Gate Value Method Overview document

Similar documents
Cumulative trends Problems and issues since last report

EARNED VALUE MANAGEMENT. Is it worth the effort?

INSE 6230 Total Quality Project Management

Earned Value Management An Overview March 2014

RETURN TO ROME Dr. Kenneth F. Smith, PMP Project Management Fundamentals 1

Project Performance Evaluation By Earned Value Method

Earned Value Management - EVM

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

Project Management -- Monitoring the progress

Earned Value and PRINCE2 Alex Davis. Programme Manager Close Combat Programme Support Office Ministry of Defence

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

CS 413 Software Project Management LECTURE 9 COST MANAGEMENT FOR SOFTWARE PROJECT III

Department of Industrial Engineering

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

Earned Value Formulae

Earned Value Management Handbook. arne. alu

PROJECT MANAGEMENT BODY OF KNOWLEDGE

The Cost Monitoring of Construction Projects Through Earned Value Analysis

PMP Exam Prep Coaching Program

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

MMZG 523 PROJECT MANAGEMENT

Detailed Project Scheduling and Cost Management

Spheria Australian Smaller Companies Fund

From Suspicion to Invaluable Transition of Two Project Managers

The First Steps in Implementing a Simplified Earned Value Management System

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM

THE PMP EXAM PREP COURSE

Earned Schedule Analysis

EARNED VALUE AS A RISK ASSESSMENT TOOL

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327

Project Assessment Exercise

Professional Development Seminar Series

NEW HORIZONS ONLINE LIVE. Project Management Professional (PMP ) PMBOK Guide 6th Edition DAY 4

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

Administration. Course Aim. Introductions

Self-Assessment Questions for Module 07 Project Cost Management

Schedule Analysis and Predictive Techniques Using Earned Schedule. 16 th IPM Conference Tysons Corner, Virginia

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management

HUD NSP-1 Reporting Apr 2010 Grantee Report - New Mexico State Program

Project Connect Connect January 11, 2012

Thomas Carlos Consulting. Simple Earned Value Management

Earned Value Management Guide

PROJECT BY PROJECT MANAGEMENT T OOLS

30 April 2 May 2018 ICC Sydney Unlocking the Future through Systems Engineering. sete2018.com.au BRETT THIELE

Security Analysis: Performance

A Case for Project Revenue Management. Peter Varani PMP

QUARTERLY FINANCIAL REPORT March 31, 2018

Humphreys &Associates, Inc.

QUARTERLY FINANCIAL REPORT June 30, 2017

Title: COST CONTRACT CONTINUOUS MAINTENANCE AND EMERGENT WORK REPORT. Number: DI-FNCL Approval Date:

Factor Leave Accruals. Accruing Vacation and Sick Leave

TRACKING AND MANAGEMENT OF CONSTRUCTION PROJECTS USING PRIMAVERA

Predicting The Future

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

Earned Schedule Training

Connecting Earned Value to the Schedule

MEDICAID FEDERAL SHARE OF MATCHING FUNDS

for 9 Sep 15 SoCal ICEAA Workshop

Earning Value From Risk

Earned Schedule in Action

Project Connect. July 11, 2012

Project Connect. May 9, 2012

The Mystery of Earned Value - An Oil & Gas Owner s Perspective

EV in a War Zone: Understanding Earned Value & How to apply it.

IP-CIS : CIS Project Management

QUARTERLY FINANCIAL REPORT December 31, 2017

Corporate Accounting: Earnings and Distribution

Review of Registered Charites Compliance Rates with Annual Reporting Requirements 2016

Carlos Consulting Group

Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique

Performance measurement

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

A Layman s Guide to Earned Value

Project Connect. June 22, 2011

Prepared by DCMA Lockheed Martin Fort Worth

Earned Value Management

2011 Budget Initial Stakeholder Call

Financial & Business Highlights For the Year Ended June 30, 2017

PROJECT COST MANAGEMENT

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

Effective Budgeting and Cost Control. Contents are subject to change. For the latest updates visit

Project Connect. September 14, 2011

Danny Elder - KIDASA Software, Inc.

SAMPLE. AACE International Recommended Practice No. 80R-13

INTRODUCING PROJECT COST MANAGEMENT EXERCISES & QUIZ. Introducing Project Cost Management Exercises & Quiz

Approve Assure Note. Board of Directors Meeting Report 31 July Agenda item 254/13. Title. Sponsoring Director. Authors.

WESTWOOD LUTHERAN CHURCH Summary Financial Statement YEAR TO DATE - February 28, Over(Under) Budget WECC Fund Actual Budget

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

SUGGESTED SOLUTIONS. KE2 Management Accounting Information. March All Rights Reserved

The total number of people officially waiting for treatment to begin is likely to be around 5.38 million compared to the current 4.08 million.

Work Program Integration Initiative (WPII)

A Study on Risk Analysis in Construction Project

Project CONNECT Executive Steering Committee Update. February 26, 2014

Predicting Project Completion Date Using Earned Value Management

Formulas to Know for EXAM

Earned Schedule schedule performance

Transcription:

Gate Value Method Overview document Version 7 Dated 7 th May 2009 Author: Martin Vaughan Note: This document has been prepared by Core Consulting Group to explain the Gate Value Method. While any person may use and adapt the approach and ideas contained within, Core Consulting Group must be recognised as the originator of this approach. A statement along the lines of Noted Core Consulting Group are the originators of the Gate Value Method would be expected.

Core Consulting Group 1 INTRODUCTION The Gate Value Method was developed by Core Consulting Group as an alternative to Earned Value for business and technology projects. Organisations often struggle with the implementation of Earned Value due to the effort required to set up and maintain Earned Value Management systems. The Gate Value Method is a far simpler approach which can provide significant benefits in terms of visibility of cost performance without the overhead and complexity associated with Earned Value Management systems. The heart of the Gate Value Method is aligning Planned Value to key gateways through the project rather than to work packages and specified time periods. Rather than deriving dollar values at a point in time, the method focuses on a time for a particular dollar value. The Gate Value Method therefore supports staged delivery approaches, particularly phased delivery as promoted by PRINCE2 and the Gateway Review Process promoted by the Victorian State Government (initially developed by OGC UK). This document requires some understanding of Earned Value by the reader, but not detailed knowledge. The Earned Value approach has been clearly defined in Australian Standard AS4817 Project performance measurement using Earned Value. Readers should note that the approach to this document is Open Source. This means organisations and individuals are free to use the method on the condition that Core Consulting Group is recognised as the originator of the method and any contributions or modifications to the method are fed back to our office via email (info@coreconsulting.com.au) so they may be made available to others. 2 Determining Planned Value (PV) Typical Earned Value requires organisations to estimate work packages at a detailed level then distribute these dollar estimates to measurable work packages and also assign Earned Value Techniques (ways of measuring Earned Value). Planned Value is then derived cumulatively on a time phased basis, usually end of month. This can prove to be difficult, complex and time consuming. The Gate Value Method approach simply requires detailed estimating for the next stage or phase of the project, eg getting from Gate 1 to Gate 2. The estimate is therefore assigned to the next gate. A schedule for that next stage, which should be done anyway, is used to predict when that gate will be achieved. The Planned Value curve is therefore derived from the dates the gates will be met and the dollar values of those gates. Using a Rolling wave approach to planning, budget allowances can be made for future work, for example getting from gate 3 to 4 and 4 to 5. These can then be validated as the next gate gets closer and detailed estimates are made. These plans can be validated at gate reviews. CCG Gate Value method overview Page 2 of 6

2/02/2009 16/02/2009 2/03/2009 16/03/2009 30/03/2009 13/04/2009 27/04/2009 11/05/2009 25/05/2009 8/06/2009 22/06/2009 6/07/2009 20/07/2009 3/08/2009 17/08/2009 Core Consulting Group An example is shown below for a sample project with gates added at key points in the schedule. Planned Value - Budget to gates BAC $ Jan Feb Mar Apr May Jun Jul Aug Sep Business Requirements $20,000 Gate 1 - Requirements Review $ 20,000 Functional Specification $50,000 Technical Specification $40,000 Gate 2 - Prelim Design Review $ 90,000 Detailed design $90,000 Gate 3 - Detailed Design Review $ 90,000 Build $180,000 Gate 4 - Code freeze $ 180,000 Test $165,000 Gate 5 - Operational readiness $ 165,000 Deploy $20,000 Gate 6 - Closure $ 20,000 $565,000 Gate Start 1 2 3 4 5 6 Dates 2/02/2009 13/02/2009 20/03/2009 24/04/2009 19/06/2009 31/07/2009 28/08/2009 PV gate $0 $ 20,000 $ 90,000 $ 90,000 $ 180,000 $ 165,000 $ 20,000 PV cum $0 $20,000 $110,000 $200,000 $380,000 $545,000 $565,000 The following graph shows the curve of Planned Value over time using the approach shown above. $600,000 $500,000 $400,000 $300,000 PV $200,000 $100,000 $0 3 Determining Earned Value (EV) Typical Earned Value requires Organisations to implement an approach whereby work packages are statused on a regular basis which then derives Earned Value at a point in time against each work package via an Earned Value Technique. Earned Value requires an historical control system capturing previous Earned Value at a detailed level as well as content for the graphical and statistical analysis. Earned Value requires discipline from Project Managers and alignment of Actuals to ensure Actual Cost and Earned Value are recorded in the same period. All of which again can prove to be difficult, complex and take significant effort. The Gate Value Method approach is far simpler since analysis is only ever done as a gate is passed. At that point in time the Earned Value is known, it is the value of the gate. The Earned Value figures are therefore derived from the dates the gates are met and the dollar values of the gates. CCG Gate Value method overview Page 3 of 6

Core Consulting Group An example is shown below for the sample project as it passes through Gate 2. BAC $ % Compl Jan Feb Mar Apr May Jun Jul Aug Sep Business Requirements Gate 1 - Requirements Review $20,000 100% Completed 20/2/09 $ 20,000 Functional Specification Technical Specification Gate 2 - Prelim Design Review $90,000 100% Completed 10/4/09 $ 90,000 Detailed design Gate 3 - Detailed Design Review $90,000 0% Build Gate 4 - Code freeze $180,000 0% Test Gate 5 - Operational readiness $165,000 0% Deploy Gate 6 - Closure $20,000 0% $545,000 Earned Value - Status as at Gate 2 Gate Start 1 2 3 4 5 6 Actual 2/02/2009 20/02/2009 10/04/2009 % Compl 100% 100% 100% BAC gate $0 $ 20,000 $ 90,000 EV inc $0 $20,000 $90,000 EV cum $0 $20,000 $110,000 4 Determining Actual Cost (AC) Traditional Earned Value requires Project Managers to extract Actual cost, against work packages on a regular basis, typically end of month. Since this ties in well with normal accounting practices, extracting Actual costs is fairly straight forward. Complexity sometimes arises with Accruals, with aligning Actual Costs with Earned Value however and with structuring cost control accounts in line with work packages. The Gate Value Method approach only requires calculation of cumulative Actual cost as each gate is passed, incremental Actual cost can be derived. There is no need to structure Cost control accounts by phase or work package. Since a gate may fall mid month, an Estimated Actuals approach may be required to determine Accrual of Actual costs since the previous end of month cumulative Actual cost. For mature environments, Actual costs at a point in time may be possible directly from the accounting system. The example below shows the same example project with hypothetical Actual costs added at the end of each gate (they would have been obtained from the accounting system plus an estimate of Accrual). Actual costs - as at Gate 2 Gate Start 1 2 3 4 5 6 Actual 2/02/2009 20/02/2009 10/04/2009 AC inc $0 $19,450 $74,430 AC cum $0 $19,450 $93,880 CCG Gate Value method overview Page 4 of 6

17/01/09 31/01/09 14/02/09 28/02/09 14/03/09 28/03/09 11/04/09 25/04/09 9/05/09 23/05/09 6/06/09 20/06/09 4/07/09 18/07/09 1/08/09 15/08/09 29/08/09 12/09/09 $ Core Consulting Group 5 Analysis 5.1 Graphical analysis Traditional Earned Value shows dollars over set time periods. The Gate review process shows dollar values at the gates. What can be easily derived graphically is the schedule variance in time. The example below shows a three week schedule variance graphically using a scatter graph (note the time increments are 2 weeks). Cost Performance Graph $600,000 $500,000 $400,000 $300,000 $200,000 PV EV AC $100,000 Schedule variance = -3 w eeks approx $0 Time 5.2 Numerical analysis Through analysis of the figures, more traditional Earned Value data can be derived including: CV = EV-AC Cost variance (-ve bad) CPI = EV/AC Cost Performance Index (<1.0 bad) Where EV is AC is Earned Value Actual Cost Cost Variance shows by how much the costs have already blown out. It is particularly useful for showing performance over time, trends etc if graphed. This can then be used to predict future performance, especially useful for deriving an Estimate at Completion (EAC). In the example, the numerical analysis would be as shown below: CCG Gate Value method overview Page 5 of 6

Core Consulting Group Gate 0 1 2 3 4 5 6 EV cum $0 $20,000 $110,000 AC cum $0 $19,450 $93,880 CV cum $0 $ 550 $16,120 CPI cum n/a 1.03 1.17 5.3 Independent Estimate at Completion Through derivation of CPI as a gate is passed, an independent Estimate to Complete (ETC) and hence Estimate at Completion can be derived using the formula: IEAC = AC + (BAC-EV)/CPIF Where CPIF is a forecast of CPI through to completion taking into account past performance, productivity and other factors BAC is Budget at Completion EV is Earned Value AC is Actual Cost From a Project Manager and Sponsor s perspective they are most interested in the Variance at Completion. The IEAC could be used if need be. VAC = BAC - EAC Cost Variance - as at Gate 2 In the example used in this document, the IEAC would be as shown below: IEAC Calc - as at Gate 2 Gate 0 1 2 3 4 5 6 BAC $565,000 EV cum $0 $20,000 $110,000 AC cum $0 $ 19,450 $93,880 ETC $565,000 $544,434 $436,112 EAC $565,000 $563,884 $529,992 Figures such as these would give the Project Manager confidence that the budget will be met despite being three weeks behind schedule. 6 Aligning gates to real work Since the method is reliant on gates, they must be representative of the culmination of lead up work. Gate names may change from organisation to organisation although often their intent is similar. Proposed gates could include: Validation of Concept and/or Strategic need, often aligned to initiation, sometimes culminating in a Business Requirements review Completion of feasibility, usually aligned to sign off of Business case and/or funding approval Design review aligned with culmination of design. This could be further broken down into Preliminary and Detailed design Completion of build (eg Code freeze), or alignment with commencement of System Testing, typically a Test Readiness Review Completion of testing and preparation for deployment, often aligned with an Operational Readiness Review. Completion and post project wrap up tasks, typically culminating in a Post Implementation Review or Project Closure Review. Potentially well after Project completion there may be a follow up Benefits Review. This could align with culmination of post project support. CCG Gate Value method overview Page 6 of 6