Investor Presentation. Cover slide (same as IR cover)

Similar documents
Eskom Presentation Standing Committee on Appropriations

Cover slide (same as IR cover)

Group Interim results for the six months ended 30 September Cover slide (same as IR cover)

Cover slide (same as IR cover)

Eskom group interim results for the six months ended 30 September 2017

Interim integrated results for the six months ended 30 September 2014

Eskom Regulatory Clearing Account (RCA) year 5 of MYPD 3. Public Hearings- Port Elizabeth Date: 16 January 2019

Eskom 2018/19 Revenue Application

Eskom group annual results for the year ended 31 March 2018

Integrated Results Presentation for the year ended 31 March 2013

MYPD 3 (Year 2013/14) Regulatory Clearing Account Submission to NERSA

MYPD3 Application January 2013

Integrated Results Presentation for the six months ended 30 September 2013

PRESENTATION AT NERSA PUBLIC HEARINGS FOR ESKOM S MYPD3 RCA FOR YEAR 5 RONALD CHAUKE 14 JANUARY 2019

Eskom 2018/19 Revenue Application

Submission to SALGA and National Treasury

Eskom MYPD4 Revenue Application

MYPD 3 (Year 2014/15) Regulatory Clearing Account Submission to NERSA

Draft Eskom 2018/19 Revenue Application

Eskom Audited Annual Results Presentation for the year ended 31 March 2011

Eskom 2018/19 Revenue Application

FY2017/18, Year 5 of MYPD 3 Period

Demystifying Tariff Setting The tariff conundrum Lower rates now, blackouts later?

YPD 3: Regulatory Clearing Account Submission to NERSA

Integrated Results for the year ended 31 March 2014

Annual financial statements. 31 March 2016

OUTA Presentation to NERSA Eskom s 2018/19 application NOVEMBER 2017

AFRICAN UTILITY WEEK 2009 At van der Merwe & Louis Fourie

NATIONAL ENERGY REGULATOR. Eskom MYPD2 Regulatory Clearing Account (RCA) and RCA Balance THE DECISION

Finance and Group Capital division continued PIC TO COME

Eskom RCA: Revenue Application NERSA Public Hearing. City Power Presentation Frank Hinda 11 May 2018

Eskom RCA applications M o r n è M o s t e r t M a y

Unipro PJSC 2016 Full year results

Eskom 2018/19 Revenue Application. Closing remarks

Eskom s Draft Application to NERSA for Price. Increase in 2008/9

NATIONAL ENERGY REGULATOR. Eskom s Regulatory Clearing Account (RCA) Application Third Multi-Year Price Determination (MYPD3) Year 1 (2013/14)

Arise Windpower AB. Company presentation February 2013

SALGA Position on Eskom Revenue Proposal 2018/19 Cllr M. Mfikoe Nhlanhla L Ngidi Lonwabo Magida 16 November 2017

Endesa FY 2017 Results 28/02/2018

NERSA COMMENTS ON ESKOM S REVENUE APPLICATIONFOR 2018/19 FINANCIAL YEAR

NERSA Submissions ESKOM RCA

Eskom Revenue Application. Multi Year Price Determination. 2010/11 to 2012/13 (MYPD 2)

2009 Results Presentation. Warsaw, March 16, 2010

OUTA Presentation to NERSA Eskom s 2018/19 application NOVEMBER 2017

Credit Opinion: Eskom Holdings SOC Limited

ESKOM S FINANCIAL CRISES AND CONTINUING TARIFF INCREASES

MYPD3 Application Gauteng January 2013

Transforming RWE and securing a sound financial base. (as of December 2016)

Annual Financial Results. for the twelve months ended 31 December 2009

COMPANY OVERVIEW. US$812mn. Largest Energy Generator in Chile 5,063MW 531 MW 100% 11 Years. US$2.2bn. BBB-/Baa3 66.7% of installed capacity

2014 Fixed Income Investor Update

Statkraft Investor Update. March 2014

Endesa 1Q 2018 Results 08/05/2018

Net debt of 15.1bn by Sep-17, -5% YTD Portfolio reshuffling (disposal of Naturgas & reinforecement in EDPR stake to 82.6%): - 1.

Pretoria Portland Cement Company Limited Beyond 2010 Unaudited interim results

Earnings Conference Call. Fourth Quarter and Full Year 2014

Looking to the medium term

Public Hearing Presenter: D Matsheketsheke Designation: CFO (act) Date: 9 June 2011

Vattenfall Q results

MYPD Methodology Eskom Response to Consultation Paper

RCAs submitted for FY2014/15, FY 2015/16 and FY 2016/17. NERSA Public Hearings 17 April 2018

Statkraft Investor Update. European Energy & Utilities Credit Conference 2013

H results. innogy SE 11 August 2017 Bernhard Günther CFO

Origin Energy. Macquarie Australia Conference. Frank Calabria, CEO 1 May 2018

Analyst and investor conference Repower's market environment and positioning

Electricity blackouts in South Africa: proximate and ultimate causes & recommendations for the future

Financial Report. CHUBU ELECTRIC POWER COMPANY, INCORPORATED (April 28, 2015) Stock Code: 9502

ASX Release. 4 December 2008 PRESENTATION FOR INVESTOR ROADSHOW

Q4/17 Analyst Conference Call

Vattenfall Q2 and H1 results 2015

Financial results for the year ended December 2013

Recurring EBITDA: 1,902m, -5% YoY 62% decline YoY of hydro production in Iberia: 42% below historical avg. in 1H17 vs.

BOARD MEETING. Knoxville, Tennessee. August 21, 2014

FINANCIAL RESULTS Q CFO Irene Egset 4 th May 2017

BUSA presentation to NERSA on Eskom s RCA Application Multi Year Price Determination (MYPD3) Year 1 (2013/2014) 5 February 2016

Long-Term Reliability Assessment

+0.6GW additions of wind and solar capacity Efficiency savings of 141m (26% above 2017 target for OPEX IV Programme)

INTERIM RESULTS PRESENTATION. for the six-month period ended 30 June 2017

Vattenfall Q3 and 9M 2012 results

Half Year Results 2018/19. 8 November 2018

Recurring (1) EBITDA -4% YoY to 911m Renewables and Brazil underlying growth offset by forex (-6%) and regulatory changes in Portugal (- 66m YoY)

Investor Conference Call FY March 2018»

Portland General Electric

RAINMAKER ENERGY. Comments to 2011 NERSA REFIT Review Tariffs

Vattenfall Full Year 2011 results

A Rational Price Path for South Africa

Vattenfall Q2 results 2011

Title of presentation

GLOBAL POWER SECTOR REFORM AND THE CASE FOR REFORM IN SOUTH AFRICA

Vattenfall Capital Markets Day 2009

Endesa 9M 2017 Results 07/11/2017

Margins(%) EBITDA 30.0% 26.3% 25.4% NPM 26.5% 12.5% 18.1%

Public Power Corporation SA. Financial Results Athens, March 30, 2010

Eskom Holdings SOC Limited. Standard Presentation July 2014

TVA BOARD MEETING AUGUST 22, 2013

Korea South-East Power Co., Ltd. Annual Ratings Review

Results Presentation Six month period ended 31 December 2010

2018 Interim Financial Results 24 July 2018

Financial Report. CHUBU ELECTRIC POWER COMPANY, INCORPORATED (April 26, 2013) Stock Code: 9502

Fixed Income Investor Update. innogy SE November 2016

Transcription:

Investor Presentation Cover slide (same as IR cover)

Contents Eskom at a glance Financial review Operational review Design-to-Cost RCA High Court Decision Funding overview Progress on the new build programme 2

Eskom at a glance 27 operational coal power stations with generating capacity of 45GW as 31 March 2016 2 operational nuclear reactors (Koeberg) with a generating capacity 0.18GW Hydro Eskom Generation Capacity 31 March 2016 10.9GW of new generation capacity (Medupi, Kusile and Ingula) being built, completion expected by FY2022, of which 1.2GW is Pumped Storage Coal already commissioned As at 31 March 2016 : FY2016 Capex spend of R57.4 billion 5 688 640 customers (31 March 2015: 5 477 602) Nuclear 1.4% 3.3% 4.4% 5.6% 45GW of nominal capacity 85.1% 47 978 employees, inclusive of fixed-term contractors, in the group (31 March 2015: 46 490 ) Sizeable assets of R661 billion Gas Credit Ratings 31 March 2016 Topline Figures Eskom Eskom Stand Alone Revenue EBITDA Net Profit Moody s: Ba1 / Negative Moody s : b3 R163.4bn R32.0bn R4.6bn S&P : BB+ / Negative S&P : ccc+ (10.6% increase) (37.4% increase) (>100%) 3

Improved financial performance Revenue (R bn) 2015/2016 EBITDA (R bn) 2015/2016 Profit (R bn) 2015/2016 165 160 155 150 145 140 11% 163 35 37% 32 5 >100% 30 25 23 4 20 3 148 15 2 10 5 1 0.2 0 0 2015 2016 2015 2016 2015 2016 BPP savings: R17.5 billion (target R13.4 billion) Key financial ratios 2015/2016 4.6 Interest cover ratio Debt service cover ratio Debt / equity Gross debt / EBITDA 0.6 0.5 0.4 0.3 0.27 0.55 1.1 1.1 1.0 1.0 0.92 1.07 3.0 2.5 2.0 1.5 2.53 1.67 20.0 15.0 10.0 16.1 11.4 0.2 0.1 0.9 0.9 1.0 0.5 5.0 0 2015 2016 0.8 2015 2016 0.0 2015 2016 0.0 2015 2016 4

Overall electricity sales volumes International sales volume growth of 12.2% due Eskom having surplus capacity Increase in commercial (5.2%), agriculture (6.1%), mining (2.1%) and residential (2.9%) sales volumes Decline in municipalities (1.6%), rail (7.9%) and industrial (6.2%) sales volumes Overall electricity sales volumes declined by 0.8% Electricity volumes % growth/(decline) & contribution -10% -5% 0% 5% 10% 15% Contribution Redistributors (1.6%) Residential 2.9% Commercial 5.2% Industrial (6.2%) Mining 2.1% Agriculture 6.1% Rail (7.9%) International 12.2% Total (0.8%) 41.8% 5.6% 4.7% 23.4% 14.3% 2.7% 1.2% 6.3% Electricity debtors age analysis (R m) Total Within due date < 60 days overdue > 60 days overdue Large power users, excluding municipalities 6 913 6 250 246 417 Large power users, municipalities (including interest) 11 325 5 320 932 5 073 Small power users 2 576 1 465 178 933 Soweto (excluding interest) 4 746 189 179 4 378 Other customers 1 534 846 680 8 Total at 31 March 2016 27 094 14 070 2 215 10 809 % of total 100% 52% 8% 40% 5

Primary energy costs analysed 2% YoY increase only 2015/16 Primary energy cost analysis Year-on-year analysis 18% % of cost % of production 4% R billion R83.4 4% 4% 4% 4% R6.0 4% (R9.5) 78% 92% 92% 78% 2014/15 Primary energy cost analysis (R0.9) 4% 12% % of cost 4% 4% % of production 3% 4% R5.7 R0.3 4% (R0.2) R84.7 Eskom generation Independent power producers 84% International purchases 92% 78% 93% 6

1 As of 20 September 2016 Key Operational Performance There has been no load shedding for more than year Generation has achieved EAF of 78.3 % for month of August vs a Q2 target of 75 % Ingula 2 commercial operation on 22 August 2016 Relative particulate emissions of 0.29 kg/mwhso vs target of 0.35 kg/mwhso for August 2016 Generation continues to strive for zero harm. Current performance is 0.16 employee LTIR rate year-to-date vs a target of 0.3 No Eskom diesel was used for the month of August. Last time it was used was in June 2016 for commissioning activities after dual fuel conversion Koeberg Unit 1 has been online for 456 days as at 31 August 2016, exceeding its previous record In August 2016, Matimba Power Station achieved 1000 LTI free days and Tutuka Power Station achieved one million LTI free contractor man-hours

Update on New Build Medupi Unit 5 achieved all seven of the principal milestones for 2016. Commercial operation of Unit 5 is planned within the first half of 2018, based on the P80 schedule. Unfortunately a fatality was recorded on 5 July 2016, when a worker fell from the 63m level on Unit 3 to ground level. The incident is under investigation Kusile Kusile Power Station continues to achieve set milestones on the path for Unit 1 commercial operation in the second half of 2018, based on the P80 schedule The new control and instrumentation (C&I) contractor, mobilised in 2015, has delivered the engineering and manufacturing of equipment within tight schedules, to ensure integration with other packages lngula Units 2 and 1 were synchronised on 21 May and 16 June 2016 respectively, ahead of the P80 schedule. Unit 4 was commissioned on 10 June 2016, adding 333MW to the national grid Ingula Unit 3 was synchronised on 3 March 2016. However, during the commissioning and optimisation of the unit by the contractor, an unfortunate incident occurred on 6 April 2016, when the unit faulted and was damaged. Repairs on the unit are progressing well; the unit is on track for commercial operation as planned by the end of the financial year

We remain focused on bringing new capacity online P80 dates CO = Commercial Operation CO in Mar 2015 CO in Aug 2015 CO achieved in Jun 16 CO achieved in Aug 16 CO by Jul 2018 100 794 333 333 800 Mar 2015 Sere Wind Farm Aug 2015 Medupi Unit 6 Jun 16 Ingula Unit 4 Aug 2016 Ingula Unit 1 Jul 2018 Kusile Unit 1 5 020MW Mar 2015 Majuba recovery Jan 2017 Ingula Unit 3 Aug 2016 Ingula Unit 2 Mar 2018 Medupi Unit 5 1200 333 333 794 600MW from Unit 3 gap solution in Feb 2015 600MW from Unit 4 in Mar 2015 CO by Jan 2017 CO achieved in Aug 16 CO by Mar 2018 Completion of Duvha Unit 3 recovery expected during 2020 and will add 600MW to the national grid 9

Other Issues Update on Tegeta Prepayment queries have been addressed however additional information has been requested, which Eskom is busy compiling, on all coal quality tests done from 10 June 2014 to 31 March 2015 National Treasury Review of Contracts National Treasury has issues a number of procurement guidelines where SOC s are required to provide information and obtain approval prior to placing contracts and for deviation from existing contracts RCA Court Case Ruling There are a number of instances where the judge in our view clearly erred. With respect, the judgment is poorly reasoned and open to a number of attacks on appeal which is being carefully considered by Eskom s legal team on appeal. Futuregrowth Awaiting FGA feedback wrt to NDA and the associated questions they would like to have addressed, following engagements on 1 & 15 September 2016

High court decision RCA 2013/14 : Options The decision of the High Court has been considered to: Determine what options are available to Eskom Determine the impact on Eskom liquidity and contingency plans to address the potential liquidity gap 1. Implement court decision RCA 2013/14 cash at risk R11bn Decision is set aside, and remitted to NERSA NERSA reviews decision and either upholds R11bn decision or decides to lower RCA amount or make zero Any adjustment to revenue will be adjusted in 2017/18 price increases no impact on liquidity for 2016/17 Nersa awarded Eskom for RCA 2013/14 R11bn, 9.4% RCA 2014/15 and RCA 2015/16 cash at risk +- R20bn x2 Both RCAs will face same arguments for appeal Decision is all future RCAs the court order is dated 16 August 2016 Does the order apply retrospectively or going forward Eskom can request condonation for the quarterly reports NERSA would need to provide reasons for approving condonation and then process the applications 2. Appeal decision RCA 2013/14, RCA 2014/15 and RCA 2015/16 NERSA appeals decision, supported with an Eskom appeal Effectively suspends the decision on 16 August 2016 Eskom and NERSA continue with RCA implementation Awaits the appeal decision, which will take not less than 6 months Stakeholders will challenge process of the other two RCA s on the same weakness as the 2013/14 RCA Eskom s response Eskom has submitted quarterly reports since September 2015 and will submit the outstanding quarterly reports for MPYD3 by 24 August Support NERSA in their appeal process Devised liquidity response plan for the worst case scenario to provide additional liquidity of R50bn Submit MYPD4 by 1 April 2017 to mitigate and possibility recover any amounts not recovered via RCA process. 1 1

Design-to-Cost: Key strategic drivers Increase the energy availability factor ( EAF ) from 70% to 80% by FY20/21 Deliver the New Build programme (Ingula March 2017 / Medupi May 2020 / Kusile by September 2022) Drive cost containment effort (primary energy, manpower and other external spend) Strategic Objectives Ensure regulatory and legal compliance Deliver on the South African Government s strategic objectives (transformation, IPPs and other key initiatives targets) Continually improve performance in the short term Ensure revenue certainty through regulatory mechanism (RCA) and preparation for the tariff period starting 1 April 2018 (MYPD4) Stretch the balance sheet in the short term, while establishing long term stability Revenues Submit early MYPD4 by applying for a 3-year determination and a further 2-year indication Target price increase of c. 10 13% p.a. over last two years of MYPD3 and 13 19% during first three years of MYPD4 Key Drivers Opex Optimise manpower costs through headcount reductions Reduce external spend on major commodities by at least 10% Ensure primary energy cost escalation is no higher than 8 12% for own production Capex Future Fuel (coal and nuclear) Transmission (strengthening and refurbishments) Distribution (IPP connections, refurbishments, electrification) Generation (outage, technical plans) GCD new build programme completion Total capex spend FY17-FY21 R12.3bn R27.6bn R36.0bn R64.9bn R155.6bn R339bn 12

Design-to-Cost forecast to deliver strong EBITDA growth of 27% p.a. until FY21, driven by strong cost containment efforts Income statement R bn, FY16 - FY26 Revenue Primary energy expense Operating Cost EBITDA 162 85 69 26 180 95 108 118 125 136 144 79 29 204 85 231 92 264 36 49 73 292 89 323 107 357 154 128 394 168 147 432 476 179 192 98 102 111 118 126 134 141 170 198 CAGR FY16-21 FY21-26 12,6% 10,2% 9,8% 7,1% 8,1% 6,7% 27,4% 17,4% Key drivers Successful outcome of RCAs Delivery of maintenance within budget, an additional R1,8 bn p.a. Impact from Primary Energy, Manpower and Commercial savings programme Net Profit After Tax 1,0 Surge in financing and depreciation costs impact net profits in short term -3,9-4,6-8,4-1,1 3,1 9,0 From FY21 onwards Eskom will rally on higher net profits 20,0 29,2 41,0 60,5 24,7% 81,5% FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 Forecasts based on internal Eskom assumptions and model outputs 13

Plan will deliver improvement in financial ratios over the 10-year period Key Ratios %, 2016 2026, R bn Debt / Equity 1.7 2.4 3.0 3.7 4.1 4.1 4.0 3.6 3.1 2.4 1.7 FFO/Debt 10.5 8.2 8.4 10.2 13.5 16.0 18.4 20.6 23.2 26.2 31.2 EBITDA Margin, % DSCR 1 20% 1.1 16% 17% 20% 27% 30% 32% 35% 37% 39% 41% 1.6 1.5 1.0 0.9 1.2 1.3 1.5 1.1 0.8 0.7 Key to delivering the forecast ratios is ensuring CAPEX over the period is phased: Eskom can sustain CAPEX of R339 bn in the first 5 years and R394 bn in the last 5 years Cash Interest Cover 1.7 1.7 1.4 1.5 1.9 2.1 2.4 2.8 3.2 3.7 4.8 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 1 Debt Service Coverage Ratio Forecasts based on internal Eskom assumptions and model outputs 14

Group capital expenditure per division R Billion, Percentage of Spend, FY16/17-FY25/26 Subsidiaries Other Environmental Future Fuel Tx Dx Gx GCD 339 394 1% 1% = 100% Future Fuel (R12.3bn) Coal and nuclear Transmission (R27.6bn) Strengthening and refurbishments Distribution (R36.0bn) Refurbishments Electrification Generation (R64.9bn) Outage Technical plans 9% 2% 4% 8% 11% 19% 20% 5% 7% 25% Environmental (R21.2bn) EMS compliance Transmission (R99.1bn) IPP Connections Grid Safety Compliance 14% Distribution (R56.7bn) Electrification GCD (R155.6bn) New Build programme completion (Medupi, Kusile, Ingula) 46% FY16/17-FY20/21 15% 12% FY21/22-FY25/26 Generation (R59.6bn) Outages Technical Plan GCD (R48.7bn) Medup FGD Kusile Ash Dump 1 5

Funding and capital plan to deliver the Design-to-Cost over the next 5 years R bn Funding required 68.5 68.7 68.1 68.4 53.3 Key principles Increases in costs above inflation require business case Capex FY17 FY18 FY19 68.0 72.0 76.0 FY20 69.0 FY21 54.0 Alternative funding models for new capacity and business Overall CAPEX has been defined to deliver target year end cash-flow and support improvement of key ratios FY17 FY18 FY19 FY20 FY21 Delivering the plan will require R327bn of funding over the next 5 years and capital spend will total R339bn over the next 5 years Eskom funding levels are considered healthy, based on expected long term cash improvement 16

Eskom s funding plan FY2016/17-2020/21 To date Eskom has secured 75% of the required funding for FY2016/17 FY16/17 FY17/18 FY18/19 FY19/20 FY20/21 Total Committed and Signed DFI Financing 29 216 11 418 14 930 7 103 0 62 667 ECA Financing 7 307 2 265 5 161 1 847 0 16 580 Structured Products 1 750 2 214 2 930 3 472 3 312 13 678 CPBS 2 000 0 0 0 0 2 000 Domestic Bonds 11 388 0 0 0 0 11 388 Total: Committed and Signed 51 661 15 897 23 021 12 422 3 312 106 313 75% 23% 34% 18% 6% 32% Signed Documention Domestic Bonds 5 773 8 000 8 000 8 500 10 000 40 273 International Bonds GMTN 0 5 500 7 000 12 000 0 24 500 CPBs 4 000 6 000 7 500 8 500 10000 36 000 Total Signed 9 773 19 500 22 500 29 000 20 000 100 773 14% 28% 33% 42% 38% 31% Currently under Negotiation DFI Financing 6 000 30 020 20 000 25 500 0 81 520 ECA Financing 1 373 3 263 2 613 1 428 0 8 677 Structured Products 0 0 0 0 30000 30 000 Total Under Negotiation 7 373 33 283 22 613 26 928 30 000 120 197 11% 48% 33% 39% 56% 37% Total 68 808 68 680 68 134 68 350 53 312 327 284

2017 2019 2021 2023 2025 2027 2029 2031 2033 2035 2037 2039 2041 2043 2045 2047 2049 2051 Funding plan considers current debt maturity profile and level of Government Guarantee utilisation Strategic and Trading Portfolio Nominal and Interest Cashflows (including Swaps) as at 31 March 2016 Eskom Government Guarantee Utilisation R bn as at 31 March 2016 60 350 50 40 Interest Capital 218 30 20 132 10 102 30 - Total value Committed Available Under negotiation Remaining available Eskom s current debt maturity profile of the R315 bn total debt extends to 2043 with frequent maturities occurring in 2017 through to 2043 Maturities consist of the various local and international funding sources In line with the Borrowing Programme, longer term funding is required to support the near term debt maturities and alleviate debt repayment pressure Currently committed guarantees include the R150bn DMTN programme, and R67,5bn committed to existing DFIs Amount approved for guarantee utilisation includes transactions under negotiation that require Guarantees to secure the funding Eskom will continue to leverage its available government guarantees to maximise funding options 18

End