Project costs have to be actually incurred due to the project implementation, in order to be considered as eligible costs.

Financial errors in FP7 How to improve the quality of financial statements?

AUDIT CERTIFICATE GUIDANCE NOTES 6 TH FRAMEWORK PROGRAMME

AUDIT CERTIFICATE WORKING NOTES 6 TH FRAMEWORK PROGRAMME

Certification of Financial Statements for ICT PSP projects

Audit certificates. Training Seminar Brussels 28 November 2006

Market Replication: Eco-Innovation F I N A N C I A L G U I D E L I N E S for co-ordinators and co-beneficiaries

Mono-Beneficiary Model Grant Agreement

Coordinators' day on ICT PSP project management Financial Issues, Reporting, payments, cost claims and Certification Modalities

Multi-beneficiary Model Grant Agreement

Audit certificate template for Horizon2020 projects funded by SERI

FP6 Contract and Financial Reporting. The Basics for EC Consortia. Linda Polik Research Services

European Metrology Programme for Innovation and Research (EMPIR) Multi-beneficiary Model Grant Agreement. (EMPIR MGA - Multi)

Multi-beneficiary Model Grant Agreement for Members

MODEL FOR THE CERTIFICATE ON THE FINANCIAL STATEMENTS

Practicalities in the Financial Management of FP7 projects - An outlook to audits and Horizon 2020 rules

Model terms of reference for the certificate on the financial statements

RESEARCH TRAINING NETWORKS

Multi-Beneficiary Model Grant Agreement

Mono-Beneficiary Model Grant Agreement

Multi-Beneficiary Model Grant Agreement

Guide to Financial Issues relating to Indirect Actions of the Sixth Framework Programmes

IMI Financial Guidelines

COMMISSION OF THE EUROPEAN COMMUNITIES DIRECTORATE-GENERAL INFORMATION SOCIETY AND MEDIA

ANNEX III : ESTIMATED BUDGET OF THE ACTION Project Title : All amounts should be provided in euro. Table 1 : Overview of expenditure 1/10

COMMISSION DECISION. of

IMI Financial Guidelines

Financial Rules in FP7 Projects

Financial Guidelines for Beneficiaries EDCTP Association October 2016

Annex X to the Model LIFE Grant Agreement Financial and Administrative Guidelines

Funding for companies research and development operations Eligible costs and project monitoring

ANNEX A - I. Note: it is important that each tenderer has read the Working Practice and its annexes very carefully.

Marina ZANCHI DG Research Directorate N International scientific cooperation

Guide to Financial Issues relating to ICT PSP Grant Agreements

Cost Guidelines. Version 1.4. V1.4_valid as of 1/4/2014 Page 1

FAQ. Questions and answers relating to the 2014 call for proposals for NGO operating grants for funding in 2015 (Latest update September 2014)

Legal and Financial Issues in H2020

COMMISSION DECISION. of ON THE MANAGEMENT AND CONTROL OF THE SCHENGEN FACILITY IN CROATIA. (only the English text is authentic)

Guide for Applicants

Financial relations within the 6th Framework Programme

South East Europe (SEE) SEE Control Guidelines

Administrative, Financial and Operational Aspects of Project Management

AIA Document A103 TM 2007

Document A Exhibit A

Annex II Draft specific grant agreement

Investing in your future

ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5

Overview on the changed articles of H2020 MGAs with retroactive applicability

EA-1/20 S1 A-AB: 2016

Annex X to the Model LIFE Grant Agreement Financial and Administrative Guidelines

A CEPR / DFID Research Initiative MAJOR RESEARCH GRANT BUDGET GUIDELINES

EACEA. Cluster Meeting

PROFESSIONAL SERVICES AGREEMENT NO

FINANCIAL PROVISIONS

COMMISSION DELEGATED REGULATION (EU)

Important Messages - Grants

Annex III Model specific grant agreement

The Hitchhiker s Guide to the Financial Rules and Management of Horizon 2020 Projects

IN2IT FINANCIAL WORKSHOP

Legal and financial issues in Horizon Bonn,

Rules. Unofficial translation. - for aid from the EUDP to projects within research, development and demonstration.

Effective as of 1 January 2007 Promulgated, SG, No 78 of 28 September 2007

LIFE Grant Agreement Financial Aspects Highlights

Acceptable costs in SBO and TBM projects (COST MODEL)

FRAMEWORK PARTNERSHIP AGREEMENT

FCH 2 JU Grant Agreement.

8 th Financial Managers Seminar

Guidance document on. management verifications to be carried out by Member States on operations co-financed by

CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS

Table of contents. Introduction Regulatory requirements... 3

Cemr! Government Audi t Svice

Coalition for Epidemic Preparedness Innovations. CEPI Cost Guidance Version:

ESA TENDERING STANDARDS FOR EXPRESS PROCUREMENT ( EXPRO & EXPRO+ ) PROPOSAL TEMPLATE V5

FP7 CERTIFICATION MODALITIES

GETBACK SPÓŁKA AKCYJNA

GUIDING PRINCIPLES FOR BUDGET MAKING IN PHASE 2 WINDOW 1

PROVISIONS FOR IMPLEMENTING SPECIFIC SUPPORT ACTIONS

RULES ON ELIGIBILITY OF COSTS

Model Grant Agreement FINANCIAL ISSUES

CSJU-Procedure 2.5. Guidelines for Members and Partners on Subcontracting

DECISION 05/2014/GB OF THE GOVERNING BOARD OF THE EUROPEAN POLICE COLLEGE

ANNUAL ACCOUNTS OF THE EUROPEAN COMMISSION

Construction Industry Scheme

Eligibility of costs in the Horizon 2020 funded EUROfusion project

Education, Audiovisual and Culture Executive Agency

MARCO POLO GRANT AGREEMENT 1

Proposal for a COUNCIL DECISION

Brussels, 11 May FP7 Audit. DG RTD Unit M2

Financial Webinar. IMI 2 projects :00 CET

Document A Exhibit A Determination of the Cost of the Work

EASO Final Annual Accounts 2015

Auditors Report & Audited Financial. Statements of. Grameenphone IT Ltd.

ELIGIBILITY RULES. Rule No 1: Expenditure Actually Paid Out

MODEL CONTRACT. Marie Curie individual fellowships

Terms of Business with Client for the Supply of a Contractor (Opted out of the Conduct Regulations)

COMMISSION IMPLEMENTING REGULATION (EU)

Administrative and financial aspects: recommendations for the preparation of proposals

ANNEX II. EU-LISA: STATEMENT OF REVENUE AND EXPENDITURE FOR FINANCIAL YEAR 2018 (EURO) - Amending Budget No 1 A. REVENUE

GRANT AGREEMENT for a: Project with multiple beneficiaries under the ERASMUS+ Programme 1. AGREEMENT NUMBER [EPLUS LINK Generated No.

CERTIFICATES ISSUED BY EXTERNAL AUDITORS FREQUENTLY ASKED QUESTIONS

Transcription:

European Commission THE FIFTH FRAMEWORK PROGRAMME The Fifth Framework Programme focuses on Community activities in the field of research, technological development and demonstration (RTD) for the period 1998 to 2002 GUIDELINES ON MAJOR FINANCIAL PROVISIONS FOR COST REIMBURSEMENT CONTRACTS FOR RESEARCH AND TECHNOLOGICAL DEVELOPMENT PROJECTS, DEMONSTRATION PROJECTS AND COMBINED PROJECTS This document can be downloaded from URL: http://www.cordis.lu/fp5/financial-guides.htm Version 10 August 1999 Ref. No. fig_en_199902

FOREWORD Guidelines on major financial provisions - Version 10 August, 1999 Purpose of Guidelines These guidelines have been prepared to help contractors to understand the financial provisions of the cost reimbursement model contracts. Contractors should read the guidelines carefully together with the contract and its annex II. If the guidelines conflict with the provision of the contract then the latter shall prevail. The contract references below refer to the model contract for research and technological development projects. Scope of the Guidelines The guidelines apply to cost reimbursement contracts for research and technological development projects, for demonstration projects and for combined projects. They also apply in general to Euratom contracts but they are not applicable to the European Coal & Steel Community (ECSC) RTD contract. The conditions and eligible costs for the latter are not the same. The Commission will amend these guidelines as necessary. They will be available on http://www.cordis.lu/fp5/financial-guides.htm. 2

TABLE OF CONTENT TABLE OF CONTENT...3 1. ACCOUNTING PRINCIPLES...4 2. AN OVERVIEW OF COST REIMBURSEMENT RESEARCH CONTRACTS...4 2.1. THE "FULL COST MODEL"...4 2.2. THE "ADDITIONAL COST MODEL"...5 3. ADVANCE PAYMENTS...5 4. WHAT ARE ELIGIBLE COSTS?...6 5. WHAT ARE NOT ELIGIBLE COSTS?...7 6. COST CATEGORIES...8 6.1. PERSONNEL...8 6.2. DURABLE EQUIPMENT...10 6.3. SUBCONTRACTING...10 6.4. TRAVEL AND SUBSISTENCE...10 6.5. CONSUMABLES...10 6.6. COMPUTING...11 6.7. INTELLECTUAL PROPERTY RIGHTS...11 6.8. OTHER SPECIFIC PROJECT COSTS...12 6.9. ADMINISTRATIVE AND FINANCIAL COORDINATION...12 6.10. OVERHEADS...12 7. PUBLIC FINANCE AND AUDIT...13 3

1. ACCOUNTING PRINCIPLES All organisations, including universities, must keep proper books of account and supporting documentation to justify as necessary the costs that they charge. Documentation must be kept for five years after each payment of the Community contribution. Explanations and justifications, especially concerning the allocation and apportionment of overheads, must be readily available for inspection by the Commission and its authorised representatives, and by the European Court of Auditors. Each prospective contractor must satisfy the Commission that it will have all the necessary resources as and when needed for carrying out the contract, as required in Article 8 of Council Regulation 1999/65/EC 1. 2. AN OVERVIEW OF COST REIMBURSEMENT RESEARCH CONTRACTS Research funding is based on cost-sharing contracts. This means that the Commission normally contributes up to 50% (or up to 35% for Demonstration projects) of the eligible costs incurred for the performance of the work defined in the contract. The main Cost Reimbursement Contracts (research and technological development, demonstration and combined) provide for two models of funding (cost participation basis): 2.1. The "Full Cost Model" The "Full Cost Model" (FC), where the Commission reimburses up to 50% of the total eligible costs. In this model all costs including overheads are based on actual costs and therefore the contractor must be able to identify with precision his direct and indirect costs. Overheads must be calculated in accordance with normal accounting conventions and principles applicable to the contractor and acceptable to the Commission. Even in this circumstance a contractor may nevertheless opt for the Full Cost Model with fixed overheads below. The Full Cost Model with Fixed Overheads" (FF), where the Commission reimburses up to 50% of the total eligible costs. In this model overheads are based on a fixed contribution of 80 % of the eligible personnel costs (the contractor may request a lower percentage when this required, for instance, by his internal rules but this must be discussed with the Commission services). The contractor must be able to identify with precision its direct costs but cannot identify with precision its indirect costs or opts for the fixed overhead rate. 1 See OJ L 26, 1.2.1999, p.46 4

2.2. The "Additional Cost Model" The "Additional Cost Model" (AC), where the Commission reimburses 100% of the eligible costs incurred that are "additional" to the normal running (recurrent) costs of the contractor. Please note that this Model is applicable only in cases where the contractor cannot identify precisely the Full Costs related to the project. The Cost Model applied by a contractor must be the same for all his cost-sharing research contracts and should apply throughout the Framework Programme. The Commission policy is: One organisation (legal entity) one accounting system one cost-basis. There are a number of reasons for this policy. The control function in an organisation should be separate from the operational departments. The development of different systems in each department of an organisation would weaken this separation and would inevitably be detrimental to the development of a satisfactory overall system. A separate paper on the cost-basis to be applied by a contractor and entitled Participants Choice can be downloaded from URL:http://www.cordis.lu/fp5/cont-admin.htm 3. ADVANCE PAYMENTS An initial advance of 40% will be paid by the Commission to speed up or facilitate the start of the work. The 40% may be reduced either to protect the Communities financial interests or where there is a significant difference between the amount of the advance and the real needs of the project during the first year. The advance payment will be recovered over the life of the project. 5

4. WHAT ARE ELIGIBLE COSTS? Eligible costs must be necessary for the project, incurred during its duration 2, be determined in accordance with the accounting principles based on historic costs and consistent with the usual internal rules of the contractor. They must be recorded in the accounts of the contractor no later than the contract completion date and exclude any profit margin. Budgeted costs are used as a guide for establishing a budget proposal. Actual costs should be used where possible on cost statements. It may also be acceptable to apply budgeted costs as long as they are adjusted to actual costs once the financial year is closed and actual rates are calculated. If there is a difference between actual and budgeted costs they must be indicated in the next cost statement as an adjustment. Eligible costs shall be presented in the cost statements under the following headings: Direct Costs 1. Personnel 2. Durable equipment 3. Subcontracting 4. Travel and subsistence 5. Consumables 6. Computing 7. Intellectual property rights 8. Other specific project costs 9. Administrative and financial co-ordination Indirect Costs 10. Overheads 2 Costs relating to the drawing up of the final report may be allowed if incurred by the co-ordinator within a maximum of two months after the end of the project (see Article 22.1 of Annex II). Also, durable equipment may be purchased or leased within the 6 months prior to the commencement date of the contract. Another exception is permitted (by Article 23.2 of Annex II) for equipment used for a previous contract with the Community for which the depreciation period has not been exceeded. 6

5. WHAT ARE NOT ELIGIBLE COSTS? Costs calculated in accordance with other conventions e.g. "current costs", "notional rents", "opportunity costs", etc. are not eligible. Therefore, no notional costs should be charged, e.g. in respect of revaluation of buildings or capital equipment, estimated or imputed interest, estimated rentals, etc. Other costs, which are not eligible, include in particular: return on capital employed, including dividends and other distributions of profits provisions for possible future losses or charges costs related to any interest provisions for doubtful debts resources made available to a contractor free of charge value of contributions in kind unnecessary or ill-considered expenses marketing, sales and distribution costs for products and services indirect taxes and duties, including VAT 3 entertainment or hospitality expenses except such reasonable expenses as are wholly and exclusively necessary for carrying out the work under the contract any cost incurred or reimbursed in particular in respect of another Community, international or national project or internal not funded project (except for the undepreciated amount of durable equipment in certain special cases to be determined by the contract provisions) leasing costs (or part thereof) where the leasing arrangement has the effect of unnecessarily increasing the charge made to the project (e.g. where the cost without interest of the leased equipment is higher than if purchased). 3 VAT is not an eligible cost. Contractors should refer to national legislation. 7

6. COST CATEGORIES 6.1. PERSONNEL For contractors using the "Full Cost" model Personnel The costs (e.g. remuneration, pensions and other employment costs) of the actual hours worked by the persons directly carrying out the scientific and technical work under the project may be charged to the contract. Such persons must be Directly employed by the contractor in accordance with his national law Under the contractor s sole technical supervision (in essence the technical output must belong to the contractor) Remunerated in accordance with the normal practices of the contractor provided these are acceptable to the Commission Work contracts (where the person engaged on such a contract is a user of the overheads of the contractor) which fulfil the above criteria may be charged as personnel costs. The work contract must be economical and not increase unnecessarily the cost of the project. If the employment on a work contract of a former employee increases the cost of the project then the prior approval of the Commission should be requested. The costs of administrative personnel in charge of the administrative and financial co-ordination of the project (which are not included in the indirect costs) may also be charged as personnel costs. The costs of all other administrative support should be included in overheads. Personnel Costs are calculated as follows: The following three elements must be known in order to calculate the total personnel costs which can be charged to the project: a) Working time to be charged must be recorded throughout the duration of the project or in the case of a co-ordinator no later than two months after the end of the duration of the project. The records should be certified at least once a month by the person in charge of the work designated by the contractor (Article 23.1.a of Annex 2 of the contract refers). Estimates of hours worked are not allowable. 8

b) Remuneration costs charged should be taken from the payroll account and should be the total gross remuneration plus the employer s portion of social charges (e.g. holiday pay, pension contributions, health insurance and social security payments). Remuneration costs can be calculated individually for each researcher or as an average by category of staff (the method should fairly represent actual labour costs). In the case of work contracts, the costs excluding VAT, should be taken from the invoice received for the work performed. Invoices should indicate the project on which the persons have worked, the tasks carried out and the hours spent. c) Productive time is the total hours worked, excluding holidays, personal time, sick leave, or other allowances. In order to obtain an hourly rate, the salary costs must be divided by the productive time. Total productive hours can be obtained either on the basis of actual hours recorded in time sheets or on the basis of standard hours. In the latter they should represent the total workable hours based on the contract of employment less a provision for non-chargeable time such as holiday and sick leave (these must correspond to the actual situation of the contractor). There are two overriding matters with regard to productive time: The time charged out by the participant should not exceed the productive time. Otherwise a participant would recover more than his actual personnel costs. On average, the Commission considers a figure of about 210 days per fulltime employee per year to be reasonable. If the contractor uses a lower figure it may indicate that surplus staff have been charged to the project. As a general rule, no overtime should be charged to Commission projects. In exceptional cases, overtime may be considered if this element has been taken into account in the calculation of the total productive hours. For contractors using the "Additional Costs" model The contract does not allow the cost of the personnel permanently employed on a full-time basis and paid from the participant's normal recurrent funds. Only the additional actual employment cost (gross remuneration, grants, etc.) of the scientific and technical personnel expressly engaged to carry out work under externally funded contracts is allowed. The costs of supplementary contracts, which seek to increase the publicly declared hours worked and the salaries of employees, are not eligible. 9

6.2. DURABLE EQUIPMENT Durable equipment charged to the contract must be specifically required for the project, have an expected life equal to or greater than the duration of the work under the contract and must be capitalised in the books of the contractor according to the national accounting rules. Depreciation can be calculated on equipment which has been purchased after the commencement date of the contract or within the preceding six months or under a previous Commission RTD contract if the depreciation period has not already expired. For prototypes or manufactured equipment see Point 6.8 below. Durable equipment costs are charged to the project by means of depreciation calculations as defined in the contract (Article 23.2 of Annex II). 6.3. SUBCONTRACTING A copy of the invoice from each subcontractor (making reference to the project and providing a detailed description of the tasks or supply concerned), certified by the contractor, must be submitted to the Commission with the corresponding cost statement. Supporting documentation should be kept in the contractor s files and provided to the Commission if requested. Subcontracts, which either cumulatively exceed 20% of the contractor s estimated eligible costs or which exceed ÃDUHÃVXEMHFWÃWRÃSULRUÃZULWWHQÃDJUHHPHQWÃRIÃWKHÃ&RPPLVVLRQ (unless sufficient details of the subcontracts have been included in Annex I of the contract). In addition, subcontracts with entities located in a third country require EC approval (unless the contractor is also based in one of those countries). The Commission should be notified in any case where there is a conflict of interest between the contractor and the sub-contractor. 6.4. TRAVEL AND SUBSISTENCE Actual travel and related subsistence costs, based on the internal rules of the contractor, may be charged to the project. The prior approval of the Commission shall be required for any destination outside the Member States, the Associated states or a third country where a contractor is established, unless such a destination is provided for in Annex I of the contract. 6.5. CONSUMABLES Consumables shall relate to the purchase, fabrication, repair or use of any materials, goods or equipment and software which: Does not have a life expectancy greater than the duration of the work under the contract; Are not placed in the inventory of durable equipment of the contractor; Are not treated as capital expenditure in accordance with the accounting conventions and policies of the contractor. 10

This category of costs covers access rights or licences for software but does NOT include office supplies, mailing, utilities, etc. which are covered in the overheads category. No direct charge shall be made for consumables where it is the usual practice of the contractor to include these costs in actual overheads. 6.6. COMPUTING Computing costs may be charged as a direct cost where: The contractor can provide a detailed justification of these costs. A computer cost centre exists in which all the computer costs (direct and indirect) are recorded. A computer register is maintained which can substantiate the total usage of the computer service charged to the projects. Without these three fundamental sources of information, it is not possible to calculate an acceptable chargeable computer rate. Otherwise computer costs should be included in overheads. No direct charge shall be made for computing costs where it is the usual practice of the contractor to include these in actual overheads. 6.7. INTELLECTUAL PROPERTY RIGHTS The costs associated with protecting knowledge generated during the life of the project can be charged to the project with the prior approval of the Commission. Fees for legal counsel will only be considered if an application has been filed for the granting of an industrial property right. There is a limitation on the EC contribution to fees for legal counsel of ÃÃSHUÃ LQGXVWULDOÃ SURSHUW\Ã ULJKWÃ Ã 7KHÃ DPRXQWÃ LGHQWLILHGÃ IRUÃ SURWHFWLRQÃ RI knowledge requires the approval of the Commission and should be negotiated at the time of creation of the contract. However, it may be possible to obtain EC approval during the life of the project for IPR protection costs if savings can be found from other cost categories. The amount agreed for this category of cost can be transferred to another contractor for the protection of knowledge but cannot be used for any other purpose (i.e. no transfer between cost categories). The contribution is lost if at the end of the project the amount estimated for protection of knowledge has not been used by one of the contractors during the life of the project. Where costs arise after the end of the project for the protection of intellectual property generated during the project there is a possibility to apply to the Commission for assistance. Further information is available on URL: http://www.cordis.lu/ipr-helpdesk. 11

6.8. OTHER SPECIFIC PROJECT COSTS All other specific project costs, which cannot be included under the previous classifications of direct costs, may only be charged either with the prior written approval of the Commission or alternatively if these costs were foreseen in Annex I to the contract. These costs include such items, as creation of prototypes, seminars, workshops, conferences and charges for financial guarantees required by the Commission, etc. 6.9. ADMINISTRATIVE AND FINANCIAL COORDINATION The Co-ordinator can charge to the contract the costs of administrative and financial coordination of the project. These costs may be charged directly or be included in overheads. If they are charged directly, then the same rules including appropriate time recording, for the specific cost headings of other direct costs (i.e. personnel, travel, consumables, etc.) apply. Contractors working on additional cost basis may only charge administrative personnel working on co-ordination directly if they meet the same criteria as for other personnel (ie. they are not permanent staff but hired for the project). Where co-ordinators sub-contract administrative and financial co-ordination tasks then the related costs may not be charged as direct costs. They must be included in the overhead charged to the Commission. The sub-contracting of financial co-ordination tasks does not relieve the co-ordinator of the responsibility to ensure the security and proper management of the Commission s contribution to the project. Where possible, a co-ordinator outside the Euro zone should not transfer into his national currency that part of the Commissions contribution, which he must subsequently pay to contractors who are within the Euro zone. The maintenance of an Euro account for this purpose is recommended as the simplest way to avoid excessive bank charges. 6.10. OVERHEADS For contractors using the Full Cost actual overheads model Overheads should include all the indirect general costs necessary for carrying out the project under the contract. Eligible overhead costs may include the costs of administration and management, depreciation of buildings and equipment, water, electricity, telecommunications and postal charges, office supplies, and administrative personnel costs (excluding administrative and financial costs charged directly). Overhead costs must be: Eligible costs Reasonable and capable of verification, i.e. based on factual elements which can be proven by the contractor and verified by the Commission (for example global assumptions or existing commercial practice statements, or any other unsupported statements will not be accepted). 12

Not included under direct costs The following principles should also be respected: Overheads must be in accordance to normal accounting conventions of the contractor. Overheads should be extracted from or reconciled with the official accounts Overheads which do not relate to EC research should not be included in overheads for EC-funded projects Different methods and keys may be used for the distribution of overheads. However, no subjective or arbitrary keys can be accepted. For contractors using the "Full Cost" fixed overheads model A lump sum in respect of the overheads is fixed at 80% of the eligible personnel costs. The possibility exists for the contractor to request the payment of lump sum lower than 80%, if dictated by the contractor s internal rules. This should be discussed with the Commission services. For contractors using the "Additional Cost" model To recover indirect costs, contractors may charge a lump sum of 20% of the eligible costs charged for personnel, equipment, travel and subsistence, consumables, computing, protection of knowledge, other specific project costs and administrative and financial co ordination. Direct costs of subcontracting should not be included in the calculation. The possibility exists for the contractor to request the payment of a lump sum lower than 20% if dictated by the contractor s internal rules. This should be discussed with the Commission services. 7. PUBLIC FINANCE AND AUDIT The Commission is committed to ensuring that its disbursements of public finance conform to the highest standards of financial management. To ensure that this is the case audits of contractor s records are provided for in the contract. Contractors will be selected for audit on an objective basis. 13

These Guidelines will highlight problems identified during audits or elsewhere during the Fifth Framework Programme. In consequence it will be possible for contractors to make adjustments to their accounting systems where it is necessary. In time the Guidelines will also seek to address frequently asked questions as a further assistance to contractors. 14