Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

Similar documents
Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

Value for Money Analysis: Choosing the Best Project Delivery Method. Ken L. Smith, PE, CVS -HDR Engineering, Inc.

CRAVE. Cost Risk Assessment + Value Engineering. CSVA 2011 Conference Toronto, Ontario Nov 14-16, Ken L. Smith, PE, CVS

Project Risk Management

LCS International, Inc. PMP Review. Chapter 6 Risk Planning. Presented by David J. Lanners, MBA, PMP

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

Fundamentals of Project Risk Management

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

Project Theft Management,

Managing Project Risk DHY

Project Management Certificate Program

Chapter-8 Risk Management

Best Practices in Project Risk Management. Presented by: Jeff Miller, PMP - Director of Project Management Interstates Control Systems, Inc.

Presented to: Eastern Idaho Chapter Project Management Institute. Presented by: Carl Lovell, PMP Contract and Technical Integration.

RISK MANAGEMENT ON USACE CIVIL WORKS PROJECTS

Risk Management Process-02. Lecture 06 By: Kanchan Damithendra

Information Technology Project Management, Sixth Edition

Risk Management Plan for the <Project Name> Prepared by: Title: Address: Phone: Last revised:

Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule

METHODOLOGY For Risk Assessment and Management of PPP Projects

Every project is risky, meaning there is a chance things won t turn out exactly as planned.

Risk Management Made Easy. I. S. Parente 1

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017

Project Management for the Professional Professional Part 3 - Risk Analysis. Michael Bevis, JD CPPO, CPSM, PMP

AACE International 48th Annual Meeting Washington, DC June 2004 DEVELOPING & MANAGING CONTIGENCY ON THE BASIS OF RISK. Robert Tichacek, P.E.

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

RISK MANAGEMENT PROFESSIONAL. 1 Powered by POeT Solvers Limited

Managing Project Risks. Dr. Eldon R. Larsen, Marshall University Mr. Ryland W. Musick, West Virginia Division of Highways

RISK ANALYSIS GUIDE FOR PRIVATE INITIATIVE PROJECTS

SCAF Workshop Integrated Cost and Schedule Risk Analysis. Tuesday 15th November 2016 The BAWA Centre, Filton, Bristol

Risk Assessment of the Niagara Tunnel Project

UPDATED IAA EDUCATION SYLLABUS

Risk Video #1. Video 1 Recap

The Risky Business of. Risk Management

MINI GUIDE. Project risk analysis and management

RISK ANALYSIS AND CONTINGENCY DETERMINATION USING EXPECTED VALUE TCM Framework: 7.6 Risk Management

RISK MANAGEMENT MADE EASY. Susan Parente Project Management Symposium.

Project Risk Management

Learning Le cy Document

Enterprise Risk Management Integrated Framework

Probabilistic Benefit Cost Ratio A Case Study

CONTINGENCY. Filed: EB Exhibit D2 Tab 2 Schedule 7 Page 1 of 10

Objectives. What is Risk? But a Plan is not Reality. Positive Risks? What do we mean by Uncertainty?

Risk Management Guideline July, 2017

Applying COSO s Enterprise Risk Management Integrated Framework. September 29, 2004

RISK M A N A G E M E N T P L A N

Download slides on SEO Südwest

Offshore & Marine Projects and Risks Management

Poor Man s Approach to Monte Carlo

Learning Objectives. Manage Your Project Risks Like a Pro! 10/16/2015

for Major Infrastructure Projects

Welcome! A Critical Tool of the Project Manager. What People Are Doing 9/15/2016. Risk Management A Critical Tool

Applying COSO s Enterprise Risk Management Integrated Framework

Risk Management Made Easy 1, 2

Programmatic Risk Management in Space Projects

The Evolution of Risk Management and The Risk Management Process

CEVP Cost Estimate Validation Process

Running Head: RISK MANAGEMENT PLAN 1

RISK MANAGEMENT STANDARDS FOR P5M

A Study on Risk Analysis in Construction Project

Adaptation Assessment: Economic Analysis of Adaptation Measures

Project Management. A Practitioner s Guide. Steven M. Bragg

What is Risk Management? Phil Barnes Assistant Director Office of Policy Analysis, Research, & Innovation (PARI)

Risk Management Relevance to PAS 55 (ISO 55000) Deciding on processes to implement risk management

Haeryip Sihombing 1. Risk. Risk Management

EFFECTIVE TECHNIQUES IN RISK MANAGEMENT. Joseph W. Mayo, PMP, RMP, CRISC September 27, 2011

Indicate whether the statement is true or false.

Risk vs. Uncertainty: What s the difference?

Risk-Based Project Management Approach for Large- Scale Civil Engineering Projects

Project Management. Managing Risk. Clifford F. Gray Eric W. Larson Third Edition. Chapter 7

Project Management Professional (PMP) Exam Prep Course 11 - Project Risk Management

The Basics of Risk Management

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Introduction to Life Cycle Risk Management Glossary

Risk Management for Tunnel Planning, Design and Construction

Introduction to Risk for Project Controls

Understanding the Results of an Integrated Cost/Schedule Risk Analysis James Johnson, NASA HQ Darren Elliott, Tecolote Research Inc.

Risk Manage Manag ment men & the PMBOK John H. Dittmer, VI PMP, PMP CISSP CISSP ISSMP

RISK MANAGEMENT LECTURE 5. Ahmed Elyamany

Federal Transit Administration United States Department of Transportation Washington, DC 20590

CONSTRUCTION ENGINEERING & TECHNOLOGY: EMV APPROACH AS AN EFFECTIVE TOOL

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett

ISO/IEC INTERNATIONAL STANDARD. Information technology Security techniques Information security risk management

RISK-BASED, PROBABILISTIC COST ESTIMATING METHODS

Master Class: Construction Health and Safety: ISO 31000, Risk and Hazard Management - Standards

Project Management Professional (PMP) Exam Prep Course 06 - Project Time Management

Prince2 Foundation.exam.160q

Risk Management: Principles, Methodologies and Techniques. Peter Getugi Internal Audit Manager ILRI

Enterprise Risk Management (ERM)

Crowe, Dana, et al "EvaluatingProduct Risks" Design For Reliability Edited by Crowe, Dana et al Boca Raton: CRC Press LLC,2001

Risk Management: Assessing and Controlling Risk

Achieving Predictable Projects. In a World of Black Swan Risks

Project Cost Risk Analysis: The Risk Driver Approach Prioritizing Project Risks and Evaluating Risk Responses

Risk Management Plan

CRISC. Isaca CRISC Certified in Risk and Information Systems Control Version: 1.0

EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY INTRODUCTION

Presented by Kristina Narvaez President & CEO ERM Strategies, LLC

Электронный архив УГЛТУ

Transcription:

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS 360-570-4415 2015 HDR, Inc., all rights reserved.

Addressing Cost and Schedule Concerns Usual Questions Analysis Needs How much will it cost? How long will it take? Why does it cost that much? Why does it take that long? Risk Identification Qualitative and Quantitative Risk Analysis Value Engineering &Mitigation Strategies Risk Monitoring & Control 2

Comparison of the two processes Both use a team approach Cost Risk Assessment Learn about project Identify Risks Strategize how to handle Qualify and Quantify Develop response plans and triggers Value Engineering Investigate Functional analysis Speculate Evaluate Develop 3

Risk Management Process Step 1: Cost Risk Assessment Base cost review, identification and quantification of cost and schedule risks Financial Planning Step 2: Risk Response Development of risk response strategies and alternative solutions (Value Engineering) Decision Support Step 3: Monitor and Control Continuous risk tracking, monitoring and reporting Risk Allocation 4

Process 5

Accounting For Uncertainty? An Estimate is not a Single Number Projects are subject to many variables that cannot all be known beforehand Cost and schedule estimates represent just one of many possible outcomes of multiple variables Top of the shoulders Top of the Pant Line Below the Knee Cap Midpoint These variables are not all directly controllable or absolutely quantifiable A strike zone is not a single point. 6

Overview of Project Cost Base cost estimate serves as the basis against which cost risks and uncertainties are assessed Estimating is not an exact science: Cost estimate is only an approximation of the probable costs Composed of many elements that may not be completely or equally defined at the time the estimate is prepared A numerical value of uncertainty is an estimate of the error or tolerance within the quantity or unit price of an item. Level of uncertainty is directly related to its position in the project life cycle Planning Stages Design Stages Construction Stage Project Life Cycle Actual Cost Project Completion 7

Traditional Estimate Vs. Risk Based Estimate Fixed Contingency % Utility Stakeholder Construction Project Deterministic Estimate Design Project Base Cost Environmental Funding ROW 8

Project Cost 9

Base Cost Review Review base cost estimate Identify and remove any contingency and escalation from the estimate o Contingency will be replaced by events risk o Escalation will be reapplied in the risk analysis model Assign preliminary uncertainty ranges around key items within the estimate prior to the workshop. Outcomes from the base cost review will be reviewed and finalized during the workshop. 10

Building Risk Analysis Backbone (Schedule) Activity B Start Activity A Activity D Activity C $ } End For Each Task 11

12

Consensus-Based Workshops Structured Workshops to Build Consensus Among Various Stakeholders Engagement of Internal and External Subject-Matter Experts Sessions by Functional Assignment to: Identify Risks Quantify Risks Discuss Risk Response and Mitigation Strategies 13 13

Identifying Event Risks Focus on issues that matter Describe the event properly How likely is it to occur? What are the potential impacts (cost/schedule)? If the event occurs what are the impacts on the low end? on the upper end? most likely? Is the event dependent on or correlated with other events 75% Probability 14

What is Monte Carlo? Monte Carlo Analysis: A class of computational algorithms that rely on repeated random sampling to compute or iterate the project cost or schedule many times using input values selected at random from the probability distributions of possible costs or durations, to calculate a distribution of possible total project cost or completion dates. SOURCE: PMBOK Third Edition Or Production 1970 1972 Chevrolet Body style 2-door coup 15

How the Modeling Works Monte Carlo Simulation Quantities Project Schedule Risks Event Risk Environmental Permitting Right of Way o Base cost and uncertainties o Cost Event Risks o Schedule Event Risk Utilities Civil Design Hydrology Geotechnical Structures Materials Prices Project Cost Risks Contracting Schedule Making the black box transparent Construction Maintenance Operations Funding Market Conditions Management & Stakeholders 16

Contractors don t take risks, they price them! Source: http://mcgladrey.com/eclubnews/change-orders-outsize-construction-contracts 17

Baseline Risk Assessment Results Using VE to Mitigate 18

Risk Management Risk Assessment s aim is to assess potential impact of various scope, event, and budget risks on the project s cost and schedule. Risk Management s aim is to identify mitigation strategies to reduce both the likelihood of a threat event occurrence and the potential effect if it occurs AND to identify strategies to increase the both the likelihood of an opportunity event occurrence and the potential benefits if it occurs Impact INITIAL RISK MANAGED RISK Probability of Occurrence 19

Risk Response From the tornado diagrams we will define response strategies (how to respond to the risk) o Include how will be communicated in the contract documents These will assist the design team on how to respond to risks as the project progresses. 20

Develop Risk Response Strategies Threats Risk Factors that Increase Cost or Schedule Avoid: Change the project scope to eliminate the impact of a risk. Opportunities Risk Factors that Reduce Cost or Schedule Exploit: To make a proactive decision to take action to show that an opportunity is realized. Transfer: Move a risk to another party who is more capable at handling the risk (such as the developer or insurance company). Share: Assigning ownership of the opportunity to a third-party who is best able to capture the benefit for the project. Mitigate: The project team may seek to lessen the impact of a specific risk item, which may involve the consumption of additional time and/or money. Mitigation usually requires positive action and has a cost. Enhance: Take action to increase the probability and/or impact of the opportunity for the benefit of the project; seeking to facilitate or strengthen the cause of the opportunity, and proactively targeting and reinforcing its trigger conditions. Accept: To take no action when a response may be too costly to be effective or when the risks are uncontrollable and no practical action may be taken to specifically address it. In active acceptance, the project team sets up a contingency reserve fund to account for the residual expected value of the remaining risks. 21

Analysis of Results Risk Reserve Mitigation Savings $7.07M Total: $86.39 22

Program Risk Management 24

Risk Management System tool Used as a tool to proactively manage risk in the delivery of a program of projects The tool allows for the capture and storage of risk data for both pre-response and post-response scenarios Visual displays of risk impact versus risk likelihood demonstrate the risks relative impact to budget and schedule Generates reports for individual Projects and for entire Programs 25

Identification and Quantification Response Strategies Monitor and Control 26