For personal use only

Similar documents
Detailed mining study on Malcolm Challenger Project in progress

Metals Finance Limited (ABN ) and its Controlled Entities

Glencore Finances Matrix into Copper Production Summary

Thackaringa Cobalt Project Pre Feasibility Study

For personal use only

30 September 2009 QUARTERLY REPORT ABOUT MINARA

Rusina Mining NL ABN Interim financial report for the half-year ended 31 December 2008

For personal use only

For personal use only

For personal use only

TERRAMIN AUSTRALIA LIMITED. Annual General Meeting

Metals Finance Corp and its Controlled Entities ARBN APPENDIX 4D for the six months ended 28 February 2009

CRITICAL RAW MATERIALS FOR THE BATTERY REVOLUTION

September Quarterly Report

TERRAMIN AUSTRALIA LIMITED. Annual General Meeting

Nickel West Reimagining the future. Eduard Haegel, 20 October 2016

Wetar Development Update - Mobilisation HIGHLIGHTS

NEWCREST PROFITABLE GROWTH

Australian Nickel Conference 14 October Heron Resources Limited ASX: HRR

ASX: MLX OTCQX: MLXEF GR: FG5. Rapidly Expanding Gold Producer + Commodity /Risk Diversification

TUNKILLIA GOLD PROJECT

Panda Hill Niobium Project. January 2014

For personal use only

Emerging Producer in the. Murchison Goldfields

ASX Code: THR THOR MINING PLC LETTER TO SHAREHOLDERS. 19 June 2018

For personal use only

For personal use only

Low capital development cost and high grades maximise free cash flow

For personal use only

For personal use only

Bligh Strikes Joint Venture Agreement to develop Bundarra Gold Project in WA

20% Increase in T3 Feasibility Study Plant Throughput to 3Mtpa

For personal use only

QUARTERLY REPORT OCTOBER TO DECEMBER 2014

PALADIN ENERGY LTD ACN

For personal use only

PERFORMANCE UPDATE FROM HILLGROVE'S KANMANTOO OPERATION GREG HALL IIIII CEO & MANAGING DIRECTOR 1 MAY 2013

Achmmach Tin Project, Morocco DFS complete, Funding Underway. Melbourne Mining Club, 17 July 2018 Russell Clark, CEO

KBL Mining Limited (ASX: KBL) Investor Presentation October KBL Mining Limited : : Investor Presentation

Sean Gregory Managing Director & CEO RIU Explorers Conference 22 February 2018

QUARTERLY ACTIVITIES REPORT AND APPENDIX 5B FOR THE QUARTER ENDING 31 MARCH 2018

LionGold EntersAgreement to Acquire 100% stake in Amayapampa Gold Project in Bolivia for US$7.0 million (or approximately S$9.

ASX: KNL FSE: FMK BUILDING A SUSTAINABLE ECO-FRIENDLY GLOBAL GRAPHITE BUSINESS BUSINESS UPDATE CAPE TOWN 2019

An Australian gold miner for global investors BMO Conference - February 2018

SHEFFIELD SIGNS TAURUS DEBT FACILITY AND EPC CONTRACT

For personal use only

14 March ASX Announcements Platform Bridge Street Sydney NSW 2000

For personal use only

TIRIS URANIUM PROJECT EXPLOITATION LICENCE GRANTED KEY MILESTONE ACHIEVED FOR PROJECT MOMENTUM FOR DEVELOPMENT BUILDING

Graynic Completes Joint Venture for Central American Nickel Assets

Wetar Copper Project Expansion Update - Commencement

For personal use only

Outlook for Australian cathode production

TAMPIA GOLD PROJECT FEASIBILITY STUDY

Overview of our Lithium Technology

Piauí Nickel-Cobalt Royalty Acquisition

For personal use only

For personal use only

Managing g Director s Presentation Annual General Meeting Port Moresby PNG May 20 th 2008

o Placement and Framework Agreement Sinomine to invest A$10,000,000 via a share placement in Prospect at A$0.05 per share.

For personal use only. Investor presentation

Delivering Financial Returns From Tier-1 Assets in Tier-1 Locations Full Year 2018 Financial Results - August 2018

VULCAN RESOURCES AND UNIVERSAL RESOURCES MERGER TO CREATE SIGNIFICANT COPPER-FOCUSSED GLOBAL DEVELOPMENT COMPANY

A New Growth Story in Western Australian Gold

Dragon Energy Limited

Filo del Sol Pre-Feasibility Study Results Webcast & Conference Call Presentation January 15, 2019

Agreement to Acquire Remaining Interest in the Golden Ridge Gold and Nickel Project

Positive Pre-Feasibility at Borborema

Presentation August ASX Code: TNG

DRIVEN BY EXCELLENCE. Mines and Money Asia 2017 Mike Humphries, EGM Exploration

For personal use only

AZUMAH MINING LEASES GRANTED

Alecto Minerals plc / EPIC: ALO / Market: AIM / Sector: Exploration & Development. Alecto Minerals plc ( Alecto or the Company )

For personal use only

For personal use only Updated Announcement - Acquisition of an Advanced Gold Project in Haiti

JAMBREIRO IRON ORE PROJECT SET TO DELIVER STRONG CASH FLOWS AND RETURNS: PRE-FEASIBILITY STUDY

For personal use only

WODGINA ORE RESERVE COMMENTARY

2016 Half Year Financial Results. Presentation

CASSINI PRESENTS AT RIU RESOURCES INVESTOR ROADSHOW

PRESS RELEASE FOR IMMEDIATE RELEASE May 13, 2016

Mineral Hill Mine, NSW

For personal use only

Metals X Limited Extraordinary General Meeting. 10am - 24 November 2016

ALLIANCE RESOURCES L I M I T E D

For personal use only

HIGHLIGHTS. For the period ended March 2013

RNC MINERALS. Q Results Conference Call TSX:RNX. November 15, 2017

For personal use only

GME RESOURCES LTD ABN

CLEAN TEQ SUNRISE CRITICAL RAW MATERIALS FOR THE BATTERY REVOLUTION

Company Announcements Office. Subject: Australia Papua New Guinea Business Forum Golpu Project Update

ASX ANNOUNCEMENT. 22 February 2019

LARGE STRIKE LENGTH SPODUMENE PEGMATITE DISCOVERED AT MALLINA

Quarterly Activity Report For the period ending 30 September 2010

Media Announcement (For Immediate Release)

Westgold Resources Limited Australia s Newest Gold pure-play. Denver Gold - September 2016

PALADIN RESOURCES LTD THE NEW ENERGY IN THE MARKET

Aeon Metals Limited. Quarterly Report For the three months ending 30 June ASX Announcement 31 July 2018

PNG Mining & Petroleum Investment Conference Hidden Valley PNG s Newest Mine

Transcription:

26 March 2013 Company Announcements Office ASX Limited Exchange Centre 20 Bridge Street Sydney NSW 2000 BARNES HILL OPTIMISED FEASIBILITY STUDY COMPLETED HIGHLIGHTS Summary Optimised feasibility study completed Project NPV $143.6m Construction capital $ 78.4m Capital Intensity $7.50/lb 1 Mine site cash costs $ 5.75/lb 1 Annual revenue $ + 100m Average annual EBITDA $ + 30m JV to finalise permitting Proto Resources & Investments Limited ( Proto ) is pleased to announce with Metals Finance Limited ( MFC ) the completion of the Optimised Feasibility Study at the Barnes Hill Nickel and Cobalt project in Tasmania. The Optimised Feasibility Study was completed through MFC s wholly owned subsidiary Nickel Developments Limited (the Company, NDL) The Project is a 50:50 joint venture between NDL and Proto (ASX: PRW). 1 Based on nickel equivalent production that is inclusive of nickel and cobalt

The advancements made during the optimisation study confirms the Project is economically robust and endorses the Company s innovative ability to maximise the economic potential of an undeveloped nickel laterite deposit by delivering a low operating cost structure along with highly efficient use of capital. The Project is a 500,000 tpa ROM nickel and cobalt operation producing 4,800 tonnes of Ni equivalent per annum. Once developed, the Project offers the joint venture partners sustainable cash flow over the modelled 10 year period. Modelling of the base case parameters for the Project, reports an NPV of A$143.6m (@ 12.5% discount rate) yielding a 51% IRR. The optimisation study has confirmed the projects economic metrics with a capital intensity, equivalent to $7.50/lb annual production, and operating costs of $5.16/lb in the first 5 years and $5.75/lb over the first 10 years. The Joint Venture partners will continue to work collaboratively to finalise the permitting of the project and to secure funding options for construction and development of the Project, based on this final study. Background The Company completed feasibility study work on the 500,000 tonnes per annum vat leach and nickel production plant in June 2012. The study was completed on the basis of capital and operating cost savings which could be achieved through the use of the nearby 3 rd party infrastructure and utilities. Since issuing the June 2012 feasibility study, NDL has undertaken further engineering studies aimed at optimising the project economics. A number of opportunities have been identified that are advantageous to the project economics. In addition, NDL has recommended that a stand-alone operation be referenced as the base case with possible upside in the event synergies can be achieved by utilising 3rd party infrastructure and utilities. Optimising the feasibility study The Optimisation Phase has identified value adding options for the Project. These options are described below: 2

Optimisation Proposition Advantages Leaching Vessels Leach Temperature Water Medium Plant Relocation Power Options Increase Strip Ratio Employ an agitated tank system Increase leach temperature to 80 o C Utilise saline water in the process flow sheet Reposition the processing facility Connect to existing distribution system Maximises extraction of resource from deposit Reduce footprint of leach vessel and increase confidence in nickel recovery Reduce residence time in leach from 120 days to 8 hours Reduce operating cost by reducing water unit charge rates and acid consumption Reduce site establishment capital by locating plant closer to existing road infrastructure Reducing total power demand enables connection to nearby power system Ensures total resource recovery and maximises potential mine life. Construction Capital Total construction capital for the Project is $78.4m. Capital is apportioned 75% for direct capital costs and 25% for indirect capital costs. 70% of direct capital costs are allocated for the main processing activities of: Leaching, Ion Exchange, Electrowinning, and Tailings treatment. Indirect Costs are evenly divided between Engineering, Procurement and Construction expenses and percentage based line items including escalation and contingencies. The Project has a capital intensity of $7.50 per pound of annual Ni equiv production, positioning the project as a capital efficient nickel laterite project when compared to peers. 3

Mine Site Cash Costs Total mine site cash costs are dominated by the acid requirements of the project. Other key categories are shown in the adjacent figure. The project economics are most sensitive to sulphuric acid pricing. NDL has engaged with acid suppliers to substantiate that the acid pricing and volume requirements can be achieved. The Company has modelled higher than prevailing acid pricing to provide the project with upside to the current scenario. The other 5 major areas that comprise mine site cash costs are evenly distributed between; Lime - used for neutralisation, Electricity - used for electrowinning the nickel cathode production, Mining for both ore and waste movement, Wages for all staff, and other mine site cash costs. The Project has a mine site cash cost of $5.16/lb of nickel equivalent for the first 5 years of operation and $5.75/lb for the modelled 10 year period. Revenue and EBITDA Sales of nickel cathode and cobalt sulphate are projected to generate annual revenue of approximately $105m annually. Revenue is based on commodity pricing of $10/lb Ni and $13/lb Cobalt with foreign exchange parity. Allowing for operating and marketing costs, the average annual EBITDA is approximately $30m, inclusive of capital repayment and exclusive of project financing costs. Project Economics The Optimisation study has provided confidence to the number used in evaluating the economic potential of the Project. The Project provides the joint venture partners with immediate cash flow and has the capability to retire project funding within two years of commencing production under the modelled parameters. Key operational and financial highlights include: 4

Barnes Hill Project Capital cost ($ millions) Project ROM tonne throughput (million t) Nickel grade first 5 yrs (%) Nickel grade second 5 yrs (%) Nickel recovery (%) Life of mine nickel price US$/lb Foreign Exchange USD:AUD Total revenue ($ millions) Indicated NPV 12.5% ($ millions) Indicated IRR% Base 78.4 500,000 1.01% 0.73% 90% 10.00 1:1 1,045 143.7 51% Under variously modelled scenarios, the Barnes Hill nickel laterite project is economically robust with the opportunity to provide favourable returns to investors and shareholders. Ongoing Activities During the Optimisation Phase, NDL has been cognisant to minimise the environmental disturbance of the Project and maintain the biodiversity in the area. As a core part of NDL s corporate social responsibility, NDL will continue to pursue options that promote the preservation of the environment in and around the Project. NDL and PRW will continue to work with regulatory authorities to successfully finalise the Project s permitting requirements. 5

FOR FURTHER INFORMATION CONTACT: Mr Andrew Mortimer Managing Director Proto Resources & Investments Ltd T: +61 (2) 9225 4000 M: +61 (0) 433 894 923 E: andrew.mortimer@protoresources.com.au Jane Morgan Investor Relations Manager Proto Resources & Investments Ltd T: +61 (2) 9225 4000 M: +61 (0) 448 009 672 E: jane.morgan@protoresources.com.au More details are available on the company website www.protoresources.com.au Metals Finance Limited Tony Treasure Managing Director Metals Finance Limited T: +61 (7) 3807 4166 Mark Sykes Managing Director Nickel Developments Limited T: +61 (7) 3807 4166 More details are available on company website www.metalsfinance.com About Proto Resources & Investments Limited Proto Resources & Investments Limited is an ASX listed resources company with a three pronged approach to add value to shareholders. Including advancing the Exploration targets in Western Australia and the Northern Territory, Developing the near term projects such as Barnes Hill and focusing on strategic Investments including the Barrier Bay processing technology. About Metals Finance Limited Metals Finance develops mineral assets in partnership with other exploration and mining companies, rather than purchasing them. MFC applies the extensive experience of its executives, board and consultants on geologically defined resources to establish appropriate treatment processes, to undertake detailed feasibility studies and to promote the development of projects. It is currently working with three ASX-listed partners at Lucky Break in Queensland and Barnes Hill in Tasmania and Homeville in New South Wales. MFC is also seeking new opportunities, and is reviewing the development of gold and nickel projects in South America and Europe 6

Competent Person Information within this announcement which pertains to mineralisation or resources is based on information compiled by Mr Tony Treasure who is a full time employee of Metals Finance Limited and is a Member of the Australasian Institute of Mining and Metallurgy. Mr Treasure has sufficient experience in the fields under consideration to qualify as a Competent Person as defined in the 2004 edition of the Australasian Code for Reporting of Exploration results, Mineral Resources and Ore reserves and consents to the inclusion of this information in the form and context of which it appears in this report. Unless otherwise stated, all currency values are in Australian dollars. 7