LUNDIN GOLD REPORTS THIRD QUARTER 2018 RESULTS

Similar documents
LUNDIN GOLD REPORTS FIRST QUARTER 2018 RESULTS

LUNDIN GOLD RECONFIRMS PROJECT SCHEDULE AND LOWERS ALL-IN SUSTAINING COST ESTIMATE TO US$583 PER OUNCE FOR ITS FRUTA DEL NORTE GOLD PROJECT

LUNDIN GOLD REPORTS YEAR END 2018 RESULTS

LUNDIN GOLD ANNOUNCES US$400 MILLION PRIVATE PLACEMENT

INTRODUCTION FIRST QUARTER 2018 HIGHLIGHTS AND ACTIVITIES

LUNDIN GOLD INC. REPORTS Q RESULTS

LUNDIN GOLD INC. Admission to Trading on Nasdaq Stockholm of Additional Common Shares

March 2016 Prospectors & Developers Conference Toronto, Canada

LUNDIN GOLD ANNOUNCES A POSITIVE FEASIBILITY STUDY FOR THE FRUTA DEL NORTE PROJECT AND CONFERENCE CALL

Fortress Enters into Agreement to Acquire the Fruta del Norte Project from Kinross

NEWS RELEASE. Equinox Gold Commences Stockpiling of Ore at Aurizona Gold Mine

FIRST MAJESTIC SILVER CORP.

NEWS RELEASE. Lundin Mining Announces 2018 Production Results and Fourth Quarter and Full Year 2018 Results Date

NEWS RELEASE. Imperial Reports 2011 Third Quarter Financial Results

NEWS RELEASE Lundin Mining Third Quarter Results

2014 First Quarter Highlights

Gold Miner. Community Builder.

SUITE WEST HASTINGS STREET VANCOUVER, BC V6C 2W2 CANADA TEL: FAX: November 12, 2009

NEWS RELEASE New York AG February 25, 2019 Toronto FR Frankfurt FMV

Capstone Mining 2017 Production Results and 2018 Operating and Capital Guidance

FIRST MAJESTIC SILVER CORP.

Operational Outlook & Update Conference Call November 29, 2018

Spanish Mountain Gold Announces Results of New PEA for the First Zone

Q Conference Call November 2, 2012 HBM

Derisking Fruta del Norte

Three months ended Twelve months ended December 31, December 31, US$ Millions (except per share amounts)

NEWS RELEASE IMPERIAL REPORTS 2012 SECOND QUARTER FINANCIAL RESULTS

PRESS RELEASE FOR IMMEDIATE RELEASE May 13, 2016

MANAGEMENT S DISCUSSION & ANALYSIS QUARTERLY HIGHLIGHTS SEPTEMBER 30, 2017

ELGIN MINING PROVIDES STRONG FOURTH QUARTER CASH COSTS AND POSITIVE 2014 OUTLOOK

Detour Gold Reports Third Quarter 2018 Results

KINROSS GOLD CORPORATION Q Results Conference Call & Webcast

Detour Gold Announces 2016 Operating Results and 2017 Guidance

2014 Third Quarter Highlights

Q Conference Call August 15, 2012 HBM

October 01, 2018 News Release Release #

2016 Second Quarter Highlights

Dundee Precious Metals announces 2017 Fourth Quarter and Annual Results and 2018 Guidance

September 15, 2016 News Release SILVER STANDARD PROVIDES MARIGOLD FIVE-YEAR OUTLOOK

First Quarter 2018 Results April 26, 2018

Turquoise Hill files 2016 Oyu Tolgoi Technical Report

Orvana reports results for the first quarter of fiscal 2014 with adjusted net income of $1.2 million or $0.01 per share

Pretivm Reports Third Quarter 2018 Results

November 28, 2018 News Release Release #

News Release B2Gold Corp. Achieves Record Second Quarter and First-Half 2015 Gold Production; Gold Production Increases 42% in Second Quarter 2015

Platinum Group Metals Update and First Quarter Results

TSX.V:ORG Page 1 of 7. Orca Gold Inc West Georgia St. Vancouver, B.C., V6C 3E8, Canada Tel: Fax: HIGHLIGHTS

Fruta del Norte Financing and Project Update

THE UPDATE ON THE ABCOURT-BARVUE FEASIBILITY STUDY IS POSITIVE A MAJOR REDUCTION IN THE INITIAL CAPITAL COST IS EXPECTED

N E W S R E L E A S E

Allied Nevada Announces Hycroft Mill Expansion Feasibility Results Highlighted by Improved Projected Returns

Nickel Eagle 12,000-15,000 16,000-19,000 13,000-16,000 Total Nickel 12,000-15,000 16,000-19,000 13,000-16,000

TOREX GOLD RESOURCES INC. MANAGEMENT S DISCUSSION AND ANALYSIS

FOURTH QUARTER 2017 RESULTS. February 21, 2018

SANDSTORM GOLD ROYALTIES ANNOUNCES RECORD 2018 ANNUAL RESULTS

KINROSS GOLD CORPORATION

NEWS RELEASE Orca Gold Intersects 13m at 10.19g/t Au and 93.7m at 1.72g/t Au at its Block 14 Gold Project in Sudan

2015 First Quarter Highlights

Forward Looking Statement

NEWS RELEASE February 15, 2017

FIRST MAJESTIC SILVER CORP. NEWS RELEASE. First Majestic Reports Second Quarter Financial Results

Detour Gold Reports Fourth Quarter and Full-Year 2014 Results and Year-end 2014 Mineral Reserve and Resource Estimates

GOLDCORP DELIVERS RECORD 2009 GOLD PRODUCTION; PEER-LEADING FIVE-YEAR GROWTH PROFILE EXTENDED

Detour Gold Achieves Production and Cost Guidance for 2017 and Provides 2018 Guidance

November 10, 2017 News Release Pretivm Reports Third Quarter Results

AVINO SILVER & GOLD MINES LTD.

Kinross provides outlook for Production expected to rise by 32 per cent as cost per ounce declines

Claude Produces 20,672 Ounces of Gold in Q1

OPERATING AND FINANCIAL HIGHLIGHTS OPERATING HIGHLIGHTS

METALLA REPORTS FINANCIAL RESULTS FOR THE THIRD QUARTER OF FISCAL 2018

January 11, 2017 News Release SILVER STANDARD REPORTS FOURTH QUARTER 2016 PRODUCTION RESULTS AND 2017 GUIDANCE

NEWS RELEASE. Resources at Galat Sufar South ( GSS ), in-pit and outside current design, continue to increase

Goldcorp and Teck Combine El Morro and Relincho Projects in Chile

SECOND QUARTER 2018 RESULTS. August 10, 2018

2015 Third Quarter Highlights

NEWS RELEASE New York - AG Toronto FR November 16, 2015 Frankfurt FMV Mexico - AG. First Majestic Reports Third Quarter Financial Results

ARGONAUT GOLD INC. (Formerly Argonaut Gold Ltd.) MANAGEMENT S DISCUSSION & ANALYSIS FOR THE QUARTER ENDED SEPTEMBER 30, 2010

Management s Discussion & Analysis ( MD&A ) For the Quarter Ended April 30, 2011

Gold Hawk Resources Inc.

First Majestic Reports Third Quarter Financial Results

2015 First Quarter Highlights

INTERIM MANAGEMENT DISCUSSION & ANALYSIS QUARTERLY HIGHLIGHTS

NEWS RELEASE ROXGOLD DELIVERS RECORD GOLD PRODUCTION AND CASH FLOW IN FIRST QUARTER 2018; ANNOUNCES INCREASE IN FULL YEAR PRODUCTION GUIDANCE

Ero Copper Corp Reports Third Quarter 2017 Results

N E W S R E L E A S E

NEWS RELEASE February 13, 2018

McEWEN MINING ANNOUNCES POSITIVE FEASIBILTY STUDY FOR EL GALLO PHASE II, MEXICO

Alio Gold Reports Second Quarter 2018 Results

SilverCrest Announces Babi Sur Vein High-Grade Discovery at Las Chispas 2.2 Metres Grading 556 gpt AgEq. 1.5 Metres Grading 606 gpt AgEq

Eldorado Gold Reports Results of Technical Studies

CANADA S INTERMEDIATE GOLD PRODUCER

Platinum Group Metals Reports 2014 Annual Results

HIGHLIGHTS DETAILS. Commenting on the new discovery, Hugh Stuart, President and Director of Orca Gold, said Our aim in Côte 1 O r c a G o l d I n c.

Kinross gold corporation First Quarter report for the period ended March 31, Strong foundation. Strong future.

N E W S R E L E A S E

For Immediate Release Date: July 4, 2017 # ORVANA PROVIDES UPDATE ON DON MARIO OPERATION; ANNOUNCES US$11.3 MILLION DEBT FINANCING

NEWS RELEASE Lundin Mining Second Quarter Results

Third Quarter 2018 Results October 25, 2018

Detour Gold Reports 2017 Fourth Quarter and Year-End Results

MAG Silver Corp. August 14, 2013

Transcription:

885 West Georgia Street T +1 604 689 7842 Suite 2000 F +1 604 689 4250 Vancouver, BC info@lundingold.com Canada V6C 3E8 lundingold.com NEWS RELEASE LUNDIN GOLD REPORTS THIRD QUARTER 2018 RESULTS November 8, 2018 (Vancouver, Canada) Lundin Gold Inc. ("Lundin Gold" or the "Company") (TSX: LUG, Nasdaq Stockholm: LUG) is pleased to announce its results for the three and nine months ended September 30, 2018. All amounts are in U.S. dollars unless otherwise indicated. With overall construction just over a third complete and a significant portion of the Project s capital committed, Fruta del Norte remains on track for first gold expected around this time next year. This makes us one of the largest and highest-grade gold projects coming online in the near term, said Ron Hochstein, Lundin Gold s President and CEO. Underground mine development is progressing on schedule and based on planned rates, we anticipate reaching the orebody in the first quarter of 2019. Highlights Fruta del Norte Gold Project ( Fruta del Norte or the Project ) Overall engineering was 63% complete and construction 34% complete. Cumulative advance in the Kuri and K isa declines was 3.3 kilometres ( km ). Process plant excavation is done, and concrete is 40% complete. Grinding building steel erection is underway. North Access Road was substantially complete and being used by commercial vehicles. Powerline construction is ongoing on three separate work fronts. Updated mine plan and re-estimate of the Project s capital cost and operating cost were completed. It resulted in increases in the Project s NPV 5% ($786 million from $717 million) and IRR (17.5% from 16.3%). The new capital cost estimate increased only marginally by $8.0 million to $692 million. At the same time, the estimated all-in sustaining cost dropped to $583 per ounce of gold from $609 per ounce of gold. Exploration Mapping, geochemical sampling and permitting required for future drilling continues on a number of epithermal gold-silver targets in the central and southern Suarez Basin, and the Gata Salvaje target area to the west of the Basin. Fruta del Norte Gold Project Mine Development As at September 30, a total of 3.3 km of underground mine development had been achieved, with 1,565 metres ( m ) and 1,760 m in the Kuri and K isa declines, respectively. Daily advance rates continued to be above target throughout the quarter with an average advance rate of 6.2 m per day in Kuri and 7.0 m per day in K isa in September, versus a target of 4.0 m per day and 3.8 m per day, respectively. The increase in advance rates are the result of better than anticipated ground conditions, less water than expected and higher contractor productivities.

Process Plant Construction Process plant foundations are well advanced and steel erection has started on the grinding building. Fabrication of process plant equipment is on track and the flotation cells, mills, CIL tanks and thickeners are expected to arrive on site by the end of this year. Major Site Earthworks The North Access Road was substantially complete and is being used by commercial vehicles. The tailings storage facility dam and basin clearing has started, while the temporary construction coffer dams are finished. Work also began on the east diversion ditch. Polishing pond earthworks are almost done, and liner installation is underway. Paste plant access road and site preparation has begun and the fresh air raise access road was completed. Other The Company received the Mountain Pass Quarry Environmental License and is in the final stages of negotiating rights to develop the quarry with local government. Construction of the powerline started on three fronts in September. Financial Results (in thousands, except per share amounts) Three months ended September 30, Nine months ended September 30, 2018 2017 2018 2017 Results of Operations: Net income (loss) for the period $ 7,270 $ (16,032) $ 1,423 $ (21,634) Income (loss) per share Basic 0.03 (0.13) 0.01 (0.18) Diluted 0.03 (0.13) 0.01 (0.18) (in thousands) As at September 30 2018 As at December 31, 2017 Financial Position: Cash 291,599 35,018 Working capital 290,398 26,794 Property, plant and equipment 368,829 142,598 Mineral properties 256,769 246,387 Total assets 1,007,287 481,729 Long-term debt 351,591 217,940 xxxx The Company s net income in the third quarter of 2018 is due to the revaluation of the Company s long-term debt, as more fully explained below, and was offset by a foreign exchange loss from its substantial holdings of U.S. dollar cash at its Canadian entities during the quarter compared to a foreign exchange loss of only $0.8 million in the third quarter of 2017. 2

The Company generated net income of $1.4 million in the nine months ended September 30, 2018 compared to a loss of $21.6 million in the same period of 2017. This is mainly due to the revaluation of the Company s long-term debt and recognition of a substantial foreign exchange gain. Partially offsetting these gains were higher salaries and benefits during the nine months ended September 30, 2018 compared to the same period in 2017 due to the performance incentive plan payment to the Company s employees. Derivative gains or losses During the third quarter of 2018, the Company recorded a derivative gain from the fair value revaluation of its long-term debt of $17.9 million compared to a derivative loss of $8.3 million recognized in the third quarter of 2017. For the nine months ended September 30, 2018, the Company has recorded a derivative gain of $12.8 million compared to a derivative loss of $3.9 million in the same period in 2017. Liquidity and Capital Resources As at September 30, 2018, the Company had cash of $291.6 million and a working capital of $290.4 million compared to cash of $35.0 million and a working capital balance of $26.8 million at December 31, 2017. The change in cash was primarily due to net proceeds from the private placement in March 2018 of $396.5 million and the final drawdown of $110 million under the gold prepay and stream credit facilities. This is offset by costs incurred for the development of the Fruta del Norte Project of $193.3 million, general and administration costs of $14.3 million and exploration expenditures of $5.0 million. Outlook The Company is focused on advancing the Project on schedule through to first gold production in the fourth quarter of 2019. The following activities are planned over the next twelve months: Completing detailed engineering. Completing process plant construction and starting commissioning. Starting mine operations and mining ore to stockpiles. Advancing underground declines across the ore body to the bottom of the fresh air raise. Completing construction of the site infrastructure buildings such as the laboratory, reagent storage, mine dry and administration. Completing the construction of the power transmission line and connecting to the national grid at the Bomboiza substation. Signing the Mountain Pass Quarry exploitation agreement and developing the quarry. Completing construction of the tailing storage facility. Completing the design and supply of the paste plant and commencing construction. Obtaining permits and starting construction of the Zamora River bridge in El Pindal. The Company has substantially agreed to the terms of a cost overrun facility (the COF ) with a provider. Completion of the COF is a condition precedent to the initial draw down of the senior debt facility, expected to occur in the first quarter of 2019, and is now subject to acceptance by the Company s lenders and final documentation. 3

Exploration continues to focus on developing drilling targets through mapping and geochemical sampling at the Suarez Basin and Gata Salvaje targets. Drill permitting continues for a number of epithermal gold-silver target areas around the Suarez Basin. Qualified Person The technical information relating to the Fruta del Norte Project contained in this press release has been reviewed and approved by Ron Hochstein P. Eng, Lundin Gold's President and CEO who is a Qualified Person under NI 43-101. The disclosure of exploration information contained in this press release was prepared by Stephen Leary, MAusIMM CP(Geo), a consultant to the Company, who is a Qualified Person in accordance with the requirements of NI 43-101. Additional Information The Company's consolidated financial statements for the three and nine months ended September 30, 2018 and related management's discussion and analysis are available on the Company's website at www.lundingold.com or under its profile on SEDAR at www.sedar.com. The information in this release is subject to the disclosure requirements of Lundin Gold under the EU Market Abuse Regulation. This information was submitted for publication November 8, 2018 at 3:00 p.m. PT through the contact persons set out below. About Lundin Gold Lundin Gold, headquartered in Vancouver, Canada, is developing its wholly-owned Fruta del Norte gold project in southeast Ecuador. Fruta del Norte is one of the world's largest, highest-grade gold projects currently under construction. The Company's board and management team have extensive expertise in mine construction and operations, and are dedicated to advancing this project through to first gold production in the fourth quarter of next year. The Company operates with transparency and in accordance with international best practices. Lundin Gold is committed to delivering value to its shareholders, while simultaneously providing economic and social benefits to impacted communities, fostering a healthy and safe workplace and minimizing the environmental impact. The Company believes that the value created through the development of Fruta del Norte will benefit its shareholders, the Government and the people of Ecuador. For more information, please contact Lundin Gold Inc. Ron F. Hochstein President and CEO +593 2-299-6400 +604-806-3589 Lundin Gold Inc. Sabina Srubiski Manager, Investor Relations +1-604-806-3089 info@lundingold.com 4

www.lundingold.com Follow Lundin Gold on Twitter Caution Regarding Forward-Looking Information and Statements Certain of the information and statements in this press release are considered forward-looking information or forward-looking statements as those terms are defined under Canadian securities laws (collectively referred to as forward-looking statements ). Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or performance (often, but not always, identified by words or phrases such as believes, anticipates, expects, is expected, scheduled, estimates, pending, intends, plans, forecasts, targets, or hopes, or variations of such words and phrases or statements that certain actions, events or results may, could, would, will, should might, will be taken, or occur and similar expressions) are not statements of historical fact and may be forward-looking statements. By their nature, forward-looking statements and information involve assumptions, inherent risks and uncertainties, many of which are difficult to predict, and are usually beyond the control of management, that could cause actual results to be materially different from those expressed by these forward-looking statements and information. Lundin Gold believes that the expectations reflected in this forward-looking information are reasonable, but no assurance can be given that these expectations will prove to be correct. Forward-looking information should not be unduly relied upon. This information speaks only as of the date of this press release, and the Company will not necessarily update this information, unless required to do so by securities laws. This press release contains forward-looking information in a number of places, such as in statements pertaining to: the anticipated timing of production and the progress of the development, construction and operation of the Project, improvements to site logistics and completion of site and powerline infrastructure and the acquisition of land and surface rights, the success of the Company s exploration plans and activities, exploration and development expenditures and reclamation costs, timing and success of permitting and regulatory approvals, project financing and future sources of liquidity, capital expenditures and requirements, future tax payments and rates, cash flows and their uses. Lundin Gold s actual results could differ materially from those anticipated. Management has identified the following risk factors which could have a material impact on the Company or the trading price of its shares: the ability to arrange financing and the risk to shareholders of dilution from future equity financings; the ability to maintain its obligations under the gold prepay and stream credit facilities, the senior debt facility and other debt; risks related to carrying on business in Ecuador; volatility in the price of gold; the timely receipt of regulatory approvals, permits and licenses; risks associated with the performance of the Company's contractors; risks inherent in the development of an underground mine; deficient or vulnerable title to mining concessions and surface rights; shortages of critical resources, labour and key executive personnel, such as input commodities, equipment and skilled labour, and the dependence on key personnel; risks associated with the Company's community relationships; unreliable infrastructure; volatility in the market price of the Company's shares; the potential influence of the Company's largest shareholders; uncertainty with the tax regime in Ecuador; measures required to protect endangered species; the cost of compliance or failure to comply with applicable laws; exploration and development risks; the accuracy of the Mineral Reserve and Resource estimates for the Fruta del Norte Project; the Company's reliance on one project; risks related to artisanal and illegal mining; uncertainty as to reclamation and decommissioning; risks associated with the Company's information systems; competition in the mining industry; the ability to obtain adequate insurance; risks of bribery or corruption; the potential for litigation; and limits of disclosure and internal controls. There can be no assurance that such statements will prove to be accurate, as Lundin Gold's actual results and future events could differ materially from those anticipated in this forward-looking information as a result of the factors discussed in the "Risk Factors" section in Lundin Gold's Annual Information Form dated March 20, 2018, which is available under the Company s profile at www.sedar.com. 5

Figure 1. Fruta del Norte project site September 2018 Figure 2. North Access Road was substantially complete and being used by commercial vehicles 6

Figure 3. Process plant grinding building steel is progressing Figure 4. New permanent maintenance shop will have six bays 7

Figure 5. Powerline construction is ongoing on three fronts 8