LUNDIN GOLD RECONFIRMS PROJECT SCHEDULE AND LOWERS ALL-IN SUSTAINING COST ESTIMATE TO US$583 PER OUNCE FOR ITS FRUTA DEL NORTE GOLD PROJECT

Similar documents
LUNDIN GOLD REPORTS THIRD QUARTER 2018 RESULTS

LUNDIN GOLD REPORTS FIRST QUARTER 2018 RESULTS

LUNDIN GOLD ANNOUNCES US$400 MILLION PRIVATE PLACEMENT

LUNDIN GOLD REPORTS YEAR END 2018 RESULTS

LUNDIN GOLD INC. REPORTS Q RESULTS

LUNDIN GOLD ANNOUNCES A POSITIVE FEASIBILITY STUDY FOR THE FRUTA DEL NORTE PROJECT AND CONFERENCE CALL

PRESS RELEASE FOR IMMEDIATE RELEASE May 13, 2016

INTRODUCTION FIRST QUARTER 2018 HIGHLIGHTS AND ACTIVITIES

LEAGOLD FILES UPDATED TECHNICAL REPORT FOR LOS FILOS GOLD MINE, INCREASING RESERVES BY 59% TO 2.7 MILLION OUNCES GOLD

News Release. B2Gold Corp. Announces Positive Results from the Preliminary Economic Assessment for the Gramalote Project in Colombia

Spanish Mountain Gold Announces Results of New PEA for the First Zone

FIRST MAJESTIC SILVER CORP.

ELGIN MINING PROVIDES STRONG FOURTH QUARTER CASH COSTS AND POSITIVE 2014 OUTLOOK

Fortress Enters into Agreement to Acquire the Fruta del Norte Project from Kinross

SUITE WEST HASTINGS STREET VANCOUVER, BC V6C 2W2 CANADA TEL: FAX: November 12, 2009

March 2016 Prospectors & Developers Conference Toronto, Canada

Turquoise Hill files 2016 Oyu Tolgoi Technical Report

Eldorado Gold Reports Results of Technical Studies

NEWS RELEASE Lundin Mining Third Quarter Results

SECOND QUARTER 2018 RESULTS. August 10, 2018

Gold Hawk Resources Inc.

Pretivm Reports Third Quarter 2018 Results

Orezone Announces Positive Preliminary Economic Assessment

Detour Gold Achieves Production and Cost Guidance for 2017 and Provides 2018 Guidance

Marigold Life of Mine Plan

Alio Gold Reports Second Quarter 2018 Results

Kişladağ Update March 2018

Exeter Secures Second Water Source Outlines Pathway for First Stage Development of Caspiche Oxides

Skouries Update March 2018

Detour Gold Reports Third Quarter 2018 Results

PURE GOLD ANNOUNCES POSITIVE PRELIMINARY ECONOMIC ASSESSMENT FOR THE MADSEN GOLD PROJECT

FOURTH QUARTER 2017 RESULTS. February 21, 2018

Rambler Updates Reserves at its Producing Canadian Copper & Gold Mine Demonstrating a Profitable 20 Year Mine Life

KINROSS GOLD CORPORATION Q Results Conference Call & Webcast

Q Conference Call August 15, 2012 HBM

Gold Miner. Community Builder.

TSX.V:ORG Page 1 of 7. Orca Gold Inc West Georgia St. Vancouver, B.C., V6C 3E8, Canada Tel: Fax: HIGHLIGHTS

FIRST MAJESTIC SILVER CORP. NEWS RELEASE. First Majestic Reports Second Quarter Financial Results

Orvana reports results for the first quarter of fiscal 2014 with adjusted net income of $1.2 million or $0.01 per share

ALAMOS GOLD INC. 130 Adelaide Street West, Suite 2200 Toronto, Ontario M5H 3P5 Telephone: (416) or 1 (866)

Stock Symbol: AEM (NYSE and TSX) For further information: Investor Relations (416)

Capstone Mining 2017 Production Results and 2018 Operating and Capital Guidance

LEAGOLD ANNOUNCES FEASIBILITY STUDY FOR LOS FILOS MINE EXPANSION

HBM. Creating Sustainable Value through High Quality Long Life Deposits

SILVERCORP REPORTS Q1 RESULTS: NET INCOME UP 73%, CASH FLOWS FROM OPERATIONS UP 52% TO US$20.2 MILLION

November 10, 2017 News Release Pretivm Reports Third Quarter Results

SANDSTORM GOLD ROYALTIES RELEASES HOD MADEN PFS AND INCREASES PRODUCTION GUIDANCE

LEAGOLD ANNOUNCES 2018 EARNINGS, INCLUDING AISC OF $974/oz AND AISC MARGIN OF $83.2 MILLION

All amounts are in US dollars, unless otherwise indicated.

THE UPDATE ON THE ABCOURT-BARVUE FEASIBILITY STUDY IS POSITIVE A MAJOR REDUCTION IN THE INITIAL CAPITAL COST IS EXPECTED

June 19, 2014 News Release Updated Feasibility Study for Brucejack Project Confirms Positive Economics

Forward Looking Statement

Continental Gold Announces a Positive Feasibility Study for the Buriticá Project

Detour Gold Announces 2016 Operating Results and 2017 Guidance

FIRST MAJESTIC SILVER CORP.

Allied Nevada Announces Hycroft Mill Expansion Feasibility Results Highlighted by Improved Projected Returns

KINROSS GOLD CORPORATION

CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION

NEWS RELEASE GREAT PANTHER SILVER REPORTS POSITIVE PRELIMINARY ECONOMIC ASSESSMENT FOR THE CORICANCHA MINE

Nickel Eagle 12,000-15,000 16,000-19,000 13,000-16,000 Total Nickel 12,000-15,000 16,000-19,000 13,000-16,000

Fruta del Norte Financing and Project Update

Bellhaven Receives Favourable Preliminary Economic Assessment for its 100%- Controlled La Mina Gold-(Copper, Silver) Project, Colombia

POSITIONING FOR SUSTAINABLE GROWTH

GOLDCORP REPORTS FOURTH QUARTER 2018 RESULTS

Golden Star Announces Wassa Mine Feasibility Study Results

September 15, 2016 News Release SILVER STANDARD PROVIDES MARIGOLD FIVE-YEAR OUTLOOK

YEAR END 2015 CONFERENCE CALL

Gold production for the quarter of 38,500 ounces with cash flow generation from operations of $18.9 million ( M ).

January 11, 2017 News Release SILVER STANDARD REPORTS FOURTH QUARTER 2016 PRODUCTION RESULTS AND 2017 GUIDANCE

Q Conference Call November 2, 2012 HBM

WESDOME ANNOUNCES FOURTH QUARTER AND FULL YEAR 2016 FINANCIAL RESULTS AND RESERVE AND RESOURCE UPDATE

AVINO SILVER & GOLD MINES LTD.

Detour Gold Reports Fourth Quarter and Full-Year 2014 Results and Year-end 2014 Mineral Reserve and Resource Estimates

Detour Gold Reports First Quarter 2018 Results and Provides Update on Mine Plan Assessment with Guidance Revisions for 2018

GOLDCORP PROVIDES A SUMMARY OF FOURTH QUARTER 2018 MILESTONES AND 2019 PRODUCTION AND COST GUIDANCE

(PEA) for its project in. anticipated. which are. to produce. Highlights. ounces is now. The 3,500 tpd. After-tax NAV. Guatemala this year,

CANADA S INTERMEDIATE GOLD PRODUCER

Three months ended Twelve months ended December 31, December 31, US$ Millions (except per share amounts)

N E W S R E L E A S E

Detour Gold Reports Second Quarter 2017 Results

NEWS RELEASE New York AG February 25, 2019 Toronto FR Frankfurt FMV

Q P R E S T E A P E A R E S U L T S

McEWEN MINING ANNOUNCES POSITIVE FEASIBILTY STUDY FOR EL GALLO PHASE II, MEXICO

PRESS RELEASE. Banro Files NI Technical Report on Namoya Project, Democratic Republic of the Congo

May 31, 2017 News Release SILVER STANDARD FORMS JOINT VENTURE WITH GOLDEN ARROW AND FILES TECHNICAL REPORT FOR THE CHINCHILLAS PROJECT

Avnel Gold Reports that Indicated Resources Increased 55% to 2 Million Ounces at the Kalana Main Project

KINROSS GOLD CORPORATION

Detour Gold Updates Life of Mine Plan for Detour Lake

NEWS RELEASE. Resources at Galat Sufar South ( GSS ), in-pit and outside current design, continue to increase

Northgate Minerals Reports Second Quarter Results

HOD MADEN PRE-FEASIBILITY STUDY PRE-TAX NPV OF US$1.4 BILLION

N E W S R E L E A S E

NEWS RELEASE. Centerra Gold Announces Positive Feasibility Study on the Öksüt Project

Project Highlights (1) Average annual concentrate production Average annual copper production

CANADA S INTERMEDIATE GOLD PRODUCER

Kinross provides outlook for Production expected to rise by 32 per cent as cost per ounce declines

Bank of America Merrill Lynch 2014 Global Metals, Mining & Steel Conference

Q CONFERENCE CALL

YEAR END 2016 CONFERENCE CALL. February 24, 2017

First Majestic Reports Third Quarter Financial Results

Transcription:

885 West Georgia Street T +1 604 689 7842 Suite 2000 F +1 604 689 4250 Vancouver, BC info@lundingold.com Canada V6C 3E8 lundingold.com NEWS RELEASE LUNDIN GOLD RECONFIRMS PROJECT SCHEDULE AND LOWERS ALL-IN SUSTAINING COST ESTIMATE TO US$583 PER OUNCE FOR ITS FRUTA DEL NORTE GOLD PROJECT September 19, 2018 (Vancouver, Canada) Lundin Gold Inc. ("Lundin Gold" or the "Company") (TSX: LUG, Nasdaq Stockholm: LUG) is pleased to announce the results of its update of the project estimate ( UPE ) for its Fruta del Norte gold project ( Fruta del Norte or the Project ). The UPE involved a thorough review of the mine plan, capital and operating cost re-estimate and an update to the Project schedule. All amounts are in U.S. dollars unless otherwise indicated. This update should be read in conjunction with the Technical Report entitled "Fruta del Norte - NI 43-101 Technical Report on Feasibility Study" (the "Technical Report") filed by the Company in June 2016, with an effective date of April 30, 2016, and the Company s project update press release dated May 30, 2017. UPE Highlights: Reconfirmed construction schedule with first mine production planned in Q2 2019 and first gold production planned in Q4 2019. Reduced period of capital payback to 3.5 years from 4 years with improved IRR to 17.5% from 16.3%. A 10% increase in NPV 5% to $786 million from $717 million. Estimated all-in sustaining cost ( AISC ) reduced to $583 per ounce of gold from $609 per ounce of gold. Estimated operating cost per tonne decreased 7.3% from $111.84 to $103.65. Estimated total gold production increased by 73,000 ounces to 4.6 million ounces over a 15 year mine life. Total estimated capital expenditures increased only 1.2% from $684 million to $692 million. At the end of August we had committed 63% of planned capital expenditure, and construction is 27% complete. The UPE demonstrates that we are on track to build Fruta del Norte on budget and on schedule which is a credit to our Project team, said Ron Hochstein, Lundin Gold s President and CEO. We were able to lower the estimated AISC through improvements in the mine plan, refinement of processing costs and negotiation of smelting contracts for the concentrate. This further demonstrates the robustness of our high-grade Fruta del Norte gold deposit. Fruta del Norte Update: As at August 31, 2018, a total of 2.9 kilometres ( km ) had been achieved including declines and auxiliary development, with 1.4 km and 1.5 km achieved in the Kuri and K isa declines, respectively. Daily August average advance rates were 6.1 metres ( m ) for both Kuri and K isa, versus a target of 4.7 m and 4.3 m per day, respectively. Both declines have now crossed the Machinaza Fault and have gone under the Machinaza River, with no water inflows. Grinding building steel erection is underway, and process plant concrete is 30% complete. Mill process equipment is arriving on site, and the grinding mills are currently en route.

The two construction fronts on the North Access Road have met, and the road is expected to be complete by the end of September. The Environmental Licence was received for the Mountain Pass Quarry, and negotiation of the Quarry Exploitation Agreement with the Yantzaza municipality is well underway. Construction of the powerline, both onsite and offsite, is proceeding. Construction of the Tailings Storage Facility is ongoing. 63% of planned capital expenditure is now committed or incurred, of which 36% of planned capital expenditure has been incurred. Project engineering is now 60% complete. Activities have commenced to prepare for operations including the hiring of the general manager and mill manager. Update of the Project Estimate Details Probable Mineral Reserve Estimates The Company has increased its estimates for Probable Mineral Reserves slightly by 80,000 ounces when compared to the Project update annouced on May 30, 2017 (the PPR ) and by 204,000 ounces when compared to the estimates contained in the Technical Report. Table 1. Probable Mineral Reserves (1) Technical Report PPR (2)(3)(4)(5)(6)(7)(8) UPE (2)(3)(4)(5)(6)(7)(8) Mt 15.5 16.8 17.8 Au (g/t) 9.67 9.16 8.74 Au (Moz) 4.82 4.94 5.02 Ag (g/t) 12.7 12.6 12.1 Ag (Moz) 6.34 6.79 6.95 See Additional Technical Information below for further information regarding the Probable Mineral Reserve Data. Mine Plan Review As a result of the UPE, Fruta del Norte s mine plan has been improved, and a strategic decision was made to utilize primary-secondary sequencing versus end-slicing. Implementing this methodology provides greater operational flexibility with access to more areas of the ore body simultaneously and reduced backfill costs due to longer cure times and less binder requirements. Other changes to the mine plan included: Lower cut-off grade from 4.1 gram per tonne gold ( g/t gold ) to 3.8 g/t gold for transverse stoping and from 5.1 g/t gold to 5.0 g/t gold for the drift and fill stopes. Better balancing of mining methods with a slight increase in transverse stoping from 72% to 75% of ore removed. The remainder will be mined using drift and fill techniques. Total capital development, including owner and contractor, reduced from 19.0 km to 14.7 km. 2

Capital Cost Estimate Revised pre-production capital cost is now estimated to be $692 million, inclusive of contingency and pre-production expenses and revenues and net of taxes. This represents a slight increase of $8 million, or 1.2% over the PPR estimate, which totalled $684 million. This increase is mainly due to infrastructure costs and community and environmental monitoring being higher in the UPE than the PPR. Operating Cost Estimate Operating costs estimate is down 7.3% or $8.19 in the UPE to $103.65 on a per tonne basis compared to the PPR, and 3.7% or $15.89 to $408.20 on a per ounce basis. This is a result of the optimized mining methods, which reduced the mining costs, and reduced reagent consumption estimates based on the most recent metallurgical test work. Table 2. Life of Mine Operating Cost by Area Area PPR Cash Cost ($/t) PPR Cash Cost ($/oz Au payable) UPE Cash Cost ($/t) UPE Cash Cost ($/oz Au payable) Mining 54.98 208.48 47.85 188.4 Process 32.44 123.00 27.60 108.71 Surface 4.21 15.96 6.17 24.32 General & Administration 20.21 76.65 22.02 86.74 Total Operating Cost 111.84 424.09 103.65 408.20 Note: Numbers may not add due to rounding All-In Sustaining Cost Estimate AISC is now expected to be $583 per ounce of gold instead of $609 per ounce of gold, representing a $26, or 4% reduction. In addition to the lower mining costs, average concentrate treatment charges in the UPE are significantly lower than the charge of $275 per dry metric tonne estimated in the PPR, which was offset by slightly higher transportation, refining and penalty charges. Table 3. Life of Mine AISC ($/oz Au payable) Area PPR Cash Cost UPE Cash Cost On site operating cost 424 408 Treatment and refining charges 84 78 Royalties and production taxes 76 74 By-product silver credit (22) (23) Cash Cost 561 537 Sustaining capital and closure costs 49 46 AISC $ per oz Au 609 583 Note: Numbers may not add due to rounding 3

Project Economics Project economics continued to improve using the same gold ($1,250 per ounce) and silver price assumptions ($20 per ounce) used for the PPR and the Technical Report. The capital payback period is now estimated at 3.5 years with a 17.5% IRR and an NPV 5% of $786 million. Table 4: Project Economics Net Present Value at a 5% discount rate (NPV5) Internal Rate of Return (IRR) PPR After Tax UPE After Tax $717 million $786 million 16.3% 17.5% Capital Payback (years) 4.0 3.5 Notes: 1. All figures are reported on a 100% equity project basis valuation. Capital payback is calculated based on start of commercial production. 2. Economic valuation is presented using a start date of July 1, 2017. Additional Technical Information Qualified Person The technical information relating to the Fruta del Norte Project contained in this Press Release has been reviewed and approved by Ron Hochstein P. Eng, Lundin Gold's President and CEO, who is a Qualified Person under NI 43-101. Notes to Table 1. Probable Mineral Reserves (1) Except as set out below, the assumptions, parameters and risks associated with the results of the Technical Report for the Project, the Mineral Resource and Mineral Reserve estimates included therein, the PPR and the UPE, are as set out in the Technical Report. (2) All Mineral Reserves in this table are Probable Mineral Reserves. No Proven Mineral Reserves were estimated. (3) PPR estimates are as at December 31, 2017 and UPE estimates are as at September 19, 2018. (4) Mineral Reserves were estimated using key inputs listed in the table below: Key Inputs for Mineral Reserve Estimate PPR UPE Unit Gold Price 1,250 1,250 $/oz TS 57 48 $/t Overhand D&F 79 81 $/t Underhand D&F 85 71 $/t Process, Surface Ops, G&A 58 58 $/t Dilution Factor 10 10 percent Concentrate Transport & Treatment 9 9 $/t Royalty 71 71 $/oz Gold Metallurgical Recovery 91.7 91.7 percent 4

(5) Gold cut-off grades for the different mining methods are listed in the table below: Gold Cut-off Grade PPR UPE Unit Transverse Stope 4.1 3.8 g/t Overhand D&F 4.8 5.0 g/t Underhand D&F 5.1 5.0 g/t Note: An increased cut-off grade was used in the PPR Overhand D&F for the initial years of 6.5 g/t. (6) The average silver metallurgical recovery is 81.6%. The silver price assumption was $20/oz. Silver was not considered in the calculation of the cut-off grade. (7) Tonnages are rounded to the nearest 1,000 t, gold grades are rounded to two decimal places, and silver grades are rounded to one decimal place. Tonnage and grade measurements are in metric units; contained gold and silver are reported as thousands of troy ounces. (8) Rounding as required by reporting guidelines may result in summation differences. For information with respect to the key assumptions, parameters and risks associated with the results of the Technical Report for the Project, the Mineral Resource and Mineral Reserve estimates included therein and other technical information, please refer to the Technical Report filed on SEDAR at www.sedar.com. About Lundin Gold Lundin Gold, headquartered in Vancouver, Canada, is developing its wholly-owned Fruta del Norte gold project in southeast Ecuador. Fruta del Norte is one of the world's largest, highest-grade gold projects currently under construction. The Company's board and management team have extensive expertise in mine construction and operations, and are dedicated to advancing this project through to first gold production in the fourth quarter of next year. The Company operates with transparency and in accordance with international best practices. Lundin Gold is committed to delivering value to its shareholders, while simultaneously providing economic and social benefits to impacted communities, fostering a healthy and safe workplace and minimizing the environmental impact. The Company believes that the value created through the development of Fruta del Norte will benefit its shareholders, the Government and the people of Ecuador. Additional Information The information in this release is subject to the disclosure requirements of Lundin Gold under the EU Market Abuse Regulation. This information was submitted for publication September 19, 2018 at 05:00 a.m. PT through the contact persons set out below. For more information, please contact Lundin Gold Inc. Ron F. Hochstein President and CEO +593 2-299-6400 +604-806-3589 5

Lundin Gold Inc. Sabina Srubiski Manager, Investor Relations +1-604-806-3089 info@lundingold.com www.lundingold.com Follow Lundin Gold on Twitter Caution Regarding Forward-Looking Information and Statements Certain of the information and statements in this press release are considered forward-looking information or forward-looking statements as those terms are defined under Canadian securities laws (collectively referred to as forward-looking statements ). Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, identified by words or phrases such as believes, anticipates, expects, is expected, scheduled, estimates, pending, intends, plans, forecasts, targets, or hopes, or variations of such words and phrases or statements that certain actions, events or results may, could, would, will, should might, will be taken, or occur and similar expressions) are not statements of historical fact and may be forward-looking statements. By their nature, forward-looking statements and information involve assumptions, inherent risks and uncertainties, many of which are difficult to predict, and are usually beyond the control of management, that could cause actual results to be materially different from those expressed by these forward-looking statements and information. Lundin Gold believes that the expectations reflected in this forward-looking information are reasonable, but no assurance can be given that these expectations will prove to be correct. Forward-looking information should not be unduly relied upon. This information speaks only as of the date of this press release, and the Company will not necessarily update this information, unless required to do so by securities laws. This press release contains forward-looking information in a number of places, such as in statements pertaining to: timing of first gold production and commercial production, scheduling, gold and silver price and exchange rate assumptions, cash flow forecasts, projected capital and operating costs, metal or mineral recoveries, mine life and production rates, the Company's potential plans and operating performance, changes to the mine plan, the estimation of mineral reserves or the tonnage, potential production from and viability of the Company's Project, access to funding, the terms of the Company s smelting contracts, performance of the Company's contractors, construction and infrastructure development. Lundin Gold s actual results could differ materially from those anticipated. Management has identified the following risk factors which could have a material impact on the Company or the trading price of its shares: the ability to arrange financing and the risk to shareholders of dilution from future equity financings; the ability to maintain its obligations under its debt facilities; risks related to carrying on business in Ecuador; volatility in the price of gold; the timely receipt of regulatory approvals, permits and licenses; risks associated with the performance of the Company's contractors; risks inherent in the development of an underground mine; deficient or vulnerable title to mining concessions and surface rights; shortages of critical resources, labour and key executive personnel, such as input commodities, equipment and skilled labour, and the dependence on key personnel; risks associated with the Company's community relationships; unreliable infrastructure; volatility in the market price of the Company's shares; the potential influence of the Company's largest shareholders; uncertainty with the tax regime in Ecuador; measures required to protect endangered species; the cost of compliance or failure to comply with applicable laws; exploration and development risks; the accuracy of the Mineral Reserve and Resource estimates for the Fruta del Norte Project; the Company's reliance on one project; risks related to artisanal and illegal mining; uncertainty as to reclamation and decommissioning; risks associated with the Company's information systems; competition in the mining industry; the ability to obtain adequate insurance; risks of bribery or corruption; the potential for litigation; and limits of disclosure and internal controls. 6

There can be no assurance that such statements will prove to be accurate, as Lundin Gold's actual results and future events could differ materially from those anticipated in this forward-looking information as a result of the factors discussed in the "Risk Factors" section in Lundin Gold's Annual Information Form dated March 20, 2018, which is available under the Company s profile at www.sedar.com. Figure 1. Fruta del Norte project site as at August 2018 Figure 2. Underground mine development in the Kuri decline 7

Figure 3. Grinding building steel erection is underway Figure 4. Carbon-in-leach tank foundations 8

Figure 5. North Access road is expected to be complete by the end of September Figure 6. Construction of the Tailings Storage Facility ongoing 9