Workshop 4 FIDIC Contracts (Update on New Documents)

Similar documents
Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.

Suspension and Termination

Conditions of Contract for PLANT and Design-Build

Session 3 by Zoltán Záhonyi, FIDIC AIT,

MDB Harmonised Particular Conditions

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC)

Appendix K Model Letters for Use by the Engineer

SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS

FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management

Comparison between the Red Book 1999 and the MDB Harmonised Edition 2010

Conditions of Contract for Construction

DOWN THE RABBIT HOLE WITH THE TAKING-OVER PROCEDURE UNDER FIDIC

AH: STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WOPKS SCC.1

CIOB TIME AND COST MANAGEMENT CONTRACT CONSULTANCY APPOINTMENT CONTRACT ADMINISTRATOR SCHEDULES EDITION

(1) In these sub-contract conditions of agreement, the following words and phrases shall have the following meanings:-

Consultancy Services Contract

PROCUREMENT CODE. Part A Authority to Bind County to a Contract

CS ENERGY LIMITED SERVICE CONDITIONS

AMENDMENTS TO GDLA 82 (re-printed 18 th June 2003) REVISED FAIR WAGES CLAUSE AND RELEVANT COMPLIANCE CERTIFICATES. Contents. - Clause 39 Fair Wages

Sub Contract Agreement

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals

The definitions which shall apply to these Terms and Conditions are set out in paragraph 8.

AIRPORT AUTHORITY HONG KONG

DRAFT FORM OF CONTRACT

Breakdown of the Overall Price: A heading-by-heading list of the rates and costs making up the price for a lump-sum or global sum contract.

Article 6 Modification and Termination of Contracts for Supplies and Services

Czech Republic. Contributor: Alena Bányaiová. Editor: Philip Britton

Federal Acquisition Regulations: What Every Surety Professional Should Make Sure Their Clients Know

FIDIC WORKSHOP 2016 GROUP 6

Standard Contracts for the UK Offshore Oil & Gas Industry

STANDARD TERMS FOR SPARE PARTS AND/OR SITE SERVICES

OIL SANDS CONSERVATION ACT

Educational Use Only S A M P L E S A M P L E

General Conditions of Contract for the Hire of Plant With or Without an Operator

INTERNATIONAL. Plant and Design - Build TRAINING PROGRAMME DECEMBER Conditions of Contract for EPC/Turnkey Projects

Works Appointment: We, on behalf of the Employer, would like to inform you that your quotation, Reference Number

General Conditions for Consultancy Services Agreements

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)

COUNTY GOVERNMENT OF NYERI BILLS OF QUANTITIES

Section 7. General Conditions of Contract for the Procurement of Works

Western Water Development Consultant Accreditation Deed

The New NZS 3910:2013

Cosmos Projects - Standard Terms and Conditions of Sub-Contract

Programme. Contract. way. order: a) This letter; the possession of. both parties. Annex III. 2. Obligations of the Contractor. have.

Design Build Operate

Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project


Waste Treatment Plant Project Supply Chain Collaboration Event WTP - EQUITABLE ADJUSTMENT MANAGEMENT (Changes, REAs, Claims)

ROUGH DIAMOND SUPPLY AGREEMENT 1

Policy for Occupational Health, Safety and Environment Requirements for Contracted Construction and Maintenance Work

To be read in conjunction with all other pages Date: (Initials)

CLIENT-PROFESSIONAL PROJECT AGREEMENT FOR ARCHITECTURAL SERVICES BETWEEN CLIENT AND

General conditions of contract for the supply of machinery and spare parts (2006)

KENYA SAFARI LODGES AND HOTELS LIMITED (KSLH) TENDER DOCUMENT FOR REFURBISHMENT WORK AT MOMBASA BEACH HOTEL TENDER NO. MBH/RW/001(A)/

(e-procurement System)

1.5 Priority of Documents

Dividend Reinvestment Plan Rules

The Standard Form of Building Sub-Contract Edition

ANNEX II SAMPLE FORM OF CONTRACT

Educational Use Only S A M P L E S A M P L E

Document A Exhibit A Determination of the Cost of the Work

Standard Form Project Agreement (hub DBFM Projects)

REPUBLIC OF KENYA TURKANA COUNTY GOVERNMENT PROPOSED CONSTRUCTION OF BOREHOLE DRILLING SERVICES & EQUIPPING AT TURKANA COUNTY HEADQUARTERS.

CHARTERED INSTITUTE OF ARBITRATORS NEC compensation events A process for all eventualities? April 21 st 2016

Subcontract conditions

NEW ZEALAND S MOST QUALIFIED BUILDERS

TOWN OF JOHNSTOWN, COLORADO ORDINANCE NO

Subcontract agreement

DESERT COMMUNITY COLLEGE DISTRICT General Terms and Conditions

CONDITIONS OF CONTRACT. The Builder must execute and complete the Works in a workmanlike manner and ensure the Works are adequately supervised.

BIDP Standard FORMS & JBCC Minor WORKS Commentary. ARCPE SEMINAR compiled BY FRED PHIRI Arch.BW th NOVEMBER 2017

Moxtra, Inc. DATA PROCESSING ADDENDUM

CONSTRUCTION CONTRACT RIDER

DOUKPSC04 Rev Feb 2013

Experience Sharing on NEC Implementation and its Effectiveness in Hong Kong

Commentary: FIDIC Conditions

General conditions of contract for the supply of plant and machinery

QBCC PERIOD MINOR WORKS SUBCONTRACT

General Terms & Conditions of Purchase H&R Singapore Pte. Ltd.

INVITATION TO QUOTE. The Regional District of Fraser Fort George invites written quotations for the following:

3. Entry into force of the Contract Entry into force Commencement Date Non-occurrence of the Commencement Date...

SECTION D FISCAL MANAGEMENT

Danida Business Finance. Rules for Procurement

NEW CASTLE COUNTY Purchasing Division New Castle County Government Center 87 Read s Way New Castle, DE (302)

STANDARD TENDER DOCUMENTS FOR PROCUREMENT OF WORKS (MINOR CONTRACTS)

AGREEMENT FOR ENGINEERING SERVICES (AHTD VERSION COST PLUS FEE) JOB NO. FEDERAL AID PROJECT ( FAP ) NO. JOB TITLE PREAMBLE

REPUBLIC OF KENYA MINISTRY OF LAND AND PHYSICAL PLANNING PROPOSED ERECTION AND COMPLETION OF LAND REGISTRY AT BOMET, BOMET COUNTY

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

Subcontract Agreement

LEGAL NOTICE CITY OF ANSONIA, CONNECTICUT REQUEST FOR PROPOSALS

Insert Project Title Here Reference Version. Insert Title of Works Here. United Nations Office for Project Services ( UNOPS ) -and-

REQUEST FOR BIDS FOR THE CITY OF MT. JULIET, TN

1 In these Domestic Sub-Contract Conditions the following expressions and terms shall have the meanings given below:

Dividend Reinvestment Plan Rules February 2014

General Conditions of Contract for Civil Works

Conditions of Contract

CONTRACT ADMINISTRATION GUIDE

Market Procedure for: Prudential Requirements

General Purchase Conditions of Avans University of Applied Sciences

CONDITIONS OF CONTRACT FOR QUOTATION

Transcription:

Workshop 4 FIDIC Contracts (Update on New Documents) Employer s New Obstacle: Commencement Date and Related Clauses Dr.Sarwono Hardjomuljadi Tuesday, 04 October 2011, 14.00 15.30

Employer s New Obstacle: Commencement Date and Related Clauses Dr.Sarwono Hardjomuljadi INDONESIA sarwonohm2@yahoo.co.id

CASE CHRONOLOGY: The Company X was awarded as the Contractor The Employer/Engineer intend to issue the Commencement of Works [Clause 8.1] The Contractor took the Advance Payment The Contractor refused to receive the Engineer s instruction and pointed out that the precedent conditions in Sub-Clause 8.1 have not been fullfilled by the Employer (with the understanding that all the land required for the Works have to be handed over to the Contractor on the Commencement Date) The Contractor told the Employer that they wish to terminate the contract based on Sub-Clause 16.2.h.

Commencement of Works Sub-Clause 8.1 Precedent conditions commencement of The Works Programmes Sub-Clause 8.3 Programme (After Commencement Date)

2.1 Right of Access to the Site

2.1 Right of Access to the Site The Employer shall give the Contractor right of access to, and possession of, all parts of the Site within the time (or times) stated in the Contract Data. The right and possession may not be exclusive to the Contractor. If, under the Contract, the Employer is required to give (to the Contractor) possession of any foundation, structure, plant or means of access, the Employer shall do so in the time and manner stated in the Specification. However, the Employer may withhold any such right of possession until the Performance Security has been received.

If no such time is stated in the Contract Data, the Employer shall give the Contractor right of access to, and possession of, the Site within such times as required to enable the Contractor to proceed without disruption in accordance with the programme submitted under Sub-Clause 8.3 [Programme].

If the Contractor suffers delay and/or incurs Cost as a result of a failure by the Employer to give any such right or possession within such time, the Contractor shall give notice to the Engineer and shall be entitled subject to Sub-Clause 20.1 [Contractor s Claims] to: (a) an extension of time for any such delay, if completion is or will be delayed, under Sub-Clause 8.4 [Extension of Time for Completion], and (b) payment of any such Cost plus profit, which shall be included in the Contract Price. After receiving this notice, the Engineer shall proceed in accordance with Sub-Clause 3.5 [Determinations] to agree or determine these matters.

However, if and to the extent that the Employer s failure was caused by any error or delay by the Contractor, including an error in, or delay in the submission of, any of the Contractor s Documents, the Contractor shall not be entitled to such extension of time, Cost or profit.

8.1 Commencement of Works

8.1 Commencement of Works Except as otherwise specified in the Particular Conditions of Contract, the Commencement Date shall be the date at which the following precedent conditions have all been fulfilled and the Engineer s notification recording the agreement of both Parties on such fulfilment and instructing to commence the Work is received by the Contractor:

(a) signature of the Contract Agreement by both Parties, and if required, approval of the Contract by relevant authorities of the Country; (b) delivery to the Contractor of reasonable evidence of the Employer s Financial arrangements (under Sub-Clause 2.4 [ Employer s Financial Arrangements]); (c) except if otherwise specified in the Contract Data, effective access to and possession of the Site given to the Contractor together with such permission(s) under (a) of Sub-Clause 1.13 [ Compliance with Laws ] as required for the commencement of the Works; (d) receipt by the Contractor of the Advance Payment under Sub- Clause 14.2 [ Advance Payment ] provided that the corresponding bank guarantee has been delivered by the Contractor.

If the said Engineer s instruction is not received by the Contractor within 180 days from his receipt of the Letter of Acceptance, the Contractor shall be entitled to terminate the Contract under Sub-Clause 16.2 [ Termination by Contractor ]. The Contractor shall commence the execution of the Works as soon as is reasonably practicable after the Commencement Date, and shall then proceed with the Works with due expedition and without delay

8.3 Programme

The Contractor shall submit a detailed time programme to the Engineer within 28 days after receiving the notice under Sub-Clause 8.1 [Commencement of Works]. The Contractor shall also submit a revised programme whenever the previous programme is inconsistent with actual progress or with the Contractor s obligations. Each programme shall include: (a) the order in which the Contractor intends to carry out the Works, including the anticipated timing of each stage of design (if any), Contractor s Documents, procurement, manufacture of Plant, delivery to Site, construction, erection and testing, (b) each of these stages for work by each nominated Subcontractor (as defined in Clause 5 [Nominated Subcontractors], (c) the sequence and timing of inspections and tests specified in the Contract, and (d) a supporting report which includes:...etc.

3.3 Instructions of the Engineer

The Engineer may issue to the Contractor (at any time) instructions and additional or modified Drawings which may be necessary for the execution of the Works and the remedying of any defects, all in accordance with the Contract. The Contractor shall only take instructions from the Engineer, or from an assistant to whom the appropriate authority has been delegated under this Clause. If an instruction constitutes a Variation, Clause 13 [Variations and Adjustments] shall apply. The Contractor shall comply with the instructions given by the Engineer or delegated assistant, on any matter related to the Contract. Whenever practicable, their instructions shall be given in writing. If the Engineer or a delegated assistant:

The Contractor shall submit a detailed time programme to the Engineer within 28 days after receiving the notice under Sub- Clause 8.1 [Commencement of Works]. The Contractor shall also submit a revised programme whenever the previous programme is inconsistent with actual progress or with the Contractor s obligations. Each programme shall include:...etc

14.2 Advance Payment

The Employer shall make an advance payment, as an interestfree loan for mobilisation and cash flow support, when the Contractor submits a guarantee in accordance with this Sub- Clause. The total advance payment, the number and timing of instalments (if more than one), and the applicable currencies and proportions, shall be as stated in the Contract Data.

15.2 Termination by Employer

The Employer shall be entitled to terminate the Contract if the Contractor: (a) fails to comply with Sub-Clause 4.2 [Performance Security] or with a notice under Sub-Clause 15.1 [Notice to Correct], (b) abandons the Works or otherwise plainly demonstrates the intention not to continue performance of his obligations under the Contract, (c) without reasonable excuse fails: (i) to proceed with the Works in accordance with Clause 8 [Commencement, Delays and Suspension], or (ii) to comply with a notice issued under Sub-Clause 7.5 [Rejection] or Sub-Clause 7.6 [Remedial Work], within 28 days after receiving it.

16.2 Termination by Contractor

The Contractor shall be entitled to terminate the Contract if:...etc. (h) the Contractor does not receive the Engineer s instruction recording the agreement of both Parties on the fulfilment of the conditions for the Commencement of Works under Sub-Clause 8.1 [ Commencement of Works ].