Preparing Renewable Energy Power Purchase Agreements in the Middle East and North Africa: Questions to Ask

Similar documents
PPAs and Tariff Design

Power Purchase Agreement (PPA) Guidelines. Zambia Lusaka August 7 to

The policy and regulatory aspects of a bankable solar power project. Uzbekistan Energy Forum, London 18 April 2018 Louis Skyner Partner

MIX ENERGY IN MOROCCO. Prospects for the development of ENR. Amman 08/09 October 2017

Morocco s experience in financing solar projects

We guide companies leading the electricity transformation

Investing in Renewable Assets in Emerging Markets

Key lessons from South Africa s Renewable Energy IPP Programme

Basics of PPA Negotiations. Eng. David M. Mwangi, Individual Energy Consultant Nairobi, Kenya

Key Elements of a Wind / Solar PPP. Cathy Oxby Commercial Director Mob:

Energiewende. Drivers and Enablers for German Offshore Wind. Dr. Martin Schöpe

Peter Wright. Renewable Energy Projects in Africa Comparing Procurement Models for Renewable Generation Capacity. Simmons & Simmons March 2015

Regional Power Market Challenges and Opportunities from Nepalese perspective

WALK-THROUGH THE LEGAL STRUCTURE OF PPA S عرض الهيكل القانوني التفاقيا شراء الطاق

Developing the Power Sector through Private Investment in Mongolia. Edgar Saravia Program Manager

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46))

Nigeria Power Series - Part 2: Unlocking Financing for Developing Independent Power Projects in Nigeria

Power Sector Reform and Investment Comparing Uganda with Kenya and Tanzania

DEVELOPING WIND AND SOLAR POWER IN VIETNAM: KEY ISSUES

83C Questions and Answers

THE MOROCCAN RENEWABLE ENERGY MARKET OPPORTUNITIES FOR INVESTORS IN MOROCCO. - May 5th,

Renewable Energy and Mining Summit. Toronto, September 25th, 2013

WASTE HEAT TO POWER. DOE; Pacific CHP; Northwest CHP; California Stationary Fuel Cell Collaborative. Project Financing Considerations.

PacifiCorp Utah All Source Request for Proposal 2016 Resource. Issued January 6, 2012 Responses May 9, 2012

EgyptEra Regulatory Framework to Develop RES Projects in Egypt

Conditions for tender of aid for electricity generated by onshore wind turbines, open door offshore wind turbines, and solar PV installations

ECONOMIC CONSULTING ASSOCIATES LIMITED 41 Lonsdale Road London NW6 6RA UK tel +44 (0) / fax +44 (0)

COMMON MARKET FOR EASTERN AND SOUTHERN AFRICA POWER PURCHASE AGREEMENT GUIDELINES

Trinity International LLP. Ana-Katarina Hajduka

UNIQUE ATTRIBUTES OF RENEWABLE POWER PURCHASE AGREEMENTS

Addressing financial risks in RE investment in East Africa. Focus on Ethiopia and Kenya

W rksh op on I vest est en t in i U.S.. Wi W n i d In I dustr st y r by Chin i ese Comp m anies B ijing, Ch C ina June 30, 2011 Inve v stme

Risks and Risk Management of Renewable Energy Projects: The Case of Onshore and Offshore Wind Parks

GREEK RENEWABLES SUPPORT SCHEME PROPOSALS

OPPORTUNITIES IN THE ON-GRID RE SECTOR IN NIGERIA

Gabriel Zeitouni, COWI A/S

Legal aspects to take into account for small hydropower projects in Africa

Investor presentation. December 2018

NIGERIAN POWER SECTOR REFORMS AND PRIVATISATION. By Bolanle Onagoruwa Director General, Bureau of Public Enterprises

Cross Border Electricity Trade

LEGAL ASPECTS OF PROJECT FINANCE. Anjan Neupane Partner/Advocate Neupane Law Associates IN NEPAL

Overseas Private Investment Corporation

World Bank s Energy Infra-SAP: The Case of Vietnam. ESMAP Knowledge Exchange Forum, London November 30 th 2017

Regulatory Overview Tunisia

IPP TRANSACTION ADVISOR TERMS OF REFERENCE

World Bank Group Risk Mitigation Solutions for Myanmar s Infrastructure Projects. Workshop Program

World Bank IBRD and IDA Guarantees: A Triple A Risk Mitigation

The Spread of Feed-in Tariffs: Lessons Learned

Cross Border Electricity Trade in South Asia- Role of Regional Regulatory Guidelines & Way Forward

IFC Transaction Advisory Services Creating opportunity where it s needed most. From Concept Design to Project Execution

October 8, 2015 Brookfield Renewable Energy Partners

EPC CONTRACTS FOR WIND ENERGY PROJECTS - SOUTH AFRICAN RE IPP PROGRAMME - LESSONS LEARNED FROM PHASES 1 AND 2 (OCTOBER 2012)

RAINMAKER ENERGY. Comments to 2011 NERSA REFIT Review Tariffs

Enabling Renewables at Scale: Key Needs and Opportunities for Grid-Connected Solar & Wind in Asia

REQUEST FOR PROPOSALS FOR LONG-TERM CONTRACTS FOR RENEWABLE ENERGY PROJECTS

Undertaking Successful PPPs in Kazakhstan

Understanding Risk and Preparing the RFP

An Overview of the Power Purchase Agreement for Solar Farms in Lebanon

Interruptible connections: Lessons from Flexible Plug and Play. Sotiris Georgiopoulos

POWER PURCHASE AGREEMENT GUIDELINES

AN UPDATE ON RENEWABLE ENERGY IN IRAN

Overseas Private Investment Corporation

Eskom 2018/19 Revenue Application

FY 2017 results. March 29, 2018

2015 Middle East and North Africa (MNA) PPI 1 Update

Corporate Renewable Energy Procurement

Financing Utility Scale Solar

DRAFT REQUEST FOR PROPOSALS FOR VARIABLE RENEWABLE DISPATCHABLE GENERATION ISLAND OF O AHU OCTOBER 23, Docket No

IFC Overview: WBG Risk Mitigation Solutions for Myanmar Infrastructure Projects. June 3, 2015

Designing Energy Markets for the Future

Manual for the IPP Checklist

Raising Equity for large biomass to power projects

INVESTMENT OPPORTUNITIES in Central Asia Power Sector

APPENDIX B: PORTFOLIO OPTIMIZATION MODEL

Global Project Finance Alert

RENEWABLE ENERGY PROJECT FINANCING

1: Levelized Cost of Energy. Calculation. Methodology and Sensitivity

IFRS accounting outline for POWER. Purchase

BETTER EUROPEAN STAKEHOLDER WORKSHOP. Results from the EC project RES Support Schemes and Cooperation Mechanisms in Europe

Role of Power Market and Market Intermediaries in Facilitating Investments in South Asian Region

presentation 2016 VHM GROUP OF COMPANIES

Perspective on Financing Wind Energy Projects. June 16, 2016

Prototype Wind PPA Term Sheet

Investor presentation. H results September 26, 2017

Investment Opportunities in the German Solar Industry

Public Private Partnerships for Infrastructure Financing

Past, Present & Future

DUKE ENERGY OHIO REQUEST FOR PROPOSALS FOR PEAKING/INTERMEDIATE POWER SUPPLY IN RESPONSE TO OHIO SENATE BILL 221

Saudi Arabia Solar Trade Mission: Financing Panel - Introduction. Tim Armsby, Partner and Regional Head of Energy & Infrastructure

GET FIT Programme. Energy Sector Working Group. Maputo, 25 May Julia Crause Infrastructure, Southern Africa KfW Development Bank

SOLAR PV INSTALLATION AT USC BASEBALL STADIUM

Cost of Equity (USD)

Feed in Tariff Guidelines

Electricity Sector Regulatory Developments, Opportunities and Challenges

The Question of Sovereign Guarantee for the Development of Electricity Generation in Ethiopia

Review of the Reform and Privatization of the Power Sector in Nigeria. Peter Kieran Dar es Salaam January 31, 2014

2011 All Source RFP Exhibit I

Dominion Energy Virginia

Feed-in Terms. (Victoria) VIC Version v1 01/13

GROWING OUR INDUSTRY-LEADING POSITION

Transcription:

IRENA IRENA 2016 2014 2016 1

Preparing Renewable Energy Power Purchase Agreements in the Middle East and North Africa: Questions to Ask IRENA 2016 2

INTRODUCTION» Countries in the Middle East and North Africa (MENA) are diversifying their energy resources to include renewable energy (RE)» As part of the RE transition, Governments are engaging the private sector by implementing projects on an independent power producer (IPP) basis» Power Purchase Agreements (PPAs) are an essential component of engaging RE IPPs» A PPA is the long-term contract between the power producer (IPP) and the power purchaser (offtaker) that governs the sale and purchase of power» This presentation outlines the important questions a government should consider if it is starting, or in the early stages of, an RE IPP process IRENA 2016 3

CONTENTS» Before you begin» General PPA structure» Risk allocation» Additional considerations» Disputes and termination» Additional terms» Institutional considerations IRENA 2016 4

BEFORE YOU BEGIN Why engage the private sector?» Allows the government to implement renewable energy projects without paying up-front capital costs. This frees up scarce governmental budget for investment in other sectors» Brings in private sector skills and capital for construction, operations, and maintenance» Brings in the private sector to make technology choices (both initial choices and upgrades during the operational life of the project) and manage procurement IRENA 2016 5

BEFORE YOU BEGIN How do you allow private investment in vertically integrated power market structures?» Three are three common ways to incorporate private sector participation in the power market:» Utility owns the system and contracts a private sector participant to either construct or operate and maintain the system (through EPC contracts, turnkey construction contracts, or O&M contracts)» A private developer owns and operates a power plant and sells energy to the market (either distribution companies or individual customers)» A private developer owns and operates a power plant and sells energy to a single bulk purchaser (the single buyer entity)» A PPA is needed in the third case (and can be in the second case) to set out the rights and obligations of the developer and a single buyer IRENA 2016 6

BEFORE YOU BEGIN Under what kind of market structure is a PPA needed?» Single buyer market structure: generators sell to a single bulk purchaser, who then sells to distributors and other large customers» Competitive wholesale market structure: generators sell directly to distributors, to other large customers, and/or into a spot market» PPAs are used in a single buyer market structure or with direct customers» A PPA sets out the rights and obligations of the developer and the single buyer» Establishes a clear price for energy for the duration of the contract IRENA 2016 7

BEFORE YOU BEGIN What are some examples of PPAs in MENA? Type of Generation Project Country Year Contract Price (US cents/kwh) Solar PV 200MW Sheikh Maktoum Solar Park Phase II Dubai, UAE 2015 5.85 Solar PV Sheikh Maktoum Solar Park Phase III first 200MW Dubai, UAE 2016 2.99 Solar PV 50MW Al-Aflaj Saudi Arabia 2015 4.9 Solar PV 50MW Mafraq Jordan 2015 6.9 Solar PV 30MW Adenium Energy Capital Jordan 2014 16.9 Solar PV FiT Program Egypt 2015 11.8 14.3 Solar CSP 160MW Noor 1 Ouarzazate CSP Morocco 2012 18.9 Solar CSP 200MW Noor 2 Ouarzazate CSP Morocco 2015 14.0 Solar CSP 150MW Noor 3 Ouarzazate CSP Morocco 2015 15.0 Wind 301MW Tarfaya Wind Farm Morocco 2014 5.2 Wind 850MW Tanger, Tiskrad, Laayoune, Jbel Lahdid, Boujdour, Midelt Morocco 2016 3.0 (avg) Wind FiT Program Egypt 2015 9.6 11.5 Combined Cycle Gas Turbine Carthage Power Tunisia 2002 Confidential Coal Hassyan coal power plant UAE 2015 4.5 IRENA 2016 8

GENERAL PPA STRUCTURE How should prices be determined? Feed-in Tariff (FiT) Description Price is usually set by the regulator for a defined term All developers who begin commercial operations or start construction by a certain date are eligible for FiT Best Used To provide the most transparency and certainty in pricing To allow market access for newer and smaller IPPs To develop many small to medium-sized projects, where it is more efficient to have a standardized contract across all of them Considerations Because the price is administratively set rather than competitively bid, FiT may not result in the least-cost projects When costs are declining, FiTs risk setting tariffs too high Competitive Tender International competitive tender among prequalified bidders, with winning bidders selected on price To increase chances of getting the lowest price possible through competition among qualified bidders To promote bids by credit-worthy IPPs with a proven track record For large projects or for a few specific project sites Competitive tenders can take more time and institutional capacity to implement It is possible to specify project sites for developers to bid on» In either case, a long-term PPA guarantees the IPP a pre-determined price over a defined period of time IRENA 2016 9

GENERAL PPA STRUCTURE How long should the contract be for?» Contracts typically run from 15 to 30 years from the date of commercial operation, though 20 years is typical. The PPA can include an option to extend or renew the term, or to transfer ownership to the offtaker» The term of the PPA must exceed the term of the loan. Lenders will not offer terms longer than the term of the PPA.» The IPP is responsible for securing financing and therefore for negotiating a PPA term that will allow for a reasonable loan term. Technology Type System Useful Life (years) Solar PV 25 40 Wind 20 Biomass CHP 20 30 Biomass heat 20 30 Solar water heat 10 25 Solar ventilation preheat 30 40 Ground source heat pump 20 (interior components); 100 (ground loop) http://www.nrel.gov/analysis/tech_lcoe_re_cost_est.html IRENA 2016 10

GENERAL PPA STRUCTURE How should energy prices be structured?» Mostly importantly, tariff calculations must be clear and well-defined for the length of the contract» Adjustment mechanisms must be agreed in advance» Energy prices can be flat, escalating, or decreasing over the life of the project» Fixed-price scheme: recommended when utility rates are expected to change significantly» Fixed-escalator scheme: price increases at a pre-determined annual rate» Tariffs can also be indexed to annual inflation (e.g. CPI, PPI) or changes in foreign exchange Solar tariffs have decreased over time IRENA 2016 11

GENERAL PPA STRUCTURE How should tariffs be structured?» The offtaker should bear the risk that either the capacity of the power plant or the energy generated is:» 1) not necessary (market risk)» 2) curtailed because of operational issues with the grid» 3) curtailed because the offtaker purchases energy from other sources» However, the offtaker should not have to pay for capacity that is not made available by the IPP IRENA 2016 12

GENERAL PPA STRUCTURE How should tariffs be structured? Description Benefits Considerations When to use it Take-and-Pay Offtaker pays a fixed tariff that includes a capacity charge (for available capacity, not dispatch) and output charge (for energy actually delivered) Capacity charge allows IPP to cover fixed costs and repay capital investments with a reasonable return to investors. The offtaker only pays for capacity plus energy that is actually dispatched IPP may be allowed to sell excess power to third parties to mitigate revenue risk and ensure it is able to meet debt obligations Typically used for dispatchable technologies (hydropower) Take-or-Pay Offtaker is required to take and pay a fixed tariff for all energy delivered. If the offtaker cannot physically take the energy, the offtaker pays based on curtailed (deemed) energy IPP is compensated for curtailed production due to grid constraints, emergencies, or the offtaker purchasing energy from other lower-priced sources Usually offtaker only pays for curtailment losses over a predetermined threshold Important to have reliable measuring equipment and agreed upon deemed generational formula Offtaker force majeure conditions must be clearly defined Typically used for non-dispatchable technologies (wind and solar) IRENA 2016 13

RISK ALLOCATION How does a PPA address risks?» RE PPAs are long-term in nature and thus face numerous types of risk during the term of the PPA. Risks need to be thoroughly identified and allocated to the party that is most capable of managing the risk» Main risks that IPPs face are demand and pricing. PPAs address these risks by establishing a long-term purchase obligation and a tariff formula that reflects the true cost of generating power. This guarantees a certain revenue stream over the term of the contract.» The higher the risk, the higher the tariff IPPs will demand. IPPs will require a greater return on investment for bearing more risk» A PPA should not push all risk onto one party or another, but allocate each type of risk to the party that is most capable of managing the risk IRENA 2016 14

RISK ALLOCATION Who should take on risks related to transmission of power and interconnection to the grid?» The IPP or the offtaker may be required to pay for transmission and interconnection costs:» If the IPP pays, the contract should be competitively tendered to secure the best price» The offtaker/government typically will have lower construction costs for transmission lines, but may not have sufficient funds or may not want to risk paying liquidated damages if transmission line construction is delayed» In a bundled system, the offtaker takes on transmission risks because the offtaker is responsible for power purchasing, transmission, and distribution» In an unbundled system, the offtaker also usually takes on transmission risks because the offtaker and transmission company are both government-owned. The offtaker then acts as guarantor of the transmission company s obligations IRENA 2016 15

RISK ALLOCATION How should currency risk be allocated?» Most lenders require the offtaker to take on these risks» General principles:» The payment currency should be easily converted to the debt currency» Can set up an offshore debt service reserve account» Can substitute other commodities for cash payment» Can obtain political risk insurance for currency inconvertibility» There should be no limit or additional approvals required to transfer funds abroad» The offtaker should provide security for its timely payments to the developer IRENA 2016 16

RISK ALLOCATION What are ways to mitigate currency risks?» If possible, PPA should be denominated in or benchmarked to the IPP s debt currency» If this is not possible» Ways to mitigate short-term exchange rate risk:» Denominate all tariff components in the debt currency and offtaker pays in the local currency equivalent» Derivatives and future currency swap arrangements» Ways to mitigate catastrophic devaluation risk:» Currency hedge IRENA 2016 17

RISK ALLOCATION How should legal and regulatory risks be allocated?» Changes in law or the tax regime can impact the IPP s returns» Most lenders require the offtaker to take on these risks» General principle is the IPP should be no better or no worse as a result of a change in law, policy, or regulations» If the IPP is disadvantaged, should receive reimbursement or an appropriate tariff increase» If the IPP benefits, should have an appropriate tariff decrease IRENA 2016 18

ADDITIONAL CONSIDERATIONS How should land use and siting be addressed?» Land use is typically the IPPs responsibility to secure, with the offtaker and/or government assuming more responsibility if either party must make the land available to the IPP» Lenders will insist that project site availability is secured for the term of the PPA Land use IPP Typically IPP s responsibility to secure, unless it depends on government approvals Offtaker/Government Should facilitate permitting if the offtaker/government is required to grant access, lease land, etc. Site Suitability If the IPP selects the site If the offtaker/government selects the site and bidders have limited ability to review the site IRENA 2016 19

ADDITIONAL CONSIDERATIONS How can grid connection and grid upgrading costs be allocated?» If a deep connection charge method is used, the IPP bears grid connection and upgrading costs. Costs may be prohibitively high for IPPs.» If a shallow connection charge method is used, the IPP bears the grid connection costs only.» It is possible to have a mixed charge in which the IPP pays for a portion of upgrading costs based on its proportional use of new grid assets. However, it is difficult to determine an exact and fair allocation of grid extension requirements and costs for an individual IPP. IRENA 2016 20

ADDITIONAL CONSIDERATIONS What are other system operation costs to consider? Type of Cost Description Profile Costs Capacity/adequacy costs Reduced average use of thermal power plants Curtailed VRE generation Balancing Costs Reduced need for backup capacity during peak load times for variable renewable energy Reduced full-load hours for dispatchable power plants, reducing the annual and life-cycle generation per capacity Generation is curtailed because of grid constraints Technology upgrades and additional costs to ensure that other power plants can ramp up when VRE generation drops, and vice versa IRENA 2016 21

DISPUTES AND TERMINATION How should disputes be settled?» The dispute resolution process must be clearly specified in the PPA» Best practice is offshore arbitration under internationally-accepted rules, such as:» The World Bank International Centre for Settlement of Investment Disputes» The International Chamber of Commerce» The United Nations Commission on International Trade Law» The London Court of International Arbitration» Independent engineer to settle disputes» Non-binding mediation, for example by a regulator» National bodies (such as the Ministry of Energy or regulator) should not be responsible for settling disputes because of the risk of bias IRENA 2016 22

DISPUTES AND TERMINATION Under what circumstances can either party terminate the contract?» Termination should be limited to very significant events, with a pre-determined period to remedy the situation» Failure to obtain internal, regulatory, or third party approvals» Failure to obtain necessary permits» Failure to enter into an acceptable interconnection agreement» Failure to secure transmission access or site control» Failure to commence operations (e.g. after 180 days)» Abandonment of project (e.g. for over 30 days)» Failure to secure financing (e.g. after 90 days of financial close)» Repeated breach by IPP in delivery of energy (e.g. within 90 to 180 days of notice of breach)» Offtaker failure to pay (e.g. within 90 to 180 days of notice of breach)» Bankruptcy or solvency issues for either party IRENA 2016 23

DISPUTES AND TERMINATION What should be the rights and obligations in the event of termination?» In the event of termination, lenders want to make sure project debt will still be satisfied» If offtaker terminates the contract without cause, the offtaker should provide a termination payment that at least covers the full amount of the IPP s remaining debt and present value of cash flows» If the IPP terminates without cause, government would take over the project and the IPP would pay whatever engineering costs are required to get the project operating again IRENA 2016 24

DISPUTES AND TERMINATION What happens in the event of force majeure?» Force majeure does not necessarily mean the contract must be terminated. Both parties should aim to resume the terms of the contract as soon as possible after the force majeure event is over» Extensions should be granted, and deadlines adjusted, for delays due to force majeure» If force majeure affects the offtaker, the PPA should have provisions to maintain payments to the IPP» If force majeure affects the IPP, payments may be continued (for local political events) or suspended (for natural or foreign political events) IRENA 2016 25

DISPUTES AND TERMINATION What types of insurance are available?» Some events are covered under common types of business insurance for the IPP, such as:» Fire and flood» Mechanical malfunctions» Business interruption» Business liability» MIGA offers political risk insurance policies for equity investors and lenders that covers:» Currency convertibility and sufficient foreign reserve risk» Legal and tax change risk» Cancellation of permits and/or concessions risks» Expropriation risk» Not all force majeure risks can be covered by insurance. These risks are, by definition, outside of both parties ability to manage. Therefore, the key is to be clear about how these risks are allocated between the IPP and the offtaker IRENA 2016 26

ADDITIONAL TERMS What are common additional terms that can be included in a PPA?» Liquidated damage regime: requires the IPP to pay the off-taker a certain amount of money for each day of delay in operations» Minimum capacity and availability requirement: requires the IPP to guarantee a minimum level of capacity and availability (minimum level should be lower for non-dispatchable renewables because the IPP cannot control changes in weather)» Maximum purchase obligations for the off-taker: any excess energy generated beyond the maximum may be purchased at a lower price or at spot prices (if there is a spot market)» Conditions for sale or transfer of ownership should be clear to ensure risk-free transfer of obligations IRENA 2016 27

INSTITUTIONAL CONSIDERATIONS How can governments build capacity to negotiate renewable energy PPAs?» As renewable energy becomes more competitive with conventional generation and governments procure more renewable energy IPPs, agencies will need the capacity to negotiate multiple renewable energy PPAs at the same time» Organizations like IRENA can provide technical assistance to help with the initial negotiations and with drafting standard renewable energy PPAs for RfPs» It is important for the off-taker to have qualified legal counsel when drafting and negotiating a PPA» Sections of PPAs can become more standardized as more PPAs are concluded» With this technical assistance, agencies can build internal expertise over time IRENA 2016 28

INSTITUTIONAL CONSIDERATIONS What should be the role of the regulator?» Regulators are important to establish a level playing field for renewable energy IPPs to compete with conventional generation» The regulator should review and approve PPAs, ensuring that:» The PPA ensures a safe and reliable supply of electricity at a reasonable cost» The PPA protects consumers and ensures the long-term financial sustainability of the IPP» The PPA terms are consistent with the grid code, interconnection agreement, and generation license» The regulator can proactively develop standards which can be incorporated into PPAs» People need to have confidence that the regulator is acting in the best interest of consumers. This means:» The regulator should act as an independent third party to enforce the terms of the PPA» It is important to minimize regulatory lag IRENA 2016 29

INSTITUTIONAL CONSIDERATIONS How do PPAs impact a government s ability to shift towards competitive wholesale markets and regional approaches?» Competitive wholesale market: at every moment, generators compete on price to sell to the system operator» Regional approaches: cross-border electricity trade requires a common regulatory framework, including synchronized grid codes and common pricing principles» Under these approaches, long-term, fixed rate agreements through PPAs will need to be phased out over time as the term of the PPA ends. Enacting these policy shifts take time, however. The best way for governments to limit the impact of PPAs is to try to negotiate the best possible price» Allowing third-party sales is another possible option to provide greater flexibility during the transition. However, the offtaker should ensure that it has priority IRENA 2016 30

CONCLUSION» The renewable energy transition has already begun in MENA» Engaging the private sector can help MENA countries harness their vast endowment of renewable energy resources» Bankable RE PPAs are an essential part of engaging the private sector because they allow private sector developers to get an acceptable return on their investments while striving to provide the lowest possible prices for consumers» As governments build capacity in this process, it is important to complement RE PPAs with an effective, efficient regulatory framework that balances customer protection with private sector needs IRENA 2016 31

REFERENCES General PPA Info» http://ppp.worldbank.org/public-private-partnership/sector/energy/energy-power-agreements/powerpurchase-agreements#key_features» Reginal Center for Renewable Energy and Energy Efficiency (2012). User s Guide for the Power Purchase Agreement (PPA) Model for Electricity Generated from Renewable Energy Facilities. http://www.rcreee.org/sites/default/files/users_guide_ppa_reegf.pdf» Power Africa (2015). Understanding Power Purchase Agreements. http://cldp.doc.gov/sites/default/files/understanding_power_purchase_agreements.pdf» OPIC, ITA, USAID, and USTDA. Important Features of Bankable Power Purchase Agreements for Renewable Energy Power Projects. https://www.opic.gov/sites/default/files/files/10%20elements%20of%20a%20bankable%20ppa.pdf» Lowder, D., Peters, K.T., and Soldani, D.A. (2014). Renewable Energy Projects: Negotiating Power Purchase Agreements. http://media.straffordpub.com/products/renewable-energy-projects-negotiating-powerpurchase-agreements-2014-05-21/presentation.pdf» National Renewable Energy Laboratory (2009). Power Purchase Agreement Checklist for State and Local Governments. http://www.nrel.gov/docs/fy10osti/46668.pdf IRENA 2016 32

REFERENCES (CONTINUED) Developing Renewable Energy Projects» Eversheds and PWC (2016). Developing Renewable Energy Projects: A Guide to Achieving Success in the Middle East. https://www.pwc.com/m1/en/publications/documents/eversheds-pwc-developing-renewable-energyprojects.pdf» International Finance Corporation (2015). Utility-Scale Solar Photovoltaic Power Plants: A Project Developer s Guide. http://www.ifc.org/wps/wcm/connect/f05d3e00498e0841bb6fbbe54d141794/ifc+solar+report_web+_08+05.pdf?mod=ajperes» ETSAP and IRENA (2015). Renewable Energy Integration in Power Grids: Technology Brief. http://www.irena.org/documentdownloads/publications/irena- ETSAP_Tech_Brief_Power_Grid_Integration_2015.pdf Feed in Tariffs and Competitive Tenders» Kreycik, C., Couture, T.D., and Cory, K.S. (2011). Procurement Options for New Renewable Electricity Supply. http://www.nrel.gov/docs/fy12osti/52983.pdf Costs» Knight, R. (2006). Proposals for a DG Connection Charging Framework in the EU. Integration of DG into electricity networks workshop, Berlin. https://www.ecn.nl/fileadmin/ecn/units/bs/dg- GRID/Events/Berlin/dggrid-workshop2_connection-charging.pdf» Ueckerdt, F., Hirth, L., Luderer, G., and Edenhofer, O. (2013). System LCOE: What are the costs of variable renewables?. https://www.pik-potsdam.de/members/ueckerdt/system-lcoe-working-paper IRENA 2016 33

MODEL PPAS» http://ppp.worldbank.org/public-private-partnership/sector/clean-technology/agreements-renewable-energyprojects-ppa (PPAs for different RE sources, together with laws devoted to those sources, from various countries updated October 2013)» Wind Power (Brazil, France, India, Sri Lanka, Pakistan, United States)» Solar Power (United States and US Virgin Islands)» Hydropower (Brazil, India, Southeast Asia, Balkans)» Biomass and Biofuel (Brazil, India, United States)» Geothermal (United States, France) IRENA 2016 34

www.irena.org www.twitter.com/irena www.facebook.com/irena.org IRENA 2016