FUSION FOR ENERGY The European Joint Undertaking for ITER and the Development of Fusion Energy

Similar documents
FUSION FOR ENERGY. The European Joint Undertaking for ITER and the Development of Fusion Energy The Governing Board

COMMISSION STAFF WORKING DOCUMENT. The ITER Project Status. Accompanying the document

C 368/24 Official Journal of the European Union

COMMUNICATION FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL EU CONTRIBUTION TO A REFORMED ITER PROJECT. {SWD(2017) 232 final}

THE GOVERNING BOARD OF FUSION FOR ENERGY HAS ADOPTED THIS DECISION:

PRELIMINARY CONCLUSIONS

PRELIMINARY CONCLUSIONS

Round-table discussion on the process to identify information to be provided under Article 9, paragraph 5, of the Paris Agreement

EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR ENERGY AND TRANSPORT

ICC-ASP/4/32. Part II External audit, programme budget for 2006 and related documents

Report of the Programme, Budget and Administration Committee of the Executive Board

UNESCO/BIE/C.62/Decisions Geneva, 25 January 2013 Original: English SIXTY-SECOND SESSION OF THE COUNCIL OF THE INTERNATIONAL BUREAU OF EDUCATION

WORKING DOCUMENT. EN United in diversity EN. European Parliament

This document is meant purely as a documentation tool and the institutions do not assume any liability for its contents

FUSION FOR ENERGY - FINAL ACCOUNTS - FINANCIAL STATEMENTS & BUDGET IMPLEMENTATION & REPORT ON BUDGETARY AND FINANCIAL MANAGEMENT

UNFPA EXECUTIVE BOARD DECISION-TRACKING MECHANISM

143 nd meeting of the Committee of Permanent Representatives of UNEP 28 September Interventions on behalf of the EU and its MS

EU framework programme processes

FUSION FOR ENERGY. The European Joint Undertaking for ITER and the Development of Fusion Energy The Governing Board

Report of the Programme, Budget and Administration Committee of the Executive Board

Commission progress report on the implementation of the Common Approach

2 nd INDEPENDENT EXTERNAL EVALUATION of the EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS (FRA)

Report of the Seventeenth Meeting of the Independent Expert Oversight Advisory Committee (IEOAC) of the World Health Organization

Roles and Responsibilities (in replacement of Edinburgh doc. HLG 1523a, Poitiers doc. HLG 2209 and Nice doc )

This report was prepared at the request of Ms Inés Ayala Sender, rapporteur on the 2015 Agencies' Discharge.

2008 SENIOR MANAGER S COMPACT

10219/12 AFG/UM/DS/lv 1 DG G III C

COMMISSION DECISION. of

Competencies of the political bodies of EUREKA

PACA Steering Committee Meeting-Communiqué

Report on the annual accounts of the Bio-based Industries Joint Undertaking for the financial year Together with the Joint Undertaking s reply

Discharge 2012: Innovative Medicines Initiative Joint Undertaking

MODALITY FOR FUNDING ADDITIONAL ACTIVITIES UNDER THE PMR: DRAFT PROPOSAL FOR DISCUSSION. PMR Note PA

INTRODUCTION INTRODUCTORY COMMENTS

DECISION ADOPTED BY THE CONFERENCE OF THE PARTIES TO THE CONVENTION ON BIOLOGICAL DIVERSITY AT ITS ELEVENTH MEETING

Report on the annual accounts of the European Joint Undertaking for ITER and the Development of Fusion Energy for the financial year 2011

Fusion for Energy. The European Joint Undertaking for ITER and the Development of Fusion Energy ITER. 10 April 2008

STEERING COMMITTEE ON HEALTH. Report of the Sixth Meeting of the OIC Steering Committee on Health

Revised additional tool under item 8 of the agenda

COMMISSION OF THE EUROPEAN COMMUNITIES

ESF Committee - Plenary Session 30 May 2007

Partnership for Market Readiness (PMR): Technical Work Program: Report on FY15 activities and Proposal for FY16

Evaluation and Monitoring of European Research Framework Programmes

30th Ordinary Plenary Meeting of the BEREC Office Management Committee (MC)

Resolution adopted by the General Assembly. [on the report of the Second Committee (A/64/420/Add.2)]

October 2018 JM /3. Hundred and Twenty-fifth Session of the Programme Committee and Hundred and Seventy-third Session of the Finance Committee

Third Session of the Committee on Administration and Finance (CAF) Marrakech, Morocco, May 2012

Office of the Auditor General of Norway. Handbook for the Office of the Auditor General s Development Cooperation

DRAFT REPORT 2011/2217(DEC)

Report on budgetary and financial management

Decision 3/CP.17. Launching the Green Climate Fund

Summary Conclusions of the Second APEC Budget and Management Committee Meeting Cebu, Philippines 2 September 2015

Council conclusions on the European Union Strategy for the Adriatic and Ionian Region (EUSAIR)

Summary of results from the ECA s 2017 annual audit of the European research Joint Undertakings

REPORT 2015/174 INTERNAL AUDIT DIVISION

AUDIT REPORT INTERNAL AUDIT DIVISION

Decisions of the Board Eighth Meeting of the Board, October 2014

Follow-up to the financing dialogue

Year end report (2016 activities, related expected results and objectives)

Audit Committee: Terms of Reference

Governing Body Geneva, November 2007 PFA/BS FOR INFORMATION

REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL

REPORT 2015/041 INTERNAL AUDIT DIVISION. Audit of the United Nations Mine Action Service of the Department of Peacekeeping Operations

DECEMBER Ministry of Defence. Observations on the Ministry of Defence major investment approval process

Committee on Budgetary Control

the procedural aspects of its future Work Package (as contained in Annex I); the final version of the future WorkPackage (as contained in Annex II);

Annotations to the provisional agenda

together with the Foundation s reply

Executive Board of the United Nations Development Programme, the United Nations Population Fund and the United Nations Office for Project Services

2009 discharge: Joint Undertaking (Joint Technology Initiative on Innovative Medicines)

EN 7 EN. Annex II Action Fiche for West Bank and Gaza Strip/ENPI. 1. IDENTIFICATION Title/Number Total cost 10,500,000

39TH ANNUAL MEETING OF OECD SENIOR BUDGET OFFICIALS

TEXTS ADOPTED Provisional edition. P8_TA-PROV(2018)0158 Discharge 2016: European Agency for Safety and Health at Work (EU- OSHA)

Report of the International Civil Service Commission

SHEFFIELD HALLAM UNIVERSITY. Mr L Hunter, Deloitte Mr P Severs, Director of Finance Ms S Suchoparek, KPMG Ms A Temple (Minute Secretary)

DARTFORD BOROUGH COUNCIL CABINET. MINUTES of the meeting of the Cabinet held on Thursday 28 July 2016 at 7.00 pm

FINANCIAL STATEMENTS & BUDGET IMPLEMENTATION

ANNEX. to the COMMISSION DECISION

November 2016 CL 155/6 COUNCIL. Hundred and Fifty-fifth Session. Rome, 5-9 December 2016

IPCC 44 October

CENTRAL BANK OF KENYA

Economic and Social Council

Summary of results from the ECA s 2016 annual audit of the European research Joint Undertakings

Draft Programming Document th meeting of the Management Board December 2016

Armenia: Infrastructure Sustainability Support Program

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof,

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION

AIDE MEMOIRE OF THE MEETING OF THE NEGOTIATING GROUP ON THE MAI HELD ON APRIL 1996

Brunis, *00007 REGIO Il/AI/rs D(2008) /970002

(Legislative acts) REGULATIONS

EU science policy and instruments. Richard Burger Science Counsellor Delegation of the European Commission to Russia 01 October 2009

Fourth Report of the Green Climate Fund to the Conference of the Parties to the United Nations Framework Convention on Climate Change

REPORT 2015/115 INTERNAL AUDIT DIVISION

Annual Report of the Audit Committee

EVALUATION AND FITNESS CHECK (FC) ROADMAP

Executive Board of the United Nations Development Programme, the United Nations Population Fund and the United Nations Office for Project Services

Fusion Energy Research in FP7

MEMORANDUM OF UNDERSTANDING BETWEEN THE EUROPEAN COMMUNITY AND THE REPUBLIC OF HUNGARY

THE ROLE OF CESR IN THE REGULATION AND SUPERVISION OF UCITS AND ASSET MANAGEMENT ACTIVITIES IN THE EU

Factsheet N 6 Project implementation: delivering project outputs, achieving project objectives and bringing about the desired change

Transcription:

FUSION FOR ENERGY The European Joint Undertaking for ITER and the Development of Fusion Energy THE GOVERNING BOARD SUMMARY OF DECISIONS OF THE 38 th MEETING OF THE GOVERNING BOARD OF THE EUROPEAN JOINT UNDERTAKING FOR ITER AND THE DEVELOPMENT OF FUSION ENERGY ('FUSION FOR ENERGY') Barcelona, 3-4 July 2017 The Governing Board (GB) of the European Joint Undertaking for ITER and the Development of Fusion Energy (Fusion for Energy F4E ) has decided the following: Approval of the Agenda 1. The GB approved the agenda of its 38 th meeting. Written Procedures 2. The GB noted the written procedure since the previous GB meeting (37). Approval of the Minutes 3. The GB approved the minutes of its 37th meeting. Reports from EURATOM 4. The GB noted a report from Euratom on the outcome of the ITER MAC (30/05/2017), the ITER Council (IC 20) (21-22/06/2017) and the Commission`s Communication on ITER and commended the Commission for the quality and clarity of the document. Reports from F4E 5. The GB noted F4E`s report to the Council, ready for transmission to the Council of the EU and the European Parliament, and noted a general Progress Report from F4E on the recent accomplishments related to the ITER and Broader Approach Projects and: a. Commended F4E for the recent progress in many different areas; b. Recommended to consider the lessons to be learned from the testing of the JT60 TF coils in relation with the potential testing of the ITER ones. Status of Actions 6. The GB welcomed the strategic action plan and requested an updated action plan by the December GB (39) which shall contain the following improvements: a. Actions shall be regrouped around coherent management objectives; b. A follow up shall be considered for actions declared as closed; c. The updated Strategic Action plan shall serve as the key document for the GB to assess the performance of the Director and F4E. Status of IFMIF/DONES (for this agenda point the chairmanship of the GB was passed to the Vice Chair Gabriele Fioni) 7. Upon the expiration of the deadline set by the GB, two expressions of interests i.e. from Croatia and Spain were received; Approved : 04/07/2016 Page 1 of 5

8. The GB noted a progress report on the follow up of the expressions of interests from above stated Member States to host IFMIF/DONES and requested that the final report will be presented at the next GB; 9. Under the request of Spain, it was agreed that the report will be distributed by the secretariat once it is finished by the ad hoc Working Group (AhG). This document will not require the endorsement of the GB at that stage. The TAP will report to the December GB (39). Status of Nuclear Safety 10. The GB noted a report on the outcome of the Nuclear safety AhG and: a. Thanked the AhG for the comprehensive and careful analysis performed in a short period of time; b. Requested the F4E Director to prepare an action plan in response to the AhG comments and recommendations. This action plan shall be presented to the Bureau with the opinion of the AhG in October. Reports from the Chairs 11. The GB noted the report from the Chair of the GB including the summary of the Bureau meeting of 19 June 2107; 12. The GB noted the report from the Chair of the Administration and Management Committee (AMC) including the summary of the AMC meeting of 6-7 June 2016; 13. The GB noted the report from the Chair of the Procurement and Contracts Committee (PCC) including the summary of the meeting of 23 March 2017; 14. The GB noted the report from the Chair of the Technical Advisory Panel (TAP), including the summary of the meeting of 8-9 June 2016. ITER Vacuum Vessel 15. The GB discussed the progress on the EU Vacuum Vessel (VV) Sectors and: ITER Buildings a. Commended F4E for the encouraging progress in the project whilst reminding that risks still remain and a continuous effort will be needed; b. Took note of the remarks by the TAP and requested F4E to show the progress curves with the standard format showing the baseline and actual progress; c. Requested to be informed on the achievement of the August KPIs and on the possible decision on the use of the 11 M for the preparation of a spare sector; d. Requested to be informed in case a decision of a transfer of EU VV sector(s) to IO would be presented to the ITER Council. 16. The GB discussed the progress on the Buildings and: a. Discussed the progress on the Buildings and noted the achievement of the TB03 amendment 6 negotiations within the technical and financial boundaries presented to the last GB; b. Noted the progress on the Final Design of the TB04 and noted the target to have it approved by September 2017; The GB received F4E's information on the planned schedule of the decision-making on the possible partial novation between F4E and IO on the TB04 contract and highlighted the need to adapt the presented time plan so as to have time to receive the necessary approval from the Commission; c. Asked the AMC to monitor closely the contract novation process and requested to be informed of it, in particular in case the novation process leads to an increase in the cost Estimate At Completion (EAC); Approved : 04/07/2016 Page 2 of 5

d. Noted that the functional interface freeze exercise managed by IO is progressing and expected to be completed by September 2017. Nevertheless space interface will have to be finalized during the Construction Phase, all systems will have to be aligned on a level by level approach and a gate decision to start installation will have to be taken by March 2018; e. Noted the progress on the Common Assembly Sequence and the new set-up for the TB04 contract. The GB requested that risk reduction and budgetary implications will be presented to the next December GB (39). Sixth Annual Assessment of F4E 17. The GB adopted the Terms of Reference for the 2017 annual assessment; 18. The GB adopted the proposal to appoint two experts i.e. Ms Rowena Sirey and Mr Victor Rodrigo and agreed to appoint the third member of the expert group by urgent written procedure; 19. The work of the expert group should start in September 2017 and the report shall be delivered by the end of October 2017. Specific Reports from F4E 20. The GB noted the intention of the F4E Director to sign the Procurement Arrangement (PA) for the first wall blanket and recommended him to keep the preservation of the schedule as a guideline as well as to work towards cost reductions; 21. The GB noted the positive outcome of the External Audit report concerning cost evolution of Major Procurements as presented to GB 37; 22. The GB noted the updated Cost evolution of Major Procurements and requested that in the future changes with respect to the previous version should be highlighted; 23. The GB adopted the request to Implement the Agreements of Collaboration (AoC) regarding extra costs for the Broader Approach with the abstention of EURATOM; 24. The GB noted the status of Staffing and Vacancy Rate; 25. The GB discussed the 2017 Geographical distribution exercise; 26. The GB noted the Estimate at Completion-Update April 2017 and suggested that in the future it shall be reported within the financial information package. Operational Matters 27. The GB noted the Status of Commitments and Payment and appreciated the acceleration of payments which provides good evidence of the increase in project activity and closer adherence to schedule whilst requiring an increased attention to the reliability of payment planning in order to ensure continuous adequacy of payment appropriations and needs; 28. Welcomed the commitment of Euratom and France to work towards the provision of the necessary payment appropriations and requested F4E to prepare a mitigation plan as a backup solution; 29. Concerning the First Amendment to the 2017 Budget, the GB: a. Adopted this amendment whilst noting that the increase in the 2017 payment appropriations will be approved by the Bureau in due course, and possibly in multiple instalments, after the confirmation by Euratom of the available increases of the 2017 payment appropriations. 30. The GB approved the First amendment to the 2017 WP and: Approved : 04/07/2016 Page 3 of 5

a. Stressed the need for a careful high quality planning reflected in the 2018-22 Multi Annual Project Plan (MAP); b. Urged F4E to finalize the 2018-22 MAP in consultation with the AMC and TAP, early enough to facilitate a Commission`s opinion in time for the approval of the budget and work programme for 2018. Given the tight time schedule for the next MAP, the exact format of the AMC and TAP intervention will be discussed between the chairs of the GB and both subcommittees; c. Emphasized the need to preserve the 6,6 B commitments cap until 2020 (2008 value) and its compatibility with the payments profile; d. Agreed to grant the F4E Director the requested flexibility for this particular amendment. 31. The GB adopted the F4E GB Milestones update. Fusion Roadmap 32. The GB welcomed the High level Fusion Roadmap. Annual Reports and Accounts 33. The GB adopted the 2016 Final Annual Accounts while noting the preliminary remarks by the European Court of Auditors; 34. The GB noted the 2016 Annual Report; 35. The GB adopted the Analysis and Assessment of the 2015 Annual Report. Audit Matters 36. The GB noted the Report from the Chair of the Audit Committee; 37. The GB noted the Annual report from the Audit Committee; 38. The GB noted the European Parliament s Discharge for the 2015 Budget; 39. The GB noted the Note from IAS on the outstanding recommendations from past IAS audits; 40. The GB noted the 2016 Annual Report of the Internal Audit Capability; 41. The GB noted the Updated Corporate Risk Register; 42. The GB adopted the Revised IAC Annual Plan. Amendments to the Implementing Rules to F4E Financial Regulation 43. The GB adopted the Implementing Provisions for F4E`s derogations from the common EU Financial Rules; 44. The GB discussed improving the efficiency of F4E`s governance and agreed to give written inputs to the group in preparation of the proposal which will be submitted to the next December GB (39); 45. The GB adopted the Garching Host agreement. Any Other Business 46. The GB noted the Status F4E`s building refurbishment. Approved : 04/07/2016 Page 4 of 5

Closing 47. The GB approved this Summary of Decisions. Done at Cadarache, 04 July 2017 For the Governing Board Joaquin Sanchez Chair of the Governing Board For the Secretariat Approved : 04/07/2016 Page 5 of 5