Using a Dispute Avoidance Board for contracts covered by the Housing Grants, Construction and Regeneration Act 1996

Similar documents
CONTRACT DATA. Part one Data provided by the Employer CONTRACT DATA PART 1

Course agenda. Course agenda. NEC3: Introduction to the Engineering and Construction Contract (ECC)

2 The Contractor s main responsibilities

NEC4 Engineering and Construction Contract review of changes from NEC3

Professional Services Contract

Experience Sharing in the use of the NEC3 Contracts Working with Employer under NEC3 Contract Arrangement

2 nd Edition September 2005 (Second Edition of CIDB document 1020)

HKIS Resolving Disputes between Contractors

GUIDANCE ON USING THE BUILDING HUB CONTRACTS

Conditions of Appointment for an Architect for a Domestic Project 2010 (2012 revision) Incorporating Amendment 1, September 2011

ENGINEERING AND CONSTRUCTION CONTRACT

Legal Sources. 17 th Willem. C Vis International Commercial Arbitration Moot / 7 th Willem C. Vis International Commercial Arbitration Moot (East)

CONTENTS. KLRCA ARBITRATION RULES (As revised in 2017) UNCITRAL ARBITRATION RULES (As revised in 2013) SCHEDULES. Part I. Part II.

NEC4 ENGINEERING & CONSTRUCTION CONTRACT

NEC3 ECC Introductory Training

ARBITRATION RULES. of the Finland Chamber of Commerce

ARBITRATOR S GUIDELINES

Arbitration Agreements DOs and DON Ts

Sub-consultant 2010 (2012 revision)

Arbitration Rules of the Arbitration Institute of the Stockholm Chamber of Commerce

PRODUCER AGREEMENT. THIS AGREEMENT will be effective upon verification of Producer s credentials and the acceptance and appointment by Company.

Construction Law Update: NEC3 Engineering and Construction Contract Part 2 - Compensation events The role of the Project Manager

Peter Kerrigan CONTRACTING ON NEC 3 ENGINEERING CONSTRUCTION CONTRACT OPTION A - AN INTRODUCTION.

Terms and Conditions of Business for the supply of Contract/Temporary Staff

CS ENERGY LIMITED SERVICE CONDITIONS

APPEALS IN CONSULTANT JOB PLANNING AND PAY PROGRESSION DISPUTES MODEL PROTOCOL

Arbitration Rules of the Arbitration Institute of the Stockholm Chamber of Commerce

INDEPENDENT AGENTS SERVICES, INC. AGENCY CONTRACT

ARBITRATION RULES OF THE MAURITIUS INTERNATIONAL ARBITRATION CENTRE

Rules of arbitration procedure for disputes relating to building and construction (VBA' arbitration rules 2010) Part 1 Arbitration Agreement

The contract is important so that both parties understand their responsibilities and liabilities.

osb.ic.gc.ca All about Bankruptcy Mediation

Terms and Conditions

LABOUR DISPUTE ADJUDICATION

TRANSNET NATIONAL PORTS AUTHORITY RFP NUMBER TNPA 541 DESCRIPTION OF THE WORKS: PORT OF RICHARDS BAY - CONSTRUCTION OF PORT ENTRANCES AND ACCESS ROADS

BRITISH AMERICAN TOBACCOUK PENSION FUND. Understanding the What, Why & Who. The British American Tobacco UK Pension FuNd.

UNITED STATES AND CANADA TERMS AND CONDITIONS OF SALE NOVEMBER 2006

UNCITRAL ARBITRATION RULES

Introduction to Construction Arbitration

The following amendments have been made to the June 2005 edition deleted: and of notified early warning matters

Rules of ICC as Appointing Authority in UNCITRAL or Other Ad Hoc Arbitration Proceedings. in force as from 1 January 2004

Counterclaims in Arbitration

IAMA Arbitration Rules

PERMANENT COURT OF ARBITRATION ARBITRATION RULES 2012

EMP Commercial Terms and Conditions AS AT DECEMBER 2015 ENERGY DONE BRIGHT

Korean Commercial Arbitration Board

Appeals in Consultant, Associate Specialists & Specialty Doctors Job Planning, Pay Progressions & Threshold Payments Disputes

The Republic of China Arbitration Law

The Landscape Consultant s Appointment

TITLE VII RULES OF PROCEDURE FOR INTERNATIONAL COMMERCIAL ARBITRATION MODEL CLAUSE

Data Transfer Policy Version 1.1 Last amended: 18 September 2014 Policy Owner: Governance Team

INTERNATIONAL COMMERCIAL ARBITRATION - THE ESSENTIALS.

Terms and Conditions for Supply of Electricity to Non-Domestic Customers of Power NI Energy Ltd t/a Power NI

Foreign Exchange Dealing Terms and Conditions

CIlent/ConsuItant MODEL SERVICES AGREEMENT

Plain English Commercial and Industrial Building Contract

የ}hhK < ¾ÓMÓM Å w The Revised Arbitration Rules

Conditions of Deposit Disputes

RULES OF INTERNATIONAL COMMERCIAL ARBITRATION

NI Dispute Resolution Service Requirements - What Does It Mean? David Di Paolo January 26, 2012

Implementing the Construction Supply Chain Payment Charter. January Guidance Note

Do your. homework. A contractor s guide to rights and obligations when contracting with homeowners

Medicare Claims Appeals Developments and Proposals for Expansion

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.

Key Features GM Self-Invested Pension Scheme

Scottish Conditions of Appointment of an Architect SCA/2014 (Apr 2015)

PERMANENT COURT OF ARBITRATION OPTIONAL RULES FOR ARBITRATION INVOLVING INTERNATIONAL ORGANIZATIONS AND STATES

Staying out of court: Avoiding litigation in M&A

Quick Print. TIMBER HARVESTING CONTRACT AND SUBCONTRACT REGULATION published by Quickscribe Services Ltd.

Austrian Arbitration Law

SUBCONTRACT FOR LABOUR ONLY ENGINEERING AND CONSTRUCTION WORKS (September 2005) (Second Edition of CIDB document 1016)

Code of Conduct for Copyright Collecting Societies

INVESTMENT MANAGEMENT AGREEMENT

SCC PROCEDURES FOR THE ADMINISTRATION OF CASES UNDER THE 2010 UNCITRAL ARBITRATION RULES

Manager, Worldwide Markets (Compliance) LOCATION: 86/GY12 EXTENSION: 5131 DATE: 21 st February 2002 REFERENCE: Y2728 SUBJECT:

AMERICAN INTERNATIONAL COMMERCIAL ARBITRATION COURT REGULATION "ON THE PROCEDURE OF ORGANIZATION AND CONDUCT OF "AD HOC" ARBITRAL PROCEEDINGS"

Construction Law Update Comparing Contracts-A Review Of The AIA 201 and ConsensusDocs

Part VII. Part V of the Polish Code of Civil Procedure Arbitration. [The following translation is not an official document]

Between the Danish Transport and Construction Agency and XX concerning the delivery of an examination system for the aviation area

Cross-Strait Bilateral Investment Protection and Promotion Agreement

OAIA Eagle Agency. Agency Agreement

NSW Workers Compensation Act 1987 Employer s Insurance Policy

INTERNAL REGULATIONS PREAMBLE

The stock options are marked with the symbol No stock option certificates are issued for the stock options.

Deed of Indemnity and Access. Law Institute of Victoria Limited (Institute) The Officers specified in the Schedule to this Deed (Officer)

Institutional vs. ad hoc arbitration: when and why?

AGC s Preliminary Commentary to the 2007 Edition of the AIA A201 General Terms and Conditions Document

2018 DIS ARBITRATION RULES. First Edition

The NEC 3 Engineering and Construction Contract

UNCITRAL Arbitration Rules

JT Tobacco International Taiwan Corp. Notification of Standard Terms and Conditions of Business

Construction Law Update: Spotlight on the NEC3 Engineering and Construction Contract

Pursuing claims under FIDIC. Jeremy Glover

IBA Guidelines for Drafting International Arbitration Clauses

STANDARD TERMS & CONDITIONS for Construction, Engineering & Electrical Works

ARBITRATION RULES LJUBLJANA ARBITRATION RULES. Dispute Resolution Since 1928

AGC TEXT COPY THE ASSOCIATED GENERAL CONTRACTORS OF AMERICA AGC DOCUMENT NO. 603 STANDARD SHORT FORM AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR

THE JAPAN COMMERCIAL ARBITRATION ASSOCIATION COMMERCIAL ARBITRATION RULES. CHAPTER General Provisions

Commission on Settlement in

Terms & Conditions. Rev A - Feb 2017

Transcription:

NEC4 ECC 5 Using a Dispute Avoidance Board for contracts covered by the Housing Grants, Construction and Regeneration Act 1996 This practice note has been prepared due to feedback from UK based users who would like to use an independent Dispute Avoidance Board (DAB), rather than using the parties Senior Representatives to resolve disputes in a contract where W2 would normally be used. The DAB would be similar to that contained in Option W3 of the NEC4 Engineering and Construction Contract (ECC), as part of a consensual dispute resolution process. Option W3 is not suitable for use in the UK if the work under the contract is covered by the Housing Grants, Construction and Regeneration Act 1996, as amended by the Local Democracy, Economic Development and Construction Act 2009 (the Act), as the Act requires that either party to the contract must be able to refer to adjudication any matter of dispute at any time. NEC4 ECC contains Option W2 to resolve disputes in accordance with the Act via adjudication. NEC4 ECC Option W3 does not feature adjudication and instead allows for a DAB, of 1 or 3 members to be appointed to work with the parties during the course of the contract to proactively identify and help to resolve disputes before they occur. Option W3 has a number of specific characteristics these are. The DAB is appointed from the start of the contract and regularly attends site and receives updates from the parties on the progress of the works. This allows them to become familiar with the work under the contract and the issues / difficulties the parties encounter. They are able to proactively identify potential disputes and to raise these with the parties working in part as mediators, to help the parties resolve their potential disputes through negotiation, and if necessary as independent evaluators providing a recommendation on how disagreements should be resolved. The DAB makes recommendations only, which allows it greater flexibility in how it undertake its work as the recommendations will not be subject to challenge in a subsequent tribunal. This however also poses a disadvantage as a party cannot enforce the decision of the DAB and the process relies on the mutual consent of the parties. The expectation is that the parties will respect the members of the DAB and their decision and, that as a tribunal would likely come to the same decision, there would be no benefit in taking the matter further. Either party can take a matter referred to the DAB to the tribunal named in the Contract Data for a final and binding decision if they disagree with the recommendation made. Due to the costs involved in having a standing DAB for the life of the contract, whilst still, maintaining the ability of the parties to take a dispute to adjudication at any time, it is recommended that a DAB is used in conjunction with Option W2 only on projects where the value or complexity / risk of disagreement is sufficient to justify the cost. The DAB process can be included as a Z Clause and the following example sets out the wording for such a clause, prepared for the Engineering and Construction Contract. nec 2019 neccontract.com Preparing an Engineering and Construction Contract 1

Example Z Clause for the ECC Delete clause W2.1 and replace with the following. Dispute Avoidance Board W2 W2.1 (1) The Dispute Avoidance Board consists of one or three members as identified in the Contract Data. If the Contract Data states that the number of members is three, the third member is jointly chosen by the Parties. (2) The Parties appoint the Dispute Avoidance Board under the NEC Dispute Resolution Service Contract current at the starting date. (3) The Dispute Avoidance Board acts impartially. (4) If a member of the Dispute Avoidance Board is not identified in the Contract Data or if a member of the Dispute Avoidance Board is unable to act, the Parties jointly choose a new member. If the Parties have not chosen a Dispute Avoidance Board member or a replacement, either Party may ask the Dispute Avoidance Board nominating body to choose one. The Dispute Avoidance Board nominating body chooses a Dispute Avoidance Board member within seven days of the request. The chosen member becomes a member of the Dispute Avoidance Board. (5) The Dispute Avoidance Board visits the Site at the intervals stated in the Contract Data from the starting date until the defects date unless the Parties agree that a visit is not necessary. The purpose of the visit is to enable the Dispute Avoidance Board to inspect the progress of the works and become aware of any potential disputes. The Dispute Avoidance Board makes additional visits when requested by the Parties. (6) The agenda for the Site visit is proposed by the Parties and decided by the Dispute Avoidance Board. (7) The members of the Dispute Avoidance Board, their employees and agents are not liable to the Parties for any action or failure to take action in resolving a potential dispute unless the action or failure to take action was in bad faith. Resolving potential disputes (8) The Dispute Avoidance Board assists the Parties in resolving potential disputes before they become disputes. (9) A potential dispute arising under or in connection with the contract is referred to the Dispute Avoidance Board. (10) Potential disputes are notified and referred to the Dispute Avoidance Board between two to four weeks after notification of the issue to the other Party and the Project Manager. (11) The Parties make available to the Dispute Avoidance Board copies of the contract, progress reports and any other material they consider relevant to any difference which they wish the Dispute Avoidance Board to consider in advance of the visit to the Site. (12) The Dispute Avoidance Board visits the Site and inspects the works, reviews all potential disputes and helps the Parties to settle them, 2 Preparing an Engineering and Construction Contract neccontract.com nec 2019

prepares a note of their visit and unless the Parties have resolved the potential dispute by the end of the Site visit, provide a recommendation for resolving it. (13) The Dispute Avoidance Board can take the initiative in reviewing potential disputes, including asking the Parties to provide further information. (14) A Party does not call a member of the Dispute Avoidance Board as a witness in an adjudication or tribunal proceedings. Delete clause W2.2(1) and replace with the following. The Adjudicator W2.2 (1) A dispute arising under or in connection with the contract is referred to and decided by the Adjudicator. A Party may refer a dispute to the Adjudicator at any time whether or not the dispute has been referred to the Dispute Avoidance Board as a potential dispute. nec 2019 neccontract.com Preparing an Engineering and Construction Contract 3

Example Entries for the Contract Data for the ECC PART ONE DATA PROVIDED BY THE CLIENT Resolving and avoiding disputes The number of members of the Dispute Avoidance Board is one/three (delete as applicable) The Client s nomination for the Dispute Avoidance Board is The Dispute Avoidance Board visit the Site at intervals no longer than months The Dispute Avoidance Board nominating body is The Adjudicator is The Adjudicator nominating body is The tribunal is If the tribunal is arbitration The arbitration procedure is The place where arbitration is to be held is The person or organisation who will choose an arbitrator if the Parties cannot agree a choice or if the arbitration procedure does not state who selects an arbitrator is 4 Preparing an Engineering and Construction Contract neccontract.com nec 2019

PART TWO DATA PROVIDED BY THE CONTRACTOR Resolving and avoiding disputes If the number of members of the Dispute Avoidance Board is three The Contractor s nomination for the Dispute Avoidance Board is nec 2019 neccontract.com Preparing an Engineering and Construction Contract 5