Rick Garcia MCR, LLC 390 N. Sepulveda Blvd., Suite 1050 El Segundo, CA Casey Wallace

Similar documents
More Trouble With Estimating at the 80 th Percentile

Presented at the 2012 SCEA/ISPA Joint Annual Conference and Training Workshop -

A Scenario-Based Method (SBM) for Cost Risk Analysis

Do Not Sum Earned-Value-Based WBS-Element Estimates-at-Completion

Enhanced Scenario-Based Method (esbm) for Cost Risk Analysis

A Scenario Based Method for Cost Risk Analysis

Inflation Cost Risk Analysis to Reduce Risks in Budgeting

A SCENARIO-BASED METHOD FOR COST RISK ANALYSIS

BASIC COST RISK ANALYSIS: USING CRYSTAL BALL ON GOVERNMENT LIFE CYCLE COST ESTIMATES

Enhanced Scenario-Based Method (esbm) for Cost Risk Analysis

Web Science & Technologies University of Koblenz Landau, Germany. Lecture Data Science. Statistics and Probabilities JProf. Dr.

A Probabilistic Approach to Determining the Number of Widgets to Build in a Yield-Constrained Process

Cost Risk and Uncertainty Analysis

February 2010 Office of the Deputy Assistant Secretary of the Army for Cost & Economics (ODASA-CE)

The normal distribution is a theoretical model derived mathematically and not empirically.

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017

PREVENTING PROGRAM MANAGEMENT PITFALLS USING PORTFOLIO ESTIMATING

A useful modeling tricks.

RISK MITIGATION IN FAST TRACKING PROJECTS

Ground Radar Expenditure Phasing Analysis

ENHANCED SCENARIO-BASED METHOD FOR COST RISK ANALYSIS: THEORY, APPLICATION, AND IMPLEMENTATION

California Department of Transportation(Caltrans)

Using Monte Carlo Analysis in Ecological Risk Assessments

Fatness of Tails in Risk Models

Making Risk Management Tools More Credible: Calibrating the Risk Cube

Obtaining Greater Efficiency and Productivity in Defense Spending The Carter Memo

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule

EVM s Potential for Enabling Effective Integrated Cost-Risk Management

NASA Implementation of JCL Policy

Risk vs. Uncertainty: What s the difference?

Sampling Distributions and the Central Limit Theorem

Assessing the Impact of Confidence Levels in Funding and Budgeting NASA Science Missions

Probabilistic Benefit Cost Ratio A Case Study

A New Method of Cost Contingency Management

ACEIT Users Workshop January 31-February 2, 2011 Alfred Smith CCEA. PRT-73, 19 Jan 2011 Approved For Public Release Copyright Tecolote Research, Inc

TOPIC: PROBABILITY DISTRIBUTIONS

5-1 pg ,4,5, EOO,39,47,50,53, pg ,5,9,13,17,19,21,22,25,30,31,32, pg.269 1,29,13,16,17,19,20,25,26,28,31,33,38

BAE Systems Risk Opportunity & Uncertainty Modelling ACostE North West Region 4th September 2013

Understanding the Results of an Integrated Cost/Schedule Risk Analysis James Johnson, NASA HQ Darren Elliott, Tecolote Research Inc.

Lecture Data Science

9/17/2015. Basic Statistics for the Healthcare Professional. Relax.it won t be that bad! Purpose of Statistic. Objectives

value BE.104 Spring Biostatistics: Distribution and the Mean J. L. Sherley

WEAPON SYSTEMS ACQUISITION REFORM ACT (WSARA) AND THE ENHANCED SCENARIO-BASED METHOD (esbm) FOR COST RISK ANALYSIS

Making sense of Schedule Risk Analysis

Integrating Contract Risk with Schedule and Cost Estimates

Key Objectives. Module 2: The Logic of Statistical Inference. Z-scores. SGSB Workshop: Using Statistical Data to Make Decisions

Introduction to Cost Analysis. Introduction to Cost Analysis

Chapter 5. Sampling Distributions

A Study on Risk Analysis in Construction Project

ENHANCED SCENARIO-BASED METHOD FOR COST RISK ANALYSIS: THEORY, APPLICATION, AND IMPLEMENTATION

***SECTION 8.1*** The Binomial Distributions

SCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol

CHAPTER 4 DISCRETE PROBABILITY DISTRIBUTIONS

Economics 430 Handout on Rational Expectations: Part I. Review of Statistics: Notation and Definitions

Introduction to Risk, Return and Opportunity Cost of Capital

Time Phasing Methods and Metrics

A Better Way to Assess Benefits, Costs, and Risks in a Product Support Business Case Analysis

Cost Estimation as a Linear Programming Problem ISPA/SCEA Annual Conference St. Louis, Missouri

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

Technical note: Project cost contingency

AIR FORCE INSTITUTE OF TECHNOLOGY

Application of the Bootstrap Estimating a Population Mean

Full Monte. Looking at your project through rose-colored glasses? Let s get real.

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

Fundamentals of Project Risk Management

Web Extension: Continuous Distributions and Estimating Beta with a Calculator

BAE Systems SCAF Presentation June BAE SYSTEMS 2013, all rights reserved Unclassified 31/07/2013 1

We use probability distributions to represent the distribution of a discrete random variable.

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Is a Binomial Process Bayesian?

Effective Use of Cost Risk Reports

How to Consider Risk Demystifying Monte Carlo Risk Analysis

Risk management. VaR and Expected Shortfall. Christian Groll. VaR and Expected Shortfall Risk management Christian Groll 1 / 56

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Week 1 Variables: Exploration, Familiarisation and Description. Descriptive Statistics.

Pricing & Risk Management of Synthetic CDOs

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

Learning Le cy Document

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

The Binomial Distribution

Retirement. Optimal Asset Allocation in Retirement: A Downside Risk Perspective. JUne W. Van Harlow, Ph.D., CFA Director of Research ABSTRACT

SENSITIVITY ANALYSIS IN CAPITAL BUDGETING USING CRYSTAL BALL. Petter Gokstad 1

Risk Video #1. Video 1 Recap

STAT 201 Chapter 6. Distribution

RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management

Risk Management Plan for the Ocean Observatories Initiative

Paul R. Garvey a, Brian Flynn b, Peter Braxton b & Richard Lee b a The MITRE Corporation, Bedford, Massachusetts, USA

The Binomial Distribution

SMC/PMAG Control Account Manager (CAM) Notebook Evaluation

Chapter 6: Random Variables. Ch. 6-3: Binomial and Geometric Random Variables

ECONOMIC CAPITAL MODELING CARe Seminar JUNE 2016

Presented at the 2003 SCEA-ISPA Joint Annual Conference and Training Workshop -

Examination of Functional Correlation

PRE CONFERENCE WORKSHOP 3

EVMS Fundamentals v.7.0. (Part 2 of 2) Slides and Notes

The Assumption(s) of Normality

Probability Models.S2 Discrete Random Variables

The binomial distribution

Statistical Modeling Techniques for Reserve Ranges: A Simulation Approach

Transcription:

Budgeting to the Mean ISPA/SCEA - June 2011 Rick Garcia rgarcia@mcri.com Casey Wallace cwallace@mcri.com MCR, LLC 390 N. Sepulveda Blvd., Suite 1050 El Segundo, CA 90245 Filename: Budgeting to the Mean v12.ppt 4/4/2011 Presented at the 2011 ISPA/SCEA Joint Annual Conference and Training Workshop - www.iceaaonline.com

Summary / Abstract Decision makers (and policy) often require cost estimators and analysts to move to a higher confidence level on the S-Curve to ensure enough budget is requested so that a program does not overrun its budget target. Although the request to budget at a higher confidence level is a pragmatic attempt to avoid overruns (underbudgeting), there are other factors to consider besides simply moving to the right on an S- Curve; such as ensuring a cost estimate captures all relevant uncertainty and acknowledging acquisition changes that will impact a program after a budget has been set. With all of these factors to consider, the simply stated conclusion of this analysis is that the decision to pay for the project should be based on the risk adjusted expected value (mean) of a program. If an analyst believes in the completeness of their underlying cost model, it is rational to purchase the project for the risk adjusted expected value (mean) since the mean is the probability weighted, statistical norm or average. This analysis examines the rationale for advocating budgeting to the risk-adjusted mean, and compares this methodology and its results against budgeting above or below the expected value (mean). In addition, this discussion will also explore some of the misconceptions of confidence level terminology. 2

Outline Introduction What is a Cost Estimate? Is My Cost Estimate Right? The Estimate S-Curve Which Percentile Should I Recommend? Summary References 3

Introduction: The Problem Decision makers (and policy) often require cost estimators and analysts to report costs at a particular confidence level on an S-Curve, such as the 80%, to ensure enough budget is requested so that a program does not overrun its budget target Although the request to budget at a higher confidence level is a pragmatic attempt to avoid overruns (caused by underbudgeting), there are other factors to consider besides simply moving to the right on an S-Curve Ensuring a cost estimate captures all relevant uncertainty Acknowledging acquisition changes that will impact a program after a budget has been set 4

What Is a Cost Estimate? 5

What Is a Cost Estimate? Cost Analysis The accumulation and analysis of actual costs, statistical data, and other information on current and completed contracts or groups of contracts or programs. Cost analysis also includes the manipulation of cost data, comparisons and analyses of these data, and cost extrapolations of data for future projections of cost. Cost Estimating The art of approximating the probable cost or value of something, based on information available at the time. Cost Estimate Anticipated costs associated with a project or program alternative (usually representing the entire life cycle) Source: The Society of Cost Estimating and Analysis (SCEA) 6

Importance of Cost Estimates In Establishing Budgets A competent estimate is the key foundation of a good budget! A program s approved cost estimate is often used to create the budget spending plan. This plan outlines how and at what rate the program funding will be spent over time. Because resources are not infinite, budgeting requires a delicate balancing act to ensure that the rate of spending closely mirrors available resources and funding. And because cost estimates are based on assumptions that certain tasks will happen at specific times, it is imperative that funding be available when needed so as to not disrupt the program schedule. For a government agency, reliable estimates help in assessing the reasonableness of a contractor s proposals and program budgets. Credible cost estimates also help program offices justify budgets to the Congress, Office of Management and Budget (OMB), Government Accountability Office (GAO), department secretaries, and others. Cost estimates are often used to help determine how budget cuts may hinder a program s progress or effectiveness. Source: GAO Cost Estimating and Assessment Guide 7

What A Cost Estimate Looks Like Often erroneously considered to be a single value that represents program cost/schedule, when it really is a probability distribution of cost and schedule values Percentile Value 10% 516.81 20% 538.98 30% 557.85 40% 575.48 50% 592.72 60% 609.70 70% 629.19 80% 650.97 90% 683.01 10,000 Trials Cumulative Chart 71 Outliers 1.000.750.500.250.000 S-Curve Forecast: A8 462.43 537.16 611.89 686.62 761.35 10000 0 Statistics Value Trials 10,000 Mean 596.40 Median 592.72 Mode --- Standard Deviation 63.18 Range Minimum 450.19 Range Maximum 796.68 Forecast: A8 10,000 Trials Frequency Chart 71 Outliers Density.020.015.010.005 Density Curve 197 147.7 98.5 49.25.000 462.43 537.16 611.89 686.62 761.35 0 8

Is My Cost Estimate Right? 9

Is My Cost Estimate Right? NO! The statistical chances of getting the estimate exactly right are infinitesimal The cost distribution is a representation of the approximation of the probable cost or value of something, based on information available at the time A blend of Objective and Subjective components for example Objective WBS Structure Mathematical / statistical summing Inflation Indices Both Objective and Subjective Uncertainty modeling Technical baseline changes Acquisition life cycle changes Instead of asking, Is My Cost Estimate Right?, the analyst should be asking another question 10

Is My Cost Estimate a Reasonable Representation of the Actual Program? This is the question all analysts should ask themselves EVERY time they are asked to provide a cost estimate Really applies to the Cost Estimate and Cost Model that generates it Two schools of thought 1) Due to changes that occur over the acquisition life cycle, the entire cost distribution (usually) marches to the right over time 2) A complete and thorough analysis of the program and its acquisition environment can enable an analyst, even early in the program, to capture sufficient program uncertainty Truth about how an estimate changes over time is probably a combination of both #1 #2 ProbabilityDensity 0 50 100 150 200 250 300 350 400 $M 11

Cost Estimate Uncertainty It is important to continually update estimates with actual costs, so that management has the best information available for making informed decisions Narrow risk ranges should be viewed as suspect, because more cost estimates tend to overrun than under run Source: GAO Cost Estimating and Assessment Guide 12

Challenges of a Good Cost Estimate Developing a good cost estimate requires stable program requirements access to detailed documentation and historical data well-trained and experienced cost analysts risk and uncertainty analysis the identification of a range of confidence levels adequate contingency and management reserves Even Even with with the the best best of of these these circumstances, cost cost estimating is is difficult 13

Phase A Program Example 100% Total Program CV = Coef of Variation% 90% 80% POE CV = 0.06 ICE CV = 0.39 Cummulative Probability 70% 60% 50% 40% 30% POE ICE 20% 10% 0% TY$M PHASE A Program POE did a decent job of capturing Cost and Schedule risk but the POE missed the technical and programmatic risk of the proposed contractor solutions 14

The Estimate S-Curve 15

Steps to Developing a Credible S-Curve 1. Determine the program cost drivers and associated risks 2. Develop probability distributions to model various types of uncertainty (for example, program, technical, external, organizational, program management including cost estimating and scheduling) 3. Account for correlation between cost elements to properly capture risk 4. Perform the uncertainty analysis using a Monte Carlo simulation or analytic model 5. Identify the probability level associated with the point estimate 6. Recommend sufficient contingency reserves to achieve levels of confidence acceptable to the organization 7. Allocate, phase, and convert a risk-adjusted cost estimate to then-year dollars and identify high-risk elements to help in risk mitigation efforts. Source: GAO Cost Estimating and Assessment Guide 16

Now You Have a Probability Density And by definition you also have an S-Curve (CDF) what now? 50%, $184 Mean (58%), $200 SD= $84M CV = 42% Probability Density Pt Est, $105 80%, $259 CDF = PDF 0 50 100 150 200 250 300 350 400 $M SD = Standard Deviation CV = Coef of Variation% = SD /Mean Program Managers (PM) make decision of where to budget and how to manage their program We must provide the PM with as much information as possible for them to make an informed decision Acquisition leaders need to understand that cost estimates are not deterministic, they are represented by a RANGE 17

Point Estimate, 50%, 80%, Mean? Management can use the S-Curve to choose a defensible level of cost estimation No specific confidence level is universally considered a best practice Air Force Instruction (AFI) 63-101 & Guidance Memo (Mar 2010): (risk adjusted) Mean and 80% Weapon Systems Acquisition Reform Act (WSARA) (2009): 80% or justification Air Force Cost Analysis Agency (AFCAA): Risk Adjusted Mean National Reconnaissance Office Cost Analysis Integration Group (NRO CAIG): Risk Adjusted Mean National Aeronautics and Space Administration (NASA): 50% and 70% mentioned in policy Space & Missile Systems Center Instruction (SMCI) 63-104: 80% or justification [Some] Experts agree that program cost estimates should be budgeted to at least the 50% confidence level, but budgeting to a higher level (for example,70% to 80%, or the mean) is now common practice How much contingency reserve should be allocated to a program beyond the 50 percent confidence level depends on the program cost growth an agency is willing to risk. Some organizations adopt other levels like the 70th or 80th percentile (refer to the S-Curve above) to: 1. Reduce their anxiety about success within budget 2. Make some provision for risks unknown at the time but likely to appear as the project progresses, 3. Reduce the probability that they will have to explain overruns or re-baseline because they ran out of reserve budget. Source: GAO Cost Estimating and Assessment Guide 18

Moving along the Percentile Scale: Point Estimate Probability Density Pt Est, $105 0 50 100 150 200 250 300 350 400 Point Estimate = Raw Output of a Cost Model PRIOR to modeling any Risks A point estimate does not capture any uncertainty A point estimate does not tell us enough about the potential range of costs Any point on the PDF or S-Curve (CDF) can be understood only by relating it to the rest of the PDF or CDF What is the Mean and Standard Deviation? A point point estimate, by by itself, itself, provides no no information about about the the underlying uncertainty $M 19

Moving along the Percentile Scale: 50% 50%, $184 Mean (58%), $200 SD= $84M CV = 42% SD = Standard Deviation CV = Coef of Variation% Probability Density Pt Est, $105 80%, $259 0 50 100 150 200 250 300 350 400 $M Better than budgeting to the Point Estimate; the Point Estimate will never materialize (it s usually too low) 50% probability of cost coming in at or below $184M 50% probability of cost coming in above $184M Remember, the major assumption underlying your estimate is that your model had adequately captured the program risks 20

Moving along the Percentile Scale: 80% 50%, $184 Mean (58%), $200 SD= $84M CV = 42% SD = Standard Deviation CV = Coef of Variation% Probability Density Pt Est, $105 80%, $259 0 50 100 150 200 250 300 350 400 80% probability of cost coming in at or below $259M 20% probability of cost exceeding $259M Budgeting individual programs at the 80% is inefficient from a portfolio standpoint (Anderson, Book, Covert, etc.) Research has shown that if individual programs were budgeted at the 80 th percentile, the portfolio of programs was budgeted at a much higher, inefficient percentile (~95%). Not allowing for program portfolio success due to lack of adequate resources $M 21

Moving along the Percentile Scale: Mean 50%, $184 Mean (58%), $200 SD= $84M CV = 42% The Means Sum! Probability Density Pt Est, $105 80%, $259 0 50 100 150 200 250 300 350 400 The mean s percentile changes with each estimate, but AFCAA* experience is that the mean is usually between 55%-65% Jointly, the Coefficient of Variation (CV) should be reasonable (see AFCAA Cost Risk Handbook) In this example, 58% probability of cost coming in at or below $200M 42% probability of cost exceeding $200M Represents the probability weighted, statistical norm, average, or expected value Mathematical/statistical measure, not subjective in relation to other projections along the S- Curve Has Statistical Meaning * Source: AFCAA Cost Risk Handbook $M 22

Moving along the Percentile Scale: What is the Mean? The mean is the probability-weighted average, or expected value. Let s look at a stylized example. We ll use the simplest of games, an equal probability binomial coin flip game. Heads and you get a $1 Tails and you get $0 There is a 50% chance that the coin will be a heads, and the payoff to you is $1 There is a 50% chance that the coin will be a tails, and the payoff to you is $0 If you play for free, then over time this game is a guaranteed return of $0.50 to you Your expected payoff is simply sum of the product of the probability weightings (50%, 50%) with the payoffs for the 2 states of the world (Heads=$1, Tails=$0) Expected Value = E(V) = (50% * $1) + (50% $0) = $0.50 23

Expected Value Drives the Decision, 1 of 3 Now, you have some alternatives. I m not going to let you play for free. You have to put down one dollar deposit with me to play, and I m going to charge you a fee. Alternatively, you can loan your dollar to the bank for a guaranteed rate of return. What would be the maximum that you would pay me to play the game? What return would you require from the bank that would make you indifferent between the game and the bank deposit? The answer is the expected value Given the 2 (two) states of this example and your expectations for the payoffs of both, it is irrational to expect to earn more than $0.50 playing the game, you d never pay more than $0.50 to play the game, and you d require a $0.50 return from the bank to make you indifferent between the game and the deposit. Our simple 2 state model allows us to use the expected value to make logical decisions. Therefore, given the problem of predicting a payoff, or a cost, why would you ever expect any other value away from the mean? 24

Expected Value Drives the Decision, 2 of 3 (V Heads ) = $1.00, (V Tails ) = $0.00 Value of Flipping Heads = V Heads ; Value of Flipping Tails = V Tails p(heads) = 50%, p(tails) = 50% Probability of Flipping Head = p(heads) ; Probability of Flipping Tails = p(tails) E(V) = [p(heads) * (V Heads )] + [p(tails) * (V Tails )] = $0.50 Rules: You don t play for free, you will have to pay me a fee. You have the choice of loaning me a dollar to play the game, or loaning your dollar to the bank for some return. Probability Density Function Cumulative Distribution Function 0.6 1 0.5 Mean, 0.5 0.75 Mean, 0.5 Probability Density 0.4 0.3 0.2 Probability 0.5 0.25 0.1 0 0 1 0 0 1 Q: Should you play the game or loan your dollar to the bank? Q: What would be the maximum fee that you would pay to play? We base our Go/No Go decision to play the game (fund the program), and our valuation of the game (program cost), on the E(V) 25

Expected Value Drives the Decision, 3 of 3 Our previous example is a simple Bernoulli distribution (heads/tails) Increasing the number of statistically summed distributions starts to reflect a familiar PDF and CDF (S-Curve) Sum of 5 independent coin tosses Probability Density Function Cummulative Distribution Function 1800 1600 Mean, 2.5 1 0.9 1400 0.8 Probability Density 1200 1000 800 600 Probability 0.7 0.6 0.5 0.4 0.3 Mean, 2.5 400 0.2 200 0.1 0 0 1 2 3 4 5 0 0.0 1.0 2.0 3.0 4.0 5.0 Process extends to cost models with dozen or hundreds of statistically summed elements 26

Which Percentile Should I Recommend? 27

Summary of Advantages v. Disadvantages S-Curve Percentile Confidence Level Point Estimate ( Baseline Estimate) 50% ( Median ) Advantages Easy to understand Provides an easily repeatable and traceable point of reference Easy to understand Same Chance of Over/Under Running 80% Possibly reduces likelihood of overrunning; again, if your underlying model adequately captures risk Consistent with some policy/guidance Mean ( Expected Value, typically 55%-65%) Tied to a calculated Expected Value Intuitive mathematical sense ; defines your distribution (along with the sigma) Value typically in the range between 55-65%; if the risk analysis and CV are adequate Consistent with some policy/guidance The Sum of the Mean is the Mean of the Sums! Disadvantages Does not take into account various Program risks Large likelihood that cost will be higher than the Point estimate; history shows the point estimate is usually at the 35% or below Same Chance of Over/Under Running If the true Risk of the program may not be adequately captured; large CV => large spread between percentile Creates unrealistic portfolio budgeting levels Self fulfilling prophecy of high program costs Still chance of overrunning 28

Summary Budget at The MEAN Statistically the Sum of the Mean is the Mean of the Sum Need to have spent time and effort adeqautely modeling program risks Program Managers make decision of where to draw the budget line and how to manage their program We must provide the PM with as much value-adding information as possible for them to make an informed decision Acquisition leaders need to understand that cost estimates are not deterministic, they are represented by a RANGE Some things to remember if you are asked to recommend a percentile level of funding Uncertainty Analysis and Risk Incorporation will never be 100%, but the Mean is the expected value, and also has mathematical attributes in relation to the rest of the data on the S Curve and statistically and empirically makes the most sense. Cost growth can be mitigated only if we do our best to estimate the cost of the FINAL program rather than the BASELINE The mean should make logical sense with respect to the rest of the CDF (S-Curve) 29

References AFI 63-101: Acquisition and Sustainment Life Cycle Management, April 17, 2009. Anderson, Timothy, MCR. More Trouble With Estimating at the 80th Percentile, 43rd DoD Cost Analysis Symposium, Williamsburg, VA, February 2010. Book, Stephen, MCR. Cost Risk as a Discriminator in Trade Studies, SCEA/ISPA, 2007 Boulais, Ryan, et al. Understanding Risk in the Budgeting Process from a Portfolio Point of View, 2010 Brown, Bradford, Defense Acquisition University. Weapon Systems Acquisition Reform Act of 2009 (Public Law 111-23), 22 May 2009). Cincotta, Kevin, LMI. The Percentile Problem: How Much Is Enough?, SCEA/ISPA 2008 Covert, Raymond, The Aerospace Corporation. Ten Common Things Wrong With Cost Risk Analysis, 2002. Garcia, Rick, MCR Federal. S-Curves in Cost Estimating, February 2010. Government Accountability Office (GAO). GAO Cost Estimating and Assessment Guide, March 2009. Guidance Memorandum to AFI 63-101: Confidence Level Selection for Air Force Acquisition Programs, March 17, 2010. Johnson, N.L. et al., Distributions in Statistics, Ed. J. Wiley, Houghton M. Co., 1997 NRO Cost Group, NRO Cost Group Risk Process, 2003. Office of the Undersecretary of Defense (Comptroller) (USD(C)). "Department of Defense Financial Management Regulation, DoD 7000.14-R," Volume 1. 27 December 2008. Smart, Christian, MDA. Here There Be Dragons: Considering the Right Tail in Risk Management, 2010. SMCI 63-104: Software Acquisition Instruction, May 26, 2009. Troge, Sam, USAF. Space Radar Risk Metrics, 2006 30

Acronym List AFCAA - Air Force Cost Analysis Agency AFI - Air Force Instruction CAIG - Cost Analysis Improvement Group CDF - Cumulative Density Function E(V) - Expected Value GAO - Government Accountability Office PDF - Probability Density Function PM - Program Manager NASA - National Aeronautics and Space Administration NRO - National Reconnaissance Office OMB - Office of Management and Budget SCEA - Society of Cost Estimating and Analysis SMCI - Space & Missile Systems Center Instruction WBS - Work Breakdown Structure WSARA - Weapon Systems Acquisition Reform Act 31 31

Confidence Level Terminology Mean expected value Median the statistically middle value in a range; the value at the 50 th percentile Mode the value in a range with most probability concentrated near it Skewed distribution above 50% probability in one of the tails of the distribution Positively skewed distribution: Mode < Median < Mean Risk quantifiable likelihood of loss Measure standard deviation of cash flows Metric coefficient of variation (CV); sigma/e(v); (1/CV) $ cost per unit of risk Confidence Level A statistical calculation measuring the degree of certainty about a correlation, result or forecast Q: How confident are you in your forecast of the actual program cost? A: Given our model, I am 68% confident that the true cost estimate falls within +/- 1 standard deviation of our sample E(V). Percentile A value on a scale of 100 that indicates the percent of a distribution that is equal to or below it Observation of output values from a Monte Carlo simulation S-Curve at 80 th percentile means that the 80% of the output values from the model are below, and 20% are above Valuation Process of determining the expected value of an asset; E(V) Go/No Go decision to fund the project, and the valuation of the cost of that project, is based on the E(V) 32