the BCE. If environmental mitigation costs are identified to be significant and to vary between alternatives, they will need to be included in the BCE. Right of Way No ROW costs are anticipated in this Program Design and construction acceleration may be required for projects in order to meet the Program s overall schedule. Each alternative shall have a design and construction schedule with sufficient detail to determine if construction can be completed within the time constraints of the master program schedule. If the project cannot be completed within the master program schedule constraints, the design and/or construction will need to be accelerated. Accelerating the design and/or construction schedule could include prepurchasing equipment or requiring longer added construction shift or changes in construction methods. The construction costs associated with acceleration need to be included in the capital cost. Risk costs associated with acceleration need to be considered also. 3.3.3 Operation & Maintenance The checklist of activities to be considered for O&M cost estimates should include: Labor, including supervisory labor (planning, organizing, scheduling and dispatching) Regular monitoring for performance, biological impact, etc. Laboratory analysis Sacramento Regional County Sanitation District 6

Electricity, chemicals, materials, supplies and equipment Periodic inspections and repairs Major periodic overhaul, and component replacements 3.3.3.1 Labor The AWTP Program will require additional labor to operate and maintain the new facilities and may also impact operation of some existing facilities. Information on labor impact estimates should include the following information: Description of the types of labor support activities required for O&M, monitoring, and laboratory Schedule of annual and additional periodic maintenance Hours per year required Labor costs will be calculated using a standard rate of $93 per hour. All sources used to derive O&M costs should be cited and referenced. (Note: Some projects may effectively reduce existing maintenance costs, which should be included as a benefit in comparison to other project alternatives. In general, however, labor savings related to existing facilities cannot be taken into account unless positions are reduced or until five years has passed.) 3.3.3.2 Electricity Costs AWTP alternatives will require electric power. These costs are identified separately. Consideration should be given to variations in electrical costs during peak demand and other times. Costs are in kilowatt-hour. Depending on the project being evaluated, the uncertainty of the cost of power generation should be considered. If power costs are significant and could make a difference in the comparison between alternatives, it is recommended to include a sensitivity analysis of the impact of their potential variation. 3.3.3.3 Materials, Supplies & Equipment Cost Some projects may require the use of chemicals or supplies. Annual chemical and supply costs should be calculated for the BCE. Chemical and supply costs should be based on actual costs at SRWTP or supplier quotes. Equipment renovation and replacement costs should be estimated. Equipment costs also include major tools for carrying out all O&M duties. 3.3.4 Salvage Value and End of Life Disposal Cost Major capital projects often incur major expenses at the end of their planned asset life. In most instances, they may be added costs; in others they may be revenues from salvage sale of the asset or parts of the asset. End of life impacts should be based on a 60 year planning period. Sacramento Regional County Sanitation District 7

3.3.5 Indirect Costs Indirect costs include risk, public impact, schedule acceleration, and permanent and temporary public impacts. 3.3.5.1 Risk Costs Adverse events can occur anytime during construction and/or the service life of a project. These risk events, if unaccounted for, can potentially alter the life cycle value of a project to the degree that can make the project alternative less attractive compared to the alternatives discarded during the screening process. Therefore, efforts must be made to understand and, if possible, quantify risks and consider potential uncertainties. Alternatively, a risk premium can be added to alternatives with unusual risks (e.g., price escalations for certain materials beyond those included in the baseline estimate, or uncertainties associated with future procurement of specific replacement parts for newer technologies, etc.) Risk can be defined as the potential for realizing unwanted consequences of an event or the possibility that the event has an unfavorable outcome. Risk is measurable, and refers to situations where probabilities can be known. Typically, the majority of the project risks for the AWTP Program can be categorized into the following areas: Accidents/Safety Issues Cost Volatility Schedule Delay Construction O&M Equipment failure Changes to discharge requirements When considering risk, the following basic questions should be considered for each alternative: What can happen? AWTP construction can be delayed, construction and operations cost overruns occur, operation of new unit processes may be difficult to optimize, facility service life is less or more than expected, input costs such as electricity are highly volatile and could increase dramatically during the life of a project, revised discharge requirements could require additional treatment unit processes. How likely is it to happen? Some events are more likely to happen than others. Certain types of projects have predictable costs while others are less so. What are the consequences of an event happening? Sacramento Regional County Sanitation District 8

The AWTP Program is on a mandated schedule and delays in becoming operational have considerable costs. The loss of an AWTP unit process can result in significant downstream impacts that entail significant costs. Although in other cases, the failure of a specific ancillary process may result in minimal impact. Potential future changes to discharge requirements could require some unit processes to be replaced or highly modified. 3.3.5.2 Determining Probabilities Uncertain project outcomes sometimes have fairly well-known probabilities, but sometimes they do not. Among the better known probabilities are those that are associated with some recurring factors that have well-documented historical variability. Examples of recurrent probability outcomes include the following: Equipment and facility failure rates, which are documented and differentiated for various types of equipment. (Maintenance histories of most types of existing SRWTP equipment can be queried using Maximo to calculate annual average repair costs.) Worker injuries for some ongoing or frequently repeated SRCSD activities. Environmental issues associated with construction at SRWTP such as certain nesting birds or cultural resources For these types of uncertain outcomes, the information available on past patterns can provide a reasonable basis for projecting probabilities of future outcomes. Other sources of project uncertainty are not supported by direct experience. Quantifying these types of risk requires the use of informed judgment. Sources of such judgmental probabilities may include: Experience of other agencies in similar circumstance Judgment of SRCSD staff, PMO staff, or others who are familiar with the underlying uncertainty, and have at least an anecdotal basis for assigning probabilities. In some cases, the sensitivity of a specific risk should be evaluated by changing the probability of the risk occurring. This can provide considerable insight into the relative importance of the risk in selecting the preferred alternative. 3.3.5.3 Quantifying Risk Costs Risk costs are typically calculated as the probability of the risk event times the financial consequence of the event, or the expected value of the event. : The risk costs can generally be quantified based on historical plant data for the following types of failures or hazards: Mechanical failure Electrical or control systems failure Sacramento Regional County Sanitation District 9

Hostile environment or fire Structural failure from an earthquake Inadequate treatment capacity Offsite discharge 3.4 Public Impact Costs Public impact costs are minor or non-existent for SRWTP projects including most AWTP projects. Public impacts can be temporary, during the construction of a project, or permanent, lasting throughout the life of the project. For AWTP projects, potential public impact costs such as vibration, noise, dust, odor and aesthetics either do not apply or will be adequately mitigated to prevent any cost to the public. The remaining potential public impact is anticipated to be traffic delays during construction due to the amount of truck traffic delivering equipment and material. These costs are only important for the BCE if they would be significantly different between alternatives. Public impacts that cannot be quantified or mitigated by the design should be listed in the nonquantifiable factors. 3.5 Non-Quantifiable Factors Non-quantifiable costs and benefits, or intangibles, should also be considered for each alternative. The analysis can be performed using a 1 to 5 rating scale with 1 and 2 are considered low impact, 3 is considered moderate impact, and 4 and 5 are considered high impact. Examples of non-economic costs are as follows: Public relations or SRCSD image (External Customer) Operator preference (Internal Process and Employees) Social impacts such as potential for loss of business, and/or noise (External Customer) 4.0 Analysis The analysis step of the BCE process compares the alternatives against each other and provides the basis for selecting a preferable alternative. The analysis is based on the new positive value (NPV) and non-quantifiable factors. 4.1 Calculating Life Cycle Costs The key variables that are used to calculate life cycle costs are duration, discount rates, inflation rate, and electricity escalation rate. The duration for AWTP BCEs will typically be 60 years. A standard discount rate of 5% will be used with discount rates of 3% and 7% used in Sacramento Regional County Sanitation District 10

sensitivity analysis. The standard inflation rate is 3%. The standard electricity escalation rate is 5 % but it can be varied as part of sensitivity analysis to energy costs. 4.2 Sensitivity (Uncertainty) Analysis Uncertainty can be defined as a broader set of cases in which the outcomes are recognized to be variable and not predictable, and in addition, their outcomes and probabilities may not be known or knowable in advance. Some degree of uncertainty will be associated with almost any significant capital project or utility program. Utility capital projects tend to have long lives, which means that their life cycle cost analyses will extend far into the future, which is inherently uncertain. For this reason, a method known as sensitivity analysis is sometimes used to evaluate uncertainty. Generally speaking, a sensitivity analysis is a method to test what-if scenarios of the NPV analysis by varying certain parameters. In a typical sensitivity analysis, the value of an input variable that is potentially uncertain is changed, while all the other project variables are held constant, and the amount of change in results is noted. The same process is repeated for other input variables that are considered uncertain. Finally, the variables chosen can be ranked according to the effect of their variability on the net present value results. The parameters that are typically varied in a sensitivity analysis are: Discount and Inflation (Escalation) Rates - The discount rate is important in comparing O&M costs to capital costs. Inflation and escalation rates are the expected rate at which prices for inputs to the project increases over time. These rates typically have the most impact on the results of the sensitivity analysis. It should be noted that inflation rates sensitivity are typically assigned to construction cost estimates. Risk Levels- The probability of an extraordinary and/or uncertain event occurring can impact the total lifecycle costs of a project. Similarly, risk levels can vary between alternatives and the use of a risk premium can provide more realistic financial comparisons between alternatives. Cost Estimates This investigates whether the outcome of the NPV analysis is subject to change based on conservatism and/or optimism in developing cost estimates for capital, operations, maintenance, or other specific types of costs. Costs can be adjusted lower or higher (i.e. halved or doubled) as may be appropriate. 4.3 Recommendation of a Preferred Alternative The selection of the preferred alternative is based on the Total Cost in NPV (in today s dollars) and analysis of non-quantifiable factors. The project team must evaluate all results intuitively along with the economic factors and benefits to reach consensus on the preferred alternative. The case for the recommended alternative should be made clear and should stand up to scrutiny. Depending on the project, it is suggested that the stakeholders have input and agree with the selection of the recommended alternative. The recommended alternative should represent the overall best value alternative for the SRCSD and the community. Sacramento Regional County Sanitation District 11

The project team should also be aware of the degree of public influence on the project or specific project alternatives. The selected preferable alternative should promote the general welfare of the public and should be presented as such. The conclusion of the BCE should provide the justification for the recommended alternative. The justification should demonstrate how the recommended solution provides the best overall value when considering level of service, economical factors, risk, and intangible factors. 5.0 BCE Documentation The BCE process must be well documented to allow a thorough review and to record the analysis for future reference. The documentation will consist of written summaries of the steps used to develop alternatives including their costs and risks. It is anticipated that the BCE documentation will be summarized in the body of the associated BODR or design documents and attached to the report. 6.0 Reviews and Approvals All BCEs will be reviewed and signed off by the Program Engineering Lead, the BCE Coordinator (Dan Wilson) and the Program Advisor, before approval by the Program Manager. Dollar- based delegated authority for major cost outlays specific to this Program is covered elsewhere. Sacramento Regional County Sanitation District 12