Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Similar documents
For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP

Managing Project Risk DHY

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration.

LCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

Risk Management Plan Project Name: Version 1.0 Date: dd/mm/yyyy

Fundamentals of Project Risk Management

Project Theft Management,

Project Risk Management

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

RISK MANAGEMENT PROFESSIONAL. 1 Powered by POeT Solvers Limited

Project Risk Management

COPYRIGHTED MATERIAL. Index

Chapter-8 Risk Management

Risk Management Made Easy. I. S. Parente 1

M_o_R (2011) Foundation EN exam prep questions

MODULE 5 PROJECT RISK MANAGEMENT, PROCUREMENT AND CONTRACTS

Master Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

Introduction to Project Management. Modeling after NYS ITS

Project Management Certificate Program

Crowe, Dana, et al "EvaluatingProduct Risks" Design For Reliability Edited by Crowe, Dana et al Boca Raton: CRC Press LLC,2001

RISK M A N A G E M E N T P L A N

PMI - Dallas Chapter. Sample Questions. March 22, 2002

Risk Management Made Easy 1, 2

Information Technology Project Management, Sixth Edition

12 GeV CEBAF Upgrade. Risk Management Plan

Key Aspects for Managing a Project

RISK MANAGEMENT STANDARDS FOR P5M

Five-Day Schedule and Course Content

0470_022817_03_chap01.fm Page 11 Wednesday, September 8, :29 PM. Part I The basics of project risk management

Achieve PMP Exam Success Five-Day Course Syllabus

L U N D S U N I V E R S I T E T. Projektledning och Projektmetodik

Classify each risk as a Threat or Opportunity. Most risks will be classified as Threats.

Every project is risky, meaning there is a chance things won t turn out exactly as planned.

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Project Selection Risk

Best Practices in Project Risk Management. Presented by: Jeff Miller, PMP - Director of Project Management Interstates Control Systems, Inc.

Objectives. What is Risk? But a Plan is not Reality. Positive Risks? What do we mean by Uncertainty?

Quality Control & Compliance Initiative. This document is publicly available to any staff member on the following network path:

Managing Project Risks. Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways

Risk Management Guideline July, 2017

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS

APPENDIX 1. Transport for the North. Risk Management Strategy

Risk Management & FMEAs. By Jay P. Patel, ASQ Fellow CEO & President QPS Institute

Project Management. A Practitioner s Guide. Steven M. Bragg

Prince2 Foundation.exam.160q

Risk and Risk Management. Risk and Risk Management. Martin Schedlbauer, Ph.D., CBAP, OCUP Version 1.1

Common Safety Methods CSM

Running Head: RISK MANAGEMENT PLAN 1

Risk Management Guidelines

1. Define risk. Which are the various types of risk?

Intro Public-Private Partnership (P3) Finance Course

Kidsafe NSW Risk Management Plan. August 2014

Risk Management For Projects

Certificate IV in Project Management Practice

Applied Risk Assessment into EPC Projects By Pulung Susilo Rahardjo

MINI GUIDE. Project risk analysis and management

Review Criteria. Robotics Program. Reviewer SCORE SUMMARY. Extent of Need 25 Goals Objectives and Milestones

RISK MANAGEMENT MADE EASY. Susan Parente Project Management Symposium.

The Risky Business of. Risk Management

INSE 6230 Total Quality Project Management

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

IT Certification Exams Provider! Weofferfreeupdateserviceforoneyear! h ps://

Certified in Risk and Information Systems Control

Procedure for Address Business Risk and Opportunities

PROJECT COST MANAGEMENT

Project Management and Scheduling

ENTERPRISE RISK MANAGEMENT (ERM) GOVERNANCE POLICY PEDERNALES ELECTRIC COOPERATIVE, INC.

PMI PMI-SP. PMI Scheduling Professional. Download Full Version :

Section II PROJECT MANAGEMENT METHODOLOGY GUIDELINES

Risk Management Process-02. Lecture 06 By: Kanchan Damithendra

Risk Management Policy. Apollo Hospitals. Risk Management Policy

Risk Management Strategy January NHS Education for Scotland RISK MANAGEMENT STRATEGY

EAN.UCC Project Management Framework Handbook. Issue Version 3.0

Project Management Professional (PMP) Exam Prep Course 11 - Project Risk Management

Office of Audit and Evaluation. Audit of Major Capital Project Management

ก ก Tools and Techniques for Enterprise Risk Management (ERM)

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

METHODOLOGY For Risk Assessment and Management of PPP Projects

RISK MANAGEMENT FRAMEWORK

Exam Questions PMI-RMP

Risk Management FUN! Humor Me

How to Avoid the Common Problems When Using Risk Management

Study of Cost Control Techniques Used in Construction Industry and Their Impact to Minimize Cost Overrun

THE CORPORATION OF THE CITY OF WINDSOR POLICY

CRISC. Isaca CRISC Certified in Risk and Information Systems Control Version: 1.0

Risk Management User Guide. Prepared By: Neville Turbit Version Feb /01/2009 Risk Management User Guide Page 1 of 36

Topic RISK MANAGEMENT Procedure Category Risk Management Updated 07/2011

PRINCE2 Sample Papers

PRINCE2. Number: PRINCE2 Passing Score: 800 Time Limit: 120 min File Version:

RISK MANAGEMENT MANUAL

Risk Analysis and Management. May 2011 ISO 14971

We will begin the web conference shortly. When you arrive, please type the phone number from which you are calling into the chat field.

The PRINCE2 Practitioner Examination. Sample Paper TR. Answers and rationales

International Journal of Advance Engineering and Research Development A MODEL FOR RISK MANAGEMENT IN BUILDING CONSTRUCTION PROJECTS

Integrated Capital Planning Manual

MEMORANDUM. To: From: Metrolinx Board of Directors Robert Siddall Chief Financial Officer Date: September 14, 2017 ERM Policy and Framework

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Transcription:

for the <Project Name> Prepared by: Title: Address: Phone: E-mail: Last revised:

Document Information Project Name: Prepared By: Title: Reviewed By: Document Version No: Document Version Date: Review Date: Distribution List From Date Phone/Fax/Email To Action* Due Date Phone/Fax/Email * Action Types: Approve, Review, Inform, File, Action Required, Attend Meeting, Other (please specify) Version History Ver. No. Ver. Date Revised By Description Filename 1 2 3 4 5

Table of Contents Purpose:... 4 Audience:... 4 References:... 4 1. Introduction... 5 1.1. Scope of this Document... 5 1.2. References (See Appendix for sample tools)... 5 2. Risk Management Strategy, Tools and Methods... 5 2.1. Risk Management Strategy... 5 2.2. Risk Management Tools and Outputs... 6 2.3. Risk Identification... 6 2.4. Risk Analysis... 8 2.5. Risk Response Planning... 9 2.6. Risk Monitoring and Control... 9 2.7. Assumptions and Constraints... 9 3. Roles and Responsibilities... 10 3.1. Risk Stakeholders... 10 3.2. Training... 11 3.3. Resources... 11 4. Thresholds... 11 5. Budget... 11 6. Timing & Schedule... 12 7. Reporting and Communication... 12 8. Appendix... 12 8.1. Risk Response Matrix.... 12 8.2. Risk Filter Decision Tree... 13

Purpose: The purpose of this document is to provide a framework on risk management activities during lifecycle. This document details out the approach towards risk identification, analysis of risks, mitigation plans, risk monitor and control and lessons learned. The purpose of the risk management plan document is not to address the mitigation plan for the individual risks these are all covered in Risk Register. Using this risk management planning, project team strives to minimize the negative risk and maximize the opportunities for the project success. This will be done by a systematic approach identifying all possible (both positive and negative) risks associated with the project and the possibility of occurrence and their impact on the project. Action plan will be created for the identified risks in order to manage them during project lifecycle. Risk management planning is a repeated and on-going process throughout the project lifespan and it should be started as early as project initiation. The risk management activities and its approach will be reviewed on a regular basis and the risk management plan along with the risk register will be refined accordingly. Audience: Below are the primary audience for this risk management plan document. Project Team risk key stakeholders > Risk Manager Project risk manager and key stakeholders are the ones who approve this plan. References: Use this space to add any project documental references

1. Introduction 1.1. Scope of this Document The scope of this document is to provide a framework on risk management activities during lifecycle. This document describes the risk management activities and approaches for the which mirrors the > risk management approach and uses the same tools and techniques. 1.2. References (See Appendix for sample tools) Below are the references used in the development of this plan. Project Management Institute (PMI ) PMBOK 2003 Edition...... 2. Risk Management Strategy, Tools and Methods 2.1. Risk Management Strategy Using the risk management strategy, project team strives to minimize the negative risk and maximize the opportunities for the project success. This will be done by a systematic approach identifying all possible (both positive and negative) risks associated with the project and the possibility of occurrence and their impact on the project. The risk management activities are: ning Risk identification - identification all known project risks Risk Analysis assess the probability and potential impact of the identified risks Risk Response Planning - create mitigation plans to manage the identified risks Risk Monitoring and Control monitor, review and update risk plan and their status Risk Closeout document the outcome and use the lessons learned in future Risk management planning is an iterated and on-going process throughout the project lifespan and it should be started as early as project initiation. Philosophy of non-risk adverse will be applied during risk management process while complaining to the project objectives with respect to quality, schedule, legal, financial and customer satisfaction.

2.2. Risk Management Tools and Outputs Below are tools that will be used to formalize and document the outcomes of the risk management process on this project. Project Manager will be maintaining the physical storage location of this risk management plan. Risk Management Activity ning Risk Identification Risk Analysis Risk Response Planning Risk Monitoring and Control Risk Management Tools and Outputs Risk Log Risk Log Risk Log 2.3. Risk Identification Risk identification activity for will Start during the initiation of the project when it is not active. Once the project is commissioned (active), the risk identification activity needs to be repeated in a regular interval as mentioned in risk management process (Monitor and control section) For, risk identification activity will be conducted during weekly project status meeting as well as monthly risk audits Any change request submitted for should be assessed for potential new risk and if any, impact and frequency of the new risk should be quantified and added to the risk register. A comprehensive list of all potential positive (opportunities) and negative (threats) risks for should be logged and vetted with relevant project stakeholders. Risk identification process should be thorough enough by adding all relevant project stakeholders and all possible risk sources. Below is the risk sources considered for risk identification process; Engagement Definition Client Commitment Technology - Hardware & Software Legal & Contractual Project Schedule Complexity Commercial Issues Duration Related Projects Political Considerations Project Budget/Financial <CUSTOMER> divisions and internal entities Regulatory Issues Communications Sub-contractors Industrial Relations Resources Suppliers Occupational Health & Safety Vendor Experience & Capability Market Action Please note that additional risks sources can be identified and added in to the risk log as and when required.

Below are the techniques that are used in identifying the risk elements for Risk register for similar projects Lesson learned documents Interviewing subject matter experts Risk management process checklist In depth examination of each element in WBS Analysing project specific documents for identifying potential risks such as Scope statements Requirements spec Schedule documents Design documents Statement of work Contracts and commitments Group process techniques such as Workshop for risk identification Nominal group techniques Brainstorming Delphi technique Risk statements are documented with unique IDs. All assumptions need to be considered as risk elements and documented accordingly. 2.4. Risk Analysis This step is to determine which risk events need to be focussed/prioritized for the response plan by analyzing the probability of risk occurrence and impact on the project using various suitable methods. These methods can be broadly classified into three categories; 1. Qualitative 2. Quantitative 3. Prioritization Irrespective of above method, one should consider the project triple constraints while performing risk analysis Project cost (labour, equipment, materials etc), time (schedule, delay, activity duration etc.) and Scope (desired features, functionality, project requirements etc) Probability and likelihood of risk elements are derived from; Risk assessment questionnaire outcome Fair estimates Expert judgement Decision trees Network Diagram

2.4.1 Qualitative Analysis Qualitative analysis determines the risk rating for each identified risk by deciding the probability of occurrence and its magnitude of impact using risk tools such as risk log etc. Based on the rating, identified risks will be ranked and provided adequate importance during risk mitigation process. 2.4.2 Quantitative Analysis Though it is not always possible to assign a dollar value for risk impact, a narrative description will be arrived for each identified risk. For the risks that can be quantified, an Expected Value (EV) will be arrived using probability percentage and magnitude of impact (EV=Probability * Dollar Impact). We have various tools available to calculate the probability percentage for any give risk that we foresee. 2.4.3 Risk Prioritization Not all identified risks will be considered for the risk response planning due to the involvement of cost and effort. Hence, analysed risk will be forced ranked in order to identify the top risks that affect the project. Top risks will be identified based on Quantitative expected value rating and Qualitative overall rating as performed in the above two steps. In practice, the risks that are scoring HIGH in both these parameters will be ranked at the top. Other threats and opportunities also force ranked separately for further analysis. In addition to Qualitative and Quantitative ratings, a few other factors that are important to customers and stakeholders will also be considered while ranking the risks. This factor can be derived from the following sources; Statement of Work Project Scope Requirement and Design Specifications Contract and Commitment agreements In addition to this, risk differentiation and further filtering will be applied using below techniques (if needed) Comparative Risk Ranking Risk Filtering (Refer 8.2) The remaining identified risks will not be part of the list but those will be reconsidered at a regular interval as per the set duration for Risk Monitoring and Control. 2.5. Risk Response Planning Risk response plan will be developed for all the risks selected in risk prioritization and filtering process. The minimum requirement is to plan risk responses for the risks with the overall risk rating HIGH. Response plan should be integrated with Project Plan and to be captured in Risk Log. In addition to the risk responses, we need to document the following;

Risk owner who is responsible for managing the response Risk response strategy Cost of the risk response Project objectives impacted by this risk Other dependent projects impacted by this risk Stakeholders impact Description of the mitigation plan To optimize various risk responses, a risk response matrix can be created to identify priorities and primary response plan to manage several risks. 2.6. Risk Monitoring and Control This process includes risk assessment during major project milestones/events, plan for the risk identified in risk log, identify new risks and reassess the mitigation plan effectiveness for the existing risks. Minutes of Meeting needs to be duly captured and shared among risk managers and project communication managers. Project stakeholders will be duly notified in case any major change in the risk plan or high-impact potential risk identified. Project manager conducts meetings at a regular interval (as mentioned in Risk Management Plan) with project leads to review the risks with the overall rating of HIGH or VERY HIGH Monthly meetings will be conducted by Risk manager to review all identified risks Weekly meetings will be conducted to review the high value risks status and overall project risk status with project team members Adhoc risk review meetings during major project events/milestones Quarterly risk review meetings with <CUSTOMER> representatives 2.7. Assumptions and Constraints Active participation from customer and associated partners during risk review meetings All project divisions should perform same level of risk management activities Timely and relevant project reports should be made available to the project managers with a risk section included Level of expertise in identifying and assessing risks can be different at different project divisions Other project divisions must support information requirements (say COST) during risk assessment Resources must be trained on risk management processes at the early stage of the project

3. Roles and Responsibilities > Integrated Risk Manager (Program Level Accountability) > Project Sponsor/Executives/Key Stakeholders (Consulted/Informed as indicated below) Project Manager (Project Level) Project Team Members (Project Level) Track Managers (Project Level) Project Sponsor/Executives/Key Stakeholders (Program Level) Risk Mgt Plan A,R R C C Identification A,R R C C Analysis A,R R I I Response Planning A,R R I I Monitoring and Control A,R R Reporting A,R R I I Lessons Learned A,R R C C R Responsible; A Accountable/Approval; C Consulted; I Informed Person names performing the roles; Role Name Integrated Risk Management Lead Project Executives Project Leads Component Project Manager <Project Manager> Component Project team members 3.1. Risk Stakeholders Stakeholder Name Program Manager Project Lead(s) Project Sponsor Project Manager Agency Point(s) of Contact <Name> <Name> <Name> <Names>

3.2. Training Periodical risk management workshops will be created and delivered to all project members to ensure their understanding and support on risk management activities Trainings will be audience-specific as needed (Top management, Customers etc.) Mandated attendance for project managers and team members who perform risk management activities for The objective of the program should cover/enhance the knowledge of risk management, their roles and responsibilities and process that needs to be followed 3.3. Resources Project quality reviews Project status reports Risk audit reports Change requests Project outputs (WBS, Scope, SOW etc.) Project stakeholders Risk management tools and templates (Risk log etc.) 4. Thresholds Thresholds limits for project scope, budget and schedule will be identified and the same will be considered while analysing the risks on the impact. This will be used in developing risk strategies accordingly. Risks that affect schedule, budget and scope will be analysed on a case to case basis and its overall impact on project deliverables will be determined. 5. Budget A contingent plan and reserve budget should be created at the project task level to manage any risks that materialize during project life-cycle. It is the responsibility of integrated risk manager to control this budget reserve and the program director will provide the authorization for releasing this fund. 6. Timing and Schedule Risk management process needs to be initiated and performed from project initiation and continue to be in-effect till the project closure. The schedule for various risk management activities will be defined in the project plan and project Gantt chart and triggers for risk activities will also be determined in advance.

7. Timing and Schedule Risk log and other risk management tools (as applicable) will be the primary reporting modes for project. Also, project weekly status will contain a section to address the identified risk status. Risk log and associated risk reports will also be shared with the customers as applicable. Information Report type Report Owner Frequency Audience Risk identification, Qualitative and Quantitative analysis, Planning, and Tracking Risk Log,, Risk Identification Worksheets < Project Manager> Integrated Risk Manager owns for Program. Updated and posted weekly at a minimum on eroom and Share Point. All Project Team members Project Risk Status Weekly Project Status Report <Project Manager> Weekly Track Managers, and Agency contacts. > Program Risk Status > Program Status Report Weekly <CUSTOMER> and Senior Management <Project Name> Lessons Learned Project Lesson Learned report <Project Manager> Project closeout Component Project Managers, Integrated Risk Mgr, Track Mgrs, Program Executives. 8. Appendix 8.1. Risk Response Matrix The risk repose matrix can be used to identify the effective response plans that are primary for more than one risks. This way, the same response can be used to manage multiple risks and the overall risk management effort can be optimized. For an example, in the below risk response matrix, we can determine that the response plan for B is also effective response plan for risk D. In the same way, response plan for E can be effective for risk A. Hence, response plan for B, C and E can be effective for all identified risks.

Risks Risk A Response Plan Risk B Response Plan Response Plans Risk C Response Plan Risk D Response Plan Risk E Response Plan Risk A description Risk B description Risk C description Risk D description Risk E description 8.2. Risk Filter Decision Tree This tool will be helpful in identifying and prioritizing risks so that the risk management effort is optimized. Inactive Risk Log (Reconsider risk importance later) List of Risks Was the risk originally identified by the customer? Is the expected impact of the risk visible to customer (in terms of functionality, schedule etc)? Is the gain outweigh the expected cost of managing this risk? Is there a risk response plan for other risk manages this risk too? Active Risk Log No