SUMMARY OF REVISIONS PROPOSED / NOT PROPOSED

Similar documents
Regional Planning and Cost Allocation Review EB Working Group meeting #1 - Webinar

POWER TO CONNECT A ROADMAP TO A BRIGHTER ONTARIO

Ontario Energy Board

PROJECT COSTS, ECONOMICS, AND OTHER PUBLIC INTEREST CONSIDERATIONS

Canadian Manufacturers & Exporters (CME) INTERROGATORY #1 List 1

Transmission Connection Procedures EB

REGULATORY ACCOUNTS. The purpose of this Exhibit is to provide a description of Hydro One Distribution s regulatory accounts.

EXHIBIT 9 DEFERRAL AND VARIANCE ACCOUNTS

Independent Electricity System Operator Licence EI

GUELPH HYDRO ELECTRIC SYSTEMS INC.

Balsam Lake Coalition Interrogatory # 8

TORONTO HYDRO CORPORATION MANAGEMENT S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS FOR THE YEAR ENDED DECEMBER 31, 2005

RATE DESIGN. The proposed distribution rates for each rate class over the Custom COS period are summarized in Table 1.

SUMMARY OF APPLICATION

LOCAL PLANNING REPORT ERINDALE TS T1/T2 DESN CAPACITY RELIEF GTA WEST SOUTHERN SUBREGION. Revision: 0 Date: July 9, 2015.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB GUELPH HYDRO ELECTRIC SYSTEMS INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB VERIDIAN CONNECTIONS INC.

Horizon Holdings Inc. Auditors Report to the Shareholders and Consolidated Financial Statements Year Ended December 31, 2016 and December 31, 2015

Consumer Deposit Security Policy

DECISION AND ORDER ON PHASE 1

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB NIAGARA PENINSULA ENERGY INC.

STATE OF MINNESOTA BEFORE THE MINNESOTA PUBLIC UTILITIES COMMISSION. LeRoy Koppendrayer

SECOND QUARTER REPORT JUNE 30, 2015

BEFORE THE PUBLIC UTILITY COMMISSION OF OREGON

Rate Base Issues Section 3.3

STANDING COMMITTEE ON PUBLIC ACCOUNTS

DEC CDM Innovation for Success Themes and Outcomes

How Ontario is Putting Conservation First

AIRD BERLIS. October 16, 2017 VIA COURIER, AND RESS

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB ALGOMA POWER INC.

Ontario Energy Board

TORONTO HYDRO CORPORATION MANAGEMENT S DISCUSSION AND ANALYSIS OF FINANCIAL CONDITION AND RESULTS OF OPERATIONS FOR THE YEAR ENDED DECEMBER 31, 2010

EB Hydro One Networks Inc. s 2019 Transmission Revenue Requirement Application and Evidence Filing

EXECUTIVE SUMMARY OF APPLICATION

Access Arrangement Information. Standard Access Contract Demonstration of Code Compliance

microfit RULES Version 1.6 December 8, 2010

BEFORE THE NEW MEXICO PUBLIC REGULATION COMMISSION SOUTHWESTERN PUBLIC SERVICE COMPANY S UNOPPOSED RESPONSE TO STAFF S COMMENTS

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC.

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB HYDRO ONE NETWORKS INC.

Orangeville Hydro Limited 2019 IRM APPLICATION EB Submitted on: September 24, 2018

DEFERRAL AND VARIANCE ACCOUNTS

WHITBY HYDRO ELECTRIC CORPORATION

RATES FOR EXPORT TRANSMISSION SERVICE

ENERSOURCE HYDRO MISSISSAUGA INC. HORIZON UTILITIES CORPORATION & POWERSTREAM INC.

Financial Statements of FESTIVAL HYDRO INC. Year ended December 31, 2014

ONTARIO ENERGY BOARD. Distribution System Code. Last revised on April 1, 2011 (Originally Issued on July 14, 2000)

Enersource Hydro Mississauga Inc. Application for Distribution Rates Effective January 1, 2017 Board File No.: EB

Province-Wide Pay-For-Performance (P4P) Draft Program Documents Webinar: IESO response to input received

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB KENORA HYDRO ELECTRIC CORPORATION LTD.

Electrical Distribution Safety Regulation - Proposed Amendments

Doug Curtiss, CEO, GPI Shafee Bacchus, Chair, NWTC Encls. *Mark Rodger Professional Corporation TOR01: : v1

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c.15, (Schedule B);

DECISION AND RATE ORDER

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB WEST COAST HURON ENERGY INC.

FEED-IN TARIFF CONTRACT (FIT CONTRACT)

Market Rule Amendment Proposal

REGULATORY ACCOUNTS. The purpose of this evidence is to provide a description of Hydro One Transmission s Regulatory Accounts.

Demande de renseignements du Distributeur et du Transporteur d électricité à OC

CHAPLEAU PUBLIC UTILITIES CORPORATION ED IRM APPLICATION EB

microfit RULES Version 4.1 January 1, 2017

Connection and Cost Recovery Agreement. between. (Customer Legal Name) and. Hydro One Networks Inc. for. (Project Description)

FEED-IN TARIFF CONTRACT (FIT CONTRACT)

Electricity Power System Planning

Fair Hydro Plan. An Assessment of the Fiscal Impact of the Province s Fair Hydro Plan

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);

Long Run Marginal Cost (LRMC)

HYDRO ONE INC. ANNUAL CONSOLIDATED FINANCIAL STATEMENTS

Contact: Gerry Guthrie Kitchener-Wilmot Hydro Inc. Telephone ext 271

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB ORANGEVILLE HYDRO LIMITED

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB TILLSONBURG HYDRO INC.

DEFERRAL AND VARIANCE ACCOUNTS

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB COLLUS POWERSTREAM CORP.

Audit Funding Program - Participant Agreement

REGULATORY ASSETS, VARIANCE AND DEFERRAL ACCOUNTS

TABLE OF CONTENTS. C. Business Planning and Budgeting Process and Economic Assumptions

Reform of the Queensland infrastructure planning and charging framework

Conservation and Demand Management Information Solution (CDM-IS) FAQ s

ECONOMIC EVALUATIONS

DSM Mid-Term Review. Presentation to the Conservation Mid-term Review Advisory Group Valerie Bennett

Retrofit Program - Participant Agreement

Electricity Distribution Licence ED PowerStream Inc.

ATTACHMENT 8 SUMMARY OF FIXED/VARIABLE SPLITS HORIZON UTILITIES RZ

Where Do We Go From Here

Natural Gas Demand Side Management Evaluation, Measurement, and Verification (EM&V) Plan

Nova Scotia Utility and Review Board

Advancing Customer-Driven Solutions for Ontario

ORDER NUMBER G IN THE MATTER OF the Utilities Commission Act, RSBC 1996, Chapter 473. and

2014 Fixed Income Investor Update

IN THE MATTER OF the Ontario Energy Board Act, 1998, S.O. 1998, c. 15, (Schedule B);

Ontario s Renewable Energy Standard Offer Program - LDC Information Package

Ontario Energy Board Commission de l énergie de l Ontario

Ontario Energy Board Commission de l énergie de l Ontario DECISION AND RATE ORDER EB ALGOMA POWER INC.

Request for Advice on Cost Recovery for Mandated Smart Metering Infrastructure

Ontario Energy Board s (OEB S) Response to the. International Accounting Standards Board s. Request for Information on Rate Regulation

Re: Legislative and Regulatory Proposals Relating to the Goods and Services Tax/Harmonized Sales Tax

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

Statewide Transition Plan Toolkit for Alignment with the Home and Community-Based Services (HCBS) Final Regulation s Setting Requirements

2.11 EXHIBIT 8: RATE DESIGN... 2 Overview... 2

2. CRITERIA FOR FUNDING OF EXTENSIONS AND UPGRADES

NORTHEASTERN ISO/RTO PLANNING COORDINATION PROTOCOL DESIGNATION OF FILING PARTY

Transcription:

Attachment E to Notice of Revised Proposed Amendments to the System Code and the Distribution System Code August 23, 2018 EB-2016-0003 SUMMARY OF REVISIONS PROPOSED / NOT PROPOSED Below is a high level summary of section B of this Notice that addresses the issues in the same order as they are set out in section B but organizes them differently consolidated into two tables as follows: Proposed revisions to the September Proposed Amendments Changes that were considered but not accepted and are therefore not included in the Revised Proposed Amendments These tables are provided for stakeholder convenience. Section B of this Notice should be relied on for providing comments, as it includes the full rationale for adopting (or not adopting) a suggested change and background for context. Issue / Code / Section Apportioning Connection Investment Costs to Network Pool section 6.3.18A Broaden to include generator customers not only load (better align with beneficiary pay principle) Benefits considered for cost apportionment purposes to Network pool: o Broaden scope beyond reliability (e.g., reduced system losses) o Place limitations on scope using criteria similar to those for Z-factor applications, such as: identifiable, quantifiable, material o Not codifying benefits Consider proposals in utility applications (with supporting evidence from IESO) in adjudicative process to maintain flexibility Focus section on introduction of proportional benefit concept o Reference TSC sections that address all cost responsibility scenarios (e.g., load, generator, mix, etc.) - 1 -

Upstream Connection Investments: Treatment of Embedded Distributors and Large Load Customers sections 3.2.4A (DSC), 6.3.20 End-of-Life (EOL): Replacement of and Distribution Connection Assets sections 6.7.2, 3.1.17 (DSC) General Increase materiality threshold from 3 MW to 5 MW for large C&I customers based on non-coincident peak demand Refer to new, as well as modified, transmission assets Only use economic evaluation methodology in TSC (Appendix 5) for determining all capital contributions host & embedded distributors and distribution-connected large customers o Transmitter required to undertake the DCF calculation following a host distributor request; i.e., all capital contributions calculated at the same time, based on the same methodology, by the same entity o Methodologies differ in TSC and DSC Change to modernize both Codes from implying wires replacement is the only option when an asset reaches EOL to provisions only apply where wires replacement at EOL is determined to be the optimal solution Before EOL Customer Request Add third subsection (both Codes) to address cost responsibility where a customer requests replacement before EOL (not limit to a Notice expectation) Customer required to also pay advancement costs not limited to remaining net book value (NBV) Obligation to Consult Limit obligation for distributors to consult on distribution assets at EOL to: distribution stations connected to the transmission system and, for distribution lines, only where large C&I customers are connected (5 MW and above) o Not all customers and all distributor-owned assets Regional Distribution Solution: LDC Feeder Transfer section 3.1.18 (DSC) Revise to take into account cases where an investment in existing assets is required (as well as new and modified assets) Clarify that the agreement between the distributors would also require OEB approval (as part of the application) - 2 -

Annual Installment Option section 6.3.19 Require the transmitter to allow the capital contribution to be recovered from a distributor over a longer period of time than five years, on a case-by-case basis, where the OEB has approved a distributor application to do so Advanced Funding Options Defer further consideration of both advanced funding options Upstream Connection Adder & Upstream Capacity Payment until changes to the Filing Guidelines are considered, where design and implementation issues would be addressed o Amendments to Code appendices are not necessary Refund / Rebate to Initial Customer sections 3.2.27 & 3.2.23 (DSC) Revise to maintain the status quo five (5) years for all customers which does not involve a materiality threshold o Not increase the timeframe from five (5) to 15 years for large C&I customers due to potential unfair treatment concerns; i.e., no rebate for customer below threshold True-Ups and Load Forecasts sections 3.2.20 and 3.2.24 (DSC) Revise to maintain a five (5) year return period for all customers in relation to expansion deposit refunds o Not increase it to 15 years for large C&I customers Bypass Compensation sections 3.5.1 (DSC), 11.2.1 Revise to clarify the initial intent -- bypass compensation would also apply to partial bypass The requested clarification regarding how the proposed bypass compensation charge (in this consultation) would work with the proposed capacity reserve charge (in the C&I customer consultation EB-2015-0043) is not possible now o Will be provided once the OEB has reached a conclusion on the CRC (as part of C&I policy consultation), when there is more certainty on both charges (i.e., not both proposals) Clarification on load management In conjunction with conservation, it would capture all distributor CDM programs administered by the IESO and all activities identified in the OEB s CDM Guidelines (including those that would defer infrastructure investments) - 3 -

Relocation of Connection Assets sections 3.1.20 and 3.1.21 (DSC) Where the customer requests relocation, revise to clarify that the amount to be recovered from the customer should be the maximum permitted under law, where full cost recovery is not permitted Remove the existing provision section 3.4 which did not fully address cost responsibility and referenced distribution plant which is not defined (nor used elsewhere in the DSC) Definition of Customer (DSC) Revise proposed definition of customer by removing embedded distributor o Instead, deem them to be customers for the purpose of only section 3 of the DSC (except section 3.3) o Deeming will be referenced as part of the definition and, for clarity, at the beginning of section 3 Distributor-Owned Assets sections 3.1.17A, 3.1.19, 3.1.20, 3.1.21, 3.5.2(c), 3.5.3 (DSC) New definition of distributor-owned asset which would exclude all assets that are installed as part of a basic connection to use an existing form of materiality threshold and reduce the scope of assets o See section B of this Notice for a brief description of each applicable DSC provision As discussed above, a revision to section 3.1.17 (DSC) is also proposed to further limit the applicable EOL assets (that need to be consulted on) to distribution stations that are connected to the transmission system and distribution lines that connect large customers (at or above 5 MW) Definition of Embedded Distributor (and section 9.7.1 of DSC) Change the definition of embedded distributor by removing the reference to not being a wholesale market participant o Many are now market participants Also amend section 9.7.1 to add their wholesale market participant status as it is required Clarification on Capital Contribution Refunds section 6.3.17A Revise to clarify the load forecasts of the initial customer and subsequent customer should not to be aggregated when the capital contribution calculations (including the refund) for each customer is carried out as part of an Economic Evaluation; i.e., calculations should be performed separately - 4 -

Changes Considered but Not Included in Revised Proposed Amendments Issue / Code / Section Apportioning Connection Investment Costs to Network Pool; i.e., Proportional Benefit section 6.3.18A Upstream Connection Investments: Treatment of Large Load Customers section.3.2.4a (DSC) End-of-Life: Replacement of and Distribution Connection Assets sections 6.7.2 & 3.1.17(DSC) Changes Considered Not Proposed Maintain case-by-case application approach o Not change to a simplified process Maintain Network pool to attribute costs related to broader system benefits o Not change to Connection pool to address administrative burden concerns (less aligned with beneficiary pays and almost 10% cost shift) Maintain capital contribution requirement from large C&I customers o Not exempt those customers for economic development purposes Right-sizing to Lower Capacity at EOL Not agree the Codes should obligate right-sizing (i.e., specify same basis where all utilities must downsize) o Continue to rely on expectation in Notice and new affected customer consultation requirement. o As acknowledged at the Stakeholder Conference, there are issues if utility judgment is not permitted OEB will consider if (and to what extent) further action is necessary once current initiatives are completed including: OEB-established Regional Planning Process Advisory Group (RPPAG) is in the process of developing an EOL guidance document (appendix to the RPPAG Report) The IESO received a Directive from the Minister of Energy to develop a coordinated, cost-effective, longterm approach to addressing the need to replace transmission assets at EOL Other End-of-Life Issues No guidance to be provided at this time to distributors on how to determine when an asset is at its EOL o o Distributors are better positioned based on their experience with their own assets and how they use them Premature to provide guidance at this time in advance of RPPAG finalizing its EOL guidance document and IESO completing its EOL review - 5 -

Regional Distribution Solution: LDC Feeder Transfer section 3.1.18 (DSC) Annual Installment Option section 6.3.19 Utility Discretion Cost Responsibility Code Provisions (DSC) Refund / Rebate to Initial Customer sections 3.2.27 and 3.2.23 (DSC) True-Ups and Load Forecasts sections 3.2.20 & 3.2.24 (DSC) Mix of load and generator customers on a connection asset section 3.1.9 (DSC), section 6.3.16 Treatment of Overload (TSC, DSC) Changes Considered Not Proposed No change in the wording needed to accommodate an arrangement between more than two distributors o The facilitating distributor would have a separate agreement with each connecting distributor Not changing interest paid to transmitter by distributor to the OEB approved cost of capital on the unpaid balance to offset the incremental financing costs o Maintain OEB s construction work in progress (CWIP) rate will hold transmitter harmless No revision to retain existing distributor discretion to address economic development concerns Also not proposing the use of more liberal terminology o Maintain proposal to change may to shall in the cost responsibility provisions Continue to make the DSC more user-friendly and clear for stakeholders by including the reference to five years directly in section 3.2.27 rather than referring to a separate document Appendix B o Similar consequential revisions to section 3.2.23 Continue to change the references from the same generic term parties to identify the specific types of customers that are applicable generator and load Continue to remove distributor discretion to require an expansion deposit by replacing may with shall (only where a capital contribution is required) Retain may where capital contribution not required Not accept that the reference to proportional benefit in section 6.3.16 should be removed and restricted in its use to one section (6.3.18A) of the TSC (i.e., apportionment between customer and Network pool) o A revision is therefore not proposed Not proposing a revision to implement an incremental revenue scheme associated with overload to help pay for new facilities o Utilities should focus on managing load on the assets in an appropriate manner (rather than such a scheme when load is not managed appropriately) - 6 -