Optimization of China EPC power project cost risk management in construction stage based on bayesian network diagram

Similar documents
Study of Interest Rate Risk Measurement Based on VAR Method

Study on the Price Types of Construction Contracts for Construction Works

Information Security Risk Assessment by Using Bayesian Learning Technique

Risk Element Transmission Model of Construction Project Chain Based on System Dynamic

Present situation, forecasting and the analysis of fixed assets investment in Zhejiang province

Empirical Study on Short-Term Prediction of Shanghai Composite Index Based on ARMA Model

An Empirical Analysis of the Impact of Disposable Income of Urban Residents on Consumption Expenditure in Beijing. Jia-Nan BAO

The Empirical Study on Factors Influencing Investment Efficiency of Insurance Funds Based on Panel Data Model Fei-yue CHEN

The Analysis of ICBC Stock Based on ARMA-GARCH Model

Analysis of Income Difference among Rural Residents in China

A Study on the Relationship between Monetary Policy Variables and Stock Market

Application of Data Mining Technology in the Loss of Customers in Automobile Insurance Enterprises

Based on BP Neural Network Stock Prediction

Cost Overrun Assessment Model in Fuzzy Environment

Neural Network Prediction of Stock Price Trend Based on RS with Entropy Discretization

Research on PPP Mode Applying to Pension Real Estate

Kunming, Yunnan, China. Kunming, Yunnan, China. *Corresponding author

The Role of Cash Flow in Financial Early Warning of Agricultural Enterprises Based on Logistic Model

Comparative study of credit rating of SMEs based on AHP and KMV. model

Human - currency exchange rate prediction based on AR model

The Models of Investing Schools

The analysis of the multivariate linear regression model of. soybean future influencing factors

A Study on the Motif Pattern of Dark-Cloud Cover in the Securities

A Study on the Risk Regulation of Financial Investment Market Based on Quantitative

Comparative study of methods of risks assessment in rural power network

International Journal of Advance Engineering and Research Development A MODEL FOR RISK MANAGEMENT IN BUILDING CONSTRUCTION PROJECTS

Research of Chinese Stock Market Complex Network Structure

Analysis of the Employment Promotion Function of China s Unemployment Insurance System

Risk Identification and Analysis of Communication Project Based on Fault Tree: The Case of the Telecom IVR Project

Analysis of the Coordination of International Policies Based on the Mundell-Fleming Model

The Empirical Research on the Relationship between Fixed Assets Investment and Economic Growth

Research on Optimization Direction of Industrial Investment Structure in Inner Mongolia, the West of China

COMPARATIVE STUDY OF TIME-COST OPTIMIZATION

An Empirical Analysis of Effect on Copper Futures Yield. Based on GARCH

Research on Stock Market Volatility

Empirical Research of the Capital Structure Influencing Factors of Electric Power Listed Companies

Based on Fuzzy Comprehensive Evaluation Method The Investment Risk Assessment of Chinese Enterprises in The Countries Along The Belt and Road

Establishment of Risk Evaluation Index System for Third Party Payment in Internet Finance

The Impact and Countermeasures of Foreign Multinational Investment in Shandong Province of Industry Safety

Assessment on Credit Risk of Real Estate Based on Logistic Regression Model

Research on Chinese Consumer Behavior of Auto Financing

Game Theory Analysis of Price Decision in Real Estate Industry

The Present Situation of Empirical Accounting Research in China and Its Gap with Foreign Countries. Wei-Hua ZHANG

Asset Selection Model Based on the VaR Adjusted High-Frequency Sharp Index

Study on Characteristics of the Financial Report Restatements

Risk Analysis And Management Of Track Construction On Running Railway Line Of High Speed Railway For PDL Zhao Teng 1,a, Liu Xin 1,b, Yang Wenqi 1,c

Analysis of the Operating Efficiency of China s Securities Companies based on DEA Method

The Countermeasures Research on the Issues of Enterprise Financial Early Warning System

Estimation and Management of Construction Cost

Study on the Construction of Community Endowment Service System Based on SEM

INVESTOR SENTIMENT, MANAGERIAL OVERCONFIDENCE, AND CORPORATE INVESTMENT BEHAVIOR

BioTechnology. An Indian Journal FULL PAPER. Trade Science Inc.

Study on Debt Structure, Ownership Structure and Solvency: Based on Automobile Listed Companies Jie Liu 1, a* and Mingran Deng 2, b

Chapter-8 Risk Management

A Study of Financing Risk Management in Land Reserve Yanfeng Yang1, a and Junqi Xie1, b

Analysis of PPP Project Risk

MARKET REACTION TO THE NASDAQ Q-50 INDEX. A Project. Presented to the faculty of the College of Business Administration

An Empirical Analysis on the Management Strategy of the Growth in Dividend Payout Signal Transmission Based on Event Study Methodology

Problems and Strategies of Cross-border Mergers and Acquisitions for Chinese Enterprises

Peer to Peer Lending Supervision Analysis base on Evolutionary Game Theory

Research on Financing Model of the Chinese SMEs in Supply Chain Finance

A Comparative Analysis of Medical Insurance Payment Methods between China and the United States

INTER-ORGANIZATIONAL COOPERATIVE INNOVATION OF PROJECT-BASED SUPPLY CHAINS UNDER CONSIDERATION OF MONITORING SIGNALS

Multidimensional Time Series Analysis of Financial Markets Based on the Complex Network Approach

International Journal of Business and Economic Development Vol. 4 Number 1 March 2016

The Assessment of Financial Leasing Risk in Grid Corporation Zhu Guorong1, a, Feng Hao1, a, Qin Honghao2, a, Zhu Guodong2, a and Niu Dongxiao2, a

Ricardo-Barro Equivalence Theorem and the Positive Fiscal Policy in China Xiao-huan LIU 1,a,*, Su-yu LV 2,b

OPTIMIZATION STUDY OF RSI EXPERT SYSTEM BASED ON SHANGHAI SECURITIES MARKET

Lihong Li. Jianghan University, Wuhan, China. Miaoyan Li. Ministry of Finance, Beijing, China

Research on Capital Cost Analysis of State Owned Enterprises in China

Available online at ScienceDirect. Procedia Engineering 161 (2016 )

RESEARCH ON INFLUENCING FACTORS OF RURAL CONSUMPTION IN CHINA-TAKE SHANDONG PROVINCE AS AN EXAMPLE.

The Empirical Study on the Relationship between Chinese Residents saving rate and Economic Growth

Trends of Project Funding in Provincial-Level Agricultural Research Institutions in China and Recommendations for Fund Management

Analysis of Dividend Policy Influence Factors of China s Listed Banks

THE MULTIVARIATE REGRESSION MODEL OF THE PRICES OF CHINA S URBAN COMMERCIAL RESIDENCE

Investor Sentiment on the Effects of Stock Price Fluctuations Ting WANG 1,a, * and Wen-bin BAO 1,b

A micro-analysis-system of a commercial bank based on a value chain

Defining the Safety Integrity Level of Public Safety Monitoring System Based on the Optimized Three-dimension Risk Matrix

Risk analysis and countermeasures for international trade under the economic downturn pressure Fang Fengxia

The Relationship between Consumer Price Index and Producer Price Index in China

The Notable Problems and Countermeasures of Budget Management in Project Investment Control

Research on the Selection of Discount Rate in Value-for-money Evaluation

An Analysis of the Hong Kong Economy after the Financial Crisis

The Research for Flexible Product Family Manufacturing Based on Real Options

Journal of Chemical and Pharmaceutical Research, 2013, 5(12): Research Article

Efficiency Analysis of Listed Agricultural Company Base on FIA Jian-dong ZHANG and Jian ZHANG *

Financial Engineering and the Risk Management of Commercial Banks. Yongming Pan, Xiaoli Wang a

Research on Credit Risk Measurement Based on Uncertain KMV Model

Research on Value Assessment Methods of the NEWOTCBB Listed Company

The Effect of Chinese Monetary Policy on Banking During the Global Financial Crisis

Research on investment decisions model of trans-regional transmission network based on the theory of NPV

A Selection Method of ETF s Credit Risk Evaluation Indicators

Empirical Study on the Impact of Commercial Bank Income Structure on Profitability

PM2.5, Investor Sentiment, and Stock Returns

Open Access Asymmetric Dependence Analysis of International Crude Oil Spot and Futures Based on the Time Varying Copula-GARCH

An Analysis Summary of Factors Affecting China Assembled Funds Trust Products Expected Return Rate

Comparison and Reflection of China's Biological Assets Standard and International Accounting Standard

An Indian Journal FULL PAPER ABSTRACT KEYWORDS. Trade Science Inc. Analysis and prevention of risks of enterprise merger and acquisition

Subject CS1 Actuarial Statistics 1 Core Principles. Syllabus. for the 2019 exams. 1 June 2018

Transcription:

Acta Technica 62 (2017), No. 6A, 223 232 c 2017 Institute of Thermomechanics CAS, v.v.i. Optimization of China EPC power project cost risk management in construction stage based on bayesian network diagram Guiqin Zhang 1, Zheng Wang 1, 2 Abstract. In recent years, the application of EPC mode in China s power construction field has become more extensive, which is apparently improve the efficiency of construction, but meanwhile EPC mode put forward higher requirements of risk management and control capabilities for the EPC general contractor. As a key stage to form actual costs, optimize the risk construction stage has the profound significance. This paper firstly uses the form of interview to identify the type of construction risk and then constructs the logical structure between the risk factors, finally builds the Bayesian network model by MATLAB. By inputting the edge probability, the probability value of actual cost risk can be calculated under any condition. According to the results of calculation, this paper puts forward the difference management level of risk factors based on the process of risk transmission and the sensitivity of risk factors. It can help project management department enhance the risk management ability under the premise of limited resources and provide the power data support for risk management decision. Key words. risk. EPC power project, Bayesian network diagram, differentiation Management of 1. Introduction Nowadays, China is widely using the general contracting mode (EPC mode), which has made outstanding contributions to China s power construction [1]. But at the same time it should be noted that under the mode of EPC, the contractors will take great losses if they don t identify risk accurately in time [2]. To solve this problem, we should start with the relationship between risk factors of each stage of EPC mode, and identify risk by combining the characteristics of EPC mode. Considering the suitability of the problem and the maturity of the model research, 1 College of Economics and Management, North China Electric Power University, Changping District 102206, Beijing, China 2 Corresponding Author, e-mail: 188104110787@163.com http://journal.it.cas.cz

224 GUIQIN ZHANG, ZHENG WANG this paper chooses Bayesian network model as the basic framework. Tugrul and Daim [3] who apply Bias network for analysis and estimation of the clean energy project investment risk, depict the probability of risks in the whole life cycle of clean energy project.levent Koc [4] combines Bias network technology with network antiinvasion mechanism, and effectively estimate the probability of hacker attacks At present, the application of Bias network model in engineering risk research is quite limited, so it cannot meet the needs of practical engineering construction. Based on current situation, this article carries out the research of engineering risk by Bias network, 2. The bayesian model of epc power project cost risk in construction stage 2.1. The identification of cost risk Construction stage is one of the important stages in the engineering projects. At this stage the contractor invests a lot of manpower, material resources and capital. If this stage of risk management is ignored, it may bring serious consequences to the project and cause a great loss [5], so as EPC project contractor, they must focus on the risk identification and control at this stage [6]. The general contractor at this stage is not mainly responsible for risk of equipment damage caused by the accident or personnel casualty risk, but also bear the risk due to design or procurement stage problems influenced by the time lag, poor quality and other unforeseen risks [7]. In addition, the contractor also needs to take risks of market price fluctuation, low management efficiency and social environment [8]. Table 1. The result of Delphi method Risk categories Risk name Mention frequency Subjective risk Objective risk Budget preparation 0.07 Requirements of Quality and functional 0.13 Construction technology 0.06 Design 0.12 Engineering investigation and survey 0.07 Engineering quantity 0.12 Construction organization 0.08 Construction schedule 0.07 Management 0.11 Accident 0.1 Natural environment 0.19 Market supply 0.18 Social environment 0.17 Price of labour, equipment and material 0.18

OPTIMIZATION OF CHINA EPC POWER PROJECT COST RISK MANAGEMENT 225 According to a large number of literature and construction experience [9, 10], we have figured out the most influential factors of cost as the basic elements of Bayesian network, meanwhile ignore the less mentioned factors, the results of the survey is shown in table 1. According to the table 2, we combine the form of expert evaluation and case study to set up the Bayesian logical risk table. The result is shown in table 2. Table 2. Main risks logic relationship at construction stage Risk name Construction technology Engineering quantity Market supply Accident Construction organization Construction schedule Transaction cost Price of labour, equipment and material Management cost Parent logical point Natural environment, Budget preparation, Requirements of Quality and functional Construction technology, Design, Engineering investigation and survey Natural environment, Social environment Social environment, Construction technology Construction technology, Engineering quantity Construction organization, Design Market supply Market supply, Construction technology Social environment, Accident, Construction schedule 2.2. Bayesian Network Model Of Cost Risk At Construction Stage According to the logic table shown in table 2, the risks factor model are portrayed in Figure 1 by MATLAB. Fig. 1. Bayesian network model of cost risk at construction stage After the Bayesian network diagram is completed, we can collect the EPC project data similar to the proposed project as a reference, and analyze the probability of each risk factor in Figure 1.Then the analysis probability values are introduced to

226 GUIQIN ZHANG, ZHENG WANG the Bayesian network diagram, which can be dealt with MATLAB. The outcome of a program is the probability of the actual cost overrun caused by different risks, which is the basis of risk differentiation management. Through the analysis of the probability value, the general contractor can be more targeted to the differentiation risk management at construction stage. Not only that, the EPC general contractor can analyze the sensitivity of a certain risk, they can adjust the probability of risk in the network, such as increased or decreased by 5%, then observe the change of probability value of actual cost risk after running the program. In this paper, the sensitivity is defined as formula 1. S i = C p C i (1) S i : The sensitivity of the risk factors i to risk of the actual construction cost. C p : The variation range of actual construction cost. C i : The variation range of the risk factors i. Through the above analysis, EPC general contractor can make it clear in advance that which risks in this project has a more significant impact on actual cost risk. Thus they will pay more attention to these factors in order to help improve the efficiency of risk management. Detailed data analysis process will be given in case study. 3.1. Data Collection 3. case study In order to ensure the validity of the data, with the aid of statistical experience, we believe the model can basically meet the requirements of the data when the sample size is greater than or equal to 30 and exclude abnormal data on the calculation results of interference. This paper collects and studies 30 EPC project in China and interviews the project management staff in order to figure out the reason of the actual cost overruns, then calculates the average probability of each risk factor in Bayesian network graph. In a network diagram, there are three forms of probability: False, True, and Default. False indicates that the risk factor does not occur, while True means that the risk factor has occurred, the Default means that the risk factor occurs in accordance with the probability of the definition [11]. In this paper, that the actual index value exceeds 20% of the expected target value is defined as risks occurrence. At the same time, we revise the probability value slightly according to the situation. Summary table of Probability is shown in table 3.

OPTIMIZATION OF CHINA EPC POWER PROJECT COST RISK MANAGEMENT 227 Risk name Table 3. Summary of risk factors prior probability Prior probability Natural environment 0.85, 0.15 Budget preparation 0.88, 0.12 Requirements of Quality and functional 0.87, 0.13 Design 0.81, 0.19 Engineering investigation and survey 0.83, 0.17 Social environment 0.95, 0.05 Transaction cost 0.94, 0.41, 0.06, 0.59 Construction schedule 0.82, 0.53, 0.18, 0.47 Market supply 0.86, 0.54, 0.71, 0.27, 0.14, 0.46, 0.29, 0.73 Accident 0.98, 0.82, 0.02, 0.18 Construction organization 0.96, 0.70, 0.84, 0.47, 0.04, 0.30, 0.16, 0.53 Price of labor, equipment and material Construction technology Engineering quantity Management cost Actual cost 3.2. Model Test 0.89, 0.72, 0.80, 0.32, 0.11, 0.38, 0.20, 0.68 0.90, 0.65, 0.81, 0.72, 0.68, 0.64, 0.67, 0.55, 0.10, 0.35, 0.19, 0.28, 0.32, 0.36, 0.33, 0.45 0.88, 0.62, 0.64, 0.59, 0.61, 0.55, 0.51, 0.22, 0.12, 0.38, 0.36, 0.41, 0.39, 0.45, 0.49, 0.78 0.94, 0.67, 0.71, 0.84, 0.57, 0.62, 0.63, 0.42, 0.06, 0.33, 0.29, 0.16, 0.43, 0.38, 0.37, 0.58 0.90, 0.77, 0.72, 0.76, 0.71, 0.75, 0.70, 0.39, 0.10, 0.23, 0.28, 0.24, 0.29, 0.25, 0.30, 0.61 In order to deepen the study of the relationship between the nodes in the Bayesian network and the risk probability of the actual cost, we calculate the shortest step distance from each risk factor node to the node of actual cost in the Bayesian network and arrange them in descending order. This arrangement can study more precisely of the influence on logical structure of factors to the actual cost. For the risks that have the same step distance, we arrange them in the order of occurrence. In summary, we arrange the risk factors in accordance with above rules, and number them from 1 to 16, and switch state of the risk factor from Default to True one by one when operating the MATLAB. The result is listed in the table 4.

228 GUIQIN ZHANG, ZHENG WANG Number Table 4. Actual cost risk changes under risk factors transmission Risk name Shortest step distance The probability of the actual cost risk 1 None 0.2053 2 Design 5 0.2055 3 Engineering investigation and survey 5 0.2056 4 Engineering quantity 4 0.2130 5 Requirements of Quality and functional 3 0.2114 6 Budget preparation 3 0.2072 7 Natural environment 3 0.2278 8 Construction organization 3 0.2327 9 Construction technology 3 0.2439 10 Social environment 2 0.223 11 Accident 2 0.2338 12 Market supply 2 0.2492 13 Construction schedule 2 0.2589 14 Transaction cost 1 0.2713 15 Management cost 1 0.2986 16 Price of labor, equipment and material 1 0.3176 Then we input the above results into the software and draw the tendency chart which takes the risk serial number as abscissa, the probability of actual cost as the ordinate. The tendency is portrayed in figure 2. Fig. 2. Change of risk probability the actual cost risk As what can be seen from Figure 2, if arranged according to the logical order, the later a single risk occurs in the process of risk transmission, the greater the risk of actual cost overrun will take, and the rate of increase is not linear. In order to accurately describe the practical situation of risk transmission progress in

OPTIMIZATION OF CHINA EPC POWER PROJECT COST RISK MANAGEMENT 229 the network set up in paper, we perform a regression analysis, and the Polynomial model and Exponential model have the minimum error. The R2 of two models are 0.9342 and 0.8536, respectively. Seen from Figure 2, the practical slope change of Polynomial model is more fitting than the Exponential model, so this paper chooses the Polynomial model as analysis object. The fitting Exponential function is 2 and then take the derivative, the result is shown in the formula 3. y = 0.0006x 2 0.0035x + 0.2126 (2) y = 0.0012x 0.0035 (3) According to the derived function in 3, we calculate the average slope value of all step distance. The result is in table 5. Table 5. Average slope value of all step distance Shortest step distance 5 4 3 2 1 Average slope value 0 0.0013 0.0049 0.0103 0.0435 From table 5, it can be seen that the impact of the risk to the actual cost is rising rapidly in the process of risk transmission. The slope of the risk factor with the 5 steps is negligible, while the average slope of 1 step is 30 times more than that of the 4 steps. The results also prove that the later the logical position of risk is, the greater the cost to rectify the risk is, which will lead a sharp rise of the risks of exceeding the budget. Thus, the contractor can grade the risk management into different categories according to table 5. This article only gives management levels and does not involve the specific management measures. The general contractor should stipulate different levels of management measures based on the actual situation of enterprises and projects. In the network diagram used in this paper, managers can introduce the average slope of each distance as the management standard: the value of more than 0.1 can be set into first-level management, 0 0.1 into second-level management, while the factors value close to 0 can be set in to third-level management, so that all the different nodes will have a sub-level management correspondingly. The above discussion is only for the risk transmission process, however, another kind risk is also one of the key points that the contractor needs to focus on, that is, the sensitivity of risk factors. Although some risks are at the front end of the logical order in the network diagram, their impact to the probability of the actual cost risk is much greater, so controlling this kind of the risk precisely is also of great significance. Therefore, this paper adopts sensitivity analysis on the basis of network model diagram. We can calculate the sensitivity of each risk factor by using the formula in 1. Specifically, we increase the probability of each risk factor by 5% and input them into MATLAB, it should be noted that every factor remains default in each time the program runs (that is, the risk is occurring in probability). The result of the actual cost risk value is summarized in table 6.

230 GUIQIN ZHANG, ZHENG WANG Number Table 6. Sensitivity analysis of all risk factors Risk name (increase by5%) The probability of the actual cost risk Sensitivity 1 None 0.2053 2 Design 0.2055 0.004 3 Engineering investigation and survey 0.2054 0.002 4 Engineering quantity 0.2054 0.002 5 Requirements of Quality and functional 0.2057 0.008 6 Budget preparation 0.2054 0.002 7 Natural environment 0.2066 0.026 8 Construction organization 0.2061 0.016 9 Construction technology 0.2073 0.040 10 Social environment 0.2062 0.018 11 Accident 0.2058 0.010 12 Market supply 0.2079 0.052 13 Construction schedule 0.2068 0.030 14 Transaction cost 0.2072 0.038 15 Management cost 0.2059 0.012 16 Price of labor, equipment and material 0.2109 0.112 Table 6 shows that the sensitivity of risks is unrelated to the Bayesian network diagram constitution, and it is the unique attribute of each risk factor. So sensitivity analysis is another important work of cost risk management for a contractor. Similar to the construction of Bayesian network, the measurement of risk sensitive data should also be established on the continuous acquisition of engineering data, so that different sensitivity factors can be incorporated into differentiation management system. For example, in this paper, the contractor can set the sensitivity greater than 0.05, 0.01 0.05 and less than 0.01 to first, second and third-level management respectively. The management level set up in this article is extracted in table 7, but the specific control methods need to be carefully considered by the EPC general contractor. EPC general contractor can consider the two aspects of management level comprehensively, and set reasonable management weight to develop a more scientific and accurate risk management system. Under the premise of limited management resources, the establishment of the management level system makes it possible for EPC general contractor to implement management more targeted and optimize the utilization of resources.

OPTIMIZATION OF CHINA EPC POWER PROJECT COST RISK MANAGEMENT 231 Table 7. Summary of risk factors differentiation management level Number Risk name Management level Logical order Sensitivity 1 None 2 Design 3 3 3 Engineering investigation and survey 3 3 4 Engineering quantity 2 3 5 Requirements of Quality and functional 2 3 6 Budget preparation 2 3 7 Natural environment 2 2 8 Construction organization 2 2 9 Construction technology 2 2 10 Social environment 1 3 11 Accident 1 2 12 Market supply 1 1 13 Construction schedule 1 2 14 Transaction cost 1 2 15 Management cost 1 2 16 Price of labor, equipment and material 1 1 4. Conclusions Through the Bayesian network modeling research study, this article analyzes the risk factors at construction stage from general contractor perspective, conclusions of this study are mainly the following three aspects: (1) Based on network graph and the historical data, this paper constructs a polynomial regression mode derived from its derivative expressions, and the rise of the risk probability is not linear, instead, the speed of growth is increasing rapidly in the risks transmission process. This demonstrates that the later the risk occurs in the process of risk transmission, the greater the risk of actual cost overrun will take, the heavier the eventual losses that EPC general contractor s may suffer.that is to say, the loss caused by risk in the early period of construction is easy to make up.the general contractor should pay more attention to the preparative work of construction stage, such as repeatedly verifying the rationality of design and construction scheme, investigating the various conditions of the construction site more comprehensively so as to prevent risk probability in the network transmission process enlarging and reduce the occurrence probability of the risk factors at the end of network diagram. (2) Different risk factors have different influence degree to the risk of actual cost. In this paper, the factors of market supply and price of labor, equipment and material are more sensitive to the actual cost. The general contractor shall provide preventive measures against these risks before construction stage.

232 GUIQIN ZHANG, ZHENG WANG (3) This paper discusses the importance of different factors in terms of the logical sequence of network diagram and risk factor itself, finally summarizes the risk control comprehensive level. Managers only need to weight these two aspects in accordance with the characteristics of the project. As a result, a complete set of risk prevention and control level will be built, making it easier for them to carry out a differentiation management. More money should be reserved for risk factors that have greater occurrence probability or more sensitive to the actual cost, otherwise the reserve funds of risks ought to be cut down. References [1] Lu Z. W.: Research on the choice of agent construction mode of electric power project in China. Journal of Chongqing University of Science and Technology (SOCIAL SCI- ENCE EDITION) 12 (2009), 108. [2] Chen L. D.: Study on the model choice of power engineering project management. North China Electric Power University (2012), 14 15. [3] Tugrul D., Gulgun K., Yulianto S., Yagmur B.: Clean energy investment scenarios using the Bayesian network. International Journal of Sustainable Energy 33 (2014), 400 415. [4] Levent K., Thomas A. M., Shahram S.: A network intrusion detection system based on a Hidden Naïve Bayes multiclass classifier.expert Systems With Applications 39 (2012), 13492 13500. [5] Zhang K. S.: Risk management research on the EPC mode of contractor. Southwest Jiao Tong University (2011), 20 22. [6] Liu J.: Study on the effect of investment risk management of international construction projects in China EPC mode. Huaqiao University (2012), 4 5. [7] Liu J. H.: Yue Jin Gui: Research on project risk management and its development in China. Gansu agriculture 5 (2010), 186 187. [8] Zhang Z. L., Zhou X. R., Guo S. J., Song H. Q.: The risk identification and prevention strategy of International EPC project.petroleum Engineering Construction 36 (2010), 75 76. [9] Chen L.: The risk management in EPC engineering design consulting. Architectural design management 23 (2010), 7 8. [10] Jiang G.: Study on the central building enterprise EPC general contracting mode of development way. Value engineering 01 (2012), 106 108. [11] Huang Y. P.: Bayesian network research. Graduate School of Chinese Academy of Sciences 2 (2005), 16 17. Received September 16, 2017