RICHMOND WASTE LISMORE PUBLIC POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

Similar documents
SOLO RESOURCE RECOVERY CENTRE - GATESHEAD PUBLIC POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

SOLO RESOURCE RECOVERY CENTRE - GATESHEAD PUBLIC POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

Charbon Public Notification Procedure

THE SHELL COMPANY OF AUSTRALIA (SCOA) POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN - NEWCASTLE TERMINAL

Pollution Incident Response Management Plan Clyde Terminal

FREEDOM FOODS GROUP LIMITED NSW Pollution Incident Response Management Procedure

Pollution Incident Response Management Plan Gore Bay Terminal

Pollution Incident Response Management Plan

Pollution Incident Reduction MANAGEMENT PLAN. Environment Protection Licence No Berth 104 Bulk Shipping (non-graincorp cargo) PUBLIC VERSION

Pollution Incident Response Management Plan

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) WALLACIA

Pollution Incident Response Management Plan. Kooragang 2, Port of Newcastle

Pollution Incident Response Management Plan. EPL 1697 Newcastle Bulk Terminal

Pollution Incident Response Management Plan (PIRMP) Version 1 April 2018

Pollution Incident Response Management Plan

EnergyAustralia NSW. Mount Piper and Wallerawang Power Stations. Pollution Incident Response Management Plan (PIRMP) EXTERNAL Version OCTOBER 2016

Pollution Incident Response Management

Direct Group Industries Pty Ltd 3B Williamson Road Ingleburn EP # Emergency & Pollution Incident Response Management Plan September 2016

Pollution Incident Response Management Plan

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) ST MARYS

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

Emergency Preparedness and Response Revision Date: 12/09/18. Notification of Pollution Incident Procedure

NEWMAN QUARRYING PTY.LTD ACN PO BOX 22, WOODBURN 2472 PH (02) FAX (02)

Kemps Creek Central Quarry Pollution Incident Response Management Plan (PIRMP) March 2017

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

Pollution Incident Response

PEABODY ENERGY POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

ERARING POWER STATION ROCKY POINT ROAD, ERARING NSW. (EPLs 1429 & 4297)

MGO Pollution Incident Response Management Plan

MGO Pollution Incident Response Management Plan

Risk management procedures

Marine Protection Rules Part 143 Shipboard Marine Pollution Emergency Plans for Noxious Liquid Substances

Contractor Guidelines

GASCADE Gastransport GmbH HSE-GUIDELINE-CONTRACTORS. Version 5 Status: 15th May 2017

Site-Specific Health and Safety Agreement

Spill Response What will you do? Jim Santino, May 12, 2011

CLAIM SUMMARY / DETERMINATION

Asbestos Management. Date of Approval: Date for Next Scheduled Review: Review Body: Equality Impact Assessment Complete: Policy Published on Web:

Job Safety Analysis Preparation And Risk Assessment

TO ALL MEMBERS AND BROKERS. 29 July Dear Sirs

Petroleum and Geothermal Energy Resources (Environment) Regulations 2012

ENVIRONMENTAL MANAGEMENT AND CO-ORDINATION ACT, CAP 387 LEGAL NOTICE NO.

BUNKERING LICENCE. Name of Licensed Operator:. Registered physical address from where principal business is carried on: ...

CLAIM SUMMARY / DETERMINATION

Auckland Transport HS03-01 Risk and Hazard Management

Title: Environmental, Health and Safety Revision No.: 4 Effective Date: January 1, 2017

REQUIREMENTS FOR NOTIFICATION AND REPORTING OF ACCIDENTS AND NEAR MISSES TO PREMUDA (FOR THE OWNERS OF TC TANKER VESSELS)

Environmental Impairment Liability

Contractor Management Procedure

Info Sheet for Contractor Personnel

Pipeline Regulatory Issues

Combined General Liability Insurance

Industrial Accident Risk Assessment Procedures and Risk Reduction Measures

SUPPLY OF PEST CONTROL SERVICES

APPROPRIATION MINISTER(S): Minister for Climate Change (M12), Minister for the Environment (M29)

CLAIM SUMMARY / DETERMINATION FORM

Hazard Identification, Risk Assessment and Control Procedure

PROTECTION AND PRESERVATION OF THE MARINE ENVIRONMENT

DIRECTIVE 2013/30/EU OF THE EUROPEAN PARLIAMENT AND OF THE COUNCIL

EMERGENCY SITUATION RISK ASSESSMENT

Apron Services Licence

Risk Assessment Procedure

CHAPTER 31 - HAZARDOUS SUBSTANCES ORDINANCE OF DUBUQUE COUNTY, IOWA. Adopted October 26, 1987 Amended October 19, Part 1 Introduction...

Environmental Management Policy

Accident and Incident Reporting Policy and Procedure (including Notifiable Incidents Procedure)

A Safety, Environmental and Labour rights Guide for Suppliers to British Airways

SECURITY MANAGEMENT Manage critical incidents as a security practitioner

Determination process for a major hazard facility

The University of North Texas at Dallas Policy Manual Chapter

Mine Health and Safety Regulation 2007

Latest Trends in Environmental Liability B. DARRELL CHILD INTERMOUNTAIN AWWA EXECUTIVE VICE PRESIDENT SEPTEMBER 15, 2016

Application for Filming and/or Photography Media

CONTRACTOR CONTROL DISCIPLINARY PROCESS

Environmental. A report from the IUA s Non-Marine Environmental Committee in association with Berwin Leighton Paisner LLP

The licensee shall take the actions specified to close out the non-compliances and observations raised in this Site Visit Report.

Environmental Liabilities for the Power Industry

Cowal Gold Project Addendum to the Transport of Hazardous Materials Study

Combined Liability Proposal Form

DISASTER MANAGEMENT MEASURES

JOSOP Joint Operations Standard Operating Procedure Environmental Impact Assessments

Preventing Skyrocketing Environmental Liabilities

CLAIM SUMMARY / DETERMINATION FORM

This policy aims to ensure the health, safety and welfare of contractors working on UEL premises and those affected by their work.

CLAIM SUMMARY /DETERMINATION Tahoe Keys Property Owners Association CLAIMANT TYPE Removal Costs

REMEDYING ENVIRONMENTAL DAMAGE FROM WRECKS THE LIABILITY OF OWNERS AND SALVORS. Prof. emeritus Peter Wetterstein

Health & Safety at Work Act 1974 HEALTH & SAFETY POLICY STATEMENT

Proposal Form. Tradesmen. Commercial Division

Content Copy Of Original

CREATIVE SPACE GALLERY Terms and Conditions of Hire

Name of Customer: Name of Contact Person: Address of Collateral:

THIS LICENCE IS ISSUED TO:/CET LICENCE EST DONNE A: MILLER ENVIRONMENTAL CORPORATION:

Health & Safety Policy

EUROPEAN UNION. Brussels, 31 May 2013 (OR. en) 2011/0309 (COD) PE-CONS 8/13 ENER 76 ENV 184 MARE 7 COMAR 12 PROCIV 36 CODEC 522 OC 127

Generation Licence Compliance

For inspection purposes only.

PLEASE NOTE. For more information concerning the history of these regulations, please see the Table of Regulations.

Questions and Answers Environmental Liability Directive

LAWS AND REGULATIONS

RISK AND OPPORTUNITY ASSESSMENT GUIDE RISK CRITERIA

Chapter Finance/ Administration

Transcription:

RICHMOND WASTE LISMORE PUBLIC POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN

CONTENTS 1.0 OVERVIEW... 2 2.0 DEFINITIONS... 2 3.0 SITE... 3 4.0 INCIDENT RESPONSE PROCEDURE... 4 5.0 INCIDENT RESPONSE... 4 6.0 NOTIFICATION PROTOCOLS... 5 7.0 COMMUNITY NOTIFICATION STRATEGY... 5 REVISION HISTORY Version Revision date Authorised by Comments 1.0 October 2013 QSE Manager Document created 2.0 October 2014 QSE Manager Updated IMS format 3.0 October 2015 QSE Manager Update for annual test 3.0 October 2016 Lead QSE Coordinator Reviewed for annual test 3.1 April 2017 Lead QSE Coordinator Update for annual test 4.0 April 2018 QSE Manager Update for annual test Page 1

1.0 OVERVIEW This Pollution Incident Response Management Plan (PIRMP) has been developed in accordance with the requirements of the Protection of the Environment Operations (General) Regulation 2009. Under this regulation all holders of environment protection licences must prepare a PIRMP. The objectives of the plan are to ensure comprehensive and timely communication about a pollution incident to all relevant parties, minimise and control the risk of a pollution incident occurring and ensure correct implementation by staff. As per regulations a copy of the full PIRMP is available on the activity site and to all persons responsible for the implementation of the plan. A public version of the plan outlining procedures for contacting relevant authorities and community notification guidelines is accessible via the company website. The plan is routinely tested every 12 months to ensure relevance, accuracy and compliance with applicable legislation and standards. A review of the plan will be undertaken within 1 month of a pollution incident occurring to ensure the plan is capable of being implemented in a workable and effective manner. This plan forms part of the Site Environment Management Plan which makes up part of the Solo Integrated Management System. Environmental incident reporting processes are designed to ensure that all relevant team members are trained in the correct reporting protocol and under what circumstances. 2.0 DEFINITIONS Pollution Incident - means an incident or set of circumstances during or as a consequence of which there is a likely to be a leak, spill or other escape or deposit of a substance, as a result of which pollution has occurred, is occurring or is likely to occur. It includes an incident or set of circumstances in which a substance has been placed or disposed of on a premise, but it does not include an incident of circumstances involving the emission of any noise. Material Harm to the Environment (a) harm to the environment is material, if: (i) It involves actual or potential harm to the health or safety of human beings or to ecosystems that is not trivial; or (ii) It results in actual or potential loss or property damage of an amount, or amounts in aggregate, exceeding $10,000 (or such other amount as is prescribed by the regulations), and (b) Loss includes the reasonable costs and expenses that would be incurred in taking all reasonable and practicable measures to prevent, mitigate or make good harm to the environment. Page 2

(2) For the purpose of this Part, it does not matter that harm to the environment is caused only in the premises where the pollution incident occurs. 3.0 SITE This PIRMP has been prepared for the below EPA licenced site. The site is comprised of the following: Administration Office Yard and Wash Bay Maintenance Workshop Mechanical Workshop Oily Water Treatment Plant Cardboard and Plastic transfer station (including bailer) Page 3

4.0 INCIDENT RESPONSE PROCEDURE 5.0 INCIDENT RESPONSE Should an environmental incident occur where harm to the environment has, or is likely to occur the following steps are to be taken: Assess severity of incident If appropriate take steps to prevent further discharge, isolate and contain spill using available equipment and PPE; Minor incidents not requiring notification will be attended under spill procedure IMS-AIIR-D-0010 Spills Oil or Other Substances If required enact Notification Protocols, advise relevant authorities of the incident and what steps are being taken (record details of time of call and who was told); Record the date, time and location of the incident; Record what chemical or pollutant is involved (if known) and estimated quantity; Record details of the receiving environment; Records any injuries to team members or members of the public as a result of the incident; Do not leave the incident location until advised by supervisor / state agency official. Page 4

6.0 NOTIFICATION PROTOCOLS External: Agency Fire and Rescue NSW 000* Contact (*if the incident presents an immediate threat to human health or property) 1300 729 579 EPA Environment Line 131 555 Ministry of Health via the local Public Health Unit 1300 066 055 SafeWork 13 10 50 Lismore City Council 1300 878 387 7.0 COMMUNITY NOTIFICATION STRATEGY Decisions to notify neighbours and the local community will be made in consultation with regulatory authorities based on an initial assessment of the pollution incident. Advice provided to the community will depend on the type and extent of the pollution incident and guidance from the regulatory authorities. Notifications may include (as an example) advice to close doors and windows to avoid odour etc. The appropriate method for communication will be determined by the nature of the event or as directed by the relevant agency. Methods may include door knocking by company representative (or emergency personnel), telephone contact or written correspondence. Affected community stakeholders will be regularly updated throughout the course of the pollution incident. Page 5