ELECTRICITY BALANCING IN EUROPE

Similar documents
Table of Contents List of Figures...3 List of Tables...3 Definitions and Abbreviations...4 Introduction...7

UPDATE ON ELECTRICITY BALANCING

ENTSO-E Network Code on Electricity Balancing

The Concept of Baltic CoBA

Content Abbreviations Article 1 Article 2 Article 3 Article 4 Article 5 Article 6 Article 7 Article 8 Article 9 Article 10 Article 11 Article 12

16 July 2018 DRAFT VERSION for public consultation

ACTIVATION PURPOSES BSG. 7 March 2017

Baltic Harmonised Imbalance Settlement Model Document

Baltic Harmonised Imbalance Settlement Model Document

Content Abbreviations Article 1 Article 2 Article 3 Article 4 Article 5 Article 6 Article 7 Article 8 Article 9 Article 10 Article 11 Article 12

ENTSO-E recommendations for Market Design Trilogue negotiations

ELIA LFC Block Operational Agreement

Explanatory document for the Nordic synchronous area proposal for limits for the exchange of FCR between the TSOs in accordance with Article 163(2)

COMMISSION REGULATION (EU) NO. 543/2013. Article 17.1.a: Rules on Balancing

Balancing & Intraday Markets. Markus Riegler Berlin,

P344 Project TERRE implementation into GB market arrangements

ANCILLARY SERVICES TO BE DELIVERED IN DENMARK TENDER CONDITIONS

Introduction. 1.1 The CACM Regulation & all TSOs. 1.2 Geographical application of this proposal

18 April 2016 Draft for consultation

APPROVAL BY ALL REGULATORY AUTHORITIES AGREED AT THE ENERGY REGULATORS FORUM

All NEMOs proposal for the price coupling algorithm and for the continuous trading matching algorithm, also incorporating TSO and NEMO proposals for

Status quo: Network Codes and Guidelines from NRAs perspective. Dace Bite Public Utilities Commission of Latvia Deputy Director of Energy Department

CROSS BORDER CAPACITY ALLOCATION FOR THE EXCHANGE OF ANCILLARY SERVICES

All TSOs response to the consultation on the Intraday Cross-Zonal Gate Opening and Gate Closure Times

Response to ENTSOE public consultation. Network Code on Capacity Allocation and Congestion Management for. Electricity

REQUEST FOR AMENDMENT BY ALL REGULATORY AUTHORITIES AGREED AT THE ENERGY REGULATORS FORUM ON

LFCR code update for JESG, May 2013

Intraday Cross-Zonal Gate Opening and Gate Closure Times. Consultation document. PC_2018_E_01 9 January 2018

Capacity Allocation and Congestion Management (CACM) Code Overview

Quick Guide to the Integrated Single Electricity Market. Version 1


CID Methodology Explanatory note

APPROVAL BY ALL CONCERNED CCR HANSA AUTHORITIES

XBID Information Package Published February 2018 Updated December 2018

Terms and Conditions related to Balancing

The Model of Implicit Capacity Allocation in the Baltic States

***I DRAFT REPORT. EN United in diversity EN. European Parliament 2016/0379(COD)

All CE TSOs proposal for additional properties of FCR in accordance with Article 154(2) of the Commission Regulation (EU) 2017/1485 of 2

Energinet.dk s proposal for Arrangements concerning more than one NEMO in one bidding zone in accordance with Article 45 and 57 of the Commission

DK1-DE COUNTERTRADE MODELS IMPACT ASSESSMENT

MARI Project. BSG meeting 7/12. Manually Activated Reserves Initiative - Creating a European platform for the exchange of mfrr balancing energy

MARI. Project in a Nutshell and Accession Conditions. Manually Activated Reserves Initiative. BSG Meeting 07/06/2017

Proposal for Multiple NEMO Arrangements (MNA) for the Belgian bidding zone in accordance with Article 45 and Article 57 of the Commission Regulation

Report on Proposed principles for Common Balance Management

We appreciate your feedback

DS3 System Services Protocol Interim Arrangements

Regulatory framework for crossborder redispatching and countertrading

HEnEx s Spot Markets Trading Rulebook: Intra-Day Market Operations

Marcel Cailliau, GDF Suez (Electrabel)

C2-102 COMMON NORDIC BALANCE MANAGEMENT. K.LINDSTRÖM FINGRID (Finland)

Mr Alberto Pototschnig, Director ACER. CC: Dr Klaus-Dieter Borchardt, Director Internal Energy Market DG ENER European Commission

ACER ON ALL TRANSMISSION SYSTEM OPERATORS PROPOSAL FOR INTRADAY CROSS-ZONAL GATE OPENING AND INTRADAY CROSS-ZONAL GATE CLOSURE TIMES

FORTUMS RESPONSE TO ACER CONSULTATION ON FORWARD RISK-HEDGING PRODUCTS AND HARMONISATION OF LONG-TERM CAPACITY ALLOCATION RULES

Info Session NWE Day-Ahead

IGCC Participation Elia

13 th February th February 2017 Page 1 of 7

The implementation of the Electricity Target Model in Greece. Angeliki D. Mourtzikou Director of Markets Monitoring and Competition, RAE

Cross-Border Exchange and Sharing of Generation Reserve Capacity

February February 2017 Page 1 of 12

15 MINUTES IMBALANCE SETTLEMENT PERIOD MARKET IMPACTS OF LATE IMPLEMENTATION Final report. June 15, 2018

Joint European Standing Group Meeting 29

GB TSOs Intraday proposal for arrangements concerning more than one Nominated Electricity Market Operator (NEMO) in the GB Bidding Zone in accordance

The TSO side of pan-european XBorder trading in high frequencies: The Role of Scheduling. Michael Schaefer Project Manager, Amprion System Operation

7 April ENTSO-E AISBL Avenue de Cortenbergh Brussels Belgium Tel Fax www. entsoe.

Anders Plejdrup Houmøller 10 May Wholesale market models and the role of exchanges and traders. Prepared by Anders Plejdrup Houmøller

ISO Tariff Original Sheet No. 637 ISO TARIFF APPENDIX L. Rate Schedules

According to article 9 (8) (d) of Regulation 2015/1222 the proposal is subject to approval by each national regulatory authority.

Prague, 25/09/ M Market Coupling

Draft Report (Ontwerpverslag/Project de rapport)

OPERATING PROPOSAL FOR THE INTRADAY MARKET IN MIBEL

TSOs perspective of the CACM requirements. Athanasios Troupakis Market Advisor ENTSO-E

Harmonised Allocation Rules for Forward Capacity Allocation Summary of the assessment of the comments from the public consultation

ALL TRANSMISSION SYSTEM OPERATORS OF THE CAPACITY CALCUCULATION REGION CORE, TAKING INTO ACCOUNT THE FOLLOWING: Whereas

NWE Info Session. Operational & contractual changes for Dutch wholesale market organization

The new electricity market arrangements in Ukraine

Intraday Cross Border The Netherlands-Belgium

Intraday Implicit Cross- Border allocation on BE-FR border. Description of the allocation mechanism

Draft Outline of the 2019 Work Programme

SEMO PX MARKET DESIGN

Intraday Implicit CrossBorder allocation on BE-NL. and borders (Interim Implicit Cross Border Intraday BE-NL. Description of the allocation mechanism

COMPARISION OF OFFSHORE REQUIREMENTS

Nordic Market Design Forum Feasibility study. Final report. September 2017

Regional Flow-based allocations. State-of-play

Intraday Cross Border The Netherlands-Belgium

Cross-Border Intraday: Questions & Answers

THE MONITORING REPORT FROM 16 MARCH 2018 ON THE IMPLEMENTATION OF THE JOINT DECLARATION

We appreciate your feedback

Evaluation of responses to the public consultation on the proposal for pricing intraday cross-zonal capacity

Joint European Stakeholder Group. Tuesday 23 February 2016: Meeting 10

Capacity Calculation Region Nordics regional design of long-term transmission rights in accordance with Article 31 of the Commission Regulation (EU)

Specific Annex for the Bidding Zone borders serviced by SEE CAO to the Harmonised Allocation Rules for long-term transmission rights

METIS Technical Note T3. Market module configuration for study S12. Focus on day-ahead, intraday and balancing markets

Wholesale power market challenges:

Business Process. BP_SO_13.1 Interim Long-Term Coordinated Capacity Calculation

The North Seas Countries Offshore Grid Initiative

(Text with EEA relevance)

Proposal of the Transmission System Operators of the Baltic. Capacity Calculation Region for the regional design of longterm

Implementation rules

Present: Philippe de LADOUCETTE, Chairman, Olivier CHALLAN BELVAL, Hélène GASSIN, Jean-Pierre SOTURA and Michel THIOLLIERE, Commissioners.

Implementation Guide JAN, 2018 SON -SY

Transcription:

EUROPEAN ELECTRICITY BALANCING GUIDELINE NOVEMBER 2018 AN OVERVIEW OF THE EUROPEAN BALANCING MARKET AND ELECTRICITY BALANCING GUIDELINE European Network of Transmission System Operators for Electricity

ENTSO-E: THE EUROPEAN NETWORK OF TRANSMISSION SYSTEM OPERATORS FOR ELECTRICITY, REPRESENTS 43 ELECTRICITY TRANSMISSION SYSTEM OPERATORS (TSOs) FROM 36 COUNTRIES ACROSS EUROPE. CONTENTS 1 INTRODUCTION...3 2 GENERAL FUNCTIONING OF BALANCING MARKETS...4 3 BALANCING PROCESSES...5 4 THE DIFFERENT STEPS OF THE BALANCING PROCESS...7 4.1 Products... 8 4.2 Gate closure times... 9 4.3 Bid and demand submission, common merit order list creation... 10 4.4 Activation optimisation function... 10 5 BALANCING ENERGY PRICING AND SETTLEMENT... 11 6 IMBALANCE SETTLEMENT... 12 7 EUROPEAN PLATFORMS AND PROJECTS FOR THE EXCHANGE OF BALANCING ENERGY... 14 8 TIMELINE... 15 GLOSSARY... 16 2

1 INTRODUCTION The European power system is transforming rapidly to integrate more renewables, develop flexibility and enable consumers to play a more central role. For electricity markets, this transition means that trading needs to move closer to real time, i.e. closer to delivery while respecting system security. National and regional markets are becoming increasingly integrated towards a common European market. New players such as aggregators, storage and demand response operators are entering the market. As the underlying system is changing and integration advances, the efficient balancing of the power system also needs to be developed to enable the clean energy transition for all Europeans. Efficient balancing markets shall ensure security of supply at the lowest cost and can deliver environmental benefits by reducing the need for back-up generation. The Commission Regulation (EU) 2017/2195 of 23 November 2017 establishing a guideline on electricity balancing (EBGL) lays down detailed rules for the integration of balancing energy markets in Europe, with the objectives of fostering effective competition, non-discrimination, transparency and integration in electricity balancing markets, and by doing so, enhancing the efficiency of the European balancing system as well as security of supply. This document provides an overview of the European balancing energy market target model and explains the main concepts and processes related to balancing energy markets and European platforms for the exchange of balancing energy products. In particular, it focuses on the interaction between the different balancing processes and briefly describes the legal framework of the European balancing energy target model. This is a simplified overview, which does not cover all the aspects and differences of the described processes and platforms. The target group of this overview is wide: from TSOs to the general public. It should be understandable to readers with a basic knowledge of electricity markets. 3

2 GENERAL FUNCTIONING OF BALANCING MARKETS Balancing means all actions and processes through which transmission system operators (TSOs) continuously ensure the maintenance of system frequency within a predefined stability range, as well as compliance with the amount of reserves needed with respect to the required quality. The balancing process consists of three main steps: 1) TSOs dimension their need for balancing reserves, 2) TSOs procure the required balancing capacity and 3) TSOs procure balancing energy. This paper, as does the EBGL, focuses on balancing energy markets. Balancing energy markets represent the entirety of the institutional, commercial and operational arrangements that enable a market-based balancing of the system. Wellfunctioning day ahead and intraday markets act as a foundation for the balancing market, in which the TSO s role is to ensure that considering the other markets results, demand and supply remain balanced by operating the system close to real time (Figure 1). BSP TSO BRP Provide bids Balance the system Responsible for its imbalances Forward market Day-ahead market Intraday market Balancing market Imbalance settlement Figure 1. Balancing market sequence in electricity markets and its participants Balancing service providers (BSPs) such as generators, demand response facilities and storage operators can offer balancing services (capacity and/or energy) to the TSOs, who in turn use these services to balance the system. Balance responsible parties (BRPs) such as electricity producers, consumers and suppliers shall keep their individual position (sum of the energy volume physically injected or withdrawn from the system and their trades) in balance or help the system to be balanced, as they are financially responsible for the imbalances of their portfolios. The EBGL requires the harmonisation of certain balancing market processes and rules, including the establishment of common principles for the activation and exchange of balancing energy. Based on these requirements, all TSOs jointly with relevant stakeholders will cooperate to develop sets of rules and methodologies and to establish the balancing pan-european platforms, described in the following chapters. 4

3 BALANCING PROCESSES European TSOs use different processes and products to balance the system and restore the frequency, based on historic developments and different balancing philosophies. Balancing energy in Europe is organised in up to five steps (Figure 2): Frequency containment reserve (FCR) Imbalance netting (IN) Frequency restoration reserves with automatic activation (afrr) Frequency restoration reserves with manual activation (mfrr) Replacement reserves (RR) FCR Automatic activation Max 30 s afrr Automatic activation 30 s to 15 min mfrr Semi-automatic or manual activation Max 15 min RR Semi-automatic or manual activation Min 15 min f Frequency (50 Hz) Total balancing energy (idealized) Balancing energy t 0 t 0 +30 s t 0 + 5 min t 0 + 15 min t 0 + 45 min Time Sync.area Unbalanced TSO Figure 2. Balancing market processes for frequency restoration 5

The explanation and purpose of named processes are given in the table below. RESERVE POWER TYPE DEFINITION PURPOSE 1 FCR FRR (afrr and mfrr) The active power reserves available to contain system frequency after the occurrence of an imbalance. The active power reserves available to restore system frequency to the set point value frequency and, for a synchronous area consisting of more than one load-frequency control area (LFC area), to restore power balance to the scheduled value. The frequency containment process stabilises the frequency after the disturbance at a steady-state value within the permissible maximum steady-state frequency deviation by a joint action of FCR within the whole synchronous area. The frequency restoration process controls the frequency towards its set point value by activation of FRR, and replaces the activated FCR. The frequency restoration process is triggered by the disturbed LFC area. RR The active power reserves available to restore or support the required level of FRR to be prepared for possible additional system imbalances, including generation reserves. The reserve replacement process replaces the activated FRR and/or complements the FRR activation by activation of RR. The replacement reserve process is activated in the disturbed LFC area. IN A process agreed between TSOs that enables the avoidance of the simultaneous activation of afrr in opposite directions, taking into account the respective frequency restoration control errors as well as the activated afrr and correcting the input of the involved frequency restoration processes accordingly. The imbalance netting process is designed to reduce the amount of simultaneous and counteracting afrr activation of different participating and adjacent LFC areas via imbalance netting power exchange. Table 1. Definition and purpose of balancing processes The common European platforms for the IN process, the exchange of balancing energy from afrr, the exchange of balancing energy from mfrr and the exchange of balancing energy from RR are being developed to harmonise such processes across Europe (see Chapter 6). The IN process, being a TSO-TSO activity, will not be discussed in detail in this paper; the following general process descriptions do not apply to the imbalance netting process. 1 Supporting Document for the Network Code on Load-Frequency Control and Reserves (https://www.acer.europa.eu/official_documents/acts_of_the_agency/annexes/entso-e%e2%80%99s%20supporting%20document%20to%20the%20submitted%20network%20code%20on%20load-frequency%20control%20and%20reserves.pdf) Supporting Document for the Network Code on Load-Frequency Control and Reserves 6

4 THE DIFFERENT STEPS OF THE BALANCING PROCESS All balancing processes follow similar functioning principles, as represented in Figure 3. BSPs can send to their connecting TSOs the balancing energy standard or specific product bids or update the balancing energy price of their bids until the balancing energy gate closure time (1), TSOs forward them to the relevant balancing energy exchange platform until the TSO energy bid submission gate closure time for the balancing energy product bids (2), together with the available cross-zonal capacities (CZC) and relevant network constraints (3) and TSO balancing energy demands (4). The activation optimisation function (AOF) (5) generates or accepts as input data the common merit order lists (CMOLs) and calculates and provides as output data (6) the selected bids to be activated, the netted demands, cross-border exchange (if any) and used cross-zonal capacities (8) based on which TSOs request their BSPs to activate balancing energy bids according to the algorithm outcomes. Some bids might appear unavailable, due to network constraints. The bids can be activated for balancing purposes and system constraints purposes. The information from the platform regarding the commercial flows between LFC areas or bidding zones and settlement between TSOs is also provided for the transparency and settlement purposes respectively. An example of the balancing process for the exchange of balancing energy from frequency restoration reserves with manual activation is given in Figure 3; for different products the illustrated process might slightly differ due to product specificities and timing. In the following, these steps are elaborated in more detail. Connecting TSO Area 3 CZC, HVDC and network constraints 8 Used CZC Connecting TSO Area BSP 1 Offers TSO 2 4 Bids Needs 5 Platform (AOF) 6 Selected bids Netted Needs XB Exchanges TSO Activation Requests BSP Transparency *Under discussion 7 *Under discussion Settlement Figure 3. General process of balancing process (applied to mfrr) 7

4.1 PRODUCTS In order to facilitate the exchange of balancing energy across borders, the EBGL requires the definition of a set of standard products for RR, afrr and mfrr ( for direct and scheduled activation) to be exchanged using pan-european platforms. TSOs may request their respective NRA to approve the usage of specific products to fulfil their dimensioning requirements. Balancing energy bids from specific products and bids from the integrated scheduling process from TSOs applying a central dispatch system can be converted into balancing energy bids from standard products according to certain rules, therefore further in the text the term standard product will also be used for balancing energy bids from specific products converted into balancing energy bids from standard products. The EBGL sets up certain requirements for the technical parameters of standard products (Figure 4). The list of standard products for balancing energy and balancing capacity may set out at least the following characteristics of a standard product bid: (1) preparation period, (2) ramping period, (3) full activation time, (4) minimum and maximum quantity, (5) minimum and maximum duration of delivery period, (6) deactivation period, validity period and the mode of activation. The list of standard products shall set out at least the following variable characteristics of a standard product to be determined by the BSPs: the price of a bid, its divisibility, location and minimal duration between the end of one activation and the following one. Due to differences in the existing balancing markets, TSOs foresee a progressive harmonisation, with only the essential concepts being harmonised before the launch of the pan-european platforms. More detailed information about standard products can be found in the implementation framework proposals for the afrr 2, mfrr 3 and RR platforms 4. May be defined Structure of standard balancing product 1-Preparation period 2-Ramping period 3-Full activation time quantity 4 4-Min & max quantity 5-Min & max delivery period 6-Deactivation period Validity period Mode of activation 1 2 5 6 3 Full activation time Full delivery period time Shall be defined Price of the bid Divisibility Location Min duration between end following activation Figure 4. Characteristics of a standard product 2 https://consultations.entsoe.eu/markets/afrr_implementation_framework/supporting_documents/20180426_afrrif_implementation_framework.pdf 3 https://consultations.entsoe.eu/markets/mfrr_implementation_framework/supporting_documents/mfrr%20implementation%20framework%20%20proposal.pdf 4 https://docstore.entsoe.eu/documents/network%20codes%20documents/nc%20eb/180618_rr-implementation-framework_for-nra-submission.pdf 8

4.2 GATE CLOSURE TIMES The balancing energy gate closure time (BE GCT) is the point in time at which BSPs are no longer permitted to submit or update a balancing energy bid to their connecting TSO. The BE GCT for BSPs and the TSO GCTs shall be distinguished - first BSPs send and update their bids until BE GCT, after which all submitted bids should be firm, and subsequently TSOs forward the bids to the relevant platforms until a certain point in time - TSO energy bid submission GCT (TSO GCT). An individual BE GCT is defined for each balancing energy product. Figure 5 summarises the TSO proposals for BE GCTs and TSO GCTs, whilst taking into account the interactions with other balancing processes. H-60' H-30' H H+15' ID Last hour Validity period BEGCT H-55' TSO GCT H-40' Submission RR bids Local TSO processes Clearing + Request for activations FAT TSO GCT H-25'... 12'/10' H+7,5' Submission mfrr bids Local TSO processes Clearing + request for activation + FAT BEGCT H-25' Submission afrr bids Local TSO processes Platform processes Clearing + netting + request for activations + FAT Figure 5. GCT for different products and stakeholders * RR BE GCT will be H-55 minutes. For an interim period of no more than 12 months after the entry into operation of the RR-Platform, the RR BE GCT will be H-60 minutes 9

4.3 BID AND DEMAND SUBMISSION, COMMON MERIT ORDER LIST CREATION After bid submission to the platforms, the CMOLs consisting of balancing energy bids, are created. Separate lists for downward and upward activation are created. In parallel, TSOs submit their balancing energy demands for the relevant timeframes. As a result, the respective CMOLs are merged with the TSO balancing energy demands. The upward CMOL is merged with the TSOs downward needs, and the downward CMOL with the TSOs upward needs. An example of such an input is illustrated in Figure 6. The timing and complexity for different products (afrr, mfrr, RR) differs; however, the general principles remain similar. 4.4 ACTIVATION OPTIMISATION FUNCTION All European platforms will have an activation optimisation function (AOF), which aims to balance the system in an efficient way and minimise the exchange of balancing energy amount on borders between bidding zones or LFC areas. As input, the algorithm will receive BSP standard product bids (CMOLs), TSOs individually determined balancing energy demands and technical limitations in the system (CZC or HVDC constraints). The AOF creates a cost curve consisting of the TSO balancing energy demands and the CMOLs of all bids. Based on this curve, as well as on all defined technical constraints, it provides the satisfied demands, the selected bids, the input data for the cross-border marginal prices and the cross-border exchanges (Figures 6 and 7). COMMON MERIT ORDER LIST Price Positive imbalance demands Downward bids TSO A Price EUR / MWh TSO B Volume TSO C Volume MWh Negative imbalance demands Upward bids Figure 6. CMOL creation of balancing energy bids and merging with TSOs balancing energy demands Selected BE bids CMOL with BE bids Satisfied BE demands BE demands Activation optimization function XB marginal price CZC & HVDC constraints XB BE commercial schedules Economic surplus Figure 7. AOF general scheme demands 10

5 BALANCING ENERGY PRICING AND SETTLEMENT The EBGL foresees that the settlement process shall be based on marginal pricing (pay-as-cleared). The marginal price represents the price of the last bid of a standard product, which has been activated to cover the energy demand within a specified area (Figure 8). The AOF will compute the balancing energy price per bidding zones and/or LFC areas. In the event there are no congestions between adjacent areas, the price will be the same in these areas, referred to as uncongested areas. In the event a congestion occurs, there will be a price split (same as in the day-ahead market coupling). In the event of evolving congestions over time, the uncongested areas can be different per products. The calculation of the marginal pricing will consider the differences between the different processes, therefore, for each balancing product the price will be calculated separately for each optimization cycle. Depending on the balancing process, the optimization cycle is expected to vary between seconds to 15 minutes (i.e. ISP). TERRE (RR) AOF RR Price for the optimization cycle Bid price MP B 8 B 9 B 10 MARI (mfrr) AOF Direct activation mfrr Price for the optimization cycle Scheduled activation mfrr Price for the optimization cycle B 7 B1 B 2 B 3 B 6 B 5 B 4 Demand Power PICASSO (afrr) AOF afrr Price(s) for the optimization cycle These prices will directly be used to settle BSPs Figure 8. Marginal price forming and balancing energy pricing for different processes Each connecting TSO settles with its BSPs according to the marginal price of the relevant product s market price ( for afrr, mfrr with direct and scheduled activation and RR). As a result of the European balancing processes, TSOs settle between each other according to their satisfied demands and selected balancing energy bids. 11

6 IMBALANCE SETTLEMENT Imbalance settlement is a core element of the balancing markets. It is a financial settlement mechanism aimed at charging or paying BRPs for their imbalances for each imbalance settlement period (ISP). The general principles of settlement processes aim to: establish adequate economic signals which reflect the imbalance situation, ensure that imbalances are settled at a price that reflects the real time value of energy, provide incentives to BRPs to be in balance or help the system to restore its balance, facilitate the harmonisation of imbalance settlement mechanisms, avoid distorting incentives to BRPs, BSPs and TSOs, support competition among market participants, and provide incentives to BSPs to offer and deliver balancing services to the connecting TSO. TSOs shall not incur economic gains or losses with regard to the financial outcome of the settlements of: imbalance with BRPs, balancing energy with BSPs, and intended and unintended exchanges of energy with TSOs, due to balancing processes. Entry into force (Dec 2017) Derogation on TSO or NRA request ISP = 15 min for all Jan 2018 Jan 2021 Jan 2023 Jan 2024 Jan 2025 CBA ISP = 15 min for all Exemption per synchronous area Figure 9. Timeline for 15 min ISP implementation Imbalance pricing is done within a certain timeframe, the ISP. In the European Union, countries currently apply ISPs of 60, 30 and 15 minutes. The EBGL requires all TSOs to harmonise the ISP by 2021, or at the latest by 2025, to an ISP of 15 minutes (Figure 9). 12

Figure 10 represents the general cashflows that result from the balancing market processes according to the EBGL and illustrates the principle that TSOs shall incur no economic gains or losses as a result of energy settlements from balancing markets: BRPs are settled for their imbalances, BSPs are settled for balancing energy and for balancing capacity, and TSO-TSO settlement is foreseen for energy exchange with other TSOs as a result of the European balancing processes. Arrows denote the direction of payments; some settlements may involve bidirectional payments, hence the double arrow. References to relevant project/processes and chapters in EBGL have been added. afrr mfrr RR Connecting TSO BSP Bal. energy (CH 3) BRP Imbalance (CH 4) Gain / loss EBGL Art. 44 (2) User Other TSO Exchanges (CH 2) TERRE MARI PICASSO IGCC FSkar Administrative cost Other cost related to balancing EBGL Art. 44 (3) BRP BSP Bal. capacity (CH 5) Procurement cost FCR afrr mfrr RR Figure 10. Cashflows in balancing market The general principle of imbalance settlement is that all injections and all withdrawals should be covered by balancing responsibility and, depending on the imbalance situation, an imbalance cost is imposed per ISP on the BRPs that are not in energy balance over that ISP. The imbalance settlement with BRPs will be based on a combination of marginal prices of different balancing markets (see Chapter 5). The EBGL requires the implementation of a single imbalance pricing as the preferable option. The application and justification of dual imbalance pricing by a TSO shall be approved by the relevant regulatory authority. 13

7 EUROPEAN PLATFORMS AND PROJECTS FOR THE EXCHANGE OF BALANCING ENERGY The EBGL foresees the implementation of the common European platforms and thereby the harmonisation of the European balancing market processes. For each of the processes (IN, afrr, mfrr and RR) the EBGL requires the development of a European platform. In order to achieve this goal, European TSOs have established the following implementation projects (Figure 11): International Grid Control Cooperation (IGCC) for imbalance netting process; Platform for the International Coordination of Automated Frequency Restoration and Stable System Operation (PICASSO) for afrr process; Manually Activated Reserves Initiative (MARI) for mfrr process; Trans-European Restoration Reserves Exchange (TERRE) for RR process. Currently, the named platforms are being developed according to the EBGL required timeline. The aim is to find the most efficient solutions; therefore the optimal amount of platforms, the optimal amount of entities for the operation of the functions of the platforms and the cooperation between the platforms are regularly addressed. Imbalancing netting: afrr: PICASSO IGCC mfrr: MARI RR: TERRE Member Observer Figure 11. European balancing implementation projects and their TSO members (as of November 2018) mfrr platform (MARI): MAVIR (HU), HOPS (HR) and SEPS (SK) are in the process of becoming full members. afrr platform (PICASSO): ESO (BG), Swissgrid (CH) and ADMIE/IPTO (GR) are in the process of becoming full members. More information is available HYPERLINK "https://electricity.network-codes.eu/network_codes/eb/" here. 14

8 TIMELINE The EBGL sets a challenging timeline for European platform implementation (Figure 12); however, TSOs have confirmed their intention to meet the required deadlines.glossary Obligations 2017 2018 2019 2020 2021 2022 2023 Q 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 RR TERRE Impl Framework EIF+6m RR EU Platform EIF+2yrs TSO Join Derogation +2yrs Imb. Netting IGCC Impl Framework EIF+6m IN EU Platform EIF+2yrs TSO Join Derogation +2yrs mfrr MARI Impl Framework EIF+1yr FRR EU Platform EIF+4yrs TSO Join Derogation +2yrs afrr PICASSO Impl Framework EIF+1yr FRR EU Platform EIF+4yrs TSO Join Derogation +2yrs Imbalance Settlement Harmonised Proposal EIF+1yr ISP & Proposal Impl EIF+3yrs ISP Derogation +2yrs 4yrs Pricing Pricing EIF+1yr Cross-zonal capacity CZC Alloc EIF+2yrs CZC Harm EIF+5yrs General Compliance EIF+1yr Pub Info EIF+2yr Entry into Force Derogation Deadline Proposal Figure 12. The EBGL required timeline for the implementation of European balancing platforms 15

GLOSSARY afrr AOF afrr IGCC AOF LFC area BE GCT mfrr BRP MARI BSP NRA CMOL PICASSO CZC RR EBGL TERRE FCR TSO HVDC TSO GCT IN XB frequency restoration reserves with automatic activation activation optimisation function frequency restoration reserves with automatic activation international grid control cooperation activation optimisation function load-frequency control area balancing energy gate closure time frequency restoration reserves with manual activation balance responsible party manually activated reserves initiative balancing service provider national regulatory authority common merit order list platform for the international coordination of automated frequency restoration and stable system operation cross-zonal capacity replacement reserves Commission Regulation (EU) 2017/2195 of 23 November 2017 establishing a guideline on electricity balancing trans-european restoration reserves exchange frequency containment reserve transmission system operator high voltage direct current TSO energy bid submission gate closure time imbalance netting cross-border ANY QUESTIONS? CONTACT US! @ENTSO_E info@entsoe.eu +32 2 741 09 50 www.entsoe.eu 16