What is the range of costs?

Similar documents
11 Economic Evaluation

2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Economic Analysis February 22/23, 2005

GET FIT Programme. Energy Sector Working Group. Maputo, 25 May Julia Crause Infrastructure, Southern Africa KfW Development Bank

FINANCIAL ANALYSIS: PROJECT 1

GREEK RENEWABLES SUPPORT SCHEME PROPOSALS

HVDC Inter-Island Link Upgrade Project. Investment Proposal. Part V Project Costs

TNUoS Tariffs in 10 minutes March 2018

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI

PPAs and Tariff Design

Perspective on Financing Wind Energy Projects. June 16, 2016

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46))

The Question of Sovereign Guarantee for the Development of Electricity Generation in Ethiopia

Sustainable Energy Handbook

Eskom Presentation Standing Committee on Appropriations

Title of presentation

Uniform System of Accounts for Electricity Tariff Setting.

CITY OF VANCOUVER ADMINISTRATIVE REPORT. General Manager, Engineering Services

Fiscal Policy and Financial Support Schemes for Clean Energy Mini Grids (CEMG)

presentation 2016 VHM GROUP OF COMPANIES

Investor Presentation. Cover slide (same as IR cover)

Lecture in Energy Economics: Life Cycle Cost Analysis for Bankable Projects in Sustainable Energy

1: Levelized Cost of Energy. Calculation. Methodology and Sensitivity

Eskom 2018/19 Revenue Application

It Don t Mean a Thing Without Good Marketing!! Marketing Solar for Agricultural Uses

Endesa FY 2017 Results 28/02/2018

Overview: Opportunities in Small Hydro Javier Escorriola - Norfund. Small Hydro Latin America Conference December 5, 2012

Interconnection Request Application Form for Interconnecting a Certified Inverter-Based Generating Facility No Larger than 20 kw

SMALL RENEWABLE ENERGY (HYDRO) INSURANCE PROPOSAL FORM

The Economics and Financing of Distributed Generation Investment. Budapest, Hungary November 17, 2016

UNDA RENEWABLE ENERGY PIPELINE PROJECTS

Financial Analysis and Cash Flow

Project Appraisal and Selection

Renewable Energy Insurance. The Leader in Renewable Energy Insurance Our Knowledge, Your Power

Industrialisierung von Offshore-Windenergie im internationalen Kontext

THE SOUTH AFRICAN RENEWABLE ENERGY IPP PROCUREMENT PROGRAMME

BC HYDRO S APPLICATION FOR 2004/05 AND 2005/06 REVENUE REQUIREMENTS BCOAPO et al. INFORMATION REQUESTS

Muskrat Falls Project Oversight Committee. Period Ending June 2017

POLICY NO I. INTRODUCTION

THE ECONOMIC IMPACT OF AMERICA S ELECTRIC COOPERATIVES

TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Tariff Order No 1 of 2010 dated

COSTING AND PROJECT EVALUATION USING NODOC

We believe our human capital is the key factor to success, as well as the reason r upholding a leading position on the Bulgarian financial market.

Investments in renewable energy power projects in East Africa

NEW HAMPSHIRE CODE OF ADMINISTRATIVE RULES NET METERING FOR CUSTOMER-OWNED RENEWABLE ENERGY GENERATION RESOURCES OF 1,000 KILOWATTS OR LESS

Solar PV Business Models & Investment

Infrastructure Development Fund

Financial Incentives for Deploying Carbon Capture and Storage: Tom Wilson Sr. Program Manager CSLF Financing Roundtable 2010 April 6, 2010

Business models for (MHP) village grids - two EnDev case studies - Marcel Raats Energising Development

Actual neighborhood of Sunrun customer homes

Renewable Energy Insurance. The Leader in Renewable Energy Insurance Our Knowledge, Your Power

JOINT VENTURE AGREEMENT

TRANSMISSION CHARGING STATEMENT

COMPONENTS OF REVENUE REQUIREMENT

PROGRAM EXPENDITURE AND FINANCING ASSESSMENT

J.P.Morgan 2018 Energy Conference June 20, 2018

L/C/TF Number(s) Closing Date (Original) Total Project Cost (USD) IDA-49320,IDA-H Jun ,274,997.95

Financial Analysis of Energy

Korea South-East Power Co., Ltd. Annual Ratings Review

FINANCIAL ANALYSIS OF TRANCHE 1

HOLY CROSS ENERGY November 3, 2015 GENERATOR INTERCONNECT POLICY

No.21 Rural Electrification 1

Small Generator Interconnection Application

Tanahu Hydropower Project (RRP NEP 43281) FINANCIAL ANALYSIS. A. Introduction

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy

No. 45. An act relating to renewable energy and energy efficiency. (H.446) It is hereby enacted by the General Assembly of the State of Vermont:

SESSION II: FINANCING INITIATIVES AND BUSINESS PLANS THAT WORK Unlocking Domestic Finance

Earnings Conference Call

CONNECTION OF OFFSHORE WIND ONSHORE -- Some Food for Thought to Aid the Discussion at the Post-Conference Workshop

Challenges and Solutions for Project Financing Mark Roesink, Oikocredit International

Accelerating the Integration of Renewables

Call for Tenders Document A/O

PJM & MISO Assumptions and Criteria for Testing of New Resources

Regulatory Framework for New Bagasse Based Cogeneration Projects

Economic Impacts of New Jersey s Proposed Renewable Portfolio Standard Report Schedules

Vattenfall at a glance

Leading the Way in Electricity SM. Business Update. May 2014 EDISON INTERNATIONAL. May 2,

Group Interim results for the six months ended 30 September Cover slide (same as IR cover)

Schedule NEM-V Sheet 1 VIRTUAL NET ENERGY METERING FOR MULTI-TENANT AND MULTI-METER PROPERTIES

Implementation of Solar Based Projects in MP Dated 20 July, 2012

A Utility Perspective: Subsidized Projects How Much Should You Pay?

UBS Natural Gas & Electric Utilities Conference March 2, 2016

Summary of Value of Distributed Energy Resources Phase 1 Order

FOCUS ON EDF EN Analyst Group Lunch Meeting - 6 July 2017

Atlantica Yield Reports Second Quarter 2017 Financial Results

Muskrat Falls Project Oversight Committee

Supporting Clean Energy Finance in the Asia Pacific Region

GLOBAL NEW INVESTMENT IN RENEWABLE ENERGY BY ASSET CLASS, ($BN)

Joint venture for a PV project in Honduras. January 2015

RWE Company Presentation. As of March 2018

SMA SOLAR TECHNOLOGY AG Analyst / Investor Presentation Financial Results 2017

Case-study location: Battaglia Terme\Galzignano Terme

PRE-BID CONFERENCE Wind-generated electricity

Economic and financial feasibility of PV projects

SCHEDULE 19 LARGE POWER SERVICE

Choosing Appropriate Incentives to Deploy Renewable Energy

2019 Corporate Operating Plan

FOR OFFICIAL USE ONLY RESTRUCTURING PAPER ON A PROPOSED PROJECT RESTRUCTURING

Preliminary Economic and Fiscal Impacts of the Proposed Northern Pass Transmission Project Prepared for Northern Pass Transmission LLC

Montecristo Hydroelectric Project

IBERDROLA FRAMEWORK FOR GREEN FINANCING

Transcription:

Oliver Froend Costs and Revenues are considered separately for the implementation phase and for the operation phase Implementation Costs Direct Costs Indirect Costs Possible Revenues: Subsidies & grants(mostly MHP) CDM upfront payment (usually SHP, LHP) details on following slides Operation Costs Operation and maintenance Administrative costs Possibly transmission fees Taxes Replacement costs Debt servicing of borrowed capital Revenues: Tariff payments Ancillary service / capacity fee (for peak power, if available in market) CDM and subsidies Costs and revenues - Timeline Land acquisition Costs Implementation Amortization Total Investment Operation Time Revenues Scrap value Deconstruction Abandon Alternative: reinvest and continue operation 1

Typical positions in a Bill of Quantities (BoQ) for Direct Costs Site installation: preparatory works, site office, camp, workshops, plants, spoil areas, etc. Access roads(permanent and semi-permanent) to site and within project area, including upgrading of existing roads and construction of new roads Main civil works of all permanent structures Hydro-mechanical equipment(e.g. gates, lifting equipment, stoplogs, trash racks) Penstock, erection, incl. bends, stiffeners, bifurcation, and all installation measures, incl. corrosion protection Generating equipment(e.g. turbines, generators, control equipment, transformers and switchgear Transmission line from HPP switchyard to substation / point of interconnection. Typical positions in a Bill of Quantities (BoQ) for Indirect Costs Technical Managementor pre-construction costs: All project development costs up to start of construction works Land acquisition(incl. cost related to measures according to the Environmental and Social Impact Assessment (ESIA) : Costs for purchase of land, relocation, preparation of agricultural land for compensation, mitigation measures Insurances Project administration(client) Engineering: Detailed engineering (by contractor), owners engineering (by owner s engineer), site supervision Other non billed items and expenses Taxes (VAT), custom s fees for imported equipment Interest during construction(idc) Energy Market Analysis Technical expertise FS pre-fs Desk study Project Rationale Costs and revenues- Timeline Possibility to impair the project Expertise in finance and legal aspects Destine Power Purchaser Projects decision Securing short- -term finance MoUwith power purchaser Negotiations Survey, geological analysis, DED Tender Authorization Process Project Realisation Cost / Expenses Typical Variation Financial closure IPP Contract Construction Order and Supply Test Runs of Equipment Installation Tender evaluation, negotiations, contracting Operation 2

Micro-Hydropower Projects Rural Electrification Indonesia Breakdown of costs for off-grid rural electrification MHP Source: own data The stated cost / kw (installed) include distribution and project development(engineering, supervision, admin, etc.) Cost fortransmission and distribution can vary vastly, depending on characteristics of settlements. Economy of scale applies mainly to pre-construction cost (studies, engineering), but also to civil works and E/M equipment 30 kw off-grid isolated ~2 500 USD/kW Civil Works E/M-Equipment LV-Distriburion Engineering etc. 60 kw off-grid isolated ~3 000 USD/kW Civil Works E/M-Equipment LV-Distriburion Engineering Others / Contingencies Investment costs for on-grid small hydropower plants are usually within an approximate range Large Hydropower (>10MW) On-grid Planned (Desk Level), Indonesia Civil works Electro-mechanical equipment Transmission lines, transformation, grid connection Project planning and design, site supervision, project management Total: 1500 to 3000 USD/kW 400 to 1300 USD/kW 50 to 200 USD/kW 50 to 500 USD/kW 2000 to 5000 USD/kW Source: Master Plan Study of Hydropower Development in Indonesia, Nippon Koei / JICA, 2011 3

Breakdown of costs for a 42 MW on-grid HPP Insurances Hydromechani -cal Penstock Civil Works IDC TOTAL COST E/M- Works Indirect Cost Transmission New Built HPP in Indonesia FS-Level Cost Estimate Taxes (VAT) Indirect Cost Client Admin. Engineering Tech. Mngm. Service Land & EIA- Meas. Components of Generation Cost Fixed Operation and Maintenance Costs Fixed Costs Capital cost / Loan servicing Operation & maintenance details on next slide Insurances Variable Costs Expenses for service and maintenance, which depend on operating times Taxes (depend on generation / sales) Cost item Description Annual O&M cost (% of capital cost) Personnel Administration Maintenance of civil works and access roads Maintenance of E/M equipment Maintenance of transmission & distribution works Operators, linesmen, revenue collectors (if applicable) Insurance, customer service costs, land rent, taxes, water fees, other duties materials (paint, cement, etc.) and local manpower spare-parts and salaries of local fitters, electricians bush cutting, fuses, insulators, cross-arms, poles according to local salary levels according to local rules and regulations 0.2 to 1 % of capital costs of the civil works 1 to 3 % of capital costs of e/m equipment of MHP 1 to 3 % of capital costs of T&D 4

Economics of Hydro Power Installed Capacity 1,000 kw Specific Investment Cost MHP Scheme 3,000 USD/kW Total Investment Cost MHP Scheme 3,000,000 USD Average Annual Inflation rate 0 % Average Interest/Discount Rate 10 % Inflation Corrected Interest Rate 10 % Service Life MHP Scheme 25 years Annuity of Investment 330,504 USD Annual Cost Operation & Maintenance 3.0 % of Investment Annual Cost Operation & Maintenance 90,000 USD Plant Availability 95 % Average Plant Factor 65 % Average Annual Energy Production 5,409,300 kwh Average Energy Production Cost 7.77 US /kwh Objectives of Economic Analysis Economic vs. Financial Analysis To compare costs and benefits of a projectduring its service life, and to determine which among alternative projects (e.g. hydro versus diesel options) have an acceptable return on investment, or which one is the least cost optionto supply electricity to an area or a station. The economic analysisestimates returns to society / the national economyas a whole. Thefinancial analysisestimates returns to an individual project participant, usually the developer. Economic Analysis rural electrification MHP Taxes, duties and subsidies are not consideredin least-cost analysis of e.g. rural electrification projects. Adjustment to market pricesin economic analysis is called shadow pricingand can be a very important but also difficult aspect in the analysis. Financial Analysis commercial on-grid HPP In the financial analysis market prices are usedwhen estimating project costs. Subsidies (e.g. CDM) are considered as revenue. Cash-flowis calculated based on real costs / revenues to the developer. 5

The Internal Rate of Return (IRR) is a key indicator in economic and financial analysis Generation cost as indicator in economic analyses Sensitivity analysis The net present value or cost of a project does not say anything about the value of the project as compared to other project options. Simplified, the IRR on an investment is equivalent to the interest rate received for capital based on the payments and income that occur at regular periods. Funding agencies, Governments and developers use the IRR as a selection criterion. They could accept all projects with an IRR greater than the cut-off rate, or compare several project options on the basis of the IRR. Increase of generation costs vs. increasing specific investment cost Increase of generation costs vs. service life of project Generation cost as indicator in economic analyses Sensitivity analysis 6

8.000 7.000 6.000 5.000 4.000 3.000 2.000 1.000 Generation costs of different power plant types Annual full-capacity hours of utility operated power plants Hours per year 0 nuclear energy lignite hard coal natural HYDRO pumped gas sw storage hydro wind photovoltaics mineral oil ph Split generation costs of different power plant types operated by a utility 6,60 0,2 4,0 2,4 natural gas without GCC 4,80 4,70 1,46 1,2 3,34 pumped storage hydro 2,9 2,1 0,6 naturalgas GCC 3,40 0,3 3,35 0,85 1,3 1,0 1,2 operating costs in ct/kwh fuel costs in ct/kwh capital costs ct/kwh 2,39 0,74 1,65 2,20 0,57 0,53 1,1 hard coal lignite HYDRO nuclear energy 2,90 0,6 1,16 1,14 MIX (GCC gas with combined cycle) Range of generation costs of different power plant types Tidal-/Waveenergy Geothermal Solarthermal PV Biogas Solid Biomass Wind offshore Wind onshore Hydro Power Thank you for your attention! Oliver Froend entec AG / oliver.froend@entec.ch 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 [ cent/kwh] 7

The Time Value of Money - Discounting _backup terminology Costs and benefitscan have very different valuesfor society or for the developer depending on when they occur. Present values are betterthan the same values in the future, and early returns are better than later returns. In other words, we need less money in our pocket today if the investment is due next year as compared with the same investment payable now. In order to take account of these facts in our economic and financial analysis the concept of discounting project worth is used. Discount Factor Methods of Economic Analysis Discount Factor = 1 / (1 + i) n i = discount rate, must be absolute, not in % (i.e., 10% => 0.1) n = number of periods (years) from the present (year 0) to year n when the value occurs (end of that year) Static methodslook at a project and the associated costs and benefits independent of time; they do not consider the time value of money. Dynamic methodson the other hand treat costs and benefitswhich occur at different points in time of a project with different values. Static methods should notbe usedto analyze the economics of a power project. Thanks to computer models (spread sheets), economic analysis using dynamic methods is no longer a time consuming affair. 8

Inflation Payback period: Time in years from the beginning of the project until the time when the sum of the revenues from electricity sales (and other income) equals the capital invested for the project. Break-even point:the break-even point is usually taken as the minimum tariff level required at which annual revenues from electricity sales exceed the cost of production. For a given tariff, the break-even point can also mean the year when due to increasing electricity sales the annual revenue exceeds annual costs. Annuity:An annuity is an amount paid or received annually. With the annuity method, all costs and revenues (benefits) are expressed in equal annual amounts. This allows quick calculation of unit production costs, pay-back period and break-even point. In order to simplify economic analysis, inflation-free values should be used, i.e., costs and benefits should be stated at current pricesand interest / discount rates should be inflation corrected. Inflation corrected interest rates are called realas opposed to nominal rateswhich include inflation. real interest / discount rate i* = (i+1)/(a+1)-1 i = nominal interest or discount rate (absolute, not in %) a = inflation rate (absolute, not in %) 9