EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities

Similar documents
Earned Schedule Analysis

Earned Schedule .EMERGING PRACTICE. Eleanor Haupt IPPM. ASC/FMCE Wright-Patterson AFB OH ANL327

James A. Wrisley, President 9070 Lakes Blvd. West Palm Beach FL (561)

Connecting Earned Value to the Schedule

Predicting The Future

Earned Value Management - EVM

NOVEMBER 9, An overview of the core elements of the Earned Value Management technique. Presenter:

Earned Value Management Guide

Schedule Analysis and Predictive Techniques Using Earned Schedule. 16 th IPM Conference Tysons Corner, Virginia

Earned Value Management An Overview March 2014

Earned Schedule in Action

ANALYZE THIS! EARNED VALUE MANAGEMENT CONCEPTS AND ADVANCED FORECASTING?

Performance Analyzer Formulas. Assumptions. Current Month Adjustments

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

Predicting Project Completion Date Using Earned Value Management

EARNED VALUE AS A RISK ASSESSMENT TOOL

Presenting Earned Value

Cumulative trends Problems and issues since last report

PROJECT BY PROJECT MANAGEMENT T OOLS

4/14/2017. Unit 7 Slide Lectures of 19/20/21 April 2017 PROJECT PROGRESS AND PROJECT PERFORMANCE ASSESSMENT (CH. 13)

Earned Schedule schedule performance

Earned Value Management (EVM) and the Acquisition Program

Use of EVM Trends to Forecast Cost Risks 2011 ISPA/SCEA Conference, Albuquerque, NM

PMP. Preparation Training. Cost Management. Your key in Successful Project Management. Cost Management Processes. Chapter 7 6/7/2005

Earned Schedule. James C. Blair, PhD, PMP. Project Management Institute May 19, Paladin Project Management Consultants, LLC

EARNED VALUE MANAGEMENT. Is it worth the effort?

PROJECT MANAGEMENT BODY OF KNOWLEDGE

Earned Value Management Handbook. arne. alu

Earned Value Formulae

Project Management -- Monitoring the progress

Earned Value Management

Jefferson Science Associates, LLC. 900 Glossary. Project Control System Manual Revision 7

Estimating Cost-To-Go Without Stable EVM Data

Earned Value Project Management. Amber L. Romero, CPM, P.M.P., Policy Analyst Sandia National Laboratories 505/ ;

Understanding the Differences. Accounting Practice for Measuring. Supertech Project Management

9/24/2010. Information System Structure (cont d) Information System Structure. Progress since last report Current status of project.

Project Performance Evaluation By Earned Value Method

MMZG 523 PROJECT MANAGEMENT

INSE 6230 Total Quality Project Management

Presenting Earned Value

DEFENSE ACQUISITION UNIVERSITY EMPLOYEE SELF-ASSESSMENT. Outcomes and Enablers

USING PERFORMANCE INDICES TO EVALUATE THE ESTIMATE AT COMPLETION 1. David S. Christensen Southern Utah University

GPE engineering project management. Project Management in an Engineering Context

Earning Value From Risk

+44 (0) The first annual earned value conference for continental Europe

Roberta Tomasini Defense Acquisition University DSN

Comprehensive Assessment of Contract Performance Using Earned Value Management (EVM) Data

for 9 Sep 15 SoCal ICEAA Workshop

Earned Schedule Training

IP-CIS : CIS Project Management

Objectives of Project Cost Control System

Professional Development Seminar Series

THE VALUE OF EARNED VALUE MANAGEMENT

Evaluating the Accuracy of the Estimate At Completion

Key Note Conf. for Advancing Project Controls June 27 th, 2017 Denver, Colorado

The Value of EVM. Earned Value Management

Analysis of Estimate at Completion of a Project's duration to improve Earned Value Management System 1 N.Vignesh

PMP Exam Prep Coaching Program

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

5-D Integrated Earned Value Analysis

Do Not Sum Earned-Value-Based WBS-Element Estimates-at-Completion

ENGINEERING MANAGEMENT (GE

Financial Management & Accounting in Construction (CUE304) FINANCIAL MANAGEMENT. Dr. Ahmed Elyamany

What is Earned Value Analysis?

Project Controls Expo 16 th Nov 2016

Not Your Father's Earned Value

Overview of Today s Discussion. Don t Let EVM Data Mislead You. Steve Sheamer. Brief Overview of EVM Concepts. Why you can t trust BACs or EACs

Administration. Course Aim. Introductions

Performance measurement

Master Document Audit Program. Progress Payment, Percentage of Completion. Version 5.15, dated March 2018 B-1 Planning Considerations

ACWP (actual cost of work performed) Cost of actual work performed to date on the project, plus any fixed costs.

CONTROL COSTS Aastha Trehan, Ritika Grover, Prateek Puri Dronacharya College Of Engineering, Gurgaon

SMC/PMAG Control Account Manager (CAM) Notebook Evaluation

Formulas to Know for EXAM

MTAT Software Economics. Workshop 7: Software Cost Estimation (part II)

Does Project Performance Stability Exist? A Re-examination of CPI and Examination of SPI(t) Stability

Capital Acquisition Under The President s Management Agenda. David Muzio Office of Federal Procurement Policy

What we practice (Sub) consciously

Project Control. Ongoing effort to keep your project on track Prerequisite to good control is a good plan Four primary activities:

europe GENEVA 2009 Haute école de gestion de Genève Geneva School of Business Administration EVA Europe 2009 was jointly organised by Gold Sponsors

Presented at the ICEAA 2016 Professional Development & Training Workshop

Homework 6 Questions and Answers

Quantifying Damages in Construction Claims. James L McGovern

SAMPLE. AACE International Recommended Practice No. 80R-13

Project Monitoring and Control Project Closure. Week 8

A Comparison of Earned Value and Earned Schedule Duration Forecast Methods on Department of Defense Major Defense Acquisition Programs

Application of Earned Value Management (EVM) for Effective Project Control

Department of Industrial Engineering

An Analysis of Stability Properties in Earned Value Management s Cost Performance Index and Earned Schedule s Schedule Performance Index

Earned Value Management in IT A Tiered Approach (Making change stick) John Chapman Touchstone Ltd

Slides copyright 1996, 2001, 2005, 2009, 2014 by Roger S. Pressman. For non-profit educational use only

Earned Value Management System. a system to

Downloaded from

PROJECT COST MANAGEMENT

Earned Value Management System. a system to

Project Management: Cost

Application of Data Mining Tools to Predicate Completion Time of a Project

Carlos Consulting Group

Earned Value Management. Danielle Kellogg. Hodges University

DATA ITEM DESCRIPTION

Transcription:

EVM = EVM: Earned Value Management Yields Early Visibility & Management Opportunities presented by Harry Sparrow for THE SOCIETY OF COST ESTIMATING & ANALYSIS 2004 NATIONAL CONFERENCE & TRAINING WORKSHOP June 15-18, 2004 Los Angeles, California 829 Chiles Avenue St. Helena, CA 94574 707-967-0420 hsparrow@pmassoc.com

EVM Isn t Just EV It is integrated project management Specifically, it is predicated on the development of a baseline Integrates the technical (scope), cost, and schedule elements of the plan Presumes the maintenance of this baseline over the life of the project 2

Earned Value Management (EVM): Integrated Project Management 3

EVM: A Vision* The quality of a management system is determined not by the absence of defects, but by the presence of management value Gary Christle, The Cost/Schedule Control Systems Criteria (C/SCSC) and Earned Value Management: A Vision, 9/15/94 4

How Is Value Added? The management system provides information that is used to make effective management decisions Harry Sparrow 5

Key EVM Data Elements and Variances Value Time BCWS Budgeted Cost for Work Scheduled BCWP Budgeted Cost for Work Performed ACWP Actual Cost of Work Performed BAC Budget at Completion EAC Estimate at Completion ETC Estimate to Completion Copyright 2004 6

Data Analysis 7

Schedule Performance Index Work Completed Work Planned or BCWP BCWS = SPI 2100 Hours BCWP 3000 Hours BCWS =.70 SPI 70% Efficiency to Schedule 8

Cost Performance Index Work Completed Actual Cost or $ BCWP $ ACWP = CPI $105.0 BCWP $127.4 ACWP =.82 CPI 82% Cost Efficiency 9

To-Complete Performance Index: Performance Required to Achieve EAC (TCPI EAC ) TCPI EAC = Remaining Work ETC = BAC - BCWP EAC - ACWP = $300.0 - $105.0 $350.0* - $127.4 =.88 *Re-estimate of EAC 10

Performance Factors Cumulative performance Recent experience Cost and schedule performance Other? 11

IEAC Based on Performance to Date IEAC = ACWP + BAC - BCWP CPI Cumulative = BAC CPI = $127.4K + $300.0K - $105.0K.82 = $365.2K 12

STAGE* M L EAC Formulae EAC (1) = ACWPc + (BCWR CPI6) EAC (2) = ACWPc + (BCWR CPI12)? E E M M EAC (3) = BAC CPIc EAC (4) = ACWPc + [BCWR (CPIc x SPIc)] E M L L EAC (5) = ACWPc + (BCWR CPI3) EAC (6) = ACWPc + (BCWR CPI6) *E = EARLY M = MID L = LATE In these formulae: EAC is estimated cost at completion. ACWPc is actual cost of work performed (cumulative). BCWR is budgeted cost of work remaining (equal to BAC - BCWP). c signifies cumulative. Sub numbers (m, 3, 6, 12) refer to months; e.g. CPI6 is the average of six months current period CPIs. A bar over CPI (CPI) refers to a CPI based on a sum of BCWPs divided by a sum of ACWPs. CPI3 for example is based on the latest 3 months current BCWPs 3 months current ACWPs. CPI3 (no bar), on the other hand, is the average of the latest 3 months current CPIs. In general, CPI is a better figure to use than CPI. 13

EAC Comparisons The probable range of Completion Cost Based on Calculated EACs X IEAC 3 X IEAC 2 X IEAC 1 $ X Reported EAC Time 14

Is There More? Based on a study done by Michael Popp, there is statistical evidence that program behavior can be counter intuitive The wider range of variation in CPI movement in development contracts versus production ones is not as significant as anticipated There is not a significant difference in behavior of small versus large contracts There is clear evidence that, even as late as 70 80 % complete, cost performance can worsen significantly Good programs do not improve either freebies? 15

Formulae from the Popp Study Further statistical analysis yielded formulae that can be used to calculate what the CPI will be upon completion of the contract Development CPI 100%Cmplt = 0.438+0.057(BCWP/BAC)+(0.497 x CPI CUM ) Production CPI 100%Cmplt = 0.383+0.066(BCWP/BAC)+(0.622 x CPI CUM ) Keep in mind that these formulae are based on data for completed contracts The character of changes from now to the end can and will affect future efficiencies e.g. Can you say get well change? 16

OTHER CONSIDERATIONS: Do You Have Enough People Given Your Performance? When you assess your CPI in terms of hours, how do the authorized resources for remaining work compare with Planned Resources * CPI Is your estimate to complete (ETC) in your EVMS consistent with this? *Budgeted Resources for remaining work 17

EVMS VARIANCES Our Interest Right now Time Now BCWS FORECAST OF COST VARIANCE AT COMPLETE $ SCHEDULE VARIANCE TO DATE EXPRESSED IN DOLLARS (BCWP BCWS) ACWP FORECAST OF SCHEDULE VARIANCE AT COMPLETION COST VARIANCE TO DATE (BCWP ACWP) BCWP NOTE: REPORT DATE BCWS ACWP BCWP = = = BUDGETED COST FOR WORK SCHEDULED ACTUAL COST OF WORK PERFORMED BUDGETED COST FOR WORK PERFORMED Time 18

What Does $875,000 Behind Schedule Mean?! Well, it depends. It definitely means you haven t completed as much work as you had planned to by now. One approach to translating an earned value schedule variance into a time oriented one is Months Ahead or Behind = SV Avg. Monthly BCWS * *The average BCWS may be calculated using the total contract months to date or a selected number of recent months 19

Per Average BCWS, $875K = How Many Months Inception to Date Average Monthly BCWS 875.2 404.9 = 2.16 months behind Most Recent 3 Months 875.2 594.7 = 1.47 months behind Most Recent Month 875.2 728.4 = 1.20 months behind 20

However Depending on which activities are behind schedule per the plan, you may or may not be behind schedule. Whatever the situation is, if $875K represents a significant variance as a percentage, you need to look at your physical schedules NOW. 21

And, The Schedule Says Here is a partial screen capture of all the activities associated with our WBS element that are late. Activities XP7121, XP7122, XP7124, and XP7125 are late and are all contributing to the -$875K SV But only activities XP7121, XP7122, and XP7125 are on the critical path. Regardless of the $ value of our SV, these are significant, because they put the project end date is in jeopardy. TRAKKER Example from Dekker, Ltd. 22

Are There Other Concerns? Here a filter is applied identifying one or more of the following conditions: The activity is forecasted to complete more than 30 days late. There have been 3 slips of the execution schedule in the last 4 months. The activity has negative float Thus, while Activity XP7124 is not on the critical path, it is still a worry AND, how about those unstarted activities (e.g. XP7123, et al) Notice that most of these are in other legs of the WBS, but there is some dependency between the work in branch 1.2 and them TRAKKER Example from Dekker, Ltd. 23

FOOD FOR THOUGHT: Schedule Problem Variance Categories Critical tasks that did not start on time Late with Float Tasks that did not start on time but are not critical Purposely Delayed Tasks delayed due to work-around Early Tasks begun ahead of planned start Anomalies/Errors There are tools that automatically provide this information; Dekker TRAKKER from prior slides is one of these. 24

Schedule Variance Example Schedule variance 3500-4000 = (500) Problem - 100 Late with float - 300 Purposely delayed - 200 Early + 100-500 25

The Schedule Performance Index (SPI) Let s pause and talk about another EVMS concept The SPI is a measure of how efficient we have been in accomplishing our work relative to our plan for its accomplishment As a reminder, it is calculated per the formula BCWP SPI = BCWS 26

Are Your SPI and Your Schedule Data in Agreement It is possible to confirm that the schedule performance data are consistent with the SPI by use of one of these two formulas. Critical Path Length (CPL) + Float CPL or Project Length ± Time Ahead or Behind Project Length Significant differences between the SPI and either of these calculations should be assessed. 27

Earned Schedule and SPI Time The last slide brings up a point not unlike that of Walt Lipke and Kym Henderson They have espoused a theory documented in a presentation called, Earned Schedule The Concept, Initial Evaluation and Potential Benefits Their position is that the traditional EVM schedule variance and SPI are limited in value, because as a program approaches completion, the SV and SPI march inexorably toward 0 and 1.0, respectively Even if the program finishes late or early 28

EVMS VARIANCES Time Now BCWS $ SCHEDULE VARIANCE TO DATE EXPRESSED IN DOLLARS (BCWP BCWS) ACWP BCWP SV in Time REPORT DATE NOTE: BCWS ACWP BCWP = = = BUDGETED COST FOR WORK SCHEDULED ACTUAL COST OF WORK PERFORMED BUDGETED COST FOR WORK PERFORMED M A M J J A S O N D J F M A M J J A S O Time 29

ES Calculation The Earned Schedule (ES) is the combination of all full time periods (7 months here) up to the point where today s BCWP intersects the BCWS curve Plus any fraction of a time period (the portion of October here) associated with the intersection In our case, the fraction of October would be arrived at by the following calculation BCWP JAN CUM BCWS SEP CUM BCWS OCT ONLY This is similar to our earlier calculations 30

ES Calculation (cont d) Thus, in our case, if the cumulative BCWP through January were $55K, the cumulative BCWS through September were $50K and the BCWS for the month of October had been $7.5K our earned schedule would be $55,000 $50,000 ES = 7 + = $7,500 7.67months Given that time now is the end of January (our project s 10 th month), we have a schedule variance (SV t ) SV = BCWP t - BCWS t = 7.67-10.0 = t - 3.33 Months 31

Earned Schedule SPI? Since we can calculate ES and we know where we are in the project, we can calculate a time oriented SPI analogy SPI t = Earned Actual Schedule Duration 0.767 Per the earlier figures, the traditional SPI is BCWP 55,000 SPI = = = BCWS 72,500 Yes, these are close, but look at the next slide The data are for two actual projects, not our example Notice the correlation between the two until later In the later stages the difference between the time-based SPI and the traditional one, becomes apparent. = 7.67 10.0 = 0.759 32

SPI Comparisons for Late & Early Finish Projects This slide is used with the permission of Walter Lipke and Kym Henderson 33

ES Observations This concept may have better predictive utility for late finish programs, however The concept developers say that more research is needed, including More project data for retrospective analysis, especially for large scale projects Data from Earned Schedule early adopters Finally, there is no substitute for analysis of the integrated project schedule 34

So, what can we conclude from all of this? EVM isn t a panacea (hmmm, let me think about some of those DOD and DOE programs) EVM isn t always applicable, and where it is It isn t simple to implement, BUT It is a tool that can provide added value to the project team by offering earlier visibility into project issues, which leads to the opportunity to shift the direction of undesirable trends earlier and therefore increases the likelihood of project success 35

Thank you. Harry Sparrow 829 Chiles Avenue St. Helena, CA 94574 707-967-0420 hsparrow@pmassoc.com 36