STANDARD SUMMARY PROJECT FICHE Project Fiche Number: CZ Project Title : Krimov Hora Sv.Šebestiána - Re-laying of Road I/7

Similar documents
STANDARD SUMMARY PROJECT FICHE Project Fiche Number: CZ

STANDARD SUMMARY PROJECT FICHE Project Fiche Number: CZ

STANDARD SUMMARY PROJECT FICHE Project Fiche Number: CZ

Rehabilitation and Partial Reconstruction of Road II-19 Razlog Bansko Gotse Delchev Sadovo

STANDARD SUMMARY PROJECT FICHE PROJECT PREPARATION FACILITY FOR THE PHARE CBC PROGRAMME BULGARIA-GREECE

2002/ Sulechow by-pass

STANDARD PROJECT FICHE

PL CBC PL/D Mieszka I Crossroads reconstruction

STANDARD SUMMARY PROJECT FICHE

STANDARD SUMMARY PROJECT FICHE - TRANSITION FACILITY

Cross Border Co-operation between Bulgaria & Romania Multi-annual Programme Project Fiche for Programme Support

STANDARD SUMMARY PROJECT FICHE TRANSITION FACILITY

Standard Summary Project Fiche. The project meets the following Accession Partnership priorities:

Standard Summary Project Fiche Project Number

STANDARD SUMMARY PROJECT FICHE

Standard Summary Project Fiche for the Transition Facility

1.5 Contracting Authority (EC) European Commission, EC Delegation, on behalf of the beneficiary

STANDARD SUMMARY PROJECT FICHE

Standard Project Fiche. 1.2 Title: Further Institutional Strengthening of the Court of Accounts

Annex C. The objectives of the 2003 Phare External Border Initiative for Romania are

Standard Summary Project Fiche IPA centralised programmes Project Fiche: 18

05.01 Strengthen environmental impact assessment

04.02 EAGGF EAGGF - p.1

PHARE 2003 STANDARD SUMMARY PROJECT FICHE

Neighbourhood Programme Romania - Serbia & Montenegro 2005 fiche for Project 3 Priority 3 Technical Assistance

Standard Summary Project Fiche No. HU

1.2 Title: Project Preparation and Support Facility (PPF)

CENTRAL FINANCE AND CONTRACTS UNIT (CFCU) POLAND MEMORANDUM OF UNDERSTANDING. Article 1 - Explanatory Statement

03.03 Border crossing in Dorohusk / 1

STANDARD SUMMARY PROJECT FICHE

STANDARD SUMMARY PROJECT FICHE - TRANSITION FACILITY

COMMISSION DECISION. C(2007)5980 of 10/12/2007

01.02 National Bank of Poland/1

COMMISSION DECISION. C(2007)6376 on 18/12/2007

PHARE 2004 STANDARD PROJECT FICHE

Standard Summary Project Fiche Project No. TR Twinning No. TR/2004/IB/EC/06

Article 2 The maximum amount of Community assistance shall be 20 million to be financed through Budget line in 2005.

PROJECT FICHE. 2.2 Project purpose: To provide sustainable access to longer-term financing to SMEs at market conditions in Cyprus.

ANNEX: IPA 2010 NATIONAL PROGRAMME PART II - BOSNIA AND HERZEGOVINA. at the latest by 31 December years from the final date for contracting.

COMMISSION OF THE EUROPEAN COMMUNITIES REPORT FROM THE COMMISSION TO THE EUROPEAN PARLIAMENT AND THE COUNCIL

01.05 Tax administration/1

IPA National Programme 2010 for Albania Project Fiche 09 "Support to the Food Safety Infrastructure "

Programme number: Title: DUration:

The INTERREG III Community Initiative

2010 IPA Horizontal Programme on Nuclear Safety and Radiation Protection PF1 Albania - Final Project Fiche No. 1

Standard Summary Project Fiche. Project Number 2002/

Standard Summary Project Fiche IPA Decentralised National Programmes Project Number TR

CONSTRUCTION OF THE BYPASS OF 3 VILLAGES ALONG THE M3 NATIONAL ROAD CHISINAU- GIURGIULESTI

Standard Summary Project Fiche IPA centralised programmes Project Fiche: 9

Project number: TR Twinning number: TR03-SPP Location: Turkey Public Administration at Central and Regional level.

STANDARD SUMMARY PROJECT FICHE

Standard Summary Project Fiche IPA centralised programmes

IPA National Programme 2009 Part II - Bosnia and Herzegovina Fiche 3 Preparation for IPA components III and IV

ISPA Manual Working Document TABLE OF CONTENTS PREFACE...4 I. INTRODUCTION...6 PROGRAMMING DECISIONS FOR ISPA PROJECTS...14

Project Fiche IPA National programmes IPA 2012/Component I

National Agriculture and Rural Development Plan

Annex 16 Template of Project Fiche for IPA programmes / component I - decentralised management

SUMMARY PROJECT FICHE

Standard Summary Project Fiche. Project number: TR Twinning number: TR02-JH-05

STANDARD SUMMARY PROJECT FICHE. 1.2 Title: Upgrade of the Latvian Statistical System in accordance with EU requirements

Final PF2 Project Fiche IPA centralised programmes Part II of the Horizontal Programme on Nuclear Safety and Radiation Protection

FINANCING MEMORANDUM

MEGAPROJECT Case Study

COMMISSION DECISION. C(2007)6121 of 12/12/2007

Standard Summary Project Fiche. Project PL : Improved Tax Administration

PHARE PROJECT FICHE. 2.3 Accession Partnership, NPIEU priority and Croatian Transport Development Strategy

Standard Summary Project Fiche IPA decentralised National programmes (maximum 12/15 pages without the annexes)

SUMMARY PROJECT FICHE

Standard Summary Project Fiche

DRAFT AMENDING BUDGET N 2 TO THE GENERAL BUDGET STATEMENT OF EXPENDITURE BY SECTION Section III - Commission. (presented by the Commission)

Standard Summary Project Fiche for the Transition Facility

INTERREG IIIC West Zone. Programme Complement

Having regard to the Treaty on the Functioning of the European Union, and in particular Article 291 thereof,

Contacts: Anastasija Trajkovska, Head of Sector, telephone: (0)

FIN AN CIN GMEM 0 RAND UM

ANNUAL IMPLEMENTATION REPORT

Standard Summary Project Fiche

:~,~{~J;tJ, .-.,-.' ;0,; FINANCING MEMORANDUM , " '. ;...\'~:, :\' ~

Local Government Budget Management System. 1.1 CRIS Number: 2006/ Twinning No: PL/06/IB/FI/02

How to Develop High-Quality Full Application Writing a Winning Proposal

This Legal Update provides information on some important legislative changes which have been passed in October, November and December 2010.

ANNEX ICELAND NATIONAL PROGRAMME IDENTIFICATION. Iceland CRIS decision number 2012/ Year 2012 EU contribution.

PPP Projects in Finland Success or not Kari Ruohonen General Director, Investments Finnish Transport Agency

PL CBC PL/D Environmental disaster prevention Szczecin

Regional Policy in the Czech Republic in the Period Around Its Accession to the European Union

COMMISSION OF THE EUROPEAN COMMUNITIES COMMISSION DECISION. of 2008

SUMMARY PROJECT FICHE

Standard Summary Project Fiche for the Transition Facility

COMMISSION DECISION. of on technical provisions necessary for the operation of the transition facility in the Republic of Croatia

EUROPEAN COMMISSION Enlargement Directorate-General. Brussels, 08 May 2008 ELARG/D(2008) REG Dear Mr Ivanovski,

ANNEX III FINANCIAL and CONTRACTUAL RULES I. RULES APPLICABLE TO BUDGET CATEGORIES BASED ON UNIT CONTRIBUTIONS

2002 SUMMARY PROJECT FICHE

Project Fiche IPA National programmes / Component I

JESSICA JOINT EUROPEAN SUPPORT FOR SUSTAINABLE INVESTMENT IN CITY AREAS JESSICA INSTRUMENTS FOR ENERGY EFFICIENCY IN LITHUANIA FINAL REPORT

STANDARD SUMMARY PROJECT FICHE

CHECK-LIST FOR CONTROLLERS/AUDITORS

Project Fiche IPA centralised programmes Regional Programme on Disaster Risk Reduction in South-East Europe

Standard Summary Project Fiche

PROJECT CYCLE MANAGEMENT & LOGICAL FRAMEWORK MATRIX TRAINING CYPRIOT CIVIL SOCIETY IN ACTION V INNOVATION AND CHANGES IN EDUCATION VI

Standard Summary Project Fiche IPA centralised programmes

Transcription:

1. Basic Information 1.1 Project Number CZ 01.12.02 1.2 Project Title : Krimov Hora Sv.Šebestiána - Re-laying of Road I/7 1.3 Sector Transport 1.4 Project Location Euroregion: Cross-border region: District: Municipality: Cadastral territory: Krušnohorí Czech Republic Germany (Saxony) Chomutov Krimov, Hora Sv.Šebestiána Krimov, Nová Ves u Krimova, Nebovazy, Hora Sv.Šebestiána 2. Objectives 2.1 Overall Objective(s) The project is in compliance with the Joint Programming Document (JPD), Czech Republic Germany medium-term strategy and priorities for the Interreg III A - Phare CBC programmes. It meets objectives of the priority of infrastructure. Indirectly it will have positive effects on development of tourism, trade cooperation and cross-border exchange of goods and services. The project respects the mutually coordinated work procedures on German and Czech road networks (North and North-West Bohemia). This also concerns the road connection between the Czech Republic and Germany over Hora Sv.Šebestiána border crossing on road no. 174 (Chemnitz-Marienberg-Reitzenhain on the German part) and road I/7 (Hora Sv.Šebestiána-Chomutov-Praha on the Czech part). The project particularly aims to: Improve connection of the border region with national and international transport routes and border crossings; Improve the transport infrastructure in the border region for passenger and freight traffic. Phare CBC 2001, Czech Republic - Germany 1

1.2 Project Purpose To improve traffic access to the border crossing of Reitzehnhein-Hora Sv.Šebestiána; Intensity of transport on the road No I/7 in the road section Krimov Hora sv. Šebestiána: Before implementation (2002) After implementation (2005) Increase in % Number of cars/day 6 071 6 261 4 Number of lorries 457 1 019 141 Total 6 528 7 280 13 To improve the traffic flow and safety at I/7 road between Krimov and Hora sv. Šebestiána; To improve access to the important industrial zones around Chomutov and Klášterec nad Ohrí which are currently under development; To improve the quality of environment in the area. 1.3 Accession Partnership and NPAA Priority The project is in line with the Partnership for Accession document and with the objectives of the National Programme for the Adoption of Acquis (NPPA) in the area of transport policy. The facilitation of access to border crossings and from border crossings to the country is in compliance with the objectives of the CR s EU integration process. 1.4 Cross-border Impact of the Project The project will improve the transport infrastructure and by that safety of transport and comfort of the travellers on the road connecting Chemnitz Marienberg the border crossing Reitzenhain, Hora Sv.Šebestiána Chomutov Praha, i.e. road no. 174 on the German side and road 1/7 on the Czech side. Another outcome of the project which will be beneficial for the border region will be an improved condition for freight transport and better access to the important industrial zones around Chomutov and Klášterec n.o. which are under development and where new investment from German investors is expected (e.g. MAGNA AG, PARKER AG). A more fluent traffic achieved as a result of implementation of the project will have a positive effect on the quality of environment in the area as well. Phare CBC 2001, Czech Republic - Germany 2

2. Description 2.1 Background and Justification The existing dual carriageway 1/7 between Krimov and Hora Sv. Šebestiána fails to meet the needs of the increasing traffic flow towards the border crossing. The road is sloping length-wise and it passes through the municipality of Krimov and protected areas of water sources, which are not properly secured from the effects of the traffic. There is also a level railroad crossing. Krimov inhabitants are excessively affected by noise, dust and emissions from the road traffic. Moreover, the inappropriate quality of the level border crossing makes it impossible to operate freight traffic (large trucks). In 1998, the total of 4,682 vehicles were handled in both directions at the Reitzenhain, Hora Sv. Šebestiánana border crossing. According to the road transport national survey, in 2000, the number of vehicles in both directions on road 1/7 between the border crossing and Chomutov ranged beween 4,800 and 5,700 in 24 hours. Compared to 1995, the number of vehicles per day increased by approximately 150. The re-laying of 1/7 road from Krimov to Hora Sv.Šebestiána is linked to the first stage of the construction of 1/7 road between Chomutov and Krimov. After the two parts of the construction are completed there will be a road leading to the border crossing, and a quality transport connection for passenger as well as freight transport will be ensured all over the part of 1/7 road between Chomutov and the Reitzenhain-Hora Sv. Šebestiána border crossing. This road, which will meet EU standards, will provide for uninterrupted traffic flow and road safety. 1.2 Linked Activities On the Czech side, the construction is linked to the 1 st stage of the construction of the re-laying of 1/7 road connecting Chomutov and Krimov. On the German side of the border there is road- work under way on road no. 174 between Chemnitz and Reitzenhain in order to increase its capacity. Also, a by-pass on this road around the city of Marienberg is under preparation. A by-pass around the city of Chemnitz is also envisaged by means of which the no. 174 road will be directly connected to the German motorway system. 1.3 Results The outcome of the project will be a re-laying of road 1/7 between Krimov and Hora Sv. Šebestiána in the length of 5,680 metres. It will be a dual carriageway of the S11,5/70 category. The construction of 6 bridges will be part of the project implementation. Phare CBC 2001, Czech Republic - Germany 3

1.4 Activities The project implementation includes all construction work associated with the re-laying of an existing road. The construction of a re-laying includes: Earth work - the approximate volume of 260,000 m 3; Construction of the road (about 71.500 m 2 ; S 11,5 profile; the maximum gradient 4,25%); Construction of 6 bridges - total area of 2,790 m 2; Construction of 2 retaining walls; Water management structures (road sewerage approximately 4,850 m long, protection of water sources); Re-layings and protection of the existing service networks; Landscaping. The re-laying will be constructed: Along the existing I/7 road in the distance of approximately 50 to 350 m; Along the railroad for some 2 km in the distance of around 100 m; In the distance of around 150 m from the periphery of the municipalities of Krimov and Nová ves. The re-laying crosses the parallel railroad in one spot by means of a road bridge. 3. Institutional Framework The National Aid Coordinator (NAC) has an overall responsibility for programming, monitoring and implementation of the Phare programme. The National Fund (NF), managed by the National Authorising Officer (NAO), will supervise financial management of the programme and will be responsible for reporting to the European Commission. The Ministry for Regional Development, in cooperation with the Centre for Regional Development, is the programme Implementing Agency (IA) with the overall responsibility for the project implementation. The NF will be transferring funds from the Phare resources to accounts managed by IA as authorised by the Financing Agreement signed between the MF/NF and IA. The IA is managed by the Programme Authorising Officer (PAO) nominated by the Ministry for Regional Development and approved by the NAO and agreed by NAC. The PAO is responsible for all activities of the IA. The investor is responsible for the Czech contribution to co-financing, for acquiring a land-use decision and a building permit, for preparing and launching the tender for a contractor, preparing a contract, supervising the works and for the final acceptance. Phare CBC 2001, Czech Republic - Germany 4

Investor : Represented by: Reditelství silnic a dálnic CR (RSD CR) Czech Roads and Motorways Administration Na Pankráci 56, Praha 4 Liberec Zeyerova 1310/2, 460 55 Liberec phone: +420-48 510 85 07,08 fax: +420-48 271 16 75 As of today, the Czech Roads and Motorways Administration the Liberec Administration has implemented several construction projects co-financed from Phare resources. It is experienced in Phare methods and in the preparation of international tenders, which are in compliance with EU requirements. Project end user: The Czech Republic, The Czech Roads and Motorways Administration. Construction supervision: The Czech Roads and Motorways Administration the Liberec Administration 4. Detailed Budget (MEUR) Investment Support Phare Institution Building Total Phare (=I+IB) National cofinancing share TOTAL Construction works 2,000 0,000 2,000 10,930 12,930 Total 2,000 0,000 2,000 10,930 12,930 The Czech contribution to the project will be covered by the resources of the State Fund for Transport Infrastructure of the CR (SFDI CR). 5. Implementation Arrangements 5.1 Implementing Agency The Ministry for Regional Development in conjunction with the Centre for Regional Development CR. PAO: RNDr. Jirí Horácek, director, Department of EU programmes, MRD CR Address: Staromestské nám. 6, 110 15 Praha 1 Phone: + 420-2 2486 1398 Fax: + 420-2 2486 1415 Phare CBC 2001, Czech Republic - Germany 5

Implementing Agency: Director: RNDr. Ivo Ryšlavý Address: Centre for Regional Development, Vinohradská 46, 120 00 Praha 2 Phone: + 420-2 21 580 285 Fax: + 420-2 21 580 229 1.2 Non-standard Aspects The project will be managed using the methodology specified for Candidate Countries in the manual for the management of programmes supported from the EU sources Practical Guide for Phare, Ispa and SAPARD. 1.3 Contracts (MEUR) No. Type of contract Description Total 1. Works contract Delivery of construction work 12,930 Total 12,930 6. Implementation Schedule Start of tendering*: 09/2002 Start of project activities: 03/2003 Project completion: 08/2004 * The tender dossier shall be submitted to the European Commission six months after the signature of the Financing Memorandum at the latest (see FM, Chapter Implementation Arrangements). 7. Equal Opportunity Principles and procedures applied during the project implementation will ensure equal opportunities for all participants of the project. 8. Environment An environmental impact assessment study for the construction in line with law no. 244/1992 Coll. (EIA) was undertaken in August 1993. It was prepared simultaneously for both construction stages, i.e. for the whole part of 1/7 road (Chomutov-Krimov-Hora Sv. Šebestiána). The EIA study was undertaken by TERPLAN, a.s, Platnérská 19, 110 00 Praha 1, order number 92 135. The person responsible was RNDr.Martin Kubeš. The EIA documentation has proved the benefit of the project particularly in relation to protection of the neighbouring water sources and protection of Krimov inhabitants against negative effects of traffic (noise, dust, emissions). Phare CBC 2001, Czech Republic - Germany 6

9. Rates of Return The economic rate of return is based on a prepared feasibility study. The economic assessment was carried out for a twenty-year life span of the road. IRR = 3,3 % The economic feasibility study was undertaken in February 2001 by Pragoprojekt a.s. Praha, K Ryšánce 16, 147 54 Praha 4, contact person - Martina Kopalová, phone: +420-2 4144 2563. 10. Investment Criteria 10.1 Catalytic Effect The project is of public nature and complies with the regional priorities. In the years to come, the action could not be implemented without support from the EU sources. 10.2 Co-financing The co-financing share of the Czech party equals 85%of the total project investment costs. Co-financing will be provided for by the State Fund for Transport Infrastructure of the CR (SFDI CR). 1.3 Additionality The project is of public nature and is not suitable for funding from private sources due to the low financial rate of return of the funds invested. Should the co-financing be provided from a bank loan, the implemented works would not generate resources sufficient for their renewal after their lifetime. 1.4 Project Readiness and Size The relevant planning decision has been issued in relation to the project and the project meets all required technical criteria. The building permit documentation has already been prepared. The Building permit will be issued by October 2001. The tender dossier shall be prepared and submitted to the European Commission six months after signature of the Financing Memorandum at the latest. 1.5 Sustainability Results of the feasibility study proved that the draft project is of a sustainable nature as it meets all the European norms and standards and complies with the EU legislation in the relevant area. The investor will cover operation and maintenance costs. Phare CBC 2001, Czech Republic - Germany 7

1.6 Compliance with State Aid Provisions The project and the award of the Phare subsidy are in compliance with the relevant rules on state aids as defined in the European Agreement; its implementation is not going to harm the market environment or the competition rules. 1.7 Contribution to National Development Plan The project respects short-term and medium-term priorities of the National Development Plan with the aim of balancing the quality of transport in areas bordering the EU countries. The project is in compliance with regional priorities and measures laid down in the cross-border regional development strategy defined in the Joint Programming Document (JPD) Czech Republic Germany for the CBC Phare programmes. Priority: Measure No.: II - Infrastructure 11. Conditionality and Sequencing 1 Improving transport infrastructure with the purpose of enhancing access to the border crossing The investor is responsible for the preparation of studies and project dossiers necessary for the execution of works, and for the preparation of documents for the selection of a contractor for the works. The investor must observe its commitment of financial participation in the project and is responsible for the quality of the works executed. He must also provide for the activities the contractor is not qualified to execute. After the completion of the project the investor shall ensure the launching of full operation of the works with a view to its use. He shall ensure regular maintenance and repairs in compliance with the international standards. Annexes 1. Phare Log Frame 2. Implementation Time Chart 3. Commitment and disbursement schedule 4. Reference to feasibility study Phare CBC 2001, Czech Republic - Germany 8

ANNEX 1 Phare log frame LOGFRAME PLANNING MATRIX FOR Project Programme name and number Phare CBC 2001 Czech Republic / Germany Krimov-Hora Sv.Šebestiána Re-laying of Road I/7 Contracting period expires Disbursement period expires Total budget : 12,930 MEUR Phare budget : 2,000 MEUR Overall objective Objectively verifiable indicators Sources of Verification Improved connection of the border region to the national and international road network Improved transport infrastructure at the state border of Euroregion Krušnohorí Quality parameters for cross border transport and traffic improved Czech Roads and Motorways Administration result of the road transport national survey Traffic surveys Road accidents statistics Project purpose Objectively verifiable indicators Sources of Verification Assumptions Phare CBC 2001, Czech Republic - Germany 9

Improved access from the Czech side to the border crossing Reitzenhein-Hora sv. Šebestiána Improved traffic flow and safety Better access to the important industrial zones around Chomutov and Klášterec nad Ohrí which are currently being developed. Restoration of freight traffic (haulage) Increased intensity and capacity of freight transport by 141% due to restored traffic Reduced travelling time at the relevant road section RSD CR Praha results of traffic census (1995, 2000); a model of capacity and traffic intensity of the Czech road network; Road accident statistics The traffic density will increase Increase in tourism due to the better road connection between CR and Germany Results Objectively verifiable indicators Sources of Verification Assumptions A new road complying with S 11.5/70 standard and suitable for freight traffic 5.68 km of new dual carriageway S 11.5 standard Maximum gradient 4.25% 6 bridges (2,790 m2) Project Final Evaluation Report Project acceptance documents Ministry of Transport Roads and Motorways Administration Activities Means Assumptions Work delivered by an experienced, reliable and well performing contractor Efficient co-ordination between the project funder, subcontractors and IA Appropriate monitoring and supervision of civil work Phare CBC 2001, Czech Republic - Germany 10

Construction work in relation to the road relaying: Earth work Construction of the road (about 71,500 m2; S 11.5 standard with maximum gradient 4.25%) including six bridges (2,790 m2) 2 retaining walls Water management structures Re-layings and protection of the existing service networks Landscaping Available funds Construction resources Materials and equipment Design documentation Engineering supervision Existence and interest of building companies with required experience and qualified staff Efficient co-ordination between the project funder, subcontractors and IA Smooth and timely funding Preconditions Signature of the Financial Memorandum Phare CBC 2001, Czech Republic - Germany 11

ANNEX 2 Implementation Time Chart Sub-project 4Q 2001 1Q 2002 2Q 2002 3Q 2002 4Q 2002 1Q 2003 2Q 2003 3Q 2003 4Q 2003 1Q 2004 2Q 2004 3Q 2004 4Q 2004 Construction works T T T/C/I I/D I/D I/D I/D I/D I/D T: Tendering C: Contracting I: Implementation D: Disbursement Phare CBC 2001, Czech Republic - Germany 12

Annex 3 Commitment and disbursement schedule Commitment Schedule No. Project Allocation Commitments (EUR) IV/2001 I/2002 II/2002 III/2002 IV/2002 I/2003 II/2003 III/2003 IV/2003 I/2004 II/2004 III/2004 IV/2004 01 Construction works 2 000 000 0 0 0 0 0 2 000 000 0 0 0 0 0 0 0 TOTAL 2 000 000 0 0 0 0 0 2 000 000 0 0 0 0 0 0 0 Disbursement Schedule No. Project Allocation Disbursements (EUR) IV/2001 I/2002 II/2002 III/2002 IV/2002 I/2003 II/2003 III/2003 IV/2003 I/2004 II/2004 III/2004 IV/2004 01 Construction works 2 000 000 0 0 0 0 0 0 200 000 410 000 410 000 380 000 400 000 200 000 0 TOTAL 2 000 000 0 0 0 0 0 0 200 000 410 000 410 000 380 000 400 000 200 000 0 Phare CBC 2001, Czech Republic - Germany 13

Reference to Feasibility Study Annex 4 The project subject is relaying of I/7 road between Krimov and Hora Sv. Šebestiána. The new re-laid road will be 5,680 m long. It will be a dual carriageway. The project stems out from the need to address inadequate access road to the border crossing which serves both for personal and goods transport. Market Analysis The analysis is based on the current status, regional development strategy and model of traffic volume on Czech roads. The analysis demonstrated that the existing access road to the border crossing is not suitable for the increased volume of traffic and the population of Krimov is exposed to a high level of traffic noise and pollution. Improved transport infrastructure will contribute to business development of the region close to German border. 1.1.1.1.1 Organisation of Operations Roads and Motorways Administration, a Czech state organisation, is the project funder. After the project completion the title will be turned to Správa a údržba silnic Liberec, a state organisation maintaining and repairing roads. All maintenance and repair costs will be fully covered by the national budget and therefore this does not pose any project risk. 1.1.1.1.2 Results of Financial Analysis It is a public road in the state ownership. It is not possible to perform a financial assessment of a project that does not generate any revenues. The project owner/funder must make necessary arrangements for the project funding from the Transport Infrastructure Fund and by subsidies or bank loans. The current inadequate quality of infrastructure requires large investments from public funds and without an EU grant the completion of I/7 road section Chomutov-Krimov-Hora Sv.Šebestiána would be threatened. The project is not suitable for funding by private capital. 1.1.1.1.1.1 Results of Economic Analysis 1.1.1.1.1.1 The economic analysis result based on 20 years period is IRR = 3.30 %. Economic assessment of the project took into consideration estimated savings on road maintenance, costs related to road accidents, savings on vehicle operating costs and reduced travelling time of people and goods. The project will improve the access to the border crossing at Hora Sv. Šebestiána, will improve the traffic flow and safety on road and will provide a better access to new industrial areas around Chomutov and Klášterce nad Ohrí. The project is in line with national and regional medium-term strategies for transport infrastructure improvements and business development. The results of the study demonstrated the project feasibility and absence of significant risks. The project is therefore recommended to be included into a relevant programme supported by the EU funds. Phare CBC 2001, Czech Republic - Germany 15

1.1.1.1.3 1.1.1.1.4 Environmental Impact Assessment The EIA study as defined in Act 244/1992 Sb. (EIA) was developed in August 1993. Both construction stages were assessed at the same time that is the entire section of road I/7 Chomutov-Krimov-Hora Sv.Šebestiána. The study assessed both the project construction and operation. During the construction there will be no significant environmental impacts. After the road commissioning the adjacent water supply zones will be better protected, the traffic flow and safety on road will improve and the exposure of Krimov population to high level of traffic noise and pollution will be reduced. The project will contribute to the better quality of environment in the region located close to the border and therefore it is recommended for implementation on the basis of the analysis performed. Phare CBC 2001, Czech Republic - Germany 16