London 2012 Risk Management. 12 th May 2011

Similar documents
Bournemouth Primary MAT Risk Management Policy

Report. by the Comptroller and Auditor General. Department for Transport. Crossrail

Goodman Group. Risk Management Policy. Risk Management Policy

Introduction by Philip Croessmann, V.P., Director of Risk Management Sources of Construction Claims Common Types of Construction Claims Risk

Risk Management Policy

Delivering London 2012: organisation and programme

A Second Runway for Gatwick Appendix. A21 Programme Risk Management

Risk Management Policy. September 2015

HSC Business Services Organisation Board

Commercial (QS) Core Competencies (Feb 17)

PRINCE2-PRINCE2-Foundation.150q

NHS North Somerset Clinical Commissioning Group Risk Management Strategy and Framework

Risk Management Framework

BASE CAPEX PROPOSAL - QUALITATIVE INFORMATION

Braindumps.PRINCE2-Foundation.150.QA

PRINCE2. Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version:

Preparing a business continuity plan

PRINCE2 Sample Papers

LONDON BOROUGH OF ENFIELD RISK MANAGEMENT STRATEGY

CORK COUNTY COUNCIL. Senior Resident Engineer Road Construction Supervision

PRINCE2 Sample Papers

NAO Report Maintaining Strategic Infrastructure: Roads

Principal risks and uncertainties

Retention Payments in the Construction Industry: A Response from Build UK and CECA

Risk Management Policy

Operational Risk Management

APPENDIX 1. Transport for the North. Risk Management Strategy

UCISA TOOLKIT. Major Project Governance Assessment. version 1.0

UNIVERSITY OF ABERDEEN RISK MANAGEMENT FRAMEWORK

Olympics Bid London 2012

Annex 8. Project Assurance Recommendations

Planning Construction Procurement. A guide to risk and value management

CITY OF JOHANNESBURG METROPOLITAN MUNICIPALITY GROUP RISK AND ASSURANCE SERVICES GROUP RISK MANAGEMENT POLICY

Risk Management for Tunnel Planning, Design and Construction

Risk Management Strategy

Cabinet Committee on State Sector Reform and Expenditure Control STAGE 2 OF TRANSFORMING NEW ZEALAND S REVENUE SYSTEM

The tool covers three key processes under three sections: selection of applicants (worksheet 1 of the spread-sheet);

Report of Head of Estates Management. Status Public (with separate exempt report) Summary

Prince2 Foundation.exam.160q

Draft Programming Document th meeting of the Management Board December 2016

Old Mutual International Singapore Branch MAS Notice 124 Disclosures

Executive Board Annual Session Rome, May 2015 POLICY ISSUES ENTERPRISE RISK For approval MANAGEMENT POLICY WFP/EB.A/2015/5-B

Risks and uncertainties facing the business

BERGRIVIER MUNICIPALITY. Risk Management Risk Appetite Framework

Actualtests.PRINCE2Foundation.120questions

Main Sections. Corporate Risk Policy Statement and Procedures AR-RMD-CR01. Executive Summary. Anglia Ruskin University Risk Management

2. 5 of the 75 questions are under trial and will not contribute to your overall score. There is no indication of which questions are under trial.

Discussion. Information

UK CONSTRUCTION MARKET VIEW SPR IN G

Fact Sheet 14 - Partnership Agreement

Assurance Approach Delivery assurance activities for Retail Market Release April 2019

Major Project Authority Integrated Assurance

Learning Legacy Document

Risk Management Policy and Procedures.

Learning Le cy Document

Information security policy

AIRBUS IFRS 15 Update

Roofers and Scaffolders Enquiry Form

RISK MANAGEMENT FRAMEWORK

MILA SULLIVAN PROCUREMENT CONSULTANT

RISK MANAGEMENT POLICY AND STRATEGY

28 July May October 2016

Key risks and mitigations

PRINCE2 Sample Papers

Approved by: Diocesan Council 17 December 2015

WNA NEW BUILD LICENSING CONFERENCE 2015 MANAGING THE LICENSING RISK IN CONSTRUCTION CONTRACTS. Jane Davies Evans 21 April 2015, Prague

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

NOT PROTECTIVELY MARKED. Public SPA Board Meeting Date Tuesday 19 December 2017 City Suite, Apex City Quay, Dundee

INTEGRATING RISK AND EARNED VALUE MANAGEMENT

UNCONTROLLED WHEN PRINTED

BCE Guidance. Advanced Wastewater Treatment Plant. Version 1.0

PRINCE2 Sample Papers

Final report Review of the effectiveness of the Payments Association of South Africa

Auckland Transport HS03-01 Risk and Hazard Management

RISK MANAGEMENT FRAMEWORK

Risk Management Policy

Risk Management Policy & Procedures. Premier Ltd.

Scouting Ireland Risk Management Framework

HEALTH RESEARCH CAPACITY STRENGTHENING INITIATIVE. Program Risk Management Policy. September Imperial : +265 (0)

RISK MANAGEMENT STRATEGY Version 3

Failure to prevent the facilitation of tax evasion: Our solution to help you avoid committing the new offence

Failure to prevent the facilitation of tax evasion:

PMI - Dallas Chapter. Sample Questions. March 22, 2002

Statement of Tax Principles & Strategy

RISK MANAGEMENT PROCEDURE GUIDANCE

Financial Policy Committee Statement from its policy meeting, 12 March 2018

Liquidity & Treasury Management Conference. Reporting to the Board Writing a Winning Treasury Report

for Major Infrastructure Projects

The Police and Crime Commissioner for Staffordshire and Chief Constable for Staffordshire. Annual Audit Letter for the year ended 31 March 2017

Finance and Asset Management for Long Term Delivery

Statement of Intent healthalliance (FPSC) Ltd. Incorporating the Statement of Performance Expectations

Pillar 3 Disclosure ICAP Europe Limited

Risk Management Plan PURPOSE: SCOPE:

Risk Management User Guide. Prepared By: Neville Turbit Version Feb /01/2009 Risk Management User Guide Page 1 of 36

Risk Management Strategy January NHS Education for Scotland RISK MANAGEMENT STRATEGY

Policy No. Contact Brian Orpin Version 3.0 Issue Date 28/11/2014 Telephone Review Date IA Date 09/08/2013

Nagement. Revenue Scotland. Risk Management Framework

l 2018 l 1. Airbus SE IFRS Consolidated Financial Statements 2. Notes to the IFRS Consolidated Financial Statements

AIRBUS. IFRS 15 and New Segment Reporting: 2017 Quarterly Restatements. 9 th April 2018

Target Operating Model Project

Transcription:

London 2012 12 th May 2011

Risk management overview Risk management is about the control of change by the promotion of activity and understanding of exposure. The three lines of defence Detailed project level identification and management of individual risks ODA Programme Assurance oversight of the process and compliance with it and the quality check of the data ODA Risk and Audit Setting of policy, audit of outputs and process and reporting to the Audit Committee

on London 2012 Risk management is part of the change control process Governance structure that required authorisation for all changes Senior management reviews at various stages of the change lifecycle Risks migrate through the risk and trends process until they become certain and are requests for change with budget authority or milestone change Change Trend Risk Increasing certainty

Risk management activities Three main activity stages to risk management 1. Identification development of risk register 2. Assessment determination of the likelihood and impact of risks 3. Control Formulation of mitigation plans and actions Repeat activities regularly to ensure registers reflect current status Hold risks centrally and monitor through assurance Ensure risk are recorded consistently with clear accountability Report key risks and overall risk status at project and programme level Escalate key decisions to higher authority levels for resolution Monitor risk management process for compliance and report Periodic review process for improvement

Risk management implementation and assurance Risk management must be part of the project or progress process Risk management carried out within the project or function Assured by the central team for review, update and compliance Risks reported by the project team as part of the process Consolidation of programme risks by the central team Project A Business Unit Programme Sub Programme 1 Risk Manager Corporate Project B, C, D Business Unit Programme Sub Programme 2 Risk Manager Project E Central risk team assurance and compliance Programme function Health & Safety Procurement Human Resources Priority Themes Programme Controls Commercial Integration

Quantification of risk - QRA QRA was used to calculate the contingency required for the budgets as part of the Baseline Report published in November 2007 Yellow Book QRA was part of the ongoing calculation of Anticipated Final Cost - the basis for programme performance QRA was also used to calculate programme risk contingency Schedule QRA was used to determine schedule risk on the complex projects and against interfaces

Control of contingency Contingency is controlled through a series of regular governance meetings Funders Contingency Funders Held by the Government funding departments QRA calculated quarterly and contingency adjusted Available quarterly by application to the Funders Group Programme Contingency Programme - Held by the ODA QRA calculated quarterly and contingency adjusted Accessible with approval to Funders Project Contingency Project held within the project budgets QRA calculated quarterly and trended from each month Available with approval of change board, also delegation

Review of risks Risks, trends and issues reviewed monthly with the project team and at implementation reviews with Programme Executive Key programme risks reviewed monthly with SROs Programme risks reviewed by ODA assurance group monthly Programme QRA and key programme risks review at the Funders Quarterly Risk Working Group Key programme risks reviewed by the Audit Committee of the ODA Board

Reporting of risks Project risks, trends and issues reported as part of Project Status Report Project QRA results included in calculation of AFC (Anticipated Final Cost) and reported on Project Cost Report Key programme risks reported as part of the Monthly Progress Report Programme QRA reported to the Government Olympic Executive and Funders as part of the Quarterly Report Key risks reported to the Audit Committee of the ODA Board Programme risk assurance report to monitor performance of and compliance with risk process

Benefits of the approach Three lines of defence model for risk management ensures Risk management applied across all projects and functions It is assured through regular challenge of the outputs Consistency guaranteed through common policy and compliance audit Risk is high priority at all levels from projects to Funders and Olympic Board Risk is embedded into the ODA processes for change control, progress reporting and calculating AFC and budget Risk management promotes specific activity aimed at reducing change Potential changes are identified and mitigated early Risk assessment was a transparent and integral part of cost forecast Free contingency identifiable and returned to Funders throughout

Key risks to the programme

Risk: Supply chain insolvency 150 Tier 1 contracts, 7,500 Tier 2 contracts and 43,000 contracts placed in total Credit crunch, recession and worsening economic outlook Number of insolvencies increasing as recession continued Our response Supply chain team to monitor all Tier 1 and critical Tier 2 suppliers using Credit scoring ratings, delinquency etc. Developed an Insolvency team to act at the first signs of insolvency Supplier held materials were vested or delivered to holding depot Intervention in procurement to prevent high risk appointments Number of insolvencies kept to a minimum against average

Risk: Credit Crunch and funding of IBC/MPC and Village Developer deals intended to fund the IBC/MPC and Athletes Village Deal might be difficult to finalise Private funding would come with additional requirements that might not be acceptable In the event the credit crunch made the deals unattractive and they collapsed What happened? Re-design to reduce cost Funded from contingency and savings

Risk: Programme interfaces and integration High number of interfaces and complexity New bridges, roads, sewers, utilities connecting to Venues Venues and infrastructure are in areas of changing topography What did we do? Try to minimise the interfaces Understand and manage the interfaces Procure in larger packages and transfer the integration risk to the supply chain

Key risk: Industrial relations Currently about 6,500 employees on the park and a further 5,000 on the Village 3 major unions represented The Olympic Programme is high profile and is a target increasing as the games approached Some demonstrations but no real industrial disputes to date What do we do? Agreed with the unions key principles of employment including: All labour directly employed and local where possible Pay to Working Rule Agreement rates Union representation on site High standard of welfare, training and employee facilities Active and regular discussion with all the key unions Enforcement of agreements

Risk: Security, considerations, changes and authority Security is key during games and construction Security includes perimeter guarding, CCTV, Fencing etc. Changes in security scope are always liable and to some extent unknowable Change in threat can mean a scope change such as: Building resilience Hostile Vehicle Mitigation Mitigation Close relationship with the security community and identification of possible measures required Developed scope to be flexible and signed of by security stakeholders Transferred cost of risk to Funders

Delay to completion of the Athletes Village Village comprises approximately 16,000 bed spaces during Games And 2,500 flats in Legacy 11 Plots of which 5 were CM and 6 tier 1 Large number of flats in one go in the UK to a strict deadline Supply chain risks for component manufacture and deliverysuch as: Bathroom pods Cladding panels What we did Negotiated with constructors to accelerate and buy off delay and disruption claims

Risk: Health and Safety Up to 10,000 workers on site during peak Complex, constrained site involving: Working at height Hot working Heavy machinery Tunnelling and underground works Temporary works Demolition Railway working What we did High focus on safety culture with Safe Start and toolbox talks etc Made senior managers responsible for safety performance Stopped work when safety was compromised World beating safety performance So far the only Olympics without a fatality

Questions?