Available online at ScienceDirect. Procedia Engineering 161 (2016 )

Similar documents
Planning of the Risk Handling Methods Related to Alterations to Project Documentation

Risk management as an element of processes continuity assurance

ScienceDirect. A Study of Construction Claim Management Problems in Malaysia

Decision-making under uncertain conditions and fuzzy payoff matrix

Comparative Study Of Pre-Planning And Actual Planning Process In Construction Industries

Procedia - Social and Behavioral Sciences 156 ( 2014 )

Feasibility Study of construction project in compliance with Bank Investment Supervision requirements

A Method for the Evaluation of Project Management Efficiency in the Case of Industrial Projects Execution

CHAPTER 1 25 INTRODUCTION

New Option Strategy and its Using for Investment Certificate Issuing

International Journal of Advance Engineering and Research Development A MODEL FOR RISK MANAGEMENT IN BUILDING CONSTRUCTION PROJECTS

Procedia - Social and Behavioral Sciences 156 ( 2014 )

ScienceDirect. A model of green investments approach

APPLICATION OF FORMAL SAFETY ASSESSMENT IN THE LEGAL ACTIVITY OF INTERNATIONAL MARITIME

International Journal of Advance Engineering and Research Development

Available online at ScienceDirect. Procedia Economics and Finance 32 ( 2015 )

Assessment of Risk and Its Application for Residential Construction Projects: A Case Study

Defining the Safety Integrity Level of Public Safety Monitoring System Based on the Optimized Three-dimension Risk Matrix

Available online at ScienceDirect. Procedia Economics and Finance 34 ( 2015 )

Feasibility Analysis Simulation Model for Managing Construction Risk Factors

Evaluation of Construction Risks Impact on Construction Project Manager s

ScienceDirect. Programme management for public budgeting and fiscal policy. Ganna Lytvynchenko a * 27 th IPMA World Congress

Procedia - Social and Behavioral Sciences 156 ( 2014 ) Ingars Erins a *, Laura Vitola b. Riga Technical University, Latvia

Risk assessments of contemporary accidents in construction industry

An Investigative Study of Risk Management Practices of Major U.S. Contractors

Report on Thesis of Master Degree Named:

Kuwait Chapter of Arabian Journal of Business and Management Review Vol. 4, No.2; October. 2014

Foreign exchange risk management practices by Jordanian nonfinancial firms

Available online at ScienceDirect. Procedia Engineering 123 (2015 ) Creative Construction Conference 2015 (CCC2015)

INTRODUCTION TO RISK MANAGEMENT FOR CONSTRUCTION PROJECTS. Prof. Reda Abdulaal Vice Presidency for Projects

Available online at ScienceDirect. Procedia Computer Science 89 (2016 )

ScienceDirect. Detecting the abnormal lenders from P2P lending data

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

King Fahd University of Petroleum and Minerals College of Environmental Design CEM 520: Construction Contracting

The Control of the Implementation and Management of European Funds

2nd Annual International Conference on Accounting and Finance (AF 2012) Current context of disclosure of corporate social responsibility in Sri Lanka

MERCER SENTINEL SERVICES

Z-score Model on Financial Crisis Early-Warning of Listed Real Estate Companies in China: a Financial Engineering Perspective Wang Yi *

Differentiation of the assessment of identified risks in the process of preparing and creating a municipal land plan

Study on Principle of Product Defect Identification

Available online at ScienceDirect. Procedia Economics and Finance 25 ( 2015 )

ScienceDirect. Statistical Analysis of the Indicators that have Influenced the Standard of Living in Romania During the Economic Crisis

Procedia - Social and Behavioral Sciences 210 ( 2015 ) Use of Public Debt Mezzanine Instruments in the Czech Republic

Available online at ScienceDirect. Procedia Computer Science 61 (2015 ) 85 91

Analysis of Risk Factors for Highway Construction Projects in Egypt

Procedia - Social and Behavioral Sciences 109 ( 2014 ) Analysis of Financial Performance of Private Banks in Pakistan

Uncertainty and the Transmission of Fiscal Policy

Risk Assessment in Construction of Highway Project

Procedia - Social and Behavioral Sciences 235 ( 2016 )

RISK REGISTERS IN CONSTRUCTION IN CROATIA

Developing Risk Source and Risk Event Breakdown Structures: A New Approach to Risk Identification in Complex Environments

Bank liquidity and its determinants in Romania

RESEARCH ON THE SOURCES OF RISK FOR AGRICULTURAL COOPERATIVES IN NORTHEASTERN BULGARIA

Procedia - Social and Behavioral Sciences 205 ( 2015 ) th World conference on Psychology Counseling and Guidance, May 2015

Establishment of Risk Evaluation Index System for Third Party Payment in Internet Finance

Research on Legal Procedural Functions of Forensic Accounting

Risk managers in the largest construction and assembly companies in Poland survey research

General Conditions for Construction GCC201. Contract Type: Document No. for the following PROJECT: (Name and location or address) EXAMPLE

Optimization of China EPC power project cost risk management in construction stage based on bayesian network diagram

Technical analysis of selected chart patterns and the impact of macroeconomic indicators in the decision-making process on the foreign exchange market

Document A201 TM 2007 SP

Risk Analysis and Strategic Evaluation of Procurement Process in Construction

AIA Document A201 TM 1997

Available online at ScienceDirect. Procedia Economics and Finance 32 ( 2015 ) Andreea Ro oiu a, *

4. Environmental insurance as an environmental policy tool: research concept and approach

Improvement and application of earned value analysis in coal project management

Possibility of Using Value Engineering in Highway Projects

machine design, Vol.7(2015) No.4, ISSN pp

Insurance as a factor affecting the effectiveness of the financial mechanism of the governing structures

Study of Cost Control Techniques Used in Construction Industry and Their Impact to Minimize Cost Overrun

A Risk Management Approach to Address Construction Delays from Client Aspect

THE REACTION OF THE WIG STOCK MARKET INDEX TO CHANGES IN THE INTEREST RATES ON BANK DEPOSITS

Procedia - Social and Behavioral Sciences 156 ( 2014 )

Jacek Prokop a, *, Ewa Baranowska-Prokop b

Procedia - Social and Behavioral Sciences 164 ( 2014 )

AN ASSESSMENT OF RISK IN CONSTRUCTION IN THE NIGERIAN CONSTRUCTION INDUSTRY

CLAIMS IN CONSTRUCTION PROJECTS DESIGN ERRORS AND CHANGE ORDERS

Methodological and organizational problems of professional risk management in construction

Procedia - Social and Behavioral Sciences 140 ( 2014 ) PSYSOC Assessment of Corporate Behavioural Finance

RISK MANAGEMENT IN CONSTRUCTION PROJECTS AND ANALYSIS

Available online at ScienceDirect. Procedia Economics and Finance 15 ( 2014 )

Available online at ScienceDirect. Procedia Economics and Finance 10 ( 2014 )

Available online at ScienceDirect. Procedia Economics and Finance 6 ( 2013 )

Procedia - Social and Behavioral Sciences 149 ( 2014 ) LUMEN Bank Universal Credit Institutions. Rada Postolache a, *

ScienceDirect. Some Applications in Economy for Utility Functions Involving Risk Theory

An Analysis of Cost-overrun Projects using Financial Data and Software Metrics

ScienceDirect. Project Coordination Model

Planning, Scheduling and Tracking Of Ongoing Bridge Construction Project Using Primavera Software and EVM Technique

Available online at ScienceDirect. Procedia Economics and Finance 32 ( 2015 ) Paula Nistor a, *

Procedia - Social and Behavioral Sciences 213 ( 2015 ) th International Scientific Conference Economics and Management (ICEM-2015)

Available online at ScienceDirect. Energy Procedia 69 (2015 )

An Approach for the Assessment of the Maximum Probable Loss for Insurance Purposes

ANTI-FRAUD CODE CONTENTS INTRODUCTION GOAL CORPORATE REFERENCE FRAMEWORK CONCEPTUAL FRAMEWORK ACTION FRAMEWORK GOVERNANCE STRUCTURE

Sheila Belayutham CHAPTER 6 CONTROL

Distribution analysis of the losses due to credit risk

RELATIONSHIP BETWEEN PROJECT COMPLEXITY AND RISK KINDS IDENTIFIED ON PROJECTS

A Simple Method for Solving Multiperiod Mean-Variance Asset-Liability Management Problem

Document A201 TM. General Conditions of the Contract for Construction. (Name and location or address)

The current state of business risk management in the Czech Republic

Procedia Computer Science

Transcription:

Available online at www.sciencedirect.com ScienceDirect Procedia Engineering 161 (2016 ) 163 167 World Multidisciplinary Civil Engineering-Architecture-Urban Planning Symposium 2016, WMCAUS 2016 Cost Risk in Water and Sewerage Systems Construction Projects Iwona Rybka a, *, Elzbieta Bondar-Nowakowska a, Mieczysaw Polonski b a Wroclaw University of Environmental and Life Sciences, C.K. Norwida 25, 50-375 Wroclaw, Poland b Warsaw University of Life Sciences, Nowoursynowska 166, 02-787 Warsaw, Poland Abstract Due to their complexity and uniqueness, all construction projects are exposed to a high risk. The condition for this risk reduction is an identification of risk events and an evaluation of their occurrence probability and effect. The subject of this study was the risk of an increase in the planned costs of water and sewerage systems construction projects. The data obtained from expert survey constitute the basis of the analyses. The questionnaire prepared especially for this purpose contains the list of 25 factors that generate cost risk events which can occur during construction works execution. The list of these factors is the result of literature studies, interviews, direct field observations, as well as the inspection of investment documents. These factors include the specific features of construction works such as: a large number of people involved, investment process formalization, a long duration of the investment, capital intensity, considerable material resources use, interference with natural environment, dependence on weather and ground conditions as well as topography. The experts pointed out in the survey whether they observed particular factor in their practice, and whether the factor affected the cost of the investment. The questionnaire was filled by 51 carefully selected respondents. Each of the experts had a long-standing professional experience at the managerial position in water supply and sewerage systems realization. 2016 Published The Authors. by Elsevier Published Ltd. This by Elsevier is an open Ltd. access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/). Peer-review under responsibility of the organizing committee of WMCAUS 2016. Peer-review under responsibility of the organizing committee of WMCAUS 2016 Keywords: cost risk; construction of water supply and sewage systems;risk management; The results were analyzed using statistical methods. Examination of the data set concerning the frequency of risk events, and the set of data determining the effect of these factors on investment cost increase, demonstrated the similarity in these structure sets, with similarity index over 0.9. The method of correspondence analysis revealed that the most common source of cost risk on water supply and sewage systems construction sites include: faulty design documentation, unforeseen physical conditions, adverse * Corresponding author. Tel.: +48 600 247 437 E-mail address: iwona.rybka@up.wroc.pl 1877-7058 2016 Published by Elsevier Ltd. This is an open access article under the CC BY-NC-ND license (http://creativecommons.org/licenses/by-nc-nd/4.0/). Peer-review under responsibility of the organizing committee of WMCAUS 2016 doi:10.1016/j.proeng.2016.08.517

164 Iwona Rybka et al. / Procedia Engineering 161 ( 2016 ) 163 167 weather and ground conditions, need of update of the design solutions as a result of technological progress, inadequate design supervision, corrective action as a result of lack of required work quality. The factor related to the quality of project documentation was the most distinctive among all the factors in the study. This indicates that particular attention should be paid to the design phase as a part of cost risk management plan. Faulty design documentation to the highest degree affects the high level of cost risk in water and sewerage systems construction projects. 1. Introduction The risk management has an increasing significance in the case of investment decisions making. Each construction project is exposed to the risk [1,2,5,6,7,8]. This is determined by specific features of construction works such as: complexity, uniqueness, large number of people involved, investment process formalization, long duration of the investment, changeable environment conditions and many others. Therefore, the commencement of the construction process should be preceded by the identification of adverse events affecting the works course, the determination of its occurrence probability, and the evaluation of the extent of their impact on the construction process [4]. The subject of this study was the risk of an increase in planned costs. The aim of the research was to examine the factors generating this type of risk related to water and sewerage systems construction projects. The results of the work provide the data that will allow reducing cost risk and mitigating its consequences. 2. Research method Gaining the information necessary to identify the potential risks is a crucial issue for an effective and efficient risk management. The knowledge and experience of the participants of the constructions process is one of the valuable sources of information about the cost risk. For this reason, an expert survey was applied to conduct the research. The selection of the experts was made on the basis of two criteria. The first criterion assumed that the person selected for the study is an expert with five years experience and participated in the realization of at least five water and sewerage systems construction projects. The second criterion assumed that the expert was involved in the construction process in managerial positions. The specified criteria were fulfilled by 51 experts, who were included into the study. The special questionnaire was prepared in order to obtain relevant information. It contains the list of 25 factors that generate cost risk events which can occur during the construction works execution. The list of these factors is the result of literature studies, interviews, direct field observations, inspection of investment documents as well as researchers work experience. These factors were as follows: 1. faulty design documentation, 2. need of update of the design solutions as a result of technological progress, 3. inadequate design supervision, 4. improper selection, insufficient number, defect of machinery, equipment and technology devices, 5. lack of qualified production workers, 6. inadequate human resources management by works contractor, lack of proper supervision of subcontractors, 7. wrong time assumption in the schedule of works, 8. inadequate management of construction work (e.g. lack of interbranch coordination), 9. unqualified and / or inadequate construction supervision, 10. misconduct in a tender procedure, 11. terms and Conditions not meeting the specifics of the contract (including the ambiguous definition of obligations of the parties), 12. delay payment of the investor, 13. inadequate preparation of human resources and organizational side by the investor, 14. changes in laws and / or inconsistent legal provisions, 15. excessive length, lack of coordination of administrative procedures and / or a large number of institutions involved in the investment process, 16. adverse economic conditions on the market,

Iwona Rybka et al. / Procedia Engineering 161 ( 2016 ) 163 167 165 17. unforeseen physical conditions / collisions, 18. adverse weather conditions, 19. adverse hydrogeological conditions, 20. extraordinary natural phenomena - floods, hurricanes, 21. force majeure events - fire, theft, vandalism, 22. adverse social activities - protests of environmentalists, residents or third parties, 23. difficulties in the preparation of areas for investments in formal, legal and technical terms, 24. misconduct in the preparation of the investment (e.g. deficiencies in completing the required permits, agreements). The experts pointed out in the survey whether they observed particular factor in their practice, and whether the factor affected the cost of the investment. Two sets - Z, K, were the result of the expert survey. Each of them consisted of 25 elements, corresponding to the considered risk factors. Factors marked by the experts as source of risk events formed the Z set, while the factors identified as affecting the investment costs were defined as K set. The results were analyzed using statistical methods. The comparison of the two sets was done in a first step. The similarity index (P) was applied for this purpose. It was calculated using the following formula [3]: P min( u iz; u ) (1) ik where:, u iz; u ik - structure indicators of Z and K sets. Structure indicators, showing the share of elements in the whole set, were calculated using the following formula: wi u i (2) w i where: u i structure indicator, w i number of elements. In the next step of the research, the data from the survey were studied in the terms of their correlations. The method of correspondence analysis was applied for this purpose. 3. Results The results of the survey are presented in Fig. 1. Considered risk factors are numbered 1-25. The bars on the graph represent the percentage of the respondents who pointed out that they observed particular factor in their practice, while the solid line indicates the percentage of the survey participants who noted that this factor caused the additional cost of the investment. The analysis of the graph indicates that each factor considered in the survey constitutes greater or smaller source of the cost risk events. The number of experts' indications of particular factors is differentiated, which makes that the set is inhomogeneous. It also demonstrates the random nature of the problem in this question. The data presented in Fig. 1 indicate that the additional cost of investment is a result of the occurrence of only certain factors from all of the identified. However, such a situation is frequent. The similarity index, calculated according to the formula no. 1, was over 0.9. This result proves that the occurrence of particular risk factor may with a high probability contribute to the investment cost increase. The importance of particular factors in the area of financial risk was identified in the next stage of the study. The method of correspondence analysis was used for this purpose. The frequency of risk events and the effect on the investment cost increase was included in the analysis. The calculations were carried out using statistical program R. The Fig. 2. represents the result of this analysis. The two-dimensional projection area contains 25 points corresponding to the considered cost risk factors. The

166 Iwona Rybka et al. / Procedia Engineering 161 ( 2016 ) 163 167 intersection of the axes in the presented graph constitutes the point of reference. This point is an average profile of the considered variables. 100 90 80 70 60 % 50 40 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Risk factor Z K Fig. 1 The frequency of risk factor occurrence (Z) and its effect on the cost of the investment (K). The risk factor events situated in the vicinity of this point are characterized by the values close to the average ones, both in terms of the frequency of risk factor occurrence and its effect on the cost of the investment. 1,1 17 1,0 0,9 2 Affected the cost of the investment 11 21 12 0,8 0,7 0,6 9 3 0,0 0,2 4 60,4 0,6 0,8 1,0 15 13 0,5 25 10 14 7 24 16 0,4 8 5 20 19 18 1 22 0,3 23 0,2 0,1 Frequency of risk factor occurrence Fig. 2 The relation between the frequency of risk factor occurrence and effect on the cost of the investment.

Iwona Rybka et al. / Procedia Engineering 161 ( 2016 ) 163 167 167 The analysis of the distance from the vertical axis refers to the frequency of the risk factor occurrence. Risk factors which frequency is higher than the average are situated on the right side of the reference point - the greater distance of a point representing risk factor is from the intersection of the axis, the greater is the frequency of its occurrence during construction works. Vertical dispersion of the points is identified with the frequency of an effect on the cost of the investment. Risk factors above the reference point have higher than average degree of impact on the investment cost. The analysis of the points position in Figure 2 indicates that factors located in the upper right quadrant of the chart have to be considered in priority in the cost risk management plan in water and sewerage systems construction projects. These are as follows: faulty design documentation (1), unforeseen physical conditions, collision (18), adverse weather conditions (19), adverse hydrogeological conditions (20), need to update the design solutions as a result of technological progress (2), corrective action as a result of lack of required work quality (9), inadequate design supervision (3). These factors constitute the highest level of cost risk on the construction of water and sewerage systems. This results both from their high frequency of occurrence, as well as a strong impact on the investment cost. It should be pointed out that the source of these factors is generated at different stages of the investment process: planning, designing and construction. They also relate to various aspects of the investment: technical, organizational and environmental. Dominant factor in the defined group of the highest risk events is the faulty design documentation. This factor poses the biggest threat to the planned budget preserving. 4. Conclusions The risk management of the construction project requires the gathering of relevant data to evaluate it. The studies consider 25 factors, which generate cost risk in the water and sewerage systems construction projects. The occurrence of these factors has a random character. The analysis indicates that in the most cases, these events affect the planned costs of the water and sewerage systems construction projects, albeit to different degrees. Factors related to the quality of project documentation distinguish among all the concerned in the study. This indicates that particular attention should be paid to the design phase as part of the cost risk management plan. Faulty design documentation has the biggest impact on the high level of cost risk in water and sewerage systems construction projects. Presented in the paper research these results could be helpful in making decisions concerning the choice of the best risk handling strategies. The obtained data can be used by both the investor and the contractor. The value of these data will increase if they are verified by a systematic risk monitoring of construction projects. References [1] P. Jakowski, S. Biruk, The analysis of risk factors affecting construction projects duration, Technical Transactions. Civil Engineering, R. 107, z. 1-B (2010) 157 166. [2] P. Jakowski, S. Biruk, The conceptual framework for construction project risk assessment. Reliability: Theory & Applications (Electronic Journal Reliability & Risk Analysis: Theory & Applications), 2, # 3(22) (2010) 27 35. [3] M. Lipiec-Zajchowska, Supporting decision making processes Vol. I, C.H. BECK Publishers, Warszawa, 2003, pp. 51-55. [4] M. Pooski, The analysis of the reliability of realization costs and investments time-limits in Warsaw. Electronic Journal of Polish Agricultural Universities Topic Civil Engineering 9(4), #10 (2006). [5] I. Rybka, E. Bondar-Nowakowska, M. Pooski, Management of alterations to project documentation - a case of study of water supply and sewerage works, International Journal of Contemporary Management, 14(3) (2015) 41-57. [6] I. Rybka, E. Bondar-Nowakowska, M. Pooski, Causes and effects of adverse events during water supply and sewerage system construction, Archives of Civil Engineering, LXII (1) (2016) 173-184. [7] D. Skorupka, Method of planning construction projects taking into account risk factors, Operations Research and Decision, 3 (2009) 119-128. [8] D. Skorupka, Identification and initial risk assessment of construction projects in Poland, Journal of Management in Engineering, 24(3) (2008) 120-127.