DOES LOST TIME COST YOU MONEY AND CREATE HIGH RISK?

Similar documents
Use of the Risk Driver Method in Monte Carlo Simulation of a Project Schedule

Chapter-8 Risk Management

PROJECT SCENARIOS, BUDGETING & CONTINGENCY PLANNING

Integrated Cost-Schedule Risk Analysis Improves Cost Contingency Calculation ICEAA 2017 Workshop Portland OR June 6 9, 2017

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Cost Risk Assessments Planning for Project or Program Uncertainty with Confidence Brian Bombardier, PE

Cost Risk Assessment Building Success and Avoiding Surprises Ken L. Smith, PE, CVS

RISK MANAGEMENT. Budgeting, d) Timing, e) Risk Categories,(RBS) f) 4. EEF. Definitions of risk probability and impact, g) 5. OPA

Fundamentals of Project Risk Management

CHAPTER 5 STOCHASTIC SCHEDULING

Integrated Cost Schedule Risk Analysis Using the Risk Driver Approach

Preprint: Will be published in Perm Winter School Financial Econometrics and Empirical Market Microstructure, Springer

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

International Journal of Advanced Engineering and Management Research Vol. 2 Issue 4, ISSN:

Performance risk evaluation of long term infrastructure projects (PPP-BOT projects) using probabilistic methods

STOCHASTIC COST ESTIMATION AND RISK ANALYSIS IN MANAGING SOFTWARE PROJECTS

SIL and Functional Safety some lessons we still have to learn.

Making sense of Schedule Risk Analysis

machine design, Vol.7(2015) No.4, ISSN pp

Probabilistic Safety Analysis (PSA): Applications. Guideline for Swiss Nuclear Installations ENSI-A06

Risk Assessment of the Niagara Tunnel Project

STRESS TEST MODELLING OF PD RISK PARAMETER UNDER ADVANCED IRB

RISK IDENTIFICATION ON CONSTRUCTION PLAN FOR HTGR-10 IN INDONESIA

METHODOLOGY For Risk Assessment and Management of PPP Projects

Cost Risk and Uncertainty Analysis

The Cost of Poor Reliability for Future Particle Accelerator Driven Systems in the UK Energy Market

International Project Management. prof.dr MILOŠ D. MILOVANČEVIĆ

Unit 9: Risk Management (PMBOK Guide, Chapter 11)

Stochastic SIL Verification for Complex Safety Instrumented Systems

Project Management Chapter 13

California Department of Transportation(Caltrans)

SCHEDULE CREATION AND ANALYSIS. 1 Powered by POeT Solvers Limited

Stochastic Modelling: The power behind effective financial planning. Better Outcomes For All. Good for the consumer. Good for the Industry.

5.- RISK ANALYSIS. Business Plan

DATA GAPS AND NON-CONFORMITIES

SIMULATION OF ELECTRICITY MARKETS

AAS BTA Baltic Insurance Company Risks and Risk Management

Expenditure Forecast Methodology

Risk Video #1. Video 1 Recap

SAMPLE. CPM SCHEDULE RISK MODELING AND ANALYSIS: SPECIAL CONSIDERATIONS TCM Framework: 7.6 Risk Management

Breaking down OpRisk Value-at-Risk for management purposes

RISK EVALUATION OF PRODUCTION AND IMPLEMENTATION OF THE PROJECT

Vanguard Global Capital Markets Model

THE JOURNAL OF AACE INTERNATIONAL - THE AUTHORITY FOR TOTAL COST MANAGEMENT TM

NATURAL SPI. Optimizing Risk Management. NDIA 9 TH Annual Systems Engineering Conference October 23-26, 2006 San Diego, CA. Rick Bollinger, PMP

Probabilistic Benefit Cost Ratio A Case Study

Managing Project Risk DHY

A. Introduction. B. Requirements and Measures

Standard Development Timeline

MODELING SCHEDULING UNCERTAINTY IN CAPITAL CONSTRUCTION PROJECTS. S. M. AbouRizk

Programmatic Risk Management in Space Projects

Pickering Whole-Site Risk

PROJECT MANAGEMENT: PERT AMAT 167

Model Risk. Alexander Sakuth, Fengchong Wang. December 1, Both authors have contributed to all parts, conclusions were made through discussion.

Project Theft Management,

Integrated Earned Value Management and Risk Management Approach in Construction Projects


Field Tests of Economic Value-Based Solvency Regime. Summary of the Results

The Risky Business of. Risk Management

Alternative VaR Models

White Paper. Risk Assessment

CONTINGENCY. Filed: EB Exhibit D2 Tab 2 Schedule 7 Page 1 of 10

RISK MANAGEMENT IN CONSTRUCTION PROJECTS

MINI GUIDE. Project risk analysis and management

Making conservative estimates for emissions in accordance with Article 70

Zurich Hazard Analysis (ZHA) Introducing ZHA

Factors Affecting the Amount of Time Required to Prepare Investment Decisions in Hungarian Processing Industries

Homeowners Ratemaking Revisited

Risk vs. Uncertainty: What s the difference?

INVESTMENT PLAN. Sample Client. For. May 04, Prepared by : Sample Advisor Financial Consultant.

Rebalancing the Simon Fraser University s Academic Pension Plan s Balanced Fund: A Case Study

European Court of Auditors

Effect of Trading Halt System on Market Functioning: Simulation Analysis of Market Behavior with Artificial Shutdown *

(RISK.03) Integrated Cost and Schedule Risk Analysis: A Draft AACE Recommended Practice. Dr. David T. Hulett

Methodology for risk analysis in railway tunnels using Monte Carlo simulation

RISK MANAGEMENT GUIDE FOR DOD ACQUISITION

CAPITAL BUDGET NUCLEAR

ADVANCED QUANTITATIVE SCHEDULE RISK ANALYSIS

System planning, EG2050 Probabilistic production cost simulation of electricity markets L12. Calculation of system index - Basic idea.

Optimization of variable proportion portfolio insurance strategy

Standard Development Timeline

For the PMP Exam using PMBOK Guide 5 th Edition. PMI, PMP, PMBOK Guide are registered trade marks of Project Management Institute, Inc.

COLUMBIAGRID GEOMAGNETIC DISTURBANCE DRAFT STUDY REPORT

Download from

Quantitative Risk Analysis with Microsoft Project

Monte Carlo Simulation (General Simulation Models)

Better decision making under uncertain conditions using Monte Carlo Simulation

PMP Exam Preparation Course. Madras Management Training W.L.L All Rights Reserved

Preparing for the New ERM and Solvency Regulatory Requirements

CHAPTER II LITERATURE STUDY

Empirical Issues in Crop Reinsurance Decisions. Prepared as a Selected Paper for the AAEA Annual Meetings

Key Points of Scenario Analysis

Project Risk Management. Prof. Dr. Daning Hu Department of Informatics University of Zurich

2011 IRP Public Input Meeting. October 5, Pacific Power Rocky Mountain Power PacifiCorp Energy

EARNED VALUE MANAGEMENT AND RISK MANAGEMENT : A PRACTICAL SYNERGY INTRODUCTION

1 of 14 4/27/2009 7:45 AM

Every project is risky, meaning there is a chance things won t turn out exactly as planned.

A Method for the Evaluation of Project Management Efficiency in the Case of Industrial Projects Execution

Case Study. IR-SIP Risk Management Plan Outline

6 th September not protectively marked 1

Transcription:

DOES LOST TIME COST YOU MONEY AND CREATE HIGH RISK? Dr. István Fekete Corvinus University of Budapest H-1093 Budapest Fővám tér 8. Tel: +3630-456-3424 e-mail: istvan.fekete@uni-corvinus.hu Keywords: risk assessment, outage, maintenance, project implementation plan, scenario analysis, Monte-Carlo Simulation Abstract The aim of the case study is to express the delayed repair time impact on the revenues and profit in numbers with the example of the outage of power plant units. Main steps of risk assessment: creating project plan suitable for risk assessment identification of the risk factors for each project activities scenario-analysis based evaluation of risk factors selection of the critical risk factors based on the results of quantitative risk analysis formulating risk response actions for the critical risks running Monte-Carlo simulation [1] using the results of scenario-analysis building up a macro which creates the connection among the results of the risk assessment, the production plan and the business plan. Results The result clearly demonstrates that if the outage of certain units is delayed by 3-4 days as compared to the scheduled date due to the inadequately managed risks, the profit before tax might decrease by approximately HUF 1.4 Bn ( 5M). With the execution of the risk management actions there are real chances to meet the planned deadline of outage works, and avoid the 5M loss. Of course, risk management activity costs certain amount of money as well, but the execution costs of the risk management actions are only a fragment of the loss we can avoid. 1

Preliminaries Risk management is a practice of systematically identifying, evaluating, treating and monitoring risks that might have a negative or positive effect on the ability of a company to achieve its strategic goals. Risk can be a future event, activity or failure of activity that has a positive or negative effect on the strategic goals. It can come from many sources, e.g. uncertainty in financial markets, credit risks, regulations and legal liabilities, authorization, accidents, natural disasters as well as unintended human mistakes, deliberate attack from an adversary or employee, cooperation between partners etc. Risk management can be used in many different business areas. One of the issues is calculating the impact of risks on the productivity and profit plan of a manufacturing company. This case study shows an example of a nuclear power plant. The Paks Nuclear Power Plant is located in South-Hungary. The license holder is the Paks NPP Joint Stock Company (Paks NPP Ltd). The majority owner of the company is the state owned Hungarian Power Companies Ltd. with a total equity of more than 99.99%. The four reactor units of the power plant were first connected to grid between 1982 and 1987. Each of the four units is a VVER-440/V-213 power reactor type, cooled and moderated with light water, and each has a thermal output power of 1,485 MW. After power upgrading program the individual electrical capacity of each reactor unit is 500 MW, giving a total electrical capacity of Paks NPP site approximately 2,000 MW. The daily production value per reactor unit is 0,5M. The yearly electricity production of the power plant is 15 000 GWh and the revenue is 700 M. The electrical energy produced by a nuclear power plant is sold to power providers. The sales contract records the volume of electric power to be sold expressed in GWh. If a nuclear power plant does not meet the production volumes of electric power commitment as scheduled in the contract, and the difference exceeds the pre-defined percentage values, the contract requires the nuclear power plant to purchase the missing amount from the electric power exchange. Since the price of electric power is much higher at the electric power exchange than the production costs of the nuclear power plant, its profit will significantly reduce. Therefore, it is the vital interest of the nuclear power plant to identify any potential risks causing production outages, and model their impact on revenues and profit via the production plan. The aim of the case study The reactor units need regular maintenance and refueling. During these works the reactors have to be shut down. There are two basic types of planned outages for Paks nuclear power plants: the longer service outage and the shorter refueling outage. The service outage includes refueling, major plant modifications, periodical inspections and tests required by the Technical Specifications. Typical duration of the service outage project is 57 days. The refueling outage mainly consists of partial refueling, corrective and preventive maintenance. Typical duration is 26 days. The typical work plan of refueling outage has about 6500 different activities. The maintenance program always has an uncertainty, which can be confronted when the reactor unit is disassembled. Based on experience the average delay of the refueling outage is 3 days. This implies 1,5 M direct financial loss. Every tool that eliminates this potential loss is essential for the company, and risk management can help reveal the reasons of loss and reduce probability and/or impact of critical risks. 2

There are two aspects of risk analysis issues related to this topic. First is a strategic view: How can we achieve the strategic goal of load factor? 1 In other words, how to ensure the highest level of production? The second targeted area is: Identifying potential delay of outage activities at the operational level and eliminate the additional cost. This case study is making an attempt to assess the effect of the unplanned outages derived from the delayed maintenance works in a nuclear power station and express the delayed repair time impact on the revenues and profit. Precondition: During risk analysis we accepted the accuracy of the project plan for the maintenance works as a starting proposition. This means, we did not examine if the outage works of the certain units could be shortened e.g. with better work organization. Main steps of risk assessment project [2] [3] The first step is to simplify the project plan for risk assessment. The project managers of the company have already prepared a project plan, but that contains thousands of activities. It is obvious that the number of activities is too big to be suitable for an efficient risk management because of the time needed for analyzing each activity. Therefore the main task is to reduce the number of activities to a manageable number but of course the content of the outage plan must be preserved. This number should be between 10 and 30. Figure 1: Simplified project plan We also have to define the logical relationships among the activities to get the critical path. [4] In this example the length of the critical path is 26 days for refueling and 57 days for service outage. 1 Load factor = Actual gross energy output in year i / Maximum gross energy output in year i 3

The next step is to identifiy the potential risk factors for each project activities. We suggest the company organize workshops for risk assessment, involving the experts of the project (engineers and project managers). We used our own risk management software named Szigma Integrisk and a premade standard risk database that is based on our several years of experience. In this database the risk factors are assigned to risk groups, e.g. legal risks, technological risks, human resources, IT-technology, cooperation, management risks etc. In our example the experts have assigned cc. 10-12 risk factors to every project activity. The scenario analysis helps calculate the probable impact of a risk. We have to estimate all of the potential outcomes, included the worst and the best case. Maximum four different scenarios can be defined and evaluated. In the course of the evaluation the experts estimate the probability of occurrence of the given scenario and the impact in terms of days. Then we can calculate the mean value and standard deviation for each risk. The selection of the critical risk factors is based on the previously defined mean value threshold and relative deviation threshold. If the calculated mean value or the deviation overruns the threshold because of a risk, that risk is labeled as critical risk. It could easily happen that the same risk factor would be critical at different project activities. In these cases the risk manager or project manager should filter these duplicities and consolidate the risk responses. Through this simplifying step we can reduce the total cost of risk mitigating activities, so the risk management process becomes more effective. The next task is to create risk mitigating actions for all critical risks. The main aim of the risk response is to help finish the given activity within predefined time that was set in the original project plan. Risk mitigation consists of the following steps: denomination of risk action, denomination of risk owner (responsible for the execution of the risk management plan), deadline of execution and the detailed description of the content of actions. In the example, the main aim of the risk response is to finish the given activity within predefined time that was set before the risk analysis. We show an example how to evaluate project risks with scenario analysis. Activity: Reassembling of reactor Risk factor: Capacity is not sufficient for completing the task. Table 1: Example of risk assessment Detailed description: Not being ready on time caused by lack of capacity. Engineers and technical supervisors cannot handle the huge amount of simultaneous tasks. SCENARIOS Scenario 1 Involving of additional capacity is belated, so a delay of 5 days is possible Explanation of estimation Lack of capacity is realized in time, so a maximum delay of 5 days is possible. Probability 0.3 Impact (days) 5.00 4

Scenario 2 Involving of additional capacity is belated, so a delay of 10 days is possible Explanation of estimation Surveying lack of capacity is belated; therefore a delay of 10 days is possible. Probability 0.5 Impact (days) 10.00 Scenario 3 Explanation of estimation Probability 0.2 Impact (days) 15.00 Involving of additional capacity is belated, so a delay of 15 days is possible. Project manager fails to realize the lack of capacity or reacts very late, so a delay of 15 days is possible. Mean value of deviation compared to original 9.5000 value (days) Standard deviation 3.5000 Critical? Describe action YES Strict control of planning activity and continuous communication with project owners and project management department Risk owner Project manager of refueling project Deadline 31.01.2012 Estimated cost of execution 160 000 HUF Monte-Carlo simulation uses the results coming from scenario-analysis and a correlation random number generator in order to get the probability distribution [5] [6] of the total duration time of the refueling project. This is the last step related to risk assessment. In the course of the scenario analysis a maximum number of four scenarios could be defined. These scenarios are the most important variations that the experts can set out but in real life much more outcomes are possible. In the course of Monte-Carlo simulation the number of samples could be multiplied so we can simulate a more realistic project environment. As a result we get the mean value, standard deviation, range and other parameters of the distribution of the execution time of each activity and the whole project. If there had been enough historical data regarding the duration and delays of former refueling and maintenance projects, Monte-Carlo simulation would have been started immediately, instead of risk assessment. In this case the company had not collected such data before the analysis. 5

Figure 2: Result of Monte-Carlo simulation As a result we can see that the expected outage duration will be in a three-day delay. But because of the huge deviation, there is a high potential for finishing the outage before the original deadline. This means the project has not only negative risks but there are positive risks as well. Positive risks can be called opportunities the company should take advantage of by immediate realization of the risk response and implementation of risk controlling and monitoring actions. The Tornado-diagram was generated by the run of Monte-Carlo simulation. The essence of this diagram is to show the activities that are mostly responsible for the project delay. These are the activities that can divert actual duration of maintenance to the greatest extent, due to their great risk exposure. That is why it is advised to execute firstly the risk response actions of these critical activities. By managing these most important risks way the original duration (26 / 57 days) can be kept. In the example of Paks Nuclear Power Plant Shutdown and Other primary circuit maintenance are the tasks that are most responsible for the project delay. 6

Figure 3: Tornado diagram Shutdown Other primary circuit maintenance Using the results of risk assessment, we can answer the most important question: What is the impact of the delayed maintenance and refueling project on the electricity production and on the business result? To answer this question we need the nuclear power plant s electricity production data and business plan. We use a macro which creates the connection among the result of the risk assessment, the production plan and the business plan. With the help of this macro we could immediately model the impact of risks on the changes in produced electricity (GWh), changes in other costs (MHUF) and changes in pre-tax profit (MHUF). If we run the macro, we can answer for example the following question: In what range the electric energy is going to fluctuate with relatively high probability (60 %) in case the previously revealed and evaluated risks happen? 7

Results and possible further steps Figure 4: Impact of risks on project duration and costs Project plan before risk assessment Duration and costs after risk assessment Project duration (scheduled) 26 days Project duration (mean value of risk analysis) 30.6 days Electric energy output (GWh) 14,328 Nuclear fuel (M HUF) 13,025 Electric energy output (GWh) 14,190 Nuclear fuel (M HUF) 12,898 Water reserve use charges (M HUF) 5,223 Water reserve use charges (M HUF) 5,172 Electric energy production revenue (M HUF) 161,692 Replacement energy purchase (M HUF) 0 Electric energy production revenue (M HUF) 160,140 Replacement energy purchase (M HUF) 0 Profit before tax (M HUF) 24,981 Profit before tax (M HUF) 23,606 The result clearly demonstrates that if the outage of certain units is delayed by 3-4 days as compared to the scheduled date due to the inadequately managed risks, the profit before tax might decrease by approximately HUF 1.4 Bn ( 5M). With the execution of the risk management actions there are real chances to meet the planned deadline of outage works, and avoid the 5M loss. Of course, risk management activity costs certain amount of money as well, but the execution costs of the risk management actions are only a fragment of the loss we can avoid. The level of details, the methodology applied and the technology are fully in line with the user environment and demand. It is able to produce rapid and exact results based on the available empirical information. Relying on the analysis we could identify opportunities that could improve the developed model: An additional customization of the presented model is required for modeling the risks related to the risk response actions of this project. 8

At the end of the analyzing period it is advisable to examine how many of the previously identified risks occurred, what their actual impacts were and whether there were any realized risks that were not identified by the analysis. It is also expedient to make a cost-benefit analysis that points out what the relationship is between the cost saving due to risk management and the costs related to the risk management. The efficiency and accuracy of the risk management can be increased and the time of the data recording can be decreased by developing an interface among the different data storing systems. Not every risk factor was taken into consideration, since this is just an analysis made for modeling, but later other risk factors can be added to the model increasing its reliability and accuracy. Conclusion We summarize shortly the advantages of risk management from the point of view of Paks Nuclear Power Plant Ltd. The management of Paks NPP Ltd. treats the realization of the strategic goals with high priority. Therefore they welcome every initiation that aims to help reach the strategic goals. And one of the most important from these goals is to ensure the delivery of the predefined amount of energy to the business partner. The chance for completing this strategic goal can be increased with the reduction in the outage durations. The turbulent economic environment forces the management to make decisions in critical situations. The application of Szigma Integrisk system can help answer many strategic dilemmas that the power plant faces. The applied risk management method ensures the execution of the efficient risk response actions. The ex-post evaluations confirm that the risk exposure related to the outage activity has decreased in the previous year. An important characteristic of risks is that they have an impact even if they are not identified in time. In this case their occurrence surprises everyone and the response of them cannot be efficient enough. By systematic risk assessment the management and project managers can identify potential risks in time and thus their efficient risk response is also possible. The additional value of risk assessment can be actions and programs that can improve the operational environment. Last but not least we can see in the case study that with the help of risk assessment the potential for successful completion of the project has increased to a great extent. The most important conclusions are as follows: The main tasks of risk management are to identify and analyze the long-term and hugebudget projects critical risks that might have an impact on duration and return. And also an important task is to formulate and execute an effective risk response plan. In the course of risk assessment not only the impacts on single projects should be analyzed, but also the impact on corporate level. It is very important to understand how the effective risk management contributes to avoid risks or mitigate their impacts and reach the strategic goals. 9

References [1] David B. Hertz: Risk Analysis in Capital Investment. Harward Business Review, Vol. 42. (January February 1964) [2] Eurescom Project Extended Investment Analysis of Telecommunication Operator Strategies, Deliverable 2, Annex C. Heidelberg, 2000 [3] Rozalia Konkoly István Fekete Attila Gyürke: Evaluation of Uncertainties in Investment Projects. Third Europeen Workshop on Techno-economics for Multimedia Networks and Services. Aveiro, Portugal 1999 [4] Stephen Grey: Pratical Risk Assessment for Project Management. John Wiley&Sons Inc. 1995 [5] Eilon, S.C. Fowkes, T.R.: Sampling Procedure for Risk Simulation Operational Research Quarterly Vol. 24. pp. 241-252. 1973 [6] Merran Evans Nicholas Hastings Brian Peacock: Statistical Distributions John Wiley&Sons Inc. 1993 10