REPORT ON THE TECHNICAL AND FINANCIAL REVIEW OF ROAD MAINTENANCE PROJECTS IN KABALE MUNICIPAL COUNCIL FOR THE FINANCIAL YEAR

Similar documents
A CASE STUDY OF MUNICIPAL COUNCILS

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF LOCAL GOVERNMENT FINANCE COMMISSION FOR THE YEAR ENDED 30 TH JUNE, 2015

MINISTRY OF LANDS, HOUSING & URBAN DEVELOPMENT

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE NATIONAL COUNCIL FOR DISABILITY FOR THE FINANCIAL YEAR ENDED 30 TH JUNE 2015

OFFICE OF THE AUDITOR GENERAL THE REPUBLIC OF UGANDA UGANDA HIGH COMMISSION, CANBERRA

REPORT OF THE AUDITOR GENERAL

OFFICE OF THE AUDITOR GENERAL THE REPUBLIC OF UGANDA

PART 6 - INTERNAL CONTROL

External Audit. April 2012

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF UGANDA INVESTMENT AUTHORITY (UIA) FOR THE YEAR ENDED 30 TH JUNE 2015

OFFICE OF THE AUDITOR GENERAL

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE UGANDA NATIONAL EXAMINATIONS BOARD FOR THE YEAR ENDED 30 TH JUNE 2014

Strengthening Public Financial Management and Accountability

Presentation at Asian Highways Investment Forum. Performance based Maintenance Contracts for Highways

The Republic of Uganda

OFFICE OF THE AUDITOR GENERAL THE REPUBLIC OF UGANDA

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE NAKIVUBO WAR MEMORIAL STADIUM TRUST FOR THE YEAR ENDED 31 ST DECEMBER 2013

Chapter 7 Department of Transportation and Infrastructure. Pre-mixed Asphalt Procurement

Laois County Council Licence for Opening Roads, Footpaths and Verges. Application Form

5.6 Annual Report. Compliance Checklist for Annual Report November Name of Issuer: Name of Submitter(s): Name of Submitter(s) Organisation:

IFAD Handbook for Financial Reporting and Auditing of IFAD- Financed Projects

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF UGANDA PRINTING AND PUBLISHING CORPORATION FOR THE YEAR ENDED 30 TH JUNE 2016

AUDIT UNDP COUNTRY OFFICE UGANDA. Report No Issue Date: 22 August 2013

IFAD Handbook for Financial Reporting and Auditing of IFAD-financed Projects

ANNUAL PERFORMANCE AGREEMENTS BETWEEN THE ROAD AGENCY AND ROAD FUND OR PARENT MINISTRY

THE REPUBLIC OF UGANDA

AUDIT UNDP COUNTRY OFFICE AFGHANISTAN FINANCIAL MANAGEMENT. Report No Issue Date: 10 December 2013

THE REPUBLIC OF UGANDA

AUDIT OF ADB LOANS 2099-FSM (SF) AND 2100-FSM OMNIBUS INFRASTRUCTURE DEVELOPMENT PROJECT SEPTEMBER 30, 2010 REPORT NO

OFFICE OF THE AUDITOR GENERAL

Norfolk County Asset Management Plan Roads

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF MINISTRY OF TRADE, INDUSTRY AND COOPERATIVES FOR THE YEAR ENDED 30 TH JUNE 2017

OFFICE OF THE AUDITOR GENERAL

AUDIT UNDP NIGERIA. DEMOCRATIC GOVERNANCE FOR DEVELOPMENT: DEEPENING DEMOCRACY IN NIGERIA (Directly Implemented Project No , Output No.

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE NATIONAL SOCIAL SECURITY FUND FOR THE YEAR ENDED 30 th JUNE, 2015

REPORT OF THE AUDITOR GENERAL

OFFICE OF THE AUDITOR GENERAL THE REPUBLIC OF UGANDA

INTERNATIONAL ASSOCIATION OF INSURANCE SUPERVISORS INSURANCE CORE PRINCIPLES SELF-ASSESSMENT QUESTIONNAIRE

MINISTRY OF LOCAL GOVERNMENT

Terms of Reference for Financial Audit of Implementing Partners. UNICEF Nigeria Country Office Expenditures

THE REPUBLIC OF UGANDA

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE UGANDA EMBASSY, RIYADH FOR THE FINANCIAL YEAR ENDED 30 TH JUNE, 2015

AUDIT UNDP COUNTRY OFFICE SOMALIA. Report No Issue Date: 20 June 2014

Securitization. Management exercises authority that should rest with the board or engages in activities that expose the institution to excessive risk.

OFFICE OF THE AUDITOR GENERAL THE REPUBLIC OF UGANDA UGANDA EMBASSY, ADDIS ABABA

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE MINISTRY OF TRADE, INDUSTRY AND COOPERATIVES FOR THE YEAR ENDED 30 TH JUNE 2014

UGANDA HUMAN RIGHTS COMMISSION

Office of the Valuer-General Audit Report

OFFICE OF THE AUDITOR GENERAL

UGANDA HIGH COMMISSION, KIGALI

OFFICE OF THE AUDITOR GENERAL

OFFICE OF THE AUDITOR GENERAL THE REPUBLIC OF UGANDA

IOPS Toolkit for Risk-Based Pensions Supervision Kenya

THE MANAGEMENT OF ROAD PROJECTS IN PAPUA NEW GUINEA

Audit Report. Canada Small Business Financing Program

PROGRAM FIDUCIARY SYSTEMS ASSESSMENT

THE REPUBLIC OF UGANDA

HDM-4 Applications. Project Appraisal. Project Formulation. Maintenance Policy Optimization. Road Works Programming. Network Strategic Analysis

Kenya Gazette Supplement No. 42 3rd April, (Legislative Supplement No. 19)

Harden Contributions Plan for Heavy Haulage Developments. Adopted by Council Resolution No. 277/11/11 16 th November, Prepared by.

The Public Financial Management Bill, 2012 THE PUBLIC FINANCIAL MANAGEMENT BILL, 2012 ARRANGEMENT OF CLAUSES PART I PRELIMINARY

INTERNAL AUDIT DIVISION REPORT 2016/155. Audit of the United Nations Human Settlements Programme project management process

AUDIT OF ADB GRANT ASSISTANCE SEPTEMBER 30, 2010 REPORT NO

Internal Audit Policy

Audit Report 2018-A-0001 City of Lake Worth Water Utility Services

Department of Enterprise, Trade & Employment

Validation of Mali Extractive Industries Transparency Initiative

SECTION 9: AUDIT OUTCOMES OF INDIVIDUAL PORTFOLIOS. Consolidated general report on national and provincial audit outcomes for

Revenue Sharing Program Guidelines

Town of South Bruce Peninsula. Tender PW Asphalt Paving

Revenue Sharing Program Guidelines

Growth in distribution and share price Governance and compliance

OFFICE OF THE AUDITOR GENERAL THE REPUBLIC OF UGANDA

TRENCH PERMIT. CITY OF SOMERSWORTH NH 18 Lilac Lane - (603) Please Fax at (603) Date: Permit# Dig Safe # Fee = $70.

City of Glendale, Arizona Pavement Management Program

Town of South Bruce Peninsula. Tender PW Resurfacing of D Line

REPUBLIC OF KENYA REPORT THE AUDITOR-GENERAL THE FINANCIAL OPERATIONS OF NAROK COUNTY EXECUTIVE FOR THE PERIOD 1 JULY 2013 TO 30 JUNE 2014

LANE TRANSIT DISTRICT EUGENE, OREGON AUDIT OF FEDERAL AWARDS

Document No: AUDIT REPORT ON THE ANNUAL FINANCIAL STATEMENTS OF MUNICIPALITY OF KAMENICA FOR THE YEAR ENDED 31 DECEMBER 2017

Specified Procedures for Assurance Engagements at Smaller Authorities Version issued on: 17 January 2017

Draft for Consultation

Themed Audit Schools Budget Setting, Management and Control

Financial Services Authority FINAL NOTICE. The Kyte Group Limited. Business Design Centre 52 Upper Street London N1 0QH. Date: 21 August 2006

Guidance on a common methodology for the assessment of management and control systems in the Member States ( programming period)

REPORT 2015/085 INTERNAL AUDIT DIVISION

EPWP INCENTIVE GRANT MANUAL

GUIDANCE DOCUMENT ON THE FUNCTIONS OF THE CERTIFYING AUTHORITY. for the programming period

Standard Operating Procedure. For. Financial Resources Management (CU/SOP/FIND/24)

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF THE DAIRY DEVELOPMENT AUTHORITY FOR THE FINANCIAL YEAR ENDED 31 ST DECEMBER, 2015

OFFICE OF THE CONTROLLER CITY OF PHILADELPHIA PENNSYLVANIA. Alan Butkovitz City Controller

MANAGERIAL ACCOUNTABILITY AND RISK MANAGEMENT

SEACO TAX POLICY. Seaco Tax Policy Page 1

Report on FSCO s Compliance Reviews Of Mortgage Administrators. Financial Services Commission of Ontario Licensing and Market Conduct Division

REPORT OF THE AUDITOR GENERAL ON THE FINANCIAL STATEMENTS OF UGANDA INVESTMENT AUTHORITY (UIA) FOR THE FINANCIAL YEAR ENDED 30 TH JUNE 2014

Assurance Approach Delivery assurance activities for Retail Market Release April 2019

HIGHLANDS COUNTY BOARD OF COUNTY COMMISSIONERS

CONSULTANT S AGREEMENT

FIDUCIARY ARRANGEMENTS FOR SECTORWIDE APPROACHES (SWAPS)

Town of Henrietta. Financial Management and Purchasing. Report of Examination. Period Covered: January 1, 2011 March 29, M-208

University System of Maryland Coppin State University

Transcription:

REPORT ON THE TECHNICAL AND FINANCIAL REVIEW OF ROAD MAINTENANCE PROJECTS IN KABALE MUNICIPAL COUNCIL FOR THE FINANCIAL YEAR 2015-16 1 P a g e

TABLE OF CONTENTS 1. EXECUTIVE SUMMARY... 3 1.1 Introduction... 3 1.2 Objective of the technical and financial reviews... 3 1.3 Scope of Review... 3 1.4 Performance assessment... 4 1.5 Summary of performance... 4 1.6 Conclusion... 4 1.7 Summary of issues and action matrix... 5 2. DETAILS OF THE TECHNICAL AND FINANCIAL REVIEW FINDINGS... 6 3. SPECIFIC TECHNICAL REVIEW FINDINGS ON SELECTED ROADS INSPECTED... 11 3.1 Sealing maintenance of Mukombe road (900 m)... 11 3.2 Periodic maintenance of Nyemera road (900 m)... 12 3.3 Periodic maintenance of Kekubo-Rutooma Road (1.2km)... 13 3.4 Sealing of Rwamafa Road (700m)... 14 4. APPENDICES... 15 4.1 Appendix I Table of detailed performance assessment... 15 2 P a g e

REPORT ON THE TECHNICAL AND FINANCIAL REVIEW OF ROAD MAINTENANCE PROJECTS IN KABALE MUNICIPAL COUNCIL FOR THE FINANCIAL YEAR 2015-16 1. EXECUTIVE SUMMARY 1.1 Introduction The Uganda Road Fund Act 2008 established the Uganda Road Fund (URF) for the purpose of financing routine and periodic maintenance of public roads; to facilitate the delivery of road maintenance services; to provide for the management of the Fund; and for other related matters. The objectives are: To finance the routine and periodic maintenance of public roads in Uganda; To ensure that public roads are maintained at all times; and To advise the Minister, in consultation with the Minister responsible for roads and the Minister responsible for local governments on; the preparation, efficient and effective implementation of the Annual Road Maintenance Programme; and the control of overloading of vehicles on public roads. 1.2 Objective of the technical and financial reviews The URF performed a technical and financial review of road maintenance projects in Kabale Municipal Council for the period July 2015 to June 2016. The purpose of the review was to provide assurance to the URF Board that funds disbursed in the period under review were utilised in accordance with the provisions in the work plans, performance agreements and the URF Act. Furthermore, the review aimed to verify that the use of such resources was efficient, effective and with due regard to economy and transparency. The specific objectives of the review were: To establish financial propriety in management of URF funds; To establish the extent of compliance with laws, regulations, guidelines, performance agreements and work plans in fund management, procurement and program implementation; To determine the extent to which funded works and services were executed by Kabale Municipal Council; and To determine effectiveness of oversight and support organs such as Internal Audit on work plans and programs of Kabale Municipal Council. 1.3 Scope of Review The review was carried out based on the relevant laws and regulations including but not limited to: a) The Uganda Road Fund Act 2008; b) The Public Finance Management Act 2015; c) The Public Procurement and Disposal of Public Assets Act 2003; d) The Internal Audit Manual of the Uganda Road Fund; e) The Finance and Accounting Manual of the Uganda Road Fund; f) One Year Road Maintenance Plans for FY2015/16; 3 P a g e

g) Performance agreements for FY2015/16; and h) Other standards of sound professional practice. The budget of the Municipal Council for the FY2015/16 was UGX 1,047,367,040/= which was planned to finance the activities summarised below in: Routine Manual (UGX) Routine Mechanised (UGX) Periodic Maintenance (UGX) Mechanical Imprest (UGX) Other Works (UGX) Total (UGX) UGX 152,639,970 (94.91KM) UGX151,740,340 (29KM) UGX 625,925,810 (3.78KM) UGX 67,976,440 UGX 49,084,480 UGX 1,047,367,040 (127.69KM) 1.4 Performance assessment This report presents performance of the Kabale MC during the period, identifying the critical exceptions in governance, financial management, procurement, project implementation and reporting that need to be addressed. The agency was rated and scored in the above mentioned performance areas against a standard scale as defined below: Overall performance rating (%) 0-25 Unsatisfactory 25-50 Weak 50-75 Adequate 75-100 Good The report also includes suggested recommendations and proposed way forward. 1.5 Summary of performance The table below summarises the Municipal Council performance in the various areas reviewed by the audit team. Details of the assessment are attached in Appendix II. 1.6 Conclusion No. Performance Area Weight (%) Aggregated Score (%) 1 Planning and Budgeting 20 15 2 Procurement Processes 8 08 3 Project Management and Control 30 22 4 Actual Works Done 25 13 5 Oversight 10 07 6 Agency Capacity 7 04 Total 100 69 Based on the evaluation of the function areas highlighted above, the performance of the Municipal Council is rated at 69% which is adequate. Management needs to put in place an appropriate action plan to address the exceptions noted and ensure effective utilisation of URF s funds in future. 4 P a g e

1.7 Summary of issues and action matrix Issue Action Required Action by To conduct quality control tests on TC 1. Deviation from engineering design, all construction materials and practices and implementation standards: during project implementation a. Inadequate quality control procedures To develop a schedule for unit rates to guide planning on annual basis b. Lack of unit rates schedule for planning in the FY To ensure adequate compaction of c. Inadequate compaction for earthworks earthworks To place signage on all major d. Narrow carriageways projects as a standard practice e. Failure to install project information To improve documentation of signage project management and prepare f. Lack of final accounts for completed final accounts / report for each projects, completed project; and Follow MoWT standards for road works at all times 2. Failure to maintain accurate records and information for the following key functions and activities: a. Tracking budget performance for projects against actual costs b. Accountability reports and source records To maintain the requisite records to budgets during implementation of projects. To reconcile the accountability reports (Q1 to Q4) to the source records. TC Deadline Effective Q2 of FY2016/17 Immediate 3. Poor drainage system of Mukombe road 4. Inadequate oversight over road maintenance funding Urgently install stone pitched side drains and relief culverts on Mukombe Road Oversight over road maintenance funds should be increased to ensure value for money. TC By June 2017 TC Immediate 5 P a g e

2. DETAILS OF THE TECHNICAL AND FINANCIAL REVIEW FINDINGS AREA STATEMENT OF CONDITION/FINDING IMPLICATION RESPONSE RECOMMENDATIONS PLANNING AND BUDGETING Annual work plan for the FY2015/16 The annual work plan for the FY2015/16 was in place and submitted to the URF on the 28 th July 2015. However, the following observations were noted: o A schedule of unit rates for formulation of the annual work plan was not availed nor used in the budgeting process. Lack of a unit rate schedule makes assessment of the reasonableness of road maintenance costs impossible The Municipal Council derives unit rates to guide planning. These shall be submitted to URF going forward The Municipal Council should derive unit rates to guide its planning and project implementation process and attached to the work plans submitted to URF. Budget performance monitoring The data on budget performance was not availed during the review. Although the team was availed actual expenditure as recorded in IFMS, it was not analysed between the different categories of expenditure as recommended by URF. As a consequence the actual expenditure of the Municipal Council could not be ascertained. Failure to analyse actual expenditure as per the recommended expenditure categories prohibits tracking of the work plan and performance. The advice of regularly analysing actual expenditure along given budget lines to enable tracking of budget performance has been noted is to be implemented going forward The agency should regularly analyse its actual expenditure between the recommended expenditure categories to enable tracking of its work plan and budget for proper decision making. PROCUREMENT OF SUPPLIES Procurement plan and records The audit team was availed with the procurement plan of the period under review. It included the planned procurements for road maintenance. Procurement records for the supply of material used in road maintenance activities were in place. In addition the Municipal executed framework contracts during the year which made the supply of materials be undertaken in a fairly timely manner. Procurements were undertaken in a transparent and competitive manner. Noted with thanks. The practice shall be upheld Keep it up PROJECT MANAGEMENT Inadequate quality control procedures Value for money cannot be guaranteed The suppliers have been requested to deliver All works should be executed in accordance 6 P a g e

AREA STATEMENT OF CONDITION/FINDING IMPLICATION RESPONSE RECOMMENDATIONS AND CONTROL Section 9 (e) of the performance agreement required the Municipal to ensure that all maintenance works are conducted in accordance with quality standards. Kabale MC violated the above provision during execution of works on some of its projects as noted below: due to uncertainty on the quality of materials used. construction materials with quality test results which shall be verified from the Municipal Council s laboratory. with acceptable standards in relation to design, documentation and testing suitability of materials used. FINANCIAL MANAGEMENT RECORDS Using aggregates and bitumen in the resealing of Rwamafa road that were not subjected to quality tests. There was no records of in-situ quality tests conducted during project implementation. Project management documentation Kabale MC maintained project monitoring reports. However, there are key documents that were not maintained by the agency such as records of approval of work program, project specific progress reports and measurement of actual works done at completion (final accounts) for the implemented projects. Discrepancies in accountability records and reports Section 5 (b) (i) of the performance agreement requires the DA to provide comprehensive and satisfactory accountability reports for the funds disbursed in a form prescribed by URF. A review of the accountability records revealed the following: The financial accountability reports for FY 15/16 were prepared by the Municipal Council Engineer instead of the Head of Finance. This undermines independence of functions between financial and technical management. A review of actual expenditure revealed a variance of UGX 100,144,925 between There is poor project implementation and improper accountability. This makes it difficult to assess value for money on implemented projects This has led to inaccuracies and inconsistencies between the records and the accountability reports submitted to URF. Poor project documentation is as a result of low staffing levels. The Municipal Council has however started to involve the road gangs overseers and headmen for improvement. The reports are jointly prepared by Finance and Engineering personnel The omission of expenditure on Rwamafa Road was an anomaly. However, it has been captured in the soft copy accountability report submitted to URF. All anomalies in practice have been noted and shall be improved going forward Kabale MC should improve project management documentation and include final accounts that are specific to road projects implemented. Accountability reports of the Municipal Council should be reviewed by the Head of Finance prior to submission to the URF. The discrepancy in the expenditure recorded should be reconciled and resubmitted to URF. 7 P a g e

AREA STATEMENT OF CONDITION/FINDING IMPLICATION RESPONSE RECOMMENDATIONS expenditure recorded in the accountability reports (UGX 765,108,970) and IFMS (UGX 664,964,045). Further analysis of the total expenditure under IFMS (UGX 664,964,045/=) against the actual release during the financial year (UGX 737,502,278/=) revealed a discrepancy of UGX72, 538,233/= as unspent. The expenditure on Rwamafa road to the tune of UGX99M/= was not captured in the accountability reports submitted to URF Lapses in reconciliation may result in loss of cash without detection. Bank reconciliations should be prepared and certified by CFO. There was failure to certify cashbooks and bank reconciliation statements Section 6.4.2.6 of the LGFAM, 2007 requires that bank reconciliation to be prepared not later than fifteen days after the end of each month. The statement should also be certified by the Head of Finance. Although the bank reconciliation statements were prepared and printed off IFMS, they were not certified by the CFO. EVALUATION OF PROJECTS IMPLEMENTED Lack of project information signage Clause 9 (k) of the performance agreements required Kabale MC to install appropriate signage at the beginning and end of every road on all road works under URF funding. The signage should show road name, funder, financial year, length of the road, activity being undertaken and the road management type. Kabale MC did not install any signage on all the roads that were inspected in the FY2015/16. This implies lack of compliance with guidelines and performance agreements. The issue of signage has been noted. There s signange installed on all major projects currently. The agency should place signage on all major projects as a standard practice. Deviation from engineering design standards and practices Section 9 (e) of the performance agreements stipulates that the designated agencies must ensure This implies lack of compliance with guidelines and The agency should follow the MoWT standards as a guide for project 8 P a g e

AREA STATEMENT OF CONDITION/FINDING IMPLICATION RESPONSE RECOMMENDATIONS that all maintenance works are conducted in accordance with the relevant quality standards and shall pay particular attention to design standards. Kabale MC was found to deviate from this stipulation on some of the inspected projects. For example; o o All inspected roads were constructed with narrow carriageways averaging 4m instead of the required minimum of 5.4 for urban roads. and Culvert installations along Kekubo-Rutooma road were undertaken without compaction of the backfill earthworks. Inadequacy of maintenance interventions in place performance agreements. Failure to follow standard practices means value for money cannot be guaranteed due to substandard output. There is a risk of extended damage and higher losses on the road asset value hence increased overall maintenance costs. There has been an issue of encroachment by developers. However, this is currently being addressed. The agency lacked a roller at the time. The pedestrian roller had also broken down. There s expectation of acquisition of compaction equipment in the new road unit implementation. Kabale MC should to prioritise projects so as to undertake the most critical projects. Project inspections revealed that there was need for urgent maintenance interventions. For example; o The drainage system of Mukombe road required urgent improvement by incorporation of stone-pitched side drains and several culvert installations, and o The loose aggregates placed on Rwamafa road should be swept urgently to curb segregation. Overdesign of Mukombe road There is risk of unnecessary loss of road maintenance funds Stone pitching on critical areas is being done while culvert installations are completed. Loose aggregates along Rwamafa road were finally swept. There was no clear justification on the use of premix hot mix asphalt to construct the wearing course of Mukombe road which cost UGX241.9M/=. A cheaper alternative of DBST could have cost UGX150M/= therefore saving funds for other road maintenance works. Mukombe road is heavily trafficked and seldom carries heavy traffic loads as a by-pass to Kisoro. Thus the justification for the use of a 40mm Asphalt overlay The agency should undertake road maintenance works with due consideration to current needs 9 P a g e

AREA STATEMENT OF CONDITION/FINDING IMPLICATION RESPONSE RECOMMENDATIONS OVERSIGHT Oversight on URF projects Although the team reviewed the internal audit reports on road maintenance activities for the FY under review, it was noted that adequate oversight on road maintenance funds is still lacking. Lack of assurance during project implementation Oversight has been intensified by involvement of other stakeholders to ensure value for money. Due to low staffing levels in Engineering department, road gang overseer and headmen being involved in works other than the road gang works. Internal Audit to ensure adequate oversight on both financial management and technical aspects of road maintenance activities.. CAPACITY Capacity to implement projects At the time of the review, Kabale MC lacked compaction equipment hence the poor construction of earthworks. This reduces Kabale MC s ability to properly implement road maintenance programs. Kabale MC lacks the appropriate road equipment such as a roller. We hope to get one in the awaited roads unit Kabale MC should ensure that it has all its key equipment for road maintenance in good shape at all times. 10 P a g e

3. SPECIFIC TECHNICAL REVIEW FINDINGS ON SELECTED ROADS INSPECTED 3.1 Sealing maintenance of Mukombe road (900 m) Planned amount (UGX) 237,390,000/= Actual sum (UGX) 241,900,000/= Variance 4,510,000/= Start date Not on file Completion date Not on file Management type Force Account Supervisor Municipal Engineer Activity done Resealing with Hot Mix Asphalt Project Description and Condition The project is a 900m paved urban road with a 7.0 m wide roadway and 5.8m carriageway. The road traverses a hilly terrain. The road received resealing by application of 40mm thick overlay of hot mix asphalt at an estimated cost of UGX 241.9M/=. At the time of the review, the road was at a good service level and motorable through the entire stretch. However, it requires urgent drainage improvement. Review Findings Over design for wearing course leading to expensive surfacing at UGX241.9M/=. A surface dressed wearing course would ve cost an estimated UGX150M/=, Lack of project information signage, and Inadequate drainage provisions. Photographs from field inspection of Mukombe road (900 m) 0+000: Surface treated with HMA Ch. 0+800: Drainage improvement required by provision of lined drains and relief culverts 11 P a g e

3.2 Periodic maintenance of Nyemera road (900 m) 4.1 Planned amount (UGX) 33,000,000/= Actual sum (UGX) 33,001,200/= Variance 1,200/= Start date Not on file Completion date Not on file Management type Force Account Supervisor Municipal Engineer Activity done Periodic maintenance Project Description and Condition The project is a 900 m unpaved urban road with a 6.0 m wide roadway and 4m carriageway. The road traverses a rolling terrain. The road received periodic maintenance by reshaping and full regravelling (100mm thickness) with drainage improvements at an estimated cost of UGX 33M/=. At the time of the review, the road was at a good service level and motorable through the entire stretch. Review Findings Lack of project information signage, High unit rate for periodic maintenance due to multiple overlapping items, Lack of final account documentation, and Narrow carriageway at 4m instead of the required 5.4m. Photographs from field inspection of Nyemera road (900m) Ch. 0+000: Project information signage lacking 4.2 4.3 A well maintained section of the road 12 P a g e

3.3 Periodic maintenance of Kekubo-Rutooma Road (1.2km) 4.4 Planned amount (UGX) 49,689,000/= Actual sum (UGX) 49,688,240/= Variance 760/= Start date Not on file Completion date Not on file Management type Force Account Supervisor Municipal Engineer Activity done Periodic maintenance Project Description and Condition The project is a 1.2 km unpaved urban road with a 6.0 m wide roadway and 4.5m carriageway. The road traverses a rolling terrain. The road received periodic maintenance by reshaping and full regravelling (100mm thickness) with drainage improvements at an estimated cost of UGX 49.7M/=. At the time of the review, the road was at a good service level and motorable through the entire stretch. Review Findings Lack of project information signage, High unit rate for periodic maintenance due to multiple overlapping items, Lack of compaction of culvert backfill, Lack of final account documentation, and Narrow carriageway at 4.5m instead of the required 5.4m. Photographs from field inspection of Kekubo-Rutooma Road (1.2km) Ch. 0+000: Project information signage lacking 4.5 1+100: Poor compaction of culvert backfill material 13 P a g e

3.4 Sealing of Rwamafa Road (700m) Planned amount (UGX) 178,500,000/= Actual sum (UGX) 99,364,640/= Variance 79,135,360/= Start date Not on file Completion date Not on file Management type Force Account Supervisor Municipal Engineer Activity done Resealing Project Description and Condition The project is a 700m paved urban road with a 6.0 m wide roadway and 4.5m carriageway. The road traverses a flat terrain. The road was resealed with double bituminous surface treatment at an estimated cost of UGX 99.4M/=. At the time of the review, the road was at a fair service level and motorable through the entire stretch. Review Findings Lack of project information signage, Segregation of aggregates, The project was not included in the accountability report, Bituminous works were not subjected to quality control tests, Lack of final account documentation. Culvert installations were not in the BOQ, and Narrow carriageway at 4.5m instead of the required 5.4m minimum. Photographs from field inspection of Rwamafa Road (700m) Sealed surface with loose aggregate Culvert installation 14 P a g e

4.6 4. APPENDICES 4.7 4.8 Appendix I Table of detailed performance assessment No. PERFORMANCE AREA Priority Score %age Aggregate (%) (0-3) Score score 1 PLANNING AND BUDGETING 20 1.1 Road Inventory and condition surveys 3.00 0.17 3 1.2 Work plan 3.00 0.17 3 1.3 Performance agreements 3.00 0.17 3 1.4 Adequacy of the unit rates 0.50 0.03 1 1.5 Budget performance monitoring 1.50 0.08 2 1.6 Procurement plan 3.00 0.17 3 18 16 2 PROCUREMENT PROCESSES 8 2.1 Compliance with PPDA guidelines 3.00 1.00 8 3 8 3 PROJECT MANAGEMENT AND CONTROL 30 3.1 Checklist of expected documents (BOQs etc.) 2.00 0.17 5 3.2 Quality and cost control records 2.50 0.21 6 3.3 Supervision reports 2.00 0.17 5 3.4 Financial management records 2.50 0.21 6 12 23 4 ACTUAL WORKS DONE 25 4.1 Signage 0.00 0.00-4.2 Verification of actual works done 3.00 0.25 6 4.3 Adherence to construction standard practices 2.00 0.17 4 4.4 Justification of maintenance needs 1.50 0.13 3 12 14 5 OVERSIGHT 10 5.1 Internal audit reports 1.50 0.13 1 5.2 District Roads Committee 2.00 0.17 2 5.3 DEC 2.00 0.17 2 15 P a g e

5.4 CAO 2.00 0.17 2 12 6 6 AGENCY CAPACITY 7 6.1 Staffing levels and competencies 2.50 0.21 1 6.2 Equipment 1.80 0.15 1 6.3 Funding needs 1.50 0.13 1 6.4 IT Infrastructure 2.50 0.21 1 12 5 TOTALS 100 71 16 P a g e