Power Grid Corporation of India Limited. Fastest Growing Electric Utility in Asia Press & Analysts Meets Mumbai May 27, 2016

Similar documents
Power Grid Corporation of India Limited

Q3 FY Press & Analysts Meet Mumbai January 28, 2016

Fastest Growing Electric Utility in the World. Analysts Meet February 12, 2015 Mumbai

POWER GRID CORPORATION OF INDIA LIMITED

1200kV AC Sub-station at Bina. Delivering Smart Grid/ Distribution Solutions `

(Asia s Fastest Growing Electric Utility, since 2014) Q1 FY Investor Presentation

Press Meet August 2, 2013 Mumbai

Power Grid Corporation of India Ltd.

figtandoni CORPORATION POWER GRID OF INDIA LIMITED C/COS/Listing/NSE/ Dt:

CMP: INR180 TP: INR209 (+16%) Buy PAT up 29%; capitalization remains strong

By attending the meeting where this presentation is made, or by reading the presentation slides, you agree to be bound by the following limitations:

Name of the Issuer. POWER GRID CORPORATION OF INDIA LIMITED 1 Type of issue (IPO/ FPO) FPO

I n v e s t o r p r e s e n t a t i o n June

Q1 FY18 Investor Update

Name of the Issuer. 1 Type of issue (IPO/FPO) FPO. 2 Issue size (Rs crore) Rs As per Prospectus dated December 11, 2013

Q4 FY18 Investor Update

Power Grid Corporation (POWGRI) 138

Q2 FY16 Investor Update

Q3 FY16 Investor Update

Power Grid Corporation (POWGRI) 132

Q3 FY18 Investor Update

Percentage (%) 9.05% 19.24% 20.66% 20.93% 21.87% N.A.

Q4 FY16 Investor Update

JSW Energy Limited. Q2 FY 2016 Results Presentation October 28, 2015

BUY POWER GRID CORP INDIA LTD. Result Update: Q2 FY14. CMP Target Price NOVEMBER 30 th 2013 SYNOPSIS ISIN: INE752E01010

PEER GROUPS CMP MARKET CAP EPS P/E (X) P/BV(X) DIVIDEND Company Name (Rs.) Rs. in mn. (Rs.) Ratio Ratio (%)

No. 100/1/EC/2012-SP&PA/ Dated: June 21, 2012

Power Grid Corporation of India

I n v e s t o r Presenta tion Q 1 F Y J u l y

India: Power Grid Transmission (Sector) Project

ABB LTD (INDIA) RESEARCH

Power Grid Corporation of India Limited. Rating: Buy. Power-Transmission & Distribution PGCIL STOCK IDEA

NTPC LIMITED RESEARCH

दव ण त र य व द य त सवमवत

Power Procurement Strategy

NTPC LIMITED RESEARCH

ROBUST OPERATIONAL PERFORMANCE

दव ण त र य व द य त सवमवत

Rs Billion Short Term Debt Programme. (Series IX & X)

KEC International. Institutional Equities. Management Meet Update BUY. On Course Towards Recovery In Operating Margin

CMD s Speech for 17 th AGM

Acquisition of Three Sponsor Assets. 7 O c t o b e r,

Investor Update March 2018

Suzlon Energy Limited. H1 FY16 Earnings Presentation

NHPC Limited. March 29, 2018

INVESTOR PRESENTATION FINANCIAL YEAR : JUNE Salal Power Station, J&K

LARGE CAP & 1,970 BSE

Bharat Forge. Result Update. Q4FY13 Result Highlights. Valuation. No Respite in Sight May 29, Institutional Research 1

ADB INDIA PORTFOLIO,

Investor Update Q2 FY14

POWER GRID CORPORATION OF INDIA LIMITED (A Govt. of India Enterprise)

Power T&D Capex boom underway, established players to make hay

05 January 2012 NHPC NHPC. Uri I and Salal project update: J&K state government has formed a. Capacity addition highlights: The NHPC management has

Fixed Income Investor Update. innogy SE November 2016

PTC INDIA LTD. INVESTOR PRESENTATION Q4FY17 & FY17

INOX WIND LIMITED Q2FY18 INVESTOR UPDATE

Powering Ahead! Corporate Presentation

Indiabulls Real Estate Limited. Unaudited Financial Results Q3 FY th January, 2017

Second Quarter 2018 Ended September 30, 2017 Earnings Presentation

NHPC (NHPC) 30. Capacity addition below estimates. Result Update. ICICI Securities Ltd Retail Equity Research. June 5, 2017

NTPC Ltd. Results in line with estimates, BUY for attractive valuations. Power. EBITDA margins up at 26% (+700bps QoQ): EBITDA margins

Hathway Cable and Datacom Limited Investor Update 9M / Q3-FY19

11 May Report.xls Office of Budget & Fiscal Planning

MEMORANDUM OF UNDERSTANDING BETWEEN MINISTRY OF POWER, GOVERNMENT OF INDIA AND NORTH EASTERN ELECTRIC POWER CORPORATION LIMITED PART-I

Can Fin Homes Ltd. at a glance

NTPC Ltd. BUY CMP (Rs.) 163 Target (Rs.) 188 Potential Upside 15% For private circulation only. Volume No.. II Issue No. 164.

Batlivala & Karani MONTHLY UPDATE. 09 October Weakness in pricing...!!! Outlook and valuation. Price volatility in western region continued...

RESULTS PRESENTATION Q3FY11

Suzlon Energy Limited. Q1 FY16 Earnings Presentation

Central Transmission Utility

Inox Wind BUY. Performance Highlights. CMP Target Price `242 `286. 4QFY2016 Result Update Capital Goods. 3 year price chart

Corporate Presentation. December

ANNUAL REVENUE REQUIREMENT & FY

Indiabulls Real Estate Limited (CIN : L45101DL2006PLC148314)

2017 CRISIL Ltd. All rights reserved. Debt s it! Why debt funds are as good a wealth-creation tool as any, and can also aid in nation building


MARGIN REACHES DOUBLE DIGIT AT 24.2% 10.0%; PAT GROWTH OF 109.5% YOY

Key Considerations for Running Mock. Exercise

Corporate Presentation. August

June 08, 2017 Ratings

PTC INDIA LTD. INVESTOR UPDATE MAY 2014

Power Finance Corporation Limited (A Government of India Enterprise) A Navratna PSU

Mending Power Sector Finances PPP as the Way Forward. Energy Market Forum

TRACK RECORD OF THE PUBLIC ISSUES MANAGED BY THE MERCHANT BANKER IN THE LAST 3 FINANCIAL YEARS RURAL ELECTRIFICATION CORPORATION LIMITED

AVANTI FEEDS LIMITED-Schedule of Audio Conference Call for Investors on * * *

MRF BUY. Performance Highlights. CMP `9,407 Target Price `11,343. Company Update Automobile. Key financials

Interim Report January September 2014

AREA OFFICES. August, 2009 BUSINESS CENTRE. 4th Floor, Industrial Assurance Bldg., Opp. Churchgate Station, Mumbai Tel. : /

Executive Summary. July 17, 2015

Hathway Cable and Datacom Limited Investor Update Q1-FY19

Hathway Cable and Datacom Limited Investor Update Q2-FY18

Margins(%) EBITDA 30.0% 26.3% 25.4% NPM 26.5% 12.5% 18.1%

Skipper Ltd. February 13, Towering high. CMP INR 153 Target INR 184 Result Update - BUY. Company Background. Investment Rationale

JSW Energy Track Record

WELCOME SHAREHOLDERS. 25 th Annual General Meeting September 19, 2018

Peru: Capital Market and Infrastructure Themes

H results. innogy SE 11 August 2017 Bernhard Günther CFO

QUARTERLY FINANCIAL REPORT March 31, 2018

Corporate Presentation October 2017

TARIFF ORDER. Petition No. 250/2017. For. Electricity Department, UT of Dadra and Nagar Haveli (Transmission Division)

Transcription:

Power Grid Corporation of India Limited Fastest Growing Electric Utility in Asia Press & Analysts Meets Mumbai May 27, 2016

Disclaimer By attending the meeting where this presentation is made, or by reading the presentation slides, you agree to be bound by the following limitations: This document has been prepared for information purposes only and is not an offer or invitation or recommendation to buy or sell any securities of Power Grid Corporation of India Limited (the Company ), nor shall part, or all, of this document form the basis of, or be relied on in connection with, any contract or investment decision in relation to any securities of the Company. The information in this document is being provided by the Company and is subject to change without notice. The Company relies on information obtained from sources believed to be reliable but does not guarantee its accuracy or completeness. This document contains statements about future events and expectations that are forward-looking statements. These statements typically contain words such as "expects" and "anticipates" and words of similar import. Any statement in this document that is not a statement of historical fact is a forward-looking statement that involves known and unknown risks, uncertainties and other factors which may cause our actual results, performance or achievements to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements. None of the future projections, expectations, estimates or prospects in this document should be taken as forecasts or promises nor should they be taken as implying any indication, assurance or guarantee that the assumptions on which such future projections, expectations, estimates or prospects have been prepared are correct or exhaustive or, in the case of the assumptions, fully stated in the document. The Company assumes no obligations to update the forward-looking statements contained herein to reflect actual results, changes in assumptions or changes in factors affecting these statements. You acknowledge that you will be solely responsible for your own assessment of the market and the market position of the Company and that you will conduct your own analysis and be solely responsible for forming your own view of the potential future performance of the business of the Company. Neither the delivery of this document nor any further discussions of the Company with any of the recipients shall, under any circumstances, create any implication that there has been no change in the affairs of the Company since that date. Annual Accounts for FY2015-16 are yet to be approved by the shareholders. 2

Major Highlights POWERGRID Overview Sector Overview & Performance Performance (FY16) Journey - Last 5 years Financial Operational Performance (FY16) Consultancy, Telecom, CSR & Sustainability Projects Targeted in FY17 & Status of TBCB Projects Outlook, Investment Programme & Way Forward Major Recognitions 3

4

POWERGRID Stock getting included 1 Thank You for your continued faith & confidence 1- w.e.f. 20-Jun-2016; Source: BSE Notice dated 20-5-16 5

FY16: Major Highlights 31,788 crore Highest ever yearly Capitalization 13,717 ckm Highest ever TL ckm addition (Annual) Financials scale new peaks Gross Fixed Assets surpassed 1.5 lakh cr. Annual Income surpassed 20,000 crore Profit After Tax surpassed 6,000 crore 6

FY16: Other Highlights NER-Agra HVDC (Pole-I) SAARC Interconnections Projects acquired through TBCB World s longest multi-terminal ±800kV HVDC Tr. Line commissioned Additional Link(s) with Nepal & Bangladesh completed & operationalised 1 st line * successfully charged in time * 400kV D/C Khammam Nagarjunasagar Support in Natural Calamities Nepal Earthquake (Apr-15) Chennai floods (Dec-15) Manipur Earthquake (Jan-16) 7

8

POWERGRID Today A NAVRATNA ENTERPRISE CENTRAL TRANSMISSION UTILITY LISTED COMPANY since 2007 GOVT. SHAREHOLDING 57.90% PAYING DIVIDEND SINCE 1993-94 Market Capitalization 72,771 crore 1 >90% ISTS Transmission Network owned by POWERGRID Trans. Lines: 1037 Nos. - ~ 129,600 ckm Sub-stations: 208 Nos. - ~ 255,000 MVA 400kV & above: >90% State-of-the-art technologies like HVDC, SVC, FACTS etc. >45% power generated in India transmitted through POWERGRID AAA Stable CRISIL ICRA AAA Stable AAA CARE CREDIT RATINGS Domestic International BBB (-) Stable Outlook S&P Fitch BBB (-) Stable Outlook 1- Based on BSE Closing Price of 139.10 per sshar as on 31.3.2016 Physical Data as on 30.04.2016 9

POWERGRID Group Government of India 57.90% Institutions 34.80% Non-Institutions 7.30% Shareholding pattern as of 31 st March, 2016 Joint Ventures (13) (% POWERGRID equity holding) Subsidiaries (11) (100%) Powerlinks Trans. Ltd. (49%) North Eastern Trans. Co. (26%) POSOCO (Grid Management) Cos. Acquired through TBCB Torrent Power Grid Ltd. (26%) Parbati Koldam Trans.Co. Ltd. (26%) Bihar Grid Company Ltd. (50%) Cross Border Power Trans. Co. Ltd. (26%) National High Power Test Laboratory (20%) Energy Efficiency Services Ltd. (13.64%) Jaypee Powergrid Ltd. (26%) Teesta Valley Power Trans. Ltd. (26%) Kalinga Bidyut Prasaran Nigam Pvt. Ltd. (50%) Power Transmission Co. Nepal Ltd. (26%) (POWERGRID s 1 st Intl JV) RINL POWERGRID TLT Pvt. Ltd. (50%) Dividend Paying Grid Conductors Limited Shareholding in PTC 4.1% 1. POWERGRID NM Trans. Ltd. 2. POWERGRID Vemagiri Trans. Ltd. 3. POWERGRID Vizag Trans. Ltd. 4. POWERGRID Unchahar Trans. Ltd. 5. POWERGRID Kala Amb Trans. Ltd. 6. POWERGRID Jabalpur Trans. Ltd. 7. POWERGRID Warora Transmission Ltd. 8. POWERGRID Parli Transmission Ltd. 9. POWERGRID Southern Interconnector Trans. System Ltd. 10

11

Power Sector Overview & Performance Generation & Power Supply Installed Capacity incl. RE (GW) RE Capacity (GW) At the end of FY12 (Mar-12) 200 24.5 At the end of FY16 (Mar-16) 302 42.8 Addn. in 4 years (Apr12-Mar16) 102 18.3 Addn. in FY16 30 7.1 Per Capita Consumption: 1075 kwh (2015-16 Prov.) Energy Generated in FY16 1,107 BU (5.6% ) RE Generation: 60.5 BU (Apr15- Feb16) Power Supply Position in FY16 Energy Deficit: 2.1% (23.5 BU) Peak Deficit: 3.2% (5 GW) Source: CEA website / GoI 12

Power Sector Overview & Performance (contd.) Transmission Infrastructure Transmission (ckm) X-formation Capacity (MVA) I-R Capacity (MW) At the end of FY12 (Mar-12) 257,481 409,551 27,750 # At the end of FY16 (Mar-16) 341,551 658,949 58,850 # Addn. in 4 years (Apr12-Mar16) 84,070 249,398 31,100 Addn. by POWERGRID 36,123 130,823 24,900 Addn. in FY16 by POWERGRID only 13,717 23,578 12,400 # including 600MW I-R Capacity pertaining to 132kV lines For voltage levels 220kV & above Power Transmission An Enabler for seamless flow of power FY16 I-R Exchange 117 BU (31% ) STOA Txns 44,545 (17% ) STOA Energy Txn. 98 BU (21% ) Source: CEA website/ POWERGRID/ POSOCO 13

Transnational Interconnections POWERGRID- Major Assets commissioned in FY16 Transmission Lines 13,717 ckm Major Lines Bareilly-Kashipur, V chal Satna, V chal-satna (2 nd line) Meerut Moga Barh-Gorakhpur Raigarh - Champa Silchar Purba Kanchan Bari Vijayawada Nellore Gwalior Jaipur, Jaipur-Bhiwani(2 nd line) Biswanath Chariyali Agra (NE-NR/WR Interconnector) & associated AC system Mysore-Kozhikode Kudgi-Kolhapur Gooty Madhugiri Ranchi-Dharamjaygarh; Dharamjaygarh Jabalpur Kurnool-Raichur Angul Jharsuguda (2 nd line) Balia Varanasi, Kishenganj-Patna LILOs- Meerut-Kaithal Sub-Stations 15 Nos. 23,578 MVA Vindhyachal PS New Melli (GIS) Champa PS Vadodara (GIS) Sub-stations Mokokchung (GIS) Biswanath Chariyali AC # Biswanath Chariyali HVDC Agra HVDC Kozhikode Kudgi (GIS) Kolhapur (GIS) Madhugiri (GIS) Kurukshetra (GIS) # Kishenganj (GIS) Varanasi (GIS) # Initially envisaged as part of HVDC Inter-Regional Capacity 12,400 MW Inter-Regional Barh Gorakhpur Gwalior-Jaipur Biswanath Chariyali Agra (NE- NR/WR Interconnector) Pole I Ranchi-Dharamjaygarh Kudgi-Kolhapur Extn. of Biharsharif-Sasaram to Varanasi India-Bangladesh (Surjyamaninagar- Comilla) India-Nepal (Muzzafarpur-Dhalkebar) 14

Transmission- Congestion Management Enhancement of Capacity in last 2 years (FY15, FY16) WR to NR: Capacity enhanced from 3,700 MW to 7,600 MW (105% ) NEW Grid to SR: Capacity enhanced from 3,450 MW to 5,900 MW (71% ) Targeted increase in Capacity in next 2 years (FY17, FY18) WR to NR: Envisaged Capacity: 17,000MW (Addn. envisaged in 2 yrs: 9,400 MW) NEW Grid to SR: Envisaged Capacity: 9,900 MW (Addn. envisaged in 2 yrs: 4,000 MW) 15

Transmission- Congestion Management I-R Power flow from WR to NR & WR to SR (MUs) 46623 24206 29908 11668 15934 7597 7841 10683 FY13 FY14 FY15 FY16 WR-NR WR - SR > 4x > 2x Source: POSOCO 16

Transmission- Positives Steps towards Project Execution Improvement in Forest Clearance Process Permission to start work after Stage-I/ In-principle approval Enhancement in delegation of powers of Regional Offices of MoEFCC Easing Compensatory Afforestation (CA) conditions in TBCB projects Right of Way (RoW) Compensation (Reviewed) New guidelines (in Oct, 2015) for compensation issued: - Compensation of land cost below tower base (85% of cost of land) - Compensation towards diminution of land value under RoW (15% of land cost) This is in addition to compensation provision prevalent earlier Recognition to early completion In the case of actual date of commissioning (COD) prior to Scheduled COD for Transmission Lines under System Strengthening Schemes - Developer entitled to claim Tr. charges from actual COD 17

18

Performance (FY16)- Financial ( in crore) Quarter ended Year ended Description Standalone Standalone Income 31.03.2016 31.03.2015 31.03.2016 31.03.2015 - Transmission Charges 5,492 4,468 19,945 16,521 - Consultancy Services 163 157 465 381 -Telecom 105 79 392 275 - Other Income 201 206 479 603 Total Income 5,961 4,910 21,281 17,780 Operating Expenses (including prior period adjustment) 666 645 2,456 2,426 EBITDA-Gross Margin 5,295 4,265 18,825 15,354 Depreciation 1,785 1,418 6,183 5,085 Interest 1,477 1,038 5,023 3,979 Extraordinary Items (Net of Tax exp.) - 0 Tax 434 397 1,592 1,311 Profit after Tax 1,599 1,412 6,027 4,979 Growth in Income : 20% Growth in Profit After Tax: 21% 19 19

Performance (FY16) - Financial ( in crore) Description As on 31.03.2016 As on 31.03.2015 Gross Fixed Assets 1,50,052 118,264 Capital Work-in-Progress 46,830 56,292 Debt 1,06,321 93,845 Net Worth 42,598 38,037 Earning Per Share ( ) 11.52 9.52 Book Value per Share ( ) 81.43 72.71 Key Financial Ratios Debt : Equity 71:29 71:29 Return on Net Worth 14.15% 13.09% 20

Performance (FY16) - Financial Billing & Realization Billing 19,178 crore Realization 18,668 crore %age realization 97.34% As on 31.03.2016 Total Outstanding ~ 2,596 crore (50 days billing # ) Transmission Outstanding (beyond 60 days) Billed but not outstanding (<60 days allowed as per CERC) ~ 367 crore (7 days billing # ) ~ 2,229 crore (43 days billing # ) # Avg. Monthly Billing: 1598 cr. => 2 months 60 days) billing = 3,196 cr. 21 21

Performance(FY16) - Operational Performance during FY16 Availability : 99.72% Reliability : 0.66 Trippings/ line Assets as on Mar-16: Trans. Lines Sub-stations : 1031 Nos. - 129,354 ckm : 207 Nos. (incl. 24 GIS) - 255,348 MVA (104 sub-stations remotely operated) Voltage Landscape migrating to 765kV (Mar 16 vs Mar 11) TL (765kV & above): 17% vs <1% S/S (765kV & above): 19% vs <1% New Initiatives in Asset Management Aerial Patrolling (using helicopters) of 17,000 km of TL to commence shortly Use of Unmanned Aerial Vehicles (UAVs/ Drones) commences w.e.f Apr-16 22

23

Journey (Last 5 years): Asset Creation Consistent Asset Growth Investment-led Asset Growth. Consistent increase in ISTS Infrastructure Gross Fixed Assets 2.37x (GFA+WIP) ( in 000 crore) 196.1 174.3 TL ('000 ckm) X-fm ('000MVA) S/S (Nos.) 207 192 184 167 255.3 150 231.7 149.8 150.1 205.9 63.4 96.7 80.6 120.8 96.5 118.3 93.0 124.5 164.8 100.2 106.8 115.6 129.4 FY12 FY13 FY14 FY15 FY16 Poised to become 3 rd Largest CPSE in the Country FY12 FY13 FY14 FY15 FY16 One of the Largest Trans. Companies Globally 24

Journey (Last 5 years): Profitability Asset Based Returns & Sustained Profitability. Income Profit After Tax CAGR: 19% 21,281 13,328 15,721 17,780 CAGR: 20% 4,979 6,027 10,785 4,235 4,497 3,255 FY12 FY13 FY14 FY15 FY16 FY12 FY13 FY14 FY15 FY16 ( in crore) FY12 FY13 FY14 FY15 FY16 25

Journey (Last 5 years): Returns to Stakeholders. and enhanced Shareholder returns. Earning Per Share & Book Value per Share 50.73 72.71 65.78 56.62 9.15 9.36 9.52 81.43 11.52 7.03 FY12 FY13 FY14 FY15 FY16 EPS BV per share Dividend for FY16: 2.31 per share (including 1.51 proposed) ( ) 26

Journey (Last 5 years): Project Efficiency Increasing Capitalization & Efficient Project Mgmt. Thrust on Capitalization and CWIP Management Capex Capitalisation Capitalization/ Capex (%) 39,882 73% 86% 69% 97% 141% 31,788 31,851 33,951 CWIP (Installed) 21,037 21,479 23,158 22,456 22,584 20,037 21,760 17,814 17,213 15,904 13,044 17,701 15,574 19,115 16,409 12,879 Const. Stores & Advances FY12 FY13 FY14 FY15 FY16 FY12 FY13 FY14 FY15 FY16 (Figures in crore) 27

Journey (Last 5 years): Employee Efficiency Increased Employee Productivity..and Employee Efficiency ckm/ Employee MVA/ Employee 27.1 23.7 18.5 13.5 13.5 11.2 12.3 10.1 15.0 29.7 Income/ Employee (Figures in lakh) Profit/ Employee 247 208 181 150 117 70 48 52 58 35 FY12 FY13 FY14 FY15 FY16 FY12 FY13 FY14 FY15 FY16 Setting new benchmarks, year after year 28

29

Performance (FY16): Consultancy - Domestic Income (incl. Intl. Business) 465 crore (22% ) Orders recd.: 27 Nos. Project Cost of Orders.: 810 crore Major Orders TS for Eastern DFCI; IPDS Implementation Line & S/S for East Central Railways Ongoing Assignments: 115; Project Cost 14,826 crore (Balance Cost) Major assignments NER Power System Improvement Project (6 NE States) Strengthening of T&D System in Arunachal & Sikkim 220kV TS to Leh-Kargil (J&K) Evacuation System for Lalitpur TPP (UP) Implementation of IPDS at Old Kashi area 30

Performance (FY16): Consultancy- International Footprints: 18 countries Orders recd.: 4 Comml. Proposals submitted: 15 EOIs submitted: 19 New countries approached Major Highlights New Interconnections with Nepal & Bangladesh - accomplished Doshi & Charikar Sub-stations & associated lines in Afganistan - completed Management Contract in Ethiopia - successfully completed Major Ongoing Assignments Ongoing Assignments: 13 Nos. 2 nd Block of 1x500MW HVDC B2B Stn. at Bheramara CASA-1000 Project Assignments from ADB & World Bank in Nepal Trans. Infrastructure works in Kenya 31

Performance (FY16): Telecom Income: 392 crore (43% ) 79 New Clients added [(Pvt. (42), Govt(37)] Total Order Book > 2100 crore Services provided: Dedicated Leased Lines, Internet, MPLS-VPN, Dark Fiber Clientele: Telcos, Govt. Deptts., PSUs & Private Cos., IT Cos. Infrastructure: Fiber Optic Network : ~ 36,500km (~3,300 km added in FY16) Points of Presence : 595 ( 233 Nos. added in FY16) Backbone Availability : 100% Major Projects: National Knowledge Network (NKN): Project completed & Under Operation National Optic Fiber Network (NOFN): Work for 7,175 Gram Panchayats under progress - 4,120 Gram Panchayats connected 32

Performance (FY16): CSR & Sustainability Rural Development Skill Development Major Thrust Areas for CSR Education Health Environment Major CSR Projects undertaken in FY16 Construction of ~9,500 toilets in ~4,250 schools in 7 States under Swachh Bharat Mission of GoI Skill Development to more than 2000 youth Installation of Hand Pumps, Borewells & Solar Street Lights in villages Supply of Solar lanterns to 10,000 students in villages Scholarships to ~ 5,500 Students Supply of Aids and appliances to ~ 2000 persons with disabilities Sustainability 50kWp Solar PV System commissioned at POWERGRID Corporate Center, Gurgaon POWERGRID Regional Hq. at Bengaluru Green Building award from HUDCO Solar Plants & LED lights in new S/S Control Rooms Rain Water Harvesting in S/S 3 rd Sustainability Report (A + Rating) - Released 33

34

Projects in FY17 Transmission Lines 15,000 GW-ckm Sub-Stations Inter-Regional Capacity 20 Nos. 12,300 MW Major Lines Gaya-Varanasi, Varanasi-Kanpur-Jhatikara Pachkula-Patiala; Sikar-Jaipur Aurangabad-Boisar; Navsari-Boisar; Kala-Kudus Raipur PS - Wardha(2 nd line),wardha- Aurangabad Dehradun-Baghpat, Roorkee-Saharanpur, Dehradun-Abdullapur Pasighat Roing Tezu - Namsai 800kV Champa-Kurukshetra HVDC Aurangabad-Padghe Mauda-Betul-Khandwa-Indore Wardha-Aurangabad (1200kV tower) Ranchi-Chandwa-Gaya Tiurnelveli-Tuticorin; Tuticorin-Salem-Madhugiri; Salem-Somnahalli; Madhugiri-Yelhanka Jabalpur-Orai-Aligarh Wardha-Nizamabad-Hyderabad Angul-Srikakulam; Dulhasti-Kishenpur-New Wanpoh Rajarhat-Purnea Singrauli-Allhabad-Kanpur; Lucknow-Kanpur LILOs- Pandiabil (Baripada-Mendhasal); Navi Mumbai (Lonikhand-Kalwa); NP Kunta (Kadapa- Kolar; Kadapa-Hindupur) Sub-stations NP Kunta Salem (Dharmapuri) Navi Mumbai (GIS) Kanpur (GIS) Pandiabil (GIS) Rajarhat (GIS) Saharanpur Bagpat (GIS) Dehradun Betul (GIS) Chandwa (GIS) Vemagiri (GIS) Srikakulam (GIS) Nizamabad Roing Tezu Namsai Alipurduar HVDC Champa HVDC Kurukshetra HVDC # Initially envisaged as part of HVDC 35 Inter-Regional Gaya-Varanasi Champa-Kurukshetra Angul-Srikakulam Wardha-Nizamabad Biswanath-Chariyali - Agra Pole-II Alipurduar Agra Green font indicates assets commissioned in FY17 35

Status of TBCB Projects (upto Mar 16) Participation 23 Projects Success 9 (39%) Cost-wise [Annual Levelised Tr. Charges] 1643 crore (47%) SPV & Date of Incorporation Completion ALTC ( in cr.) Current Status POWERGRID NM Trans. Ltd. (Mar-12) Oct-16 99 Construction under Progress POWERGRID Vizag Trans. Ltd. (Aug-13) Aug-16 231 1 st element commissioned in Dec-15. Construction under Progress POWERGRID Unchahar Trans. Ltd. (Mar-14) Sep-16 17 Construction under Progress POWERGRID Kala Amb Trans. Ltd. (May-14) Jul-17 59 Construction under Progress POWERGRID Jabalpur Trans. Ltd. (Feb-15) Jul-18 211 Construction under Progress POWERGRID Warora Trans. Ltd. (Apr-15) Nov-17 290 Construction under Progress POWERGRID Parli Trans. Ltd. (Apr-15) Jan-18 257 Construction under Progress POWERGRID Southern I/C Trans. Ltd. (Dec-15) Apr-19 359 Construction under Progress POWERGRID Vemagiri Trans. Ltd. (Apr-12) --- 120 Project discontinued [ALTC: Annual Levelised Trans. Charges] 36

37

Power Sector Outlook Capacity addition for Apr17-Mar22 period Generation initially envisaged for the period Apr17 to Mar22 (i.e. FY18-FY22) 86 GW (conventional) 30 GW (Renewables) Reworking of Generation & Trans. Plan under process by GoI Source: CEA/ MNRE 38

Power Sector Outlook (contd.) For Renewables: Revised Target 175GW by 2022 Solar- 100 GW Wind- 60 GW Others- 15 GW Solar: 100 GW Ultra Mega Solar Parks: 20 GW Rooftop: 40 GW Distributed: 40 GW Solar Capacity Addn.- Year wise Targets Upto FY16: 6.7 GW (Actual as on 31.3.16) FY17: 12 GW FY18: 15 GW FY19: 16 GW FY20: 17 GW FY21& FY22: 17.5 GW each Driving Forces Thrust on Renewables 24x7 Power for All Sector Reforms like UDAY Source: MNRE 39

POWERGRID Outlook (as on Apr 16) Ongoing Projects New Projects TBCB Projects approx. 94,000 crore approx. 34,000 crore approx. 16,000 crore (as per Empowered Committee Estimate) Total Works in Hand: 1,44,000 crore (approx.) 40

Planned Investment (Apr12-Mar17) Planned Capital Outlay* 110,000 crore Annual Capex Plan [*Projects: Ongoing Projects; Tariff Based Bidding Projects; Projects assigned by GoI; Green Energy Corridors; Intra-State Projects; Transnational Interconnections ] FY12-13: 20,037 cr. (Achieved) FY13-14: 23,158 cr. (Achieved) FY14-15: 22,456 cr. (Achieved) FY15-16: 22,584 cr. (Achieved) FY16-17: 22,550 cr. More than 88,200 crore achieved in first 4 years of XII Plan Contracts awarded Cumulative since Apr 12 to Mar 16: ~ 71,500 crore including ~ 22,600 crore in FY16 Investments Approved Cumulative since Apr 12 to Mar 16: ~ 58,850 crore including Projects worth ~ 13,200 crore in FY16 41

Way Forward Strengthening the Core Transmission Business through Capital Efficiency Operational Efficiency Process Innovation Tapping Opportunities in International Transmission Business through Consultancy EPC Asset Ownership (subsequently) Increasing Telecom Business by Leveraging tower infrastructure Deploying 100G technology for future 42

43

Major Recognitions Fastest Growing Electric Utility in Asia for 2 nd successive year Only Indian PSU in the Platts Top50 Fastest Growing Energy Companies 2015 Source: Platts Top 250 Energy Company Rankings 2014 & 2015 POWERGRID Only Indian Company among One of the Best Three Asian Companies which host most constructive Analyst Days that professionals find most beneficial Source: Institutional Investor Award: The 2015 All-Asia Best Analyst Day 4 th Largest CPSE in terms of Gross Block for 2014-15 (An improvement to previous year) Source: PSE Survey for 2014-15 released by DPE, GoI 44

Presentation available at www.powergridindia.com