Session 3 by Zoltán Záhonyi, FIDIC AIT,

Similar documents
FIDIC CONTRACTS A COMPARATIVE. Uttam Sengupta Sr. GM Contracts & Risk Management

2 THE EMPLOYER Provision of Site 2.2 Permits and Licenses 2.3 Employer s Instructions 2.4 Approvals

Conditions of Contract for PLANT and Design-Build

STANDARD TERMS FOR SPARE PARTS AND/OR SITE SERVICES

MDB Harmonised Particular Conditions

Sub Contract Agreement

Terms and Conditions for provision of Supply

ANDRA JEWELS LIMITED TERMS & CONDITIONS OF SUPPLY

SOUTHERN COMMUNICATIONS LIMITED TELEPHONE SYSTEMS - TERMS AND CONDITIONS OF SALE

Uncontrolled If Printed

JPL Telecom Limited Conditions of Sale. The customer's attention is drawn in particular to the provisions of clause 9.

Clause 17: Care of the Works and Indemnities

These Conditions and the Supplier s quotation. the Construction (Design and Management) Regulations 2014, as they apply to the works

PENTAXIA LIMITED TERMS AND CONDITIONS OF BUSINESS. 1.1 Definitions. In these Conditions, the following definitions apply:

BETWEEN name. address. AND name (hereinafter called the Subcontractor ) address

representatives, successors or permitted assigns.

General Terms and Conditions of Sale

DOUKPSC04 Rev Feb 2013

TERMS AND CONDITIONS OF SALE. 1.1 the following words and expressions shall have the following meanings unless the context otherwise requires:

SUPPLIER - TERMS AND CONDITIONS Materials and Goods

Suspension and Termination

General Terms & Conditions of Sale

Fan and Ventilation Ltd, Terms & Conditions

TERMS AND CONDITIONS OF SALE

QIOPTIQ LIMITED (UK) CONDITIONS OF SALE

CONDITIONS OF SALE. Customer means the person, firm or company who purchases the Goods from the Supplier.

CONDITIONS OF CONTRACT FOR QUOTATION

Construction Management Approach based on FIDIC Conditions of Contract for Construction, st Edition. Dr. Munther M.

Olympus Global - Standard Terms and Conditions of Sale (edition May 2010)

Emtelle UK Limited Conditions Of Sale Of Goods

Terms & Conditions of Sale

Insert Project Title Here Reference Version. Insert Title of Works Here. United Nations Office for Project Services ( UNOPS ) -and-

Contracts Management and Administration (Based on FIDIC Standard)

Standard Trading Terms and Conditions

DESERT COMMUNITY COLLEGE DISTRICT General Terms and Conditions

APPENDIX 3 FAYAIR (STANSTED) LIMITED STANDARD TERMS OF BUSINESS. Aircraft means any aircraft in respect of which the Customer has requested Services;

FIXTURE TERMS & CONDITIONS Materials & Goods

SECTION 2 : JURONG HEALTH SERVICES PTE LTD STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WORKS

Terms & Conditions Supply of Goods or Services

AH: STANDARD CONDITIONS OF CONTRACT FOR CONSTRUCTION AND IMPROVEMENT WOPKS SCC.1

Comparative analysis of key issues in D&C contracts in recent social infrastructure PPPs

SOUTHERN RESPONSE CANTERBURY EARTHQUAKE RECONSTRUCTION PROJECT GENERAL CONDITIONS OF CONTRACT FOR HOUSING REBUILD AND REPAIRS

General Conditions for Consultancy Services Agreements

SERVICE AGREEMENT. Townsville, Queensland Kevin Chard

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES

MULTI PACKAGING SOLUTIONS CONDITIONS OF SALE (IRELAND)

FATIGUE TECHNOLOGY INC. PURCHASE ORDER TERMS AND CONDITIONS DATED JANUARY 4, 2006

STONE INTERIORS Terms of Trade. 1 Definitions. 2 Estimate Validity and Existence of Contract. 3 Cancellations

Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

1.1 Definitions. In these Conditions, the following definitions apply:

STANDARD TERMS AND CONDITIONS

Works Appointment: We, on behalf of the Employer, would like to inform you that your quotation, Reference Number

JC PAYNE SPECIALIST SERVICES LIMITED TERMS AND CONDITIONS FOR SERVICE

Nutreco General Purchase Terms and Conditions

SAFETY FIRST GRANT CONTRACT

UNITED STATES AND CANADA TERMS AND CONDITIONS OF SALE NOVEMBER 2006

ABA Film Services Ltd. Terms and Conditions of Hire

The Standard Form of Building Sub-Contract Edition

PALL INDIA PVT LTD PURCHASE ORDER TERMS AND CONDITIONS

STANDARD TERMS AND CONDITIONS FOR THE SALE OF GOODS ALL MARKETS EXCEPT OIL AND GAS

TERMS AND CONDITIONS OF TRADE

Pleece&Co LTD. Terms and Conditions +44 (0)

Terms and conditions. The customer s attention is drawn in particular to the provisions of clause 9. 1.

General Conditions for Purchase (CG-2)

SAMPLE SUBCONTRACTOR AGREEMENT

Western Water Development Consultant Accreditation Deed

Standard Form of Agreement Between Contractor and Subcontractor

(1) In these sub-contract conditions of agreement, the following words and phrases shall have the following meanings:-

WESTERN RIVERSIDE COUNCIL OF GOVERNMENTS EQUIPMENT PURCHASE AGREEMENT

Conditions for the Carriage of Goods by Road

ARTICLE 1 ARTICLE 3 CONTRACTOR THE SUBCONTRACT DOCUMENTS ARTICLE 2 MUTUAL RIGHTS AND RESPONSIBILITIES

The Standard Form of Building Sub-Contract Edition

The Standard Form of Minor Works Building Contract Edition. Issued by

Cooper Heat Treating LLC Terms and Conditions of Order Effective April 2, 2013

MANITOBA LIQUOR AND LOTTERIES COPORATION CORPORATE PURCHASE ORDER - TERMS & CONDITIONS

terms and conditions of supply definitions Talisman Marketing Solutions Limited

a. Article(s) Goods and/or services described on the face of the Purchase Order

Standard Contracts for the UK Offshore Oil & Gas Industry

CS ENERGY LIMITED SERVICE CONDITIONS

Terms & Conditions of Business

CONTRACT. Owner and Contractor agree as follows: 1. Scope of Work.

JC PAYNE SPECIALIST SERVICES LIMITED TERMS AND CONDITIONS FOR REPAIR AND MAINTENANCE

PHOTOGRAPHIC GOODS RENTAL/HIRE SERVICE TERMS AND CONDITIONS

SUBCONTRACT CONSTRUCTION AGREEMENT

ANNEX A Standard Special Conditions For The Salvation Army

Standard Form of Agreement Between Contractor and Subcontractor

LUXRITE LTD Terms and Conditions of Sale (revised on 01/01/2018)

FIDIC WORKSHOP 2016 GROUP 6

TERMS AND CONDITIONS OF SALE AND/OR HIRE OF PRODUCTS

Conditions of Contract

TERMS AND CONDITIONS

Festo Ltd Terms & Conditions of Sale The customer's attention is drawn in particular to the provisions of clause 14.

General Terms and Conditions of Siemens, s.r.o.

AGREEMENT AND CONDITIONS OF SUB-CONTRACT (DOMESTIC)

SUBCONTRACT (SHORT FORM)

GENERAL SPECIFICIATIONS TABLE OF CONTENTS

McCLOSKEY INTERNATIONAL LTD CONDITIONS OF PURCHASE.

TERMS AND CONDITIONS OF PURCHASE

FRESENIUS KABI USA, LLC GENERAL TERMS AND CONDITIONS FOR THE SUPPLY OF GOODS AND SERVICES

INTERNATIONAL. Plant and Design - Build TRAINING PROGRAMME DECEMBER Conditions of Contract for EPC/Turnkey Projects

Transcription:

Session 3 by Zoltán Záhonyi, FIDIC AIT, zoltan.zahonyi@zandpartners.com

Contents of Session 3 Session 3: FIDIC 1999 Red Book Part 2 The Quality Issues (Plant, Materials and Workmanship) The Time is of Essence (Commencement, Delays and Suspensions) Completion and Taking-Over Defects Liability Accepted Contract Amount / Contract Price Measurement and Valuation Payment Procedures Risk and Responsibility, Force Majeure and Insurance 2/37

1. The Quality Issues (Plant, Materials and Workmanship) INSPECTION Full access at all reasonable times Site The Employer s Personnel Entitlement to examine, inspect, measure and test Materials Workmanship Check the progress Manufacture of Plant Production and manuf. of Materials 3/37

1. The Quality Issues (Plant, Materials and Workmanship) Whenever any work is ready and before it is covered up, put out of sight, or packaged for storage or transport the Contractor shall give NOTICE to the Engineer, who shall carry out the OR promptly give notice* examination * about declining attendance Consequences of Contractor s failure to comply (uncovering, reinstating and making good at the Contractor s costs). 4/37

1. The Quality Issues (Plant, Materials and Workmanship) Testing RESULT of» Examination» Inspection» Measurement» Testing OR not in accordance with the Contract The Engineer may REJECT (with reasons!) Employer s Claim? Contractor to CORRECT promptly and RETEST (own cost, no EoT!) 5/37

2. The Time is of Essence (Commencement, Delays and Suspensions) The commencement of work Session 3: FIDIC 1999 Red Book Part 2 max. 42 days min. 7 days Commencement Date Contractor s receipt of the Letter of Acceptance OR the date of signing the Contract Agreement Engineer s notice of the Commencement Date Time for Completion 6/37

The Time for Completion Time for Completion Tests on Completion Session 3: FIDIC 1999 Red Book Part 2 2. The Time is of Essence (Commencement, Delays and Suspensions) Commencement Date Engineer s issue of Taking-Over Certificate Defects Notification Period 7/37

2. The Time is of Essence (Commencement, Delays and Suspensions) Programme The Contractor shall submit a programme» within 28 days after receiving the notice of Commencement Date» whenever the previous programme is inconsistent with actual progress or with the Contractor's obligation» on the Engineer s request, if a programme fails to comply with the Contract or to be consistent with actual progress and the Contractor's stated intentions (revised Programme) The Engineer is NOT required to accept / approve a programme! 8/37

2. The Time is of Essence (Commencement, Delays and Suspensions) Extension of Time for Completion The Contractor is entitled for EoT in the following cases:» a Variation [Clause 13]» any specific entitlement for EoT in any of the Sub-Clauses» exceptionally adverse climatic conditions» unforeseeable shortages (goods, personnel due to epidemic, governmental actions)» any delay, impediment or prevention caused by or attributable to the Employer, it's Personnel, or to his other contractors on the Site All subject to Sub-Clause 20.1 [Contractor's Claims] 9/37

2. The Time is of Essence (Commencement, Delays and Suspensions) Delay Damages If the date indicating the completion of Works in the Taking-Over Certificate is later than the expiry date of the Time for Completion AND The Contractor has no contractual entitlement for EoT THEN The Contractor shall pay to the Employer Delay Damages (daily rate and limit to be given under the Appendix to Tender). These are the only damages due from the Contractor for such default. These damages shall not relieve the Contractor from his obligation to complete the Works. 10/37

2. The Time is of Essence (Commencement, Delays and Suspensions) Suspension of Work There are two ways how the Works can be suspended:» Suspension by the Contractor» Suspension ordered by the Engineer Due to Contractual reasons (Employer s or Engineer s faults) See Sub-Clause 16.1 Different causes and outcomes! Due to Employer s convenience See Sub-Clause 8.8 11/37

2. The Time is of Essence (Commencement, Delays and Suspensions) Suspension of Work» During suspension: The Contractor shall protect, store and secure such part or the Works against any deterioration, loss or damage.» The Engineer MAY (but not shall!) notify the cause for the suspension.» If the cause for the suspension is NOT the Contractor s failure to comply with the Contract, then the Contractor becomes entitled to: EoT payment of any Cost (but no profit!) emerging due to the suspension.» Prolonged suspension: Continue OR Omission / Termination. 12/37

3. Completion and Taking-Over Tests on Completion Contractor s notice about readiness for Tests on Completion Contractor is ready for Tests on Completion* Performing Tests on Completion min. 21 days max. 14 days Issue of Taking-Over Certificate * Contractor shall submit to the Engineer the "as-built" documents and operation and maintenance manuals. Time for Completion the deadline 13/37

3. Completion and Taking-Over Tests on Completion» if unduly delayed by the Employer the Contractor Contractor becomes entitled to EoT and cost + profit Engineer s notice to complete within 21 days Contractor s failure: Employer to have others to complete these tests at the risk and cost of the Contractor. 14/37

3. Completion and Taking-Over Taking-Over Contractor s application for issue of Taking-Over Certificate Works are complete, ready for Taking-Over Issue of Taking-Over Certificate max. 14 days max. 28 days Time for Completion the deadline 15/37

3. Completion and Taking-Over Taking-Over» Once the Engineer received the Contractor s application for issue of the Taking-Over Certificate, the Engineer issues the Taking- Over Certificate, stating the date on which the Works or Section were completed in accordance with the Contract. rejects the application, giving reasons and specifying the work required to be done by the Contractor. In case he does not take any action: Deemed Taking- Over on the 28th day after Contractor s application! 16/37

3. Completion and Taking-Over Taking-Over» In case the Employer starts using parts of the Works (other than as a temporary measure) before Taking-Over, then that part shall be deemed to have been taken over as from the date on which it is used, the Contractor shall cease to be liable for the care of such part as from this date, when responsibility shall pass to the Employer, if requested by the Contractor, the Engineer shall issue a Taking-Over Certificate for this part. 17/37

4. Defects Liability The Defects Notification Period Taking-Over Rectifying snaglist items Contractor s remedial actions Notifying Defects Defects Notification Period 18/37

4. Defects Liability Cost of Remedying Defects» The risk and cost of remedial works rests with the Contractor, provided that the remedial work is attributable to: any design for which the Contractor was responsible, Plant, Materials or workmanship not being in accordance with the Contract, failure by the Contractor to comply with any other obligation.» If the remedial work was not attributable to any of the items listed above, Clause 13 [Variations] shall apply.» The Defects Notification Period may be extended as a result of Employer s claim however extension must not exceed 2 years! 19/37

4. Defects Liability Performance Certificate» Only with the Engineer s issuing the Performance Certificate can the Contractor's obligations be considered to have been completed [date to be stated in the Certificate!].» The Performance Certificate shall be issued within 28 days the latest of the expiry dates of the Defects Notification Periods OR as the Contractor has supplied all the Contractor's Documents and completed and tested all the Works, including remedying any defects. Only the Performance Certificate shall be deemed to constitute acceptance of the Works BUT for unfulfilled obligations! 20/37

5. Accepted Contract Amount / Contract Price The Contract Price» shall include all taxes and duties to be paid by the Contractor.» Any quantities which may be set out in the Bill of Quantities or other Schedule are estimated quantities and are not to be taken as the actual and correct quantities.» A proposed breakdown of each lump-sum amount in any Schedule shall be submitted to the Engineer within 28 days after the Commencement Date. 21/37

6. Measurement and Valuation Works to be measured» Regular payments are based on Works performed, as measured (calculated from the unit prices given in the BoQ).» It is the Engineer to initiate measurement the Contractor shall attend and assist.» Wherever any Permanent Works are to be measured from records, these shall be prepared by the Engineer (Except as otherwise stated in the Contract).» In either case, Contractor s attendance is expected, if he fails to attend measurements / records shall be accepted as accurate! 22/37

6. Measurement and Valuation Method of measurement Session 3: FIDIC 1999 Red Book Part 2 shall be in accordance with the Bill of Quantities or other applicable Schedules AND shall be made of the net actual quantity of each item of the Permanent Works.» For each item of work, the appropriate rate or price for the item shall be the rate or price specified for such item in the Contract or, if there is no such item, specified for similar work.» New rate or price shall be appropriate for an item of work under certain circumstances (see S-C 12.3). 23/37

7. Payment Procedures Advance Payment» If the amount of Advance Payment is not stated in the Appendix to Tender it shall not be applicable!» Advance payment becomes due only after the Contractor furnished the Performance Security AND furnished the Advance Payment Guarantee.» Advance payment may be made in instalments.» Repayment of Advance is made always in instalments as deductions in the Interim Payment Certificates. 24/37

7. Payment Procedures Interim Payments» Interim payments are made by the Employer in possession of the Engineer s Interim Payment Certificates [IPC].» The Contractor shall apply for the Engineer s issuing the IPC-s by submitting a Statement.» The Statement shall include several items, as applicable, which shall be expressed in the various currencies in which the Contract Price is payable (See Sub-Clause 14.3).» Issuing an IPC may be withheld by the Engineer if: any thing supplied or work done by the Contractor is not in accordance with the Contract, OR the Contractor was or is failing to perform any work or obligation in accordance with the Contract. 25/37

7. Payment Procedures Interim Payments Contractor s Statement Engineer issues the IPC Employer pays Max. 28 days Max. 56 days» In case of delayed payments the Contractor becomes entitled to financing charges (without formal notice or certification or any claim procedure) 26/37

8. Risk and Responsibility, Force Majeure and Insurance Indemnities A Party shall indemnify and hold harmless the other Party against and from all claims, damages, losses and expenses. The Contractor shall indemnify for:» bodily injury, sickness, disease or death, of any person whatsoever arising out of or in the course of or by reason of the Contractor's design (if any), the execution and completion of the Works and the remedying of any defects (unless attributable to any negligence, wilful act or breach of the Contract by the Employer, the Employer's Personnel, or any of their respective agents), and» damage to or loss of any property, real or personal (other than the Works) [if attributable to the Contractor ]. Session 3: FIDIC 1999 Red Book Part 2 The Employer shall indemnify for:» bodily injury, sickness, disease or death, which is attributable to any negligence, wilful act or breach of the Contract by the Employer, the Employer's Personnel, or any of their respective agents, and» the matters for which liability may be excluded from insurance cover. 27/37

8. Risk and Responsibility, Force Majeure and Insurance Contractor s care of the Works» The Contractor shall take full responsibility for the care of the Works and Goods from the Commencement Date until the Taking-Over Certificate [TOC] is issued (After issuing the TOC responsibility for the care of the Works shall pass to the Employer).» Responsibility for outstanding Works at the issuing the TOC remains with the Contractor.» Contractor shall rectify at his own risk and cost any loss or damage happening to the Works, Goods or Contractor's Documents (from the cause not being Employer s risk) during the period of his responsibility.» Contractor remains liable for his actions after TOC is issued! 28/37

8. Risk and Responsibility, Force Majeure and Insurance Employer s Risks (a) war, hostilities (b) rebellion, terrorism (within the Country) (c) riot, commotion (within the Country) (d) munitions of war, explosives, ionising radiation (within the Country) (e) pressure waves (f) use or occupation by the Employer of any part of the Permanent Works, except as may be specified in the Contract, (g) design of any part of the Works by the Employer's Personnel or by others for whom the Employer is responsible, (h) any operation of the forces of nature, which is Unforeseeable 29/37

8. Risk and Responsibility, Force Majeure and Insurance Consequences of Employer s Risks Employer s Risk eventuates Contractor has to Loss or damage to: the Works, Goods or Contractor s Documents Give notice to the Engineer Rectify the loss or damage If the rectification results in additional cost and / or delay for the Contractor, subject to a separate notice, he becomes entitled to: + Cost AND EoT 30/37

8. Risk and Responsibility, Force Majeure and Insurance Limitation of Liability» Neither Party shall be liable to the other Party for loss of use of any Works, loss of profit, loss of any contract or for any indirect or consequential loss or damage which may be suffered by the other Party in connection with the Contract (other than payment on termination and indemnification).» The total liability of the Contractor to the Employer, under or in connection with the Contract shall not exceed the sum stated in the Particular Conditions or (if a sum is not so stated) the Accepted Contract Amount. [EXCEPTIONS!] This shall not limit liability in any case of fraud, deliberate default or reckless misconduct by the defaulting Party. 31/37

8. Risk and Responsibility, Force Majeure and Insurance Force majeure means an exceptional event or circumstance, which:» is beyond a Party's control,» such Party could not reasonably have provided against before entering into the Contract,» having arisen, such Party could not reasonably have avoided or overcome, and» is not substantially attributable to the other Party. FIDIC s example list [see S-Cl 19.1] is an OPEN list ( not limited to ) and overlaps with the Employer s Risks The cause may be both physical or LEGAL! 32/37

8. Risk and Responsibility, Force Majeure and Insurance Force majeure» If a Force Majeure event or circumstance occurs, the Party suffering from it shall give notice within 14 days to the other Party (shall also notify the end of being affected by the Force Majeure).» The Party shall, having given notice, be excused performance of such obligations for so long as such Force Majeure prevents it from performing them.» Force Majeure shall not apply to obligations of either Party to make payments to the other Party under the Contract.» Each Party shall at all times use all reasonable endeavours to minimise any delay in the performance of the Contract. 33/37

8. Risk and Responsibility, Force Majeure and Insurance Force majeure» The consequences: The Contractor shall be entitled to EoT and Cost ( only in specific Force Majeure causes! See S-Cl 19.4). Any subcontractor s broader release terms in the subcontract does not excuse the Contractor s nonperformance or additional relief not entertained. If the Force Majeure is longer than 84 days OR an aggregate of shorter FM events exceeds 140 days either Party may terminate the Contract with a 7 days notice. Upon such termination, the Engineer shall determine the value of the work done and issue a Payment Certificate. 34/37

8. Risk and Responsibility, Force Majeure and Insurance Insurance» Any of the Parties can be the insuring Party (responsible for effecting and maintaining the insurance).» If a policy is required to indemnify joint insured, the cover shall apply separately to each insured as though a separate policy had been issued for each of the joint insured.» A policy may indemnify additional joint insured.» The insuring Party shall, within the periods stated in the Appendix to Tender (calculated from the Commencement Date), submit to the other Party: evidence that the insurance have been effected, AND copies of the policies. 35/37

8. Risk and Responsibility, Force Majeure and Insurance Insurance» Neither Party shall make any material alteration to the terms of any insurance without the prior approval of the other Party.» If the insuring Party fails to effect and keep in force any of the insurances required (or fails to provide satisfactory evidence and copies of policies) the other Party may effect them and pay the premiums due and the failing Party shall reimburse the other party.» The insuring Party shall insure the Works, Plant, Materials and Contractor's Documents for not less than the full reinstatement cost including the costs of demolition, removal of debris and professional fees and profit. Effectiveness: until the date of issue the TOC. 36/37

Thank you for your kind attention! Zoltán Záhonyi zoltan.zahonyi@zandpartners.com