INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Similar documents
Financing Agreement OFFICIM. DOCUMENTS1 CREDIT NUMBER 5283-IN. (Low Income Housing Finance Project) between INDIA. and

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Financing Agreement CREDIT NUMBER 5349-IN. (Bihar Integrated Social Protection Strengthening Project) between INDIA. and

OFFICIAL DOCUMENTS. Loan Agreement. Public Disclosure Authorized LOAN NUMBER 8746-IN. Public Disclosure Authorized

OFFICIAL DOCUMENTS. Loan Agreement LOAN NUMBER 8734-GD. (OECS Regional Tourism Competitiveness Project) between GRENADA

Financing Agreement. (Additional Financing for Village Communities Support Program (Phase I)) between REPUBLIC OF GUINEA. and

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

OFFICIAL DOCUMENTS. H. E. Jean Gustave Sanon Minister of Economy and Finance Ministry of Economy and Finance Ouagadougou Burkina Faso.

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Financing Agreement. (Strengthening Regional Cooperation for Wildlife Protection in Asia Project) between NEPAL. and

PEOPLE S REPUBLIC OF CHINA

Loan Agreement OFFIAL DOCUMENTS LOAN NUMBER 8229-AM. (Lifeline Road Network Improvement Project) between REPUBLIC OF ARMENIA. and

Financing Agreement. (Energy Community of South East Europe APL 3 Montenegro Project) between THE REPUBLIC OF MONTENEGRO. and

ARAB REPUBLIC OF EGYPT

Loan Agreement. (Andhra Pradesh Economic Reform Program) between INDIA. and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Financing Agreement. (Environmental and Social Capacity Building for the Energy Sector Project) between THE REPUBLIC OF CAMEROON.

OFFICIAL DOCUMENTS ZW4

OFFICIAL DOCt HMENTS

Loan Agreement. (Eastern Indonesia Region Transport Project) between REPUBLIC OF INDONESIA. and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Loan Agreement OFFICIAL 90CUMENTS1. Public Disclosure Authorized LOAN NUMBER 8263-GE. Public Disclosure Authorized

(Real Estate Cadastre and Registration Project Additional Financing) between. FORMER YUGOSLAV REPUBLIC OF MACEDONIA (the Borrower) and

Development Credit Agreement

Project Agreement. Public Disclosure Authorized OFFICIAL DOCUMENTS LOAN NUMBER 7792-IN. Public Disclosure Authorized

Financing Agreement. (Uganda Public Service Performance Enhancement Project) between THE REPUBLIC OF UGANDA. and

Loan Agreement. Public Disclosure Authorized LOAN NUMBER 8599-GE. Public Disclosure Authorized. (Secondary Road Asset Management Project)

Financing Agreement CONFORMED COPY IDA CREDIT NUMBER 4825-KG IDA GRANT NUMBER H618-KG. (Emergency Recovery Project) between KYRGYZ REPUBLIC.

OFFICIAL DOCUMENTS. Financing Agreement. Public Disclosure Authorized CREDIT NUMBER PK. Public Disclosure Authorized

Financing Agreement,.

Loan Agreement. (Indonesia Infrastructure Finance Facility Project) between REPUBLIC OF INDONESIA. and

OFFICIAL DOCUMENTS. Financing Agreement. Public Disclosure Authorized CREDIT NUMBER 6343-RW. Public Disclosure Authorized. (Housing Finance Project)

Financing Agreement. (Additional Financing for Health Sector Development Project) between REPUBLIC OF DJIBOUTI. and

Financing Agreement. between. Dated, 2014 CREDIT NUMBER 5313-IN. (Uttarakhand Disaster Recovery Project) INDIA. and

Loan Agreement DMIUMTS OFFICIAL LOAN NUMBER 8131-CN PEOPLE'S REPUBLIC OF CHINA INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Financing Agreement CONFORMED COPY GRANT NUMBER H732 -AF. (Financial Sector Rapid Response Project) between ISLAMIC REPUBLIC OF AFGHANISTAN.

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Development Financing Agreement

Loan Agreement. (Alma Electricity Transmission Project) between JOINT STOCK COMPANY KAZAKHSTAN ELECTRICITY GRID OPERATING COMPANY.

Project Agreement CONFORMED COPY LOAN NUMBER CHA. (Hubei Shiman Highway Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Loan Agreement. (South East Europe and Caucasus Catastrophe Risk Insurance Facility Project) between REPUBLIC OF SERBIA. and

Tamil Nadu Project Agreement

OFFICIAL DOCUMENTS. Loan Agreement

Loan Agreement. (Institutional Development and Agriculture Strengthening Project) between MONTENEGRO. and

Project Agreement. (West Beka a Emergency Water Supply Project) between

Financing Agreement OFFICIAL OCUMENTS. Public Disclosure Authorized CREDIT NUMBER 5152-UZ. Public Disclosure Authorized

Financing Agreement CONFORMED COPY CREDIT NUMBER 4168-NI. (Rural Telecommunications Project) between REPUBLIC OF NICARAGUA. and

Loan Agreement (Real Estate Management Project)

Loan Agreement. (Shandong Ecological Afforestation Project) between PEOPLE S REPUBLIC OF CHINA. and

Project Agreement OFFICIAL DOCUMENTS LOAN NUMBER 8391-UA. Second Urban Infrastructure Project (Urban Infrastructure Project - 2) between

Republic of Senegal: Advance Agreement for the Preparation of the Proposed Casamance Development Pole Project Project Preparation Advance No.

Loan Agreement. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized

Loan Agreement. (Additional Financing for the Rural Poverty Reduction Project - Rio Grande do Norte) between

OFFICIAL. Letter No. CD-I 85/WB/INIS/XI/2017 November 7, 2017

Loan Agreement. (Real Property Registration and Cadastre Project) between REPUBLIC OF CROATIA. and

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

RS Project Agreement. (Second Local Initiatives (Microfinance) Project) between INTERNATIONAL DEVELOPMENT ASSOCIATION. and REPUBLIKA SRPSKA

Project Agreement. (Zanzibar Basic Education Improvement Project) between INTERNATIONAL DEVELOPMENT ASSOCIATION. and

Loan Agreement OFFICIAL DOCUMENTS LOAN NUMBER 8494-GE. (Third Regional Development Project) between GEORGIA. and

Loan Agreement. (Additional Financing for Laguna de Bay Institutional Strengthening and Community Participation Project) between

REPUBLIC OF INDONESIA

Financing Agreement CONFORMED COPY CREDIT NUMBER IQ. (Dokan and Derbandikhan Emergency Hydropower Project) between REPUBLIC OF IRAQ.

Financing Agreement CREDIT NUMBER VN. (Ho Chi Minh City Green Transport Development Project) between SOCIALIST REPUBLIC OF VIETNAM.

Financing Agreement CREDIT NUMBER 5404-PG CREDIT NUMBER 4931-PG INDEPENDENT STATE OF PAPUA NEW GUINEA INTERNATIONAL DEVELOPMENT ASSOCIATION

UNITED MEXICAN STATES

Ebola Recovery and Reconstruction Trust Fund Grant Agreement

MULTI-DONOR TRUST FUND GRANT AGREEMENT

(Health Sector Strengthening and Modernization Project) between REPUBLIC OF COSTA RICA. and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

cocumeasn Loan Agreement OFFICIAL LOAN NUMBER 8095-BR

OFFMCAL. olrakdocuments,

Development Credit Agreement. (Andhra Pradesh District Poverty Initiatives Project) between INDIA. and INTERNATIONAL DEVELOPMENT ASSOCIATION

(Taunsa Barrage Emergency Rehabilitation and Modernization Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT.

Loan Agreement. (Third Labor Reform and Social Development Policy Loan) between REPUBLIC OF COLOMBIA. and

REPUBLIC OF INDONESIA

Loan Agreement. (Power System Development Project-III) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT. and

(Punjab Barrages Improvement Phase-II Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT. and PROVINCE OF PUNJAB

OFFOAL.? DOCUMENTS. Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Project Agreement CONFORMED COPY CREDIT NUMBER 4191-TA. (Financial Sector Support Project) between INTERNATIONAL DEVELOPMENT ASSOCIATION.

Loan Agreement. (Low-Income Sanitation Technical Assistance Project) between FEDERATIVE REPUBLIC OF BRAZIL. and

CONFORMED COPY LOAN NUMBER 4100 IND LOAN NUNMBER 4100 IND

Loan Agreement. (Teresina Enhancing Municipal Governance and Quality of Life Project Programa Lagoas do Norte) between. and

Haiti Education for All Multi-donor Trust Fund Grant Agreement

Development Credit Agreement. (Basic Health Project) between BOSNIA AND HERZEGOVINA. and INTERNATIONAL DEVELOPMENT ASSOCIATION

IDBI Loan Agreement. Public Disclosure Authorized LOAN NUMBER 3779 IN. Public Disclosure Authorized. (Industrial Pollution Prevention Project)

(Java-Bali Power Sector Restructuring and Strengthening Project) between REPUBLIC OF INDONESIA. and

Development Credit Agreement. (Provincial Health Project) between REPUBLIC OF INDONESIA. and INTERNATIONAL DEVELOPMENT ASSOCIATION

Financing Agreement CREDIT NUMBER 5816-ET. (Transport Systems Improvement Project) between FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA.

Re: Grant for Institution Building for the Hungarian Office of Roma Affairs IDF Grant No. TF052240

Global Environment Facility Grant Agreement

fofficial Loan Agreement DOCUMENTS Public Disclosure Authorized LOAN NUMBER 8357-LK Public Disclosure Authorized

IDOCUMENTS. Loan Agreement OFFICIAL LOAN NUMBER 8354-CO. (Access with Quality to Higher Education Project-ACCES II-SOP Phase 2) between

OFFICIAL DOCUMENTS. Financing Agreement. Public Disclosure Authorized CREDIT NUMBER 6126-MD. Public Disclosure Authorized

Development Credit Agreement

Development Credit Agreement

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized CONFORMED COPY

Loan Agreement. (Bahia Integrated State Highway Management Project Programa de Restauração e Manutenção de Rodovias - PREMAR) between STATE OF BAHIA

OFFICIAL DOCUMENTS. Project Agreement LOAN NUMBER 8655-YF. (Additional Financing for Corridor X Highway Project) between

Financing Agreement OFFICIAL DOCUMENTS 1. (Amending and Restating the Development Credit Agreement) Public Disclosure Authorized

Development Credit Agreement

Loan Agreement. Public Disclosure Authorized LOAN NUMBER 3771 BUL. Public Disclosure Authorized. (Agricultural Development Project)

DOCUMENTS rnel or# PN FDate Log# OFFICIAL w oiros. Public Disclosure Authorized

Transcription:

Public Disclosure Authorized CONFORMED COPY LOAN NUMBER 4860-IN Public Disclosure Authorized Loan Agreement (Himachal Pradesh State Roads Project) between Public Disclosure Authorized INDIA and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT Public Disclosure Authorized Dated August 7, 2007

LOAN AGREEMENT AGREEMENT dated August 7, 2007, between INDIA, acting by its President ( Borrower ) and INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT ( Bank ). The Borrower and the Bank hereby agree as follows: ARTICLE I - GENERAL CONDITIONS; DEFINITIONS 1.01. The General Conditions (as defined in the Appendix to this Agreement) constitute an integral part of this Agreement. 1.02. Unless the context requires otherwise, the capitalized terms used in the Loan Agreement have the meanings ascribed to them in the General Conditions or in the Appendix to this Agreement. ARTICLE II - LOAN 2.01. The Bank agrees to lend to the Borrower, on the terms and conditions set forth or referred to in this Agreement, the amount of two hundred twenty million Dollars ($220,000,000) ( Loan ), to assist in financing the project described in Schedule 1 to this Agreement ( Project ). 2.02. The Borrower may withdraw the proceeds of the Loan in accordance with Section IV of Schedule 2 to this Agreement. 2.03. The Commitment Charge payable by the Borrower shall be equal to three-fourths of one percent (3/4 of 1%) per annum on the Unwithdrawn Loan Balance, subject to any waiver of a portion of such charge as may be determined by the Bank from time to time. 2.04. The Front-end Fee payable by the Borrower shall be equal to one percent (1.0%) of the Loan amount, subject to any waiver of a portion of such fee as may be determined by the Bank from time to time. 2.05. The interest payable by the Borrower for each Interest Period shall be at a rate equal to LIBOR for the Loan Currency plus the Variable Spread, subject to any waiver of a portion of such interest as may be determined by the Bank from time to time. 2.06. The Payment Dates are January 15 and July 15 in each year. 2.07. The principal amount of the Loan shall be repaid in accordance with the amortization schedule set forth in Schedule 3 to this Agreement.

-2- ARTICLE III - PROJECT 3.01. The Borrower declares its commitment to the objectives of the Project. To this end, the Borrower shall cause the Project to be carried out by the Project Implementing Entity in accordance with the provisions of Article V of the General Conditions and the Project Agreement. 3.02. Without limitation upon the provisions of Section 3.01 of this Agreement, and except as the Borrower and the Bank shall otherwise agree, the Borrower shall ensure that the Project is carried out in accordance with the provisions of Schedule 2 to this Agreement. ARTICLE IV EFFECTIVENESS 4.01. The Effectiveness Deadline is the date ninety (90) days after the date of this Agreement. ARTICLE V REPRESENTATIVE; ADDRESSES 5.01. The Borrower s Representative is any Secretary, Additional Secretary, Joint Secretary, Director, Deputy Secretary or Under Secretary of the Department of Economic Affairs in the Ministry of Finance of the Borrower. 5.02. The Borrower s Address is: Department of Economic Affairs Ministry of Finance New Delhi 110 001 India Cable address: Telex: Facsimile: ECOFAIRS 953-31-66175 91-11-23093422 New Delhi FINE IN 5.03. The Bank s Address is: International Bank for Reconstruction and Development 1818 H Street, N.W. Washington, D.C. 20433 United States of America Cable address: Telex: Facsimile: INTBAFRAD 248423(MCI) or 1-202-477-6391

-3- Washington, D.C. 64145(MCI)

-4- AGREED at New Delhi, India, as of the day and year first above written. INDIA By /s/ Madhusudan Prasad Authorized Representative INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT By /s/ Isabel M. Guerrero Country Director India

-5- SCHEDULE 1 Project Description The objective of the Project is to reduce transport costs and to improve traffic flows on priority segments of the Core Road Network of the State of Himachal Pradesh. The Project consists of the following components: 1. Core Road Network Improvement Upgrading of roads in the Core Road Network, including widening of formation, realignment, new structures and pavement strengthening of about 450 km of roads, to be completed in two phases: (i) Phase I Roads, comprising about 50 percent of total roads included in the Project for upgrading; and (ii) Phase II Roads, comprising the remaining roads included in the Project for upgrading; and implementation of ancillary social, resettlement and environmental measures, including the agreed arrangements set forth in the Component 1 EMPs. 2. Core Road Network Maintenance and Management (a) Periodic maintenance and minor rehabilitation of about 2000 km of the Core Road Network, in accordance with the agreed environmental measures set forth in the Component 2 EMP; (b) piloting performance based maintenance contracts; (c) accident black spot improvements; (d) pre-investment studies for road network improvement and maintenance; and (e) capacity enhancement in road maintenance management, including financing, institutional strengthening, road safety, collection, management and dissemination of data.

-6- SCHEDULE 2 Project Execution Section I. Institutional and Other Arrangements 1. To facilitate the carrying out of the Project, the Borrower shall make the proceeds of the Loan available to the Project Implementing Entity in accordance with Borrower s standard arrangements for developmental assistance to the States of India. 2. The Borrower shall cause the Project Implementing Entity to take all necessary steps to ensure that all Project activities are implemented in accordance with the Schedule to the Project Agreement. 3. The Borrower shall protect the interests of the Borrower and the Bank to accomplish the purposes of the Loan. Section II. Project Monitoring, Reporting, Evaluation A. Project Reports The Borrower, together with the Project Implementing Entity, shall monitor and evaluate the progress of the Project and prepare Project Reports in accordance with the provisions of Section 5.08 of the General Conditions and on the basis of indicators agreed with the Bank. Each such report shall cover the period of each Fiscal Year quarter, and shall be furnished to the Bank not later than forty five (45) days after the end of the period covered by such report. B. Financial Management, Financial Reports and Audits 1. The Borrower shall maintain or cause to be maintained a financial management system in accordance with the provisions of Section 5.09(a) of the General Conditions. 2. Without limitation on the provisions of Part A of this Section, the Borrower shall, or shall cause the Project Implementing Entity to, prepare and furnish to the Bank as part of the Project Report not later than forty five (45) days after the end of each Fiscal Year quarter, interim un-audited financial reports for the Project covering the quarter, in form and substance satisfactory to the Bank. 3. The Borrower shall have its Financial Statements audited in accordance with the provisions of Section 5.09(b) of the General Conditions. Each audit of the Financial Statements shall cover the period of one (1) fiscal year of the Borrower, commencing with the fiscal year in which the first withdrawal under the Project

-7- was made. The audited Financial Statements for each such period shall be furnished to the Bank not later than six (6) months after the end of such period. Section III. Procurement All goods, works and services required for the Project and to be financed out of the proceeds of the Loan shall be procured in accordance with the provisions of Section III of the Schedule to the Project Agreement. Section IV. Withdrawal of Loan Proceeds A. General 1. The Borrower may withdraw the proceeds of the Loan in accordance with the provisions of this Section and such additional instructions as the Bank may specify by notice to the Borrower, to finance Eligible Expenditures as set forth in the table in paragraph 2 below. 2. The following table specifies the categories of Eligible Expenditures that may be financed out of the proceeds of the Loan ( Category ), the allocations of the amounts of the Loan to each Category, and the percentage of expenditures to be financed for Eligible Expenditures in each Category: Category Amount of the Loan Allocated (Expressed in Dollars) Percentage of Expenditures to be Financed (1) Civil works under Component 1 of the Project, goods, consultants services, Training, and R&R Assistance (2) Civil works under Component 2 of the Project (3) Refund of the Project Preparation Advance 207,260,000 90% 11,190,000 20% 1,550,000 Amount payable pursuant to Section 2.07(a) of the General Conditions TOTAL 220,000,000

-8- B. Withdrawal Conditions; Withdrawal Period 1. Notwithstanding the provisions of Part A of this Section no withdrawal shall be made for payments made prior to the date of this Agreement, except that withdrawals up to an aggregate amount not to exceed $5,000,000 equivalent may be made for payments prior to this date but on or after January 1, 2007, for Eligible Expenditures under Categories (1) and (2). 2. The Closing Date is June 30, 2013.

-9- SCHEDULE 3 Amortization Schedule Principal Payment Date Principal Amount of the Loan Payable (Expressed in Dollars) January 15, 2013 4,715,000 July 15, 2013 4,850,000 January 15, 2014 4,990,000 July 15, 2014 5,135,000 January 15, 2015 5,280,000 July 15, 2015 5,435,000 January 15, 2016 5,590,000 July 15, 2016 5,750,000 January 15, 2017 5,915,000 July 15, 2017 6,090,000 January 15, 2018 6,265,000 July 15, 2018 6,445,000 January 15, 2019 6,630,000 July 15, 2019 6,820,000 January 15, 2020 7,015,000 July 15, 2020 7,220,000 January 15, 2021 7,425,000 July 15, 2021 7,640,000 January 15, 2022 7,860,000 July 15, 2022 8,085,000 January 15, 2023 8,320,000 July 15, 2023 8,560,000 January 15, 2024 8,805,000 July 15, 2024 9,060,000 January 15, 2025 9,320,000 July 15, 2025 9,590,000 January 15, 2026 9,865,000 July 15, 2026 10,150,000 January 15, 2027 10,440,000 July 15, 2027 10,735,000 APPENDIX The figures in this column represent the amount Dollars to be repaid, except as provided in Section 3.05 of the General Conditions.

-10- Definitions 1. Category means a category set forth in the table in Section IV of Schedule 2 to this Agreement. 2. Component 1 EMPs means the corridor specific environmental management plans for Component 1 of the Project related to Phase I Roads adopted by the HPRIDC on March 29, 2007, and the environmental management plan related to Phase II Roads to be adopted by the HPRIDC, satisfactory to the Bank, describing the environmental management, mitigation, monitoring and institutional measures to be undertaken by the HPRIDC during the Project, as such plans may be revised from time to time with the prior approval of the Bank. 3. Component 2 EMP means the environmental management plan for Component 2 of the Project, adopted by the Government of the State of Himachal Pradesh and the HPRIDC in September, 2006, satisfactory to the Bank, describing the general environmental management, mitigation and monitoring measures to be undertaken for periodic maintenance works by the HPRIDC during the Project, as such plan may be revised from time to time with the prior approval of the Bank. 4. Consultant Guidelines means the Guidelines: Selection and Employment of Consultants by World Bank Borrowers published by the Bank in May 2004. 5. Core Road Network means the State of Himachal Pradesh state highways and major district roads that have been designated as such by the Government of the State of Himachal Pradesh notification, dated July 19, 2005, as the same may be amended from time to time. 6. Financial Management Manual means the financial management manual adopted by the HPRIDC on April 2, 2007, satisfactory to the Bank, setting forth the overall Project financial management arrangements in respect of Project flow of funds, accounting policies and procedures, chart of accounts, financial and accounting procedures, books of accounts, financial reporting, and internal controls, as the same may be revised from time to time with the prior approval of the Bank. 7. Fiscal Year means the Borrower s and Project Implementing Entity s fiscal year, beginning on April 1 of any calendar year and ending on March 31 of the following calendar year. 8. General Conditions means the International Bank for Reconstruction and Development General Conditions for Loans, dated July 1, 2005.

-11-9. HPRIDC means the Himachal Pradesh Road and Other Infrastructure Development Corporation Limited, a State of Himachal Pradesh Government Company established under the Companies Act of 1956 (Certificate of Incorporation No. 06-22670, 1999). 10. Operations Manual means the manual approved by the State of Himachal Pradesh Government and adopted by the HPRIDC, dated April 12, 2007, satisfactory to the Bank, setting out the terms, conditions, and procedures for Project implementation, including the administrative, institutional, environmental, resettlement, land acquisition, and procurement requirements, as such manual may be revised from time to time with the prior approval of the Bank. 11. Phase I Roads and Phase II Roads mean the roads referred to under Component 1 of Schedule 1 to this Agreement. 12. Procurement Guidelines means the Guidelines for Procurement under IBRD Loans and IDA Credits published by the Bank in May 2004. 13. Procurement Plan means the Borrower s procurement plan for the Project, dated March 3 and 7, 2007, and referred to in paragraph 1.16 of the Procurement Guidelines and paragraph 1.24 of the Consultant Guidelines, as such plan shall be updated from time to time in accordance with the provisions of said paragraphs. 14. Project Implementing Entity means the State of Himachal Pradesh. 15. Project Preparation Advance means the advance referred to in Section 2.07 (a) of the General Conditions, granted by the Bank to the Borrower pursuant to the letter agreement signed on behalf of the Bank on February 1, 2006, and on behalf of the Borrower on February 9, 2006. 16. RAP means the Resettlement Action Plan for Phase I Roads adopted by the HPRIDC on February 22, 2006, and the Resettlement Action Plan for Phase II Roads to be prepared and adopted by the HPRIDC, as such plans may be revised from time to time with the prior approval of the Bank. 17. R&R Assistance means resettlement and rehabilitation assistance provided to eligible recipients in accordance with the terms and conditions set forth in the R&R Policy and the RAP. 18. R&R Policy means Resettlement and Rehabilitation Policy, adopted by the State of Himachal Pradesh Government on February 3, 2006, amended on June 3, 2006, and setting forth the policies and procedures addressing adverse temporary or permanent social impacts resulting, or likely to result from, the

-12- carrying out of the Project, as the same may be revised from time to time with the prior approval of the Bank. 19. Training means reasonable and necessary costs of training related to Project implementation, including the fees of educational or other institutions that provide training, costs related to attendance or organization of conferences, seminars and workshops, and the trainees cost of travel, boarding, lodging and per diem allowances.