ANGLO PLATINUM LIMITED

Similar documents
ANGLO PLATINUM LIMITED 2005 ANNUAL RESULTS PRESENTATION

ANGLO AMERICAN PLATINUM CORPORATION LIMITED 2004 YEAR END RESULTS PRESENTATION

ANGLO AMERICAN PLATINUM CORPORATION LIMITED 2004 INTERIM RESULTS PRESENTATION

ANGLO AMERICAN PLATINUM CORPORATION LIMITED 2003 RESULTS PRESENTATION

ANGLO AMERICAN PLATINUM CORPORATION LIMITED 2001 RESULTS PRESENTATION

ANGLO AMERICAN PLATINUM CORPORATION LIMITED 2001 INTERIM RESULTS PRESENTATION

Analyst Visit. Nico Muller. Business Leader Two Rivers Platinum

2009 Interim Results Presentation

ANGLO AMERICAN PLATINUM 2015 ANNUAL RESULTS PRESENTATION 8 FEBRUARY 2016 PLATINUM

ANGLO AMERICAN PLATINUM ANNUAL PRESENTATION RESULTS 2011

ANGLO AMERICAN SITE VISIT PLATINUM BUSINESS OVERVIEW AND UPDATE 23 NOVEMBER 2016

SALE OF THE RUSTENBURG OPERATIONS

NORTHAM PLATINUM AND THE BUSHVELD COMPLEX

ANGLO AMERICAN PLATINUM 2016 INTERIM RESULTS PRESENTATION 25 JULY 2016

Today s presentation

Anglo American Platinum Limited. Bank of America Merrill Lynch s 12 th annual Sun city conference March 2011

ANGLO AMERICAN CREATING LONG TERM SHAREHOLDER VALUE

ANGLO AMERICAN PLATINUM LIMITED INTERIM RESULTS 2018 JOURNEY TO DELIVER NEXT PHASE OF VALUE

ANGLO AMERICAN PLATINUM LIMITED 2011 ANNUAL RESULTS

AUDITED ANNUAL RESULTS FOR THE YEAR ENDED 31 DECEMBER 2018

ANGLO AMERICAN PLATINUM 2016 ANNUAL RESULTS PRESENTATION 15 FEBRUARY PGI Platinum wedding bands

Condensed Consolidated Interim Results. For the six months ended 30 June 2018

BUILDING ON OUR FOUNDATIONS POSITIONED FOR A SUSTAINABLE FUTURE

Implats delivers improved first half performance

Audited Annual Results. For the year ended 31 December 2017

ANGLO AMERICAN PLATINUM LIMITED INTERIM RESULTS PRESENTATION 30 JUNE 2014 FOCUSED ON DELIVERY RESTRUCTURING FOR PROSPERITY PLATINUM

Strategic update. Impala Rustenburg review 2 August 2018

INTERIM RESULTS SIX MONTHS ENDED 30 JUNE 2017

Disclaimer. Bank of America Merrill Lynch Conference, Sun City

INTERIM RESULTS FEBRUARY 2002

Acquisition of the Rustenburg Operations

ANGLO AMERICAN PLATINUM LIMITED Annual Results Presentation 2014 FOCUS: OPERATING SMARTER

Lonmin Plc FINAL RESULTS 2007

ANGLO AMERICAN PLATINUM LIMITED DELIVERING CHANGE BUILDING RESILIENCE POSITIONING FOR THE FUTURE

Platinum Interim Review. Johnson Matthey. 18th November abcd.

Industry Amplats operational review

more than AUDITED ABRIDGED RESULTS for the year ended 31 December 2011 mining

Marcum Microcap Conference New York 29 May 2014

CREATING LONG TERM SHAREHOLDER VALUE

Impala Platinum Holdings Limited Interim results 1 March Impala Rustenburg 16 Shaft

Development of new mine at Zimplats and Rustenburg s 17 Shaft to be restarted in two years

PLATINUM DIVISION Update. Jean Nel CEO: Platinum Division Justin Froneman SVP Finance: Platinum Division

REVIEWED INTERIM RESULTS 2017 FOR THE SIX MONTHS ENDED 31 DECEMBER. smart platinum mining

PLATINUM. STATE OF THE NATION Roger Baxter, Chief Economist and COO, Chamber of Mines of South Africa

empowered to produce 15 APRIL 2008 RBC PLATINUM DAY THE PENN CLUB : NEW YORK CITY

ANGLO AMERICAN PLATINUM LIMITED DELIVERING CHANGE BUILDING RESILIENCE POSITIONING FOR THE FUTURE

Lonmin Plc INTERIM RESULTS 2005

Strategic overview of Wesizwe Platinum Limited. forward looking & FOCUSSING

smart platinum mining

Reduced demand impacts on profitability

AUDITED ANNUAL RESULTS FOR THE YEAR ENDED 31 DECEMBER 2014

Forward looking statement

Lonmin Plc. Standard Chartered Earth Conference, Hong Kong. Albert Jamieson Chief Commercial Officer June 2012

ANGLO PLATINUM LIMITED ANNUAL REPORT 2006

MORE THAN MINING ROYAL BAFOKENG PLATINUM FACT SHEET

THE CATALYST FOR CHANGE

smart platinum mining

ANOORAQ RESOURCES CORPORATION THREE AND SIX MONTHS ENDED JUNE 30, 2009 MANAGEMENT'S DISCUSSION AND ANALYSIS TA B L E O F C O N T E N T S

Bokoni Platinum Mines. Philip Kotze, CEO 2 October 2009

Northam asset portfolio

Lonmin Plc Interim Report. For the 6 months to 31 March Building value

Quarterly review and production report for the period 1 July to 30 September 2012

ANGLO AMERICAN PLATINUM LIMITED Integrated Report 2014 FOCUS: OPERATING SMARTER

Impala Platinum Holdings Limited Annual results 14 September 2017

Q Operating and strategic update

Condensed Consolidated Interim Results for the six months ended 30 June 2016

Platinum th May 2008

South Africa s Platinum Mining Crisis

2018 INTERIM RESULTS PRESENTATION 14 MAY 2018 MANAGING CONTROLLABLES MANAGING CASH

ANALYSIS for the three and nine months ended September 30, 2018

South Africa s Platinum Mining Crisis

SUMMARISED PRELIMINARY AUDITED CONSOLIDATED FINANCIAL RESULTS FOR THE YEAR ENDED 31 DECEMBER 2018

Acquisition of Aquarius Platinum Limited. 6 October 2015

Administration and contact information

Audited Annual Results for the year ended 31 December 2017 MORE THAN MINING

Stillwater Mining Company A PGM Business

A unique, exciting, precious metals company

ATLATSA ANNOUNCES RESULTS FOR THE QUARTER ENDED MARCH 31, Significant improvements in year-on-year Q1 operating performance

Integrated Annual Report 2010 Poised for growth

NORTHAM PLATINUM LIMITED (Registration number 1977/003282/06) Share code: NHM ISIN: ZAE Debt issuer code: NHMI Bond code: NHM002 Bond ISIN:

TO THE SHAREHOLDERS OF SIBANYE GOLD LIMITED, TRADING AS SIBANYE-STILLWATER

2. Overview of the US region

LEI No: FGJZ2WAC6Y2L94 REGULATORY RELEASE. 15 May Interim Results

equity Non-controlling interest Total equity Liabilities Non-current liabilities

Deutsche Bank BRICS Metals & Mining Conference 2 3 November Stompie Shiels: Executive Director, Business Development

A New Generation of Platinum and Palladium Mines

NEWS RELEASE For immediate release

Overview Sipho Nkosi: Chief Executive Officer

Headline earnings increased by 51% to R4.8 billion including a R1 billion net fair value gain as a result of restructuring of the ARM Coal debt.

Adding Value to Natural Resources

REGULATORY RELEASE. 16 May Interim Results

abcd Platinum 2004 Interim Review 16th November 2004

Platinum Market Review

CONDENSED CONSOLIDATED ANNUAL RESULTS FOR THE YEAR ENDED 30 JUNE 2009

Strategic Highlights The Transaction is progressing on schedule, with submissions made to competition authorities.

POSITIONED FOR A SUSTAINABLE FUTURE

A unique, exciting, precious metals company. CEO, Neal Froneman

ANGLO AMERICAN MEETING THE WORLD S NEEDS

ATLATSA ANNOUNCES FINANCIAL RESULTS FOR THE HALF YEAR ENDED JUNE 30, 2017 & PROVIDES AN UPDATE ON THE IMPLEMENTATION OF THE 2017 RESTRUCTURE PLAN

Pan African Resources plc Precious Metals Summit Geneva April The African Focused Precious Metals Producer

Transcription:

ANGLO PLATINUM LIMITED 2006 INTERIM RESULTS PRESENTATION 31 July 2006 Overview Record earnings Strong PGM demand - firm prices Production growth continues Operational initiatives good progress BEE process ongoing

Overview Highlights Headline earnings up 111% - R4,50bn Dividends up 192% - R14 per share Average rand basket price (R/Pt oz sold) up 49% Refined platinum production up 6% to 1,34m oz Increased sales volumes refined metal stock restored to normal levels Overview 14000 Higher metal prices 1400 12000 10000 8000 6000 4000 1200 1000 800 600 400 Rand basket price (R/Pt oz sold) US$ platinum price ($/Pt oz sold) 2000 2001 2002 2003 2004 2005 2006 H1 Average US$ metal prices achieved: Platinum $1 104 up 27% Rhodium $3 419 up 124% 200

Overview Strong PGM demand firm prices Demand for PGM s from autocatalyst sector very strong Jewellery demand pleasing at these price levels Increased demand from a variety of industrial end-uses continues particular strength in glass sector Speculative activity still evident and supporting firm prices Overview 4000 3000 Growth continues 2000-2005 global compound demand growth 3,4% pa 2000 * Forecast range 1000 0 Anglo Platinum refined Pt production oz (000's) 2000 2001 2002 2003 2004 2005 2006* 2007* Anglo Platinum refined output growth 2000-2005: 5,5% pa Anglo Platinum expected average growth 2006 onwards: 5% pa 2007 target 2,8m to 2,9m refined Pt oz

Overview Operational initiatives good progress Focus on long term safe and sustainable production Focussed turnaround expenditure establishing sound base at Rustenburg and Amandelbult Turnaround implementation well advanced Volume improvements as expected in the first half of 2006 Overview BEE progressing Conversion process continues Ongoing Government engagement intensified Discussions with existing and potential HDSA partners continue

Financial overview Financial overview Main features Headline earnings attributable to ordinary shareholders up 118% - R4,38bn Average rand basket price (R/Pt oz sold) up 49% Rand rhodium price achieved up 125% Strong operational cash flows - net cash position of R694m Interim dividend R14,00 per ordinary share Dividend cover 1,4

Financial overview Financial summary Six months to June 2006 2005 % Profit on metal sales Rbn 6,08 2,58 135,8 Total headline earnings Rbn 4,50 2,14 110,9 Net cash / (debt) Rbn 0,69 (3,00) 123,1 Headline earnings per share cps 2 002 924 116,7 Ordinary dividend cps 1 400 480 191,7 Refined Pt production 000 oz 1 345 1 269 6,0 Interest bearing debt to equity % 5,2 22,1 76,5 ROCE % 54,8 26,4 107,6 Financial overview Headline earnings (Rm) H1 2005 to H1 2006 3193 116 133 (229) (610) (154) 38 (118) 4504 2135 2005 Price Exch Vol Inflation Cash costs Amort Interest Other 2006

Financial overview 65% 60% Operating margin and volume per mine AS 59,0% 55% 50% 45% KPM PSA 42,1% RS 43,2% Operating margin 40% 35% 30% 25% 20% 15% Marikana PSA 27,8% Modikwa 20,9% BRPM 26,2% WLTR 35,5% PPL US 39,7% 38,7% LPM 30,7% Group average 42.2% Steady state operations Ramp up Operations 10% 5% 0% 0 100 200 300 400 500 600 700 800 900 1 000 1 100 1 200 1 300 1 400 Refined Pt oz (000's) Financial overview 2006 cash flows (Rm) 6 513 (1 657) (1 835) (246) 212 694 (2 293) Dec 2005 Net debt Cash from operations Dividends Capex Tax & Interest Other June 2006 Net cash

Operational overview Safety Mining performance Process performance Cost performance Capital expenditure and projects Operational overview Safety Reduction in total number of fatalities during the period Du Pont training of executive and senior management well advanced Significant resources being invested to achieve a step change in safety performance

Operational overview Mining performance Equivalent refined platinum production - up 5% Rustenburg and Amandelbult responding to initiatives Mining flexibility improving Immediately available & stopeable reserves up Increased breast mining development and production Abnormal rainfall reduced PPRust & tailings re-treatment output Poor ground conditions at Union UG2 declines - more extensive support intervention Cash operating cost per equivalent ref. Pt oz up 11% Operational overview 1500 Mining performance 55 1300 1100 900 45 35 Equivalent refined Pt oz (000's) % UG2 mined 700 H1 04 H2 04 H1 05 H2 05 H1 06 25 Turnaround programmes starting to deliver Focus on increasing operating efficiencies

Operational overview Rustenburg turnaround Immediately available reserves increasing strongly Tons milled up 2% Volume of UG2 ore up from 55% to 62% Equivalent refined platinum production up 1% More concentrated mining footprint - 22% reduction in the number of half levels Operational overview Amandelbult turnaround Immediately available reserves up 17% from Dec 05 Tons milled up 19% Volume of UG2 ore up from 45% to 51% Equivalent refined platinum production up 9% Steady progress in addressing transition zone

Operational overview Process performance Polokwane smelter: stock reduced to normal working levels furnace cooling: encouraging results with new materials Average Waterval SO 2 emissions below permit and target levels Smelting and refining unit cost increase of 1% Cost performance Change in cash unit cost per platinum ounce (H1 06 vs H1 05) (excluding purchased ounces and associated costs) 12% 1,4% 11,3% 1,2% 10% 4,5% 3,5% 1,4% 0,3% 9,9% 10,1% (% increase) 8% 6% 1,4% 1,7% 4% 4,1% 2% 0% CPI Wages above CPI Turnaround and inefficiency costs Increased tons Ground support at Union Mech. failure & rainfall Other Mining & treatment cost/ ton milled Grade & ore mix Operating cost/ equiv refined Pt oz Release of pipeline stocks Operating cost/ refined Pt oz

Operational overview Projects PPRust North project area Operational overview Growth projects Approved and under development: Kroondal PSA R375m 280 000 Pt oz pa * Marikana JV R115m 145 000 Pt oz pa * Mototolo JV R675m 132 000 Pt oz pa * PPRust North R3 847m 230 000 Pt oz pa Under evaluation: Booysendal, Der Brochen, Ga Phasha, Pandora, Styldrift, Twickenham * 50% of this production attributable at full margin

Operational overview Project progress All projects on schedule and within budget Amandelbult 75ktpm UG2 - plant fully utilised BRPM phase 2 project - at 600m (of 1 300m) Lebowa Merensky declines - at 1 100m (of 2 500m) Waterval concentrator retrofit - on track, Q2 07 PPRust North project commenced Mototolo JV - plant commissioning, Q4 06 Paardekraal 2 shaft - final approval expected shortly Operational overview Capital Expenditure R1,84bn capex spent for the period R635m on expansion R1,14bn to maintain operations R64m capitalised interest 2006 total capex of R5,5bn R6,0bn expected

Outlook PGM markets to remain buoyant and robust 2006 target remains 2,7m 2,8m refined Pt oz Operating efficiencies to increase Platinum production growth to continue 5% pa forecast average QUESTIONS