Queensland Competition Authority

Similar documents
Final decision. Aurizon Network's revenue adjustment amounts for

QR Network Revenue Cap Adjustment

Draft Decision on Maximum Allowable Revenue Aurizon Network s 2014 Draft Access Undertaking. 30 September 2014

Aurizon Network Debt investor presentation. October 2013

For personal use only

Financial Statements for the year ended 30 June 2017 Pursuant to Aurizon Access Undertaking Below Rail Services Provided by Aurizon Network

Aurizon Network 2013 Draft Access Undertaking Engineering Technical Assessment of Maintenance, Operating and Capital Expenditure Forecast

Queensland Competition Authority Pricing Papers Anglo American Metallurgical Coal Pty Ltd

23 May Mr Charles Millsteed Chief Executive Officer Queensland Competition Authority. Dear Mr Millsteed. DBCT Incremental Expansion Study

Aurizon Network Pty Ltd ABN Financial report for the year ended 30 June 2017

RISK ADVISORY AURIZON NETWORK PTY LTD. Cost Review of 2017 Flood Claim Tropical Cyclone Debbie

Aurizon Network Pty Ltd ABN Interim Financial Report for the six months ended 31 December 2017

Aurizon Holdings Limited Appendix 4D

Background paper. Cost forecasting assumptions

27 March Dr Malcolm Roberts Chairman Queensland Competition Authority. Dear Malcolm. DBCT Post 85 Mtpa Expansion Study

Aurizon Network Pty Ltd ABN Annual Financial Report for the year ended 30 June 2018

Consultation Paper. Queensland Rail's Western System Coal Tariffs

Queensland Competition Authority ENGINEERING ASSESSMENT OF AURIZON NETWORK S CAPITAL EXPENDITURE CLAIM

The impact of inadequate recognition of these risks on such a nationally important asset as the CQCN cannot be overstated.

QCA declarations review Anglo American s submission in response to initial submissions

SUFA RENT MODEL - MONTHLY

Consultation paper. Review of Guaranteed Service Levels to apply in Queensland from 1 July 2020

SEQ Interim Price Monitoring. Guideline for Templates for 2010/11

A Comparison between the WACC Proposed for Aurizon Network and Normalised Comparators Aurizon Network DAU

Dalrymple Bay Coal Terminal Access Undertaking

Re: New Delegation to determine Regulated Retail Electricity Prices for

Port of Melbourne tariff compliance statement

SUFA RENT MODEL - MONTHLY

Dalrymple Bay Coal Terminal Draft Access Undertaking

TCI Fund Management Limited

Labour Cost Escalation Report Tasmanian Networks Pty Ltd

Dalrymple Bay Coal Terminal User Group

Table of Contents. This document should be read in conjunction with the Financial Report, including any disclaimer.

14 June Access arrangement information for the period 1 July 2017 to 30 June 2022 EDM#

Queensland Rail Submission on 2016 QCA Fee Framework. February 2016

Aurizon Holdings Limited ABN Interim Financial Report for the six months ended 31 December 2017

For personal use only

Key Characteristics. Product Type. Fixed/Floating. Payment Frequency Current Distribution Issue Margin / Coupon Franking Credits Incl.

For personal use only

Aurizon Debt Investor Roadshow December 2016

Re: Queensland Competition Authority (QCA) consultation Review of Electricity Retailer and Distributor Credit Support Arrangements - May 2010

ASX Announcement. Notice of Meeting

FINAL Framework and Approach for Powerlink

Compliance with Control Mechanisms. October 2014

Decision on the Maximum Reserve Capacity Price proposed by the Independent Market Operator for the 2015/16 Capacity Year

For personal use only

Electricity (Retail Billing Guaranteed Service Level Scheme) Code. made under the Electricity Act 1994

Expected inflation estimate for Aurizon

Aurizon Network - Debt Investor Update HY2018 Results. February March 2018

submission To the QCA 9 March 2015 QRC Working together for a shared future ABN Level Mary St Brisbane Queensland 4000

Table of Contents. This document should be read in conjunction with the Financial Report, including any disclaimer.

Estimates of royalties and company tax accrued in Estimates of royalties and company tax accrued in Minerals Council of Australia

Managing Director & CEO, Andrew Harding Australian Coal Supply: Performance & Investment

Final Determination. Regulated retail electricity prices

2013 Draft Access Undertaking

Standard User Funding Agreement (SUFA) Regulatory Notes (Volume 3)

CHANGING THE TAXATION REGIME FOR INVESTORS IN THE HOUSING MARKET

Issues Paper. Retail Electricity Price Regulation in Regional Queensland

A letter from the Chairman

I attach the following announcement for release to the market:

Appendix 5B. Mining exploration entity and oil and gas exploration entity quarterly report

positive energy 9 December 2011

The QCA reviews the Gazetted Tariffs each year and the revised tariffs are applied from 1 July 2014.

For personal use only

SEQ Interim Price Monitoring Information Requirements for 2010/11

JUNE 18 QUARTERLY PRODUCTION REPORT

Referral Notice for the Review of South East Queensland Bulk Water Prices

Compliance report. Byerwen Coal Project EPBC 2010/5778. Byerwen Coal Project, Queensland EPBC 2010/ December 2016 to 8 December 2017

QWC5.pdf; QWC7.pdf; CBPRA1.pdf; PAC1.pdf

SUPREME COURT OF QUEENSLAND

I appreciate the Authority's continued involvement in ensuring rural irrigation prices have effective regulatory oversight.

For personal use only

DRAFT REPORT: AEMO GAS MARKET FEE METHODOLOGY DRAFT REPORT

Review of Regulatory Capital Structure and Asset / Equity Beta for Aurizon Network. Report to the Queensland Competition Authority

Australian Pacific Coal Limited

It is essential that the QCA reality checks its assumptions and calculations prior to making its final Determination.

i Frontier Economics May 2017 Recent evidence on the market risk premium FINAL REPORT PREPARED FOR AURIZON NETWORK

Project Assessment Conclusions Report

Possession Protocols (CQCN)

PROSPECTUS. AXIOM MINING LIMITED (ARBN ) (Company)

Submission to the Queensland Competition Authority (QCA) Gladstone Area Water Board 2015 Price Monitoring Investigation

Submitted by Western Power

sport.ajg.com.au Boxing Australia Insurance Program

Dalrymple Bay Coal Terminal: Corporate Costs. Report prepared by Stephen J Meyrick

Small Business and General Business Tax Break

APA GROUP RETAIL ENTITLEMENT OFFER

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Maharashtra Electricity Regulatory Commission (Fees and Charges) Regulations, 2017

Aurizon Holdings Limited ABN Interim Financial Report for the six months ended 31 December 2016

SUBMISSION BY THE QUEENSLAND COUNCIL OF SOCIAL SERVICE (QCOSS) ON THE QCA DRAFT DECISION ON BENCHMARK RETAIL COST INDEX FOR ELECTRICITY

For personal use only

Cedar Pocket Water Supply Scheme

FL AGSHIP INVESTME NTS. Hyperion Flagship Investments Limited. ended 31 december 2011 ABN

Market Monitoring Report. SEQ retail electricity market monitoring: January to March 2018

Draft report. Structure of participant fees in AEMO s gas markets February Australian Energy Market Operator Limited

Cost Allocation Methodology

For personal use only

Final Report. Seqwater Bulk Water Price Review

RE: CMS-2394-P: Proposed Rule: Medicaid Program; State Disproportionate Share Hospital Allotment Reductions, (Vol. 82, No. 144, July 28, 2017)

Market evidence on the cost of equity

Response to the UT5 draft decision on the term of the risk-free rate

Transcription:

Queensland Competition Authority File Ref: 1234527 7 April 2017 Mr Alex Kummant Executive Vice President Aurizon Network Pty Ltd GPO Box 456 Brisbane Qld 4001 Dear Mr Kummant The Queensland Competition Authority (QCA) has approved Aurizon Network's application for a 2015-16 revenue adjustment amount in relation to the central Queensland coal network. The total approved adjustment amount in 2015-16 reflects an over-recovery of $20.6 million, comprising a $23.3 million over-recovery in non-electric revenues and a $2.7 million under-recovery in electric revenues. Aurizon Network submitted its application on 7 October 2016 under the 2010 access undertaking (2010 AU) that was in force then. The QCA has considered this application under the 2016 access undertaking (2016 AU), which came into effect on 11 October 2016. In accordance with the transitional provisions of the 2016 AU, the QCA has applied the process set out in the 2010 AU to assess this application. The QCA's assessment of Aurizon Network's application is summarised in Attachment 1, which will be published on the QCA's website, along with this letter. This letter of approval constitutes a written notice for the purposes of clause 3.2.12 of Part B, Schedule F of the 2010 AU. Yours sincerely Charles Millsteed Chief Executive Officer cc: Ms Donna Bowman, Network Regulation Manager, Aurizon Network Level 27, 145 Ann Street, Brisbane Q 4000 GPO Box 2257, Brisbane Q 4001 Tel (07) 3222 0555 www.qca.org.au

ATTACHMENT 1: REVENUE ADJUSTMENT AMOUNTS 2015-16 Background On 7 October 2016, Aurizon Network submitted its 2015-16 revenue adjustment amount application, proposing to return to access holders a revenue over-recovery of $20.6 million. The QCA invited comments from stakeholders and received a submission from Pacific National. Aurizon Network did not make a response submission. Aurizon Network's proposal and Pacific National's submission are available on the QCA's website. The QCA considered Aurizon Network's proposed 2015-16 revenue adjustment amounts in light of the information Aurizon Network provided and the comments Pacific National made. Aurizon Network's proposal Aurizon Network proposed a total revenue adjustment amount in 2015-16 of $20.6 million (Table 1), comprising: $23.3 million over-recovery in revenues for AT2.4 reference tariffs (non-electric revenues)-with returns to access holders of $26.4 million for the Goonyella system, $0.2 million for the Moura system, $2.6 million for the Newlands system, and $1.8 million for the Goonyella to Abbot Point (GAP) system, offset by a $7.6 million shortfall in the Blackwater system $2.7 million under-recovery in revenues for ATs reference tariffs (electric revenues)-with a return to access holders of $2 million in the Goonyella system offset by a $4.8 million shortfall in the Blackwater system. Table 1 Revenue adjustment amounts 2015-16 ($m, nominal) Systems Non-electric revenues Electric revenues Total adjustment amount 2015-16 Blackwater 7.6 4.8 12.4 Goonyella (26.4) (2.0) (28.4) Moura (0.2) - (0.2) Newlands (2.6) - (2.6) GAP (1.8) - (1.8) Total adjustment {23.3) 2.7 (20.6) amount Any discrepancies between totals and sums of components are due to rounding. Aurizon Network calculated the revenue adjustment amounts by subtracting total actual revenues from its adjusted system allowable revenues for the applicable reference tariffs.1 1 Aurizon Network, FY2016 Revenue Adjustment Amounts, Explanatory Memorandum, October 2016 2

Aurizon Network said that its 2015-16 system allowable revenues are from the approved May 2016 extension draft amending access undertaking (May 2016 Extension DAAU). Aurizon Network applied the 2010 access undertaking (2010 AU) provisions to adjust those system allowable revenues to account for the differences between actual and forecast escalation indices on maintenance and operating costs, and the difference between actual and allowed electric energy connection costs. Aurizon Network's total actual revenues are based on what it is entitled to earn regardless of whether or not it collected this amount. This includes revenues associated with reference train services (including adjustment charges approved by the QCA in September 2016), take-or-pay obligations and other revenues (including revenue adjustments). Stakeholder comments Pacific National raised concerns2 with Aurizon Network's socialisation of rebate adjustments in the revenue cap process and with the reliability of Aurizon Network's revenue forecasts, noting that there was scope for improvement in Aurizon Network's forecasting methods. QCA's assessment Aurizon Network submitted its proposed 2015-16 revenue cap adjustment amounts on 7 October 2016 under the 2010 AU. The 2010 AU was replaced by the 2016 AU, which came into effect on 11 October 2016. Therefore, the QCA considered the proposal under the transitional provisions in the 2016 AU, specifically under clauses 12.4(d) and (e), which state: If the Approval Date is not the first day of a Year, then this Undertaking will apply in respect of any calculation of Revenue Adjustment Amounts, adjustments to the Second Year Allowable Revenue and other revenue cap calculations in relation to the whole of the Year within which the Approval Date falls (clause 12.4(d)). If the Approval Date occurs prior to the calculation of Revenue Adjustment Amounts, adjustments to Second Year Allowable Revenue and other revenue cap calcu lations for the preceding Year being undertaken and submitted to the QCA for approval, then those calculations may still be undertaken, and submitted to the QCA, by Aurizon Network as though the provisions under the 2010 Undertaking still applied in respect of those calculations and their approval by the QCA (clause 12.4(e)). Taken together these transitional clauses provide for the QCA to apply the 2016 AU process to assess the 2016-17 revenue adjustment amounts (as per cl. 12.4(d)) and apply the 2010 AU process to assess the 2015-16 revenue adjustment amounts (as per cl. 12.4(e)), which is the matter being assessed in this decision. The QCA considers this approach to assessing revenue adjustment amounts is consistent with the policy intent to assess revenue cap amounts for a year (here 2015-16) under the regime which was in place prior to the end of that particular year. The QCA considers that this approach will promote regulatory certainty. Therefore, the QCA has applied the 2010 AU process to assess the 2015-16 revenue adjustment amounts. The 2010 AU approval criteria and our assessment are set out below. Approval criteria The QCA will approve the revenue adjustment amounts if it is reasonably satisfied they are calculated in accordance with provisions set out in clause 3.2 of Part B, Schedule F of the 2010 AU. These provisions provide 2 Pacific National, Response to the Aurizon Network Submission 2015-16 Revenue Adjustment Amounts to QCA, December 2016 3

for Aurizon Network to annually submit the revenue adjustment amounts for the AT2-4 and ATs reference tariff for each system in the central Queensland coal network. The revenue adjustment amounts are the difference between revenues earned (total actual revenues) and revenues allowed (adjusted system allowable revenues) for the relevant reference tariff components, and calculated as per clause 3.2 of Part B, Schedule F (Table 2). Table 2 Components of adjusted system allowable revenues and total actual revenues for 2015-16 Adjusted system allowable revenues Approved 2015-16 system allowable revenues {May 2016 Extension DAAU) Actual maintenance cost escalation-adjustment to reflect the difference between actual and forecast maintenance costs index {MCI) Actual operating cost escalation-adjustment to reflect the difference between actual and forecast consumer price index {CPI) Costs of electric energy for traction, and cost of connecting Aurizon Network's electric traction system to electric transmission or distribution network-adjustment to reflect the difference between actual and forecast costs Total actual revenues Total revenues from ATz-4 and ATs reference tariffs, including cross-system train services revenues {including adjustment charges Annual take-or-pay entitlements Relinquishment fee entitlements Rebate adjustment-rebateable revenues within approved system allowable revenue less any rebates paid Maintenance costs of branch lines for new loading facilities {where applicable) Adjusted system allowable revenues The QCA found Aurizon Network's 2015-16 system allowable revenues to be consistent with transitional revenues contained in the May 2016 Extension DAAU approved by the QCA in June 2016. Also, the QCA noted that the approved 2015-16 system allowable revenues in the 2016 AU are the same as the transitional revenues. Aurizon Network's adjustments to the approved 2015-16 system allowable revenues accounted for: actual maintenance cost escalation-using the actual, compared to forecast MCI3 to escalate the QCA's approved maintenance cost allowance The QCA found Aurizon Network correctly calculated the actual MCI for 2015-16, with an annual percentage change of 1.1 per cent, compared to the forecast of 2.4 per cent used in the approved maintenance cost allowance. Actual MCI is a weighted index of consumables, fuel, labour, and accommodation sub-indices derived using publicly available indices.4 The QCA is satisfied that Aurizon Network has accurately calculated a decrease in the system allowable revenues of $2.3 million for non-electric revenues (AT2-4), and $0.1 million for electric revenues (ATs). actual operating cost escalation-using the actual, compared to forecast, CPI to escalate the QCA's approved operating cost allowance 3 Note: Aurizon Network used forecast MCI on Table 76 of the QCA's 2014 DAU final decision (Vol 4- MAR). 4 Publicly available indices are published by the Australian Bureau of Statistics and Australian Institute of Petroleum, as outlined in Table 77 of the QCA's 2014 DAU final decision (QCA, Aurizon Network 2014 DAU, final decision, vol. 4- Maximum Allowable Revenue, April 2016). Weights are as outlined in Table 79 of the QCA's 2014 DAU final decision. 4

The QCA found Aurizon Network used the actual CPI for 2015-16 of 1.5 per cent (confirmed from ABS All Groups CPI Brisbane data), compared to the annual forecast CPI of 2.5 per cent used in the approved operating cost allowance. The QCA is satisfied that Aurizon Network has accurately calculated the net decrease of $1.2 million for non-electric revenues (AT2-4). components relating to the recovery of Aurizon Network costs of connecting its electric traction system to a transmission or distribution network-adjustments to reflect the difference between the actual connection costs paid to Powerlink and the connection cost allowance included in the calculation ofthe ATs reference tariff component for 2015-16 The QCA is satisfied Aurizon Network has accurately calculated the net increase of $1.5 million to the system allowable revenue reflected in the ATs reference tariff component, related to connection costs for 2015-16. The QCA noted that Aurizon Network did not make any adjustments in relation to maintenance costs for new branch lines. The QCA noted that Aurizon Network did not make adjustments to reflect the difference between actual and forecast electric traction costs (EC) paid to Origin Energy Limited for the consumption of electric energy, which resulted in an over-recovery of $6.3 million in 2015-16. At the time of its 2015-16 revenue cap submission, Aurizon Network said this over-recovery was included in its proposed 2016-17 EC tariffs, as part of its amended 2014 DAU. The QCA is satisfied that the $6.3 million over-recovery is reflected in the approved 2016-17 EC tariffs in the 2016 AU, and Aurizon Network's proposal to not include this amount in the 2015-16 revenue adjustment amounts avoids double counting. Overall, these adjustments represent a total net reduction of $2 million to the approved 2015-16 system allowable revenues, from $957 million to $955 million (see Table 3). Total actual revenues Aurizon Network submitted that its total actual revenues for 2015-16 are based on revenues associated with reference train services (including cross-system train services), take-or-pay amounts, rebate adjustments and relinquishment and transfer fees received. Revenues from reference train services including cross-system train services-the QCA has confirmed that reference tariff revenues were accurately estimated based on : - the approved reference tariffs (in the May 2016 Extension DAAU) - actual railings (i.e. tonnages and origin/destination). In doing so, the QCA is satisfied that Aurizon Network's actual revenues have been calculated in accordance with the relevant provisions in the 2010 AU, including: - using accurate actual railing information-aurizon Network's railing information has been verified against billing and published informations - accurately estimating revenues from cross-system train services-revenues were estimated based on the use of appropriate reference tariffs, calculated in accordance with the cross-system traffic requirements in the 2010 AU. s From Aurizon Network's Quarterly Performance Reports and 2015-16 Annual Report 5

As noted above, Pacific National raised concerns on the accuracy of forecasting revenue and the need for improvements in forecasting. The QCA considers that while some degree of uncertainty will remain in forecasting revenues (including volumes), these issues would be considered further as part of the approval process for the next access undertaking. Take-or-pay amounts and rebate adjustments-take-or-pay arrangements related to non-electric systems were triggered in 2015-16 in Blackwater and Goonyella, with total take-or-pay revenues of $3 million collected by Aurizon Network. The QCA is satisfied that the take-or-pay revenues as well as rebates repaid to some customers were accurately estimated, on the basis that: - railings within a nominated month, for the purposes of annual and variable take-or-pay, were consistently treated, including being consistent with previous years' treatment, and that any cancellations (if any) due to a 'QR Cause' were appropriately attributed - the methodology in standard access agreements for various access undertakings (i.e. UTl, UT2 and UT3) has been applied correctly rebates for particular mines, which are payable irrespective of whether take-or-pay is triggered, have been determined separately and correctly. Pacific National remained concerned about rebate treatment in Aurizon Network's revenue adjustments. It viewed these as commercial arrangements, which are separate from the allowable revenues and regulatory process. Pacific National did not agree with the 'socialisation' of these rebate adjustments and believed that more equitable rebate adjustment methods should be considered in future commercial agreements and future access undertakings. While the QCA notes Pacific National's concern, the QCA is satisfied the rebate calculations in the 2015-16 revenue adjustment amounts are consistent with Part B of Schedule F, 2010 AU. Relinquishment and transfer fees-under the relevant access agreements (i.e. UTl, UT2 and UT3), access holders must pay Aurizon Network a relinquishment or transfer fee to relinquish or transfer access rights or initiate capacity transfers. These relinquishment and transfer fees, according to the 2010 AU, must be reflected as an equivalent amount payable in Aurizon Network's total actual revenues received. The QCA considers that Aurizon Network has correctly included transfer and relinquishment fees to total actual revenue in accordance with clause 3.2.3(b), Part B of Schedule F of the 2010 AU. Overall, the QCA is satisfied that Aurizon Network's total actual revenues of $975.5 million reflect total actual revenues collected (or deemed to have been collected) for 2015-16. 6

Final decision For the reasons outlined above and having regard to the relevant obligations contained in the 2010 AU, the QCA has approved Aurizon Network's proposed $20.6 million net return to access holders for 2015-16. Table 3 below shows a breakdown of this amount, by coal system and by non-electric and electric assets. Table 3 System allowable revenues against total actual revenues ($m, nominal) System System Adjustments System Reference Take-or- Rebate Total Revenue allowable (MCI + CPI, allowable tariff pay, adjustment actual cap revenue, connection revenue revenue transfer revenue adjustment Schedule charges (excluding fees, amount F adjustments) cross- crosssystem system revenue) revenue Non-electric {ATz-4) Blackwater 322.4 (1.4) 321.0 308.4 6.1 (1.1) 313.3 7.6 Goonyella 277.7 (1.4) 276.3 290.6 11.8 0.3 302.7 (26.4) Moura 40.1 (0.2) 40.0 37.0 3.1-40.1 (0.2) Newlands 28.1 (0.1) 28.0 31.0 - (0.4) 30.6 (2.6) GAP 116.6 (0.3) 116.3 118.0 - - 118.0 (1.8) Subtotal 784.9 {3.4} 781.S 78S.1 20.9 {1.3} 804.8 {23.3} Electric (ATs) Blackwater 99.5 (0.2) 99.3 88.1 6.4-94.5 4.8 Goonyella 72.7 1.6 74.3 74.9 1.2 0.2 76.3 (2.0) Subtotal 172.1 1.4 173.S 163.0 7.6 0.2 170.8 2.7 Total 957.0 (2.0} 955.0 948.1 28.5 (1.1} 975.5 {20.6} Note: Any discrepancies between totals and sums of components are due to rounding. 7