Financial Incentives for Deploying Carbon Capture and Storage: Tom Wilson Sr. Program Manager CSLF Financing Roundtable 2010 April 6, 2010

Similar documents
KEY FINDINGS AND RESOURCE STRATEGY

New Jersey Reference Case and Policy Scenario Results

ISO Transmission Planning Process. Supplemental Sensitivity Analysis: Risks of early economic retirement of gas fleet

For the Efficiency Maine Trust October 15, 2009 Eric Belliveau, Optimal Energy Inc.

PJM & MISO Assumptions and Criteria for Testing of New Resources

2005 Integrated Electricity Plan. Provincial IEP Committee Meeting #2 Economic Analysis February 22/23, 2005

Bringing Clean Energy Projects To Reality: Presentation to the Global Workshop on Clean Energy Development

9. Integrated Resource Plan and Risk Analysis

The Economics and Financing of Distributed Generation Investment. Budapest, Hungary November 17, 2016

Contract length analysis for Feed-in Tariff with Contracts for Difference. Summary of onshore and offshore wind analysis

Decarbonizing the U.S. Power Sector Clean Energy Finance

MTEP16 Futures Development Workshop 1/15/15

Projected Impact of Changing Conditions on the Power Sector

Accelerating CCS development: a project funding mechanism, for demonstration only, built into ETS

H.R American Clean Energy and Security Act of 2009

What next for UK auctions of renewable Contracts for Difference?

APPENDIX B: WHOLESALE AND RETAIL PRICE FORECAST

Green Power for a Nation in the Red

Carbon Markets and Mexico Key Issues for Market Design

EPA s Clean Power Plan Summary of IPM Modeling Results

Compensation Rules for Climate Policy in the Electricity Sector

Generation Retirement Scenario Special Assessment Update

BC Hydro Provincial Integrated Electricity Planning Committee Meeting 5 (July 12-14, 2005)

Proposed CATR + MACT. Prepared for: American Coalition for Clean Coal Electricity. Draft May 2011

Solving India s Renewable Energy Financing Challenge: Which Federal Policies can be Most Effective?

Fact sheet: Financing climate change action Investment and financial flows for a strengthened response to climate change

NYISO Carbon Pricing

MJB&A Clean Power Plan Compliance Tool. v 1.0. User Guide M A Y 1 2, (978) /

Sanford C. Bernstein Strategic Decisions Conference AES CORPORATION. Paul Hanrahan President and Chief Executive Officer. May 31,

PPAs and Tariff Design

Actual neighborhood of Sunrun customer homes

Value Driven. Exelon Corporation. Sanford C. Bernstein Conference CO2 Emissions Limits and the Power Sector: How Will Utilities Respond?

Support mechanisms for RES-e

Solving India s Renewable Energy Financing Challenge: Which Federal Policies can be Most Effective?

MONITORING & REVIEW of IMPLEMENTATION PROGRESS. Definition and Quantification of the KPIs for the SET-Plan EIIs

SPO PLANNING ANALYSIS 2015 ENO IRP. Updates for the Final IRP SEPTEMBER 18, 2015

3. The paper draws on existing work and analysis. 4. To ensure that this analysis is beneficial to the

Development of the Renewable Dispatchable Generation Model. Overview of SEPA & ScottMadden Engagement

Financing Renewable Energy

Introduction to economics of climate change. Ankara, 5 September 2016

Introduction to RELCOST. Carolyn Roos, Ph.D. Northwest CHP Technical Assistance Partnerships Washington State University Energy Program

Commercial Operations. Steve Muscato Chief Commercial Officer

UK New Nuclear: Hinkley Point C Case Study

Question 5: In your view, how does free allocation impact the incentives to innovate for reducing emissions? b) it largely keeps the incentive

Czech Republic s Third National Communication under the United Nations Framework Convention on Climate Change, 2001.

The Clean Technology Fund. U.S. Treasury Department. June 2008

The Clean Power Plan: Key Choices in the Proposed Model Rules and Federal Plan(s)

Long-term Finance: Enabling environments and policy frameworks related to climate finance

Incentives and regulatory frameworks influence on CCS chain establishment

Financial Implications of using Energy Efficiency to contribute towards meeting a Federal RES: Case Study of Kansas

APPENDIX B: PORTFOLIO OPTIMIZATION MODEL

RESEARCH ON THE EFFECTS OF A CARBON PRICE FLOOR

Potential Impacts to Wyoming of the Coal Transition

2019 Integrated Resource Plan (IRP) Public Input Meeting January 24, 2019

CEO Presentation. Curt Morgan Chief Executive Officer

THE FUTURE OF U.S. RENEWABLE ENERGY INVESTMENT. A Survey of Leading Financial Institutions

The Renewable Heat Incentive. A reformed and refocussed scheme SVT Response

UK Onshore Wind. Investment Fundamentals

The impact of different financing structures on investor risk. Marco Cometto OECD/NEA, Nuclear Development Division

Morocco s experience in financing solar projects

SMA SOLAR TECHNOLOGY AG Analyst / Investor Presentation Financial Results 2017

SSE sustainability data set

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

Management recommends the following enhancements to these modifications to the provisions for commitment costs:

Managing Risk of a Power Generation Portfolio

Cricket Valley Energy Project: Security- Constrained Economic Dispatch Analysis

Submission for the NRG Energy Case Study

BULGARIA POWER SECTOR: MAKING THE TRANSITION TO FINANCIAL RECOVERY AND MARKET LIBERALIZATION

CGC Goals, History & Strategy Why we do what we do

UK ELECTRIC MARKET REFORM APPLICATION TO TEXAS POWER MARKET. Ingmar Sterzing CEIC Seminar April 10, 2013

Sustainable Energy Handbook

AES CORPORATION. AES Investor Presentation.

APPENDIX A: FINANCIAL ASSUMPTIONS AND DISCOUNT RATE

ČEZ, a. s. BALANCE SHEET in accordance with IFRS as of March 31, 2014 in CZK Millions

The Impacts of Policy on the Financing of Renewable Projects: A Case Study Analysis

1: Levelized Cost of Energy. Calculation. Methodology and Sensitivity

STATEMENT ON SSE S APPROACH TO HEDGING 14 November 2018

Power 2022 Tariff Evaluation Methodology. 19 July 2018

New York State Initiatives and Futures

Distributional Implications of Proposed US Greenhouse Gas Control Measures Sebastian Rausch, Gilbert E. Metcalf, John M. Reilly and Sergey Paltsev

Allocation of Emission Allowances: An Economic Perspective

Perspectives on Fossil Fuel Divestment and Shareholder Action. March 19, 2014 Coal Finance 2014

Integrated Resource Planning. Roundtable 17-3 August 24, 2017

Financial Analysis and Cash Flow

Prepared for the BC Sustainable Energy Association. Expanding Energy Efficiency for BC Hydro: Lessons from Industry Leaders.

Projected Impact of Changing Conditions on the Power Sector

Strategic Plan Update. 23 November, 2015

Community and Renewable Energy Scheme Project Development Project Toolkit Project Finance Module

December 9, City of Farmington Integrated Resource Planning (IRP)

GREEK RENEWABLES SUPPORT SCHEME PROPOSALS

Building Sustainable Efficiency Businesses

Estimating Capacity Benefits of the AC Transmission Public Policy Projects

SunEdison s Comments on NERSA REFIT 2011 Consultation Paper

An Analysis of Long Run Power-Emissions Markets Interactions Under Alternative Emissions Allocation Rules. Benjamin F. Hobbs

RGGI Program Review: REMI Modeling Results

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION

BEFORE THE PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA COMMENTS OF THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION

Feed-in Tariff Review workshop. BIS Conference Centre, London, 5 October 2015

Flexible Capacity Procurement. Market and Infrastructure Policy Issue Paper

Minimising Risk Maximising Return. Chanda Kapande Business Development Manager Wind Prospect

Transcription:

Financial Incentives for Deploying Carbon Capture and Storage: How Much are they Worth? Tom Wilson Sr. Program Manager CSLF Financing Roundtable 2010 April 6, 2010

Background Carbon capture and storage (CCS) is a critically important technology for addressing climate change IPCC estimates cost savings of trillions of dollars to meet global targets currently under discussion There are a number of barriers to early CCS deployment this presentation deals with one, cost Government incentives for initial plants are essential to help deploy the technology: Initial cost Technical risk Operation costs -- in the absence of sufficiently high CO 2 prices We estimate how companies might value potential incentives EPRI analyzes policy proposals we do not make them. 2

Study Approach Cost to Beat Coal w/o CCS Also Have to Beat Gas, Nuclear, Wind Compares a new supercritical pulverized coal (SPC) plant without capture to a new SPC with capture Assumes you have to pay for storage Sensitivity case with Enhanced Oil Recovery Calculates the cost of electricity (COE) for both and finds the cost gap Note, this evaluation considers only the value of incentives and excludes project execution risk Calculates the value of incentives in COE terms Accounts for interactions between incentives Shows how packages of incentives can bridge the COE gap CAVEAT: Our analysis provides only a general guide to valuing incentives. 3

Key Cost and Performance Parameters: Supercritical PC with and without CCS (2010$) Conventional Supercritical PC SPC with CCS Capital Cost ($/kw) a 2,115 3,540 b Dispatched Capacity Factor 92 % 65-88 % c Heat Rate (MMBtu/kWh) 9000 12,650 Variable O&M (non-fuel $/MWh) 8.50 24.66 Fixed O&M ($/kw/year) 38 40 CO 2 emissions i (tons/mwh) 0.860 0.124 a. Does not include 10% owner s cost or interest during construction. b. Assumes an amine-based capture system. c. The base scenario assumes that t the conventional PC plant is available 92% of the time. The PC+CCS plant is assumed to have 65% availability in year 1, 70% in year 2, 75% in year 3, 80% in year 4, 85% in year 5, and 88% in years 6-30. Both units are assumed to be dispatched whenever available. 4

Key Financial Assumptions for Different Project Owners Investor-owned Utility (IOU) Independent Power Producer (IPP) Public Fraction Debt 55 % 70 % 100 % Cost of Debt* 6.5 % 8.0 % 4.5 % Cost of Equity 11.5 % 13.0 % N/A Tax Rate 39.2 % 39.2 % 0 % Inflation Rate 2% For All * Assumes you can get a loan 5

Cost of Electricity (COE) Estimates Made for Two CO 2 Price Scenarios -- $15/ton CO 2 and $30/ton CO 2 CO2 Price Cases 300.00 250.00 ton CO2 CO2 Price, $ per 200.00 150.00 100.00 50.00 $15 $30 $60 0.00 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 Year CO 2 price scenario named for first year price CO 2 price assumed to increase at 5% real per year $15/ton scenario hits $62/ton after 30 years; levelized cost is $27/ton CO 2 $30/ton scenario hits $124/ton after 30 years; levelized cost is $54/ton CO 2 6

Cost of Electricity (COE) Estimates for SPC with and without CCS ($/MWh) $15/ton CO 2 Case IOU IPP Public Supercritical PC $ 97 $ 98 $ 85 SPC w/ CCS $130 $131 $104 COE Gap @ $15/ton CO2 $ 34 $ 32 $ 20 $30/ton CO 2 Case IOU IPP Public Supercritical PC $121 $122 $111 SPC w/ CCS $134 $134 $108 COE Gap @ $30/ton CO2 $ 13 $12 -$ 3 7

Government Incentives Can Help Close the Gap Value of the Incentive, $ per MWh IOU IPP Public Loan Guarantee (w/ no fee) $ 1 $ 3 $ 0 Threshold issue?? Direct Loan $ 4 $ 8 $ 0 Cost Sharing (30% w/o repay) $15 $15 $ 7 Investment t Tax Credit (20%, without accelerated depreciation) Production Tax Credit ($20 per MWh for 10 years) $ 6 $ 6 $ 0* $ 9 $ 9 $ 0* Feed-in Tariff -- $15/ton CO2 $20 $20 $16 2 Bonus Permits/ton CO2 (for 10 years) $15/ton CO2 Scenario $20 $20 $16 $30/ton CO2 Scenario $39 $39 $33 COE Gap at $15/ton CO2 $34 $32 $20 COE Gap at $30/ton CO2 $13 $12 -$3 *Comparable incentive can be made available. 8

Incentives Can Close the Gap Loan guarantees or direct loans Provide only a small benefit unless needed to get a loan Low-cost to the government Tax credits Provide significant ifi value to companies with tax liability, but none to public power Cost to government is same as benefit to company Everyone can use $$ Cost sharing, free permits, and feed-in tariff benefit all Availability insurance may provide targeted value, but the concept needs more refinement but government may want return of funds if CO 2 prices rise 9

Packages of Incentives Could Reduce or Eliminate the COE Gap Packages of incentives can address specific risks, e.g., Cost share can provide initial capital Availability insurance can provide cash if the technology fails to operate Production tax credit can reward CCS operation when CO2 price is not sufficient Value of Incentive Package, $/MWh IOU IPP Public 20% ITC + Accelerated Depreciation $12 $12 $ 0 30% Cost Share + $20 PTC $15 $15 $ 7 40% Cost Share + $30 PTC $33 $34 $10 30% Cost Share + $20 PTC + Enhanced Availability Insurance $29 $30 $ 8 COE Gap at $15/ton CO2 $34 $32 $20 COE Gap at $30/ton CO2 $13 $12 -$ 3 10

What Difference Does Claw Back Make? e.g. for an IOU Cost Sharing with Claw Back 30% government cost sharing, profit = after tax profit plus depreciation plus value of CO2 reduction pay back government with 33% of profit after capital investment is recovered $15/ton CO2 Vl Value of fincentive $15 $15 w/o Claw Back ($/MWh) Year pay back starts 8 7 Year pay back ends 13 10 Value of Incentive w/ Claw Back ($/MWh) $10.26 $9.54 COE Gap $34 $13 $30/ton CO2 11

Enhanced Oil Recovery (EOR) Can Make A Huge Difference For CO 2 used for EOR, assume $20/ton CO 2 rising at 3% real per year EOR @ $20/ton CO2 + 3% real Value in $/MWh IOU IPP Public $31 $31 $ 33 COE Gap at $15/ton CO2 $34 $32 $20 COE Gap at $30/ton CO2 $13 $12 -$ 3 12

CCS Will Likely Need to Operate Flexibly: Anti-correlation of Wind with Load Creates a Ramping Challenge (e.g., 50GW of wind in Northwest Central US) 100,000 NWC Time Series from 8/9/07 to 8/16/07 w 50 GW Added 90,000 The morning up-ramp 80,000 The evening down-ramp 70,000000 60,000 MW 50,000 40,000 Wind NWC Load 30,000 20,000 10,000 13

Final Thoughts on Financing CCS The financing gap between a plant with CCS and one without is large and very sensitive to CO 2 price CO 2 price is uncertain; lenders may/will assume it will be low or at the floor Incentive packages can address a range of risks initial iti cost, poor operatation, operation when CO2 price is low Incentive packages likely must find balance between insufficient incentive to build and excess revenues Incentives can be designed to address excess revenues Ultimately, CCS will compete with nuclear, renewables, and natural gas in supplying lower-carbon electricity Flexible operation of CCS will likely be key Government incentives provide value only if they work for enough companies to get initial plants built 14

Together Shaping the Future of Electricity 15

Cost of Electricity Depends on CO 2 Price E.g., Allowance Price Estimates for Waxman-Markey Allowance Price Estimates for Waxman Markey CRA high cost CRA core ref CRA high cost $200 IGEM no int'l offsets (7) CRA low cost ADAGE ref nuclear (5) Allowance Price 2008$/t tco2e $150 $100 $50 ADAGE sensitivity (3,4,6) ADAGE core (2) IGEM core (2) EIA no int'l offsets EIA high cost EIA core EIA high tech EIA no int'l offsets EIA high cost EIA core high tech CRA core ref IGEM no int'l offsets (7) CRA low cost ADAGE ref nuclear (5) ADAGE sensitivity (3,4,6) ADAGE core (2) IGEM core (2) $ 2010 2015 2020 2025 2030 2035 2040 2045 2050 Note: Allowance prices could approach $100/ton if offsets do not materialize in large quantities at costs assumed 16

Backup Slides Definition of the Incentives Loan Guarantee Government guarantees a loan for 80% of the capital cost. Interest rates drop 0.7% (IOU), 1.1% (IPP), and 0.0% (Public). Direct Loan Government lends 80% of the capital cost at its borrowing rate. Interest rates drop 2.0% (IOU), 3.5% (IPP), and 0.0% (Public). 30% Cost Sharing - Government (or other entity) contributes 30% of the capital cost of the plant. There is no repayment of the contribution. 30% Cost Sharing with Payback - Government contributes 30% of the capital cost of the plant. The owner pays back the cost sharing over 20 years.. 17

Definition of the Incentives 20% ITC - Government grants an investment tax credit equal to 20% of the plant capital cost to the plant owner. $20 Production Tax Credit Government gives a $20 per megawatt hour (for the electric industry) or per ton of CO2 avoided (for the petroleum sector) production tax credit (PTC) to the plant owner for a period of ten years. Accelerated Depreciation Government reduces the period for depreciating the capital investment for tax purposes p from 20 years to 5 years. Availability Insurance Government guarantees the interest on and repayment of debt on any shortfall in plant output below a negotiated target plant capacity factor for ten years. The target is 88% and the payment is the fraction shortfall from this target times the debt service. 18