Canada. Record of Proceedings, Including Reasons for Decision. Applicant. Cameco Corp_o_ra_ti_o_n _. Subject

Similar documents
Canada. Record of Proceedings, Reasons for Decision. Requestor. Hydro-Quebec. Purpose

Canada. Record of Proceedings, Reasons for Decision. Proponent. Subject

Canada. *. Canadian Nuclear Commission canadienne. Record of Decision. In the Matter of. Hydro-Quebec. Applicant

Canada. Summary Record of Proceedings and Decision. Cameco Corp_o_ra_t_io_n. Applicant

Canada. Summary Record of Proceedings and Decision. In the Matter of. Cameco Corp_o_ra_t_io_n. Applicant

Record of Proceedings, Including Reasons for Determination

Canadian Nuclear Safety Commission Quarterly Financial Report for the Quarter Ended December 31, 2016

Canadian Nuclear Safety Commission Quarterly Financial Report For the Quarter Ended June 30, 2015

Canadian Environmental Assessment Agency Canadian Nuclear Safety Commission: Joint Review Panels

Canadian Nuclear Safety Commission Quarterly Financial Report for the Quarter Ended June 30, 2017

l+i Safety Commission II Ill MEMORANDUM OF UNDERSTANDING (MoU) BETWEEN THE CANADIAN NUCLEAR SAFETY COMMISSION AND

Canadian Nuclear Safety Commission Quarterly Financial Report for the Quarter Ended September 30, 2017

Canadian Nuclear Safety Commission Quarterly Financial Report for the Quarter Ended December 31, 2017

REGULATORY DOCUMENTS. The main classes of regulatory documents developed by the CNSC are:

Canada. Record of Decision. In the Matter of. Cameco Corporation. Applicant

CNSC staff advisers were: H. Rabski, R. Ravishankar, P. Elder, G. Lamarre, M. Lord, M. Simard and B. Ecroyd

Canadian Nuclear Safety Commission. Commission canadienne de sûreté nucléaire. Public hearing. Audience publique

Oral Presentation. Exposé oral. Submission from the Power Workers Union. Mémoire du Syndicat des travailleurs et travailleuses du secteur énergétique

CNSC Cost Recovery Program

AREVA Resources Canada Inc. Cluff Lake Project

Request for Acceptance of OPG s Financial Guarantee

Canadian Nuclear Safety Commission

Financial Guarantees for Decommissioning of Canadian NPPs

Canadian Nuclear Safety Commission. Commission canadienne de sûreté nucléaire

Licensing Basis Objective and Definition

Administrative Monetary Penalties Regulations (Canadian Nuclear Safety Commission) Comment Disposition Report

Implementation of Financial Guarantees for Licensees

Mémoire de. Written submission from EnergySolutions Canada CMD 18-H4.97. File / dossier: Date: Edocs:

Canadian Environmental Assessment Act (CEAA) Aboriginal Affairs and Northern Development Canada (AANDC) An Environmental Management Approach

Use of the Graded Approach in Regulation

AREVA Resources Canada Inc. Établissement de Cluff Lake Garantie financière modifiée et changement de nom de la société

SOME CURRENT LEGAL DEVELOPMENTS AND ISSUES IN NUCLEAR LAW

FINAL Roberts Bank Terminal 2 Project Review Panel Terms of Reference

ONTARIOF Eil GENERATION. Brian Duncan Senior Vice President. Darlington Nuclear. OPG Proprietary. December 10, 2014 CD# NK38 CORR

Nuclear Law Developments in Canada

Submission of performance based action levels for fenceline gamma monitoring at Cameco s Port Hope conversion facility

Introduction to Nuclear Law

Regulatory Fundamentals

Strengthening Canada s nuclear liability regime. By Dave McCauley 1 & Jacques Hénault 2

Canadian Nuclear Safety Commission

Oral Presentation. Exposé oral. Submission from the Canadian Environmental Law Association

Oral Presentation. Exposé oral. Submission from Aecon Group Inc. Mémoire de Aecon Group Inc. CMD 18-H4.75

Cameco Corporation. Bob Steane. Senior Vice-President and Chief Operating Officer. November 20, cameco.com

Oral Presentation. Exposé oral. Submission from North American Young Generation in Nuclear. Mémoire de North American Young Generation in Nuclear

APPLICANTS MEMORANDUM OF FACT AND LAW PART I CONCISE STATEMENT OF FACTS

REGULATORY DOCUMENTS. The main classes of regulatory documents developed by the CNSC are:

Federal Budget Bills 2012 Implications for Federal Environmental Law

Canadian Nuclear Safety Commission. Commission canadienne de sûreté nucléaire. Public hearing. Audience publique

REFURBISHMENT AND NEW GENERATION NUCLEAR

RE: An Environmental Assessment for the Lakeview Waterfront Connection. Proponents: Credit Valley Co~se rvat ion and the Region of Peel

KEEPING NUCLEAR SAFE LOOKING BACK AND BEYOND CANADIAN NUCLEAR SAFETY COMMISSION ANNUAL REPORT

ONTARIO POWER GENERATION INC. and. GREENPEACE CANADA, LAKE ONTARIO WATERKEEPER, NORTHWATCH and CANADIAN ENVIRONMENTAL LAW ASSOCIATION

December 9 and 10, 2009

Oral Presentation. Exposé oral. Submission from Nuclear Waste Watch. Mémoire de Action Déchets Nucléaires CMD 18-H4.100

ONTARIO POWER GENERATION REPORTS 2008 FIRST QUARTER FINANCIAL RESULTS

Mémoire de. Written submission from Areva Resources Canada Inc. CMD 18-H File/dossier : Date : e-docs pdf :

DECISION AND ORDER ON PHASE 1

Pickering Whole-Site Risk

Canadian Nuclear Safety Commission. Commission canadienne de sûreté nucléaire. Public hearing. Audience publique

Financial and outlook information as of June 30, 2018 Mineral Reserve and Resource Estimates as of January 1, 2018.

Canadian Nuclear Safety Commission

FINANCIAL STATEMENTS

Reporting Requirements Reporting Requirements, Volume I: Non-Power Reactor Class I Nuclear Facilities and Uranium Mines and Mills REGDOC-3.1.

Fisheries and Oceans Canada Organizational Structure. Presentation to Cohen Commission November 1, 2010

OPG REPORTS 2015 THIRD QUARTER FINANCIAL RESULTS

Environmental Appeal Board

ONTARIO POWER GENERATION REPORTS 2013 FIRST QUARTER FINANCIAL RESULTS

APPLICATION FOR REVIEW PURSUANT TO SUBSECTION 43(1) OF THE ACT

NUCLEAR WASTE MANAGEMENT AND DECOMMISSIONING BACKGROUND INFORMATION

FIRST QUARTER REPORT. YEAR-TO-DATE RESULTS For the period ended June 30, 2017

Algonquin Opportunity (No.2) Corporation. Financial Statements

September 24, Canadian Nuclear Safety Commission P.O. Box 1046, Station B 280 Slater Street Ottawa, Ontario K1P 5S9

Order in Council Decret

ONTARIO POWER GENERATION INC. ANNUAL INFORMATION FORM FOR THE YEAR ENDED DECEMBER 31, 2015

Canadian Environmental Assessment Agency

Application to Participate in the Auction for Spectrum Licences for Advanced Wireless Services and other Spectrum in the 2 GHz Range

ONTARIO POWER GENERATION REPORTS 2013 THIRD QUARTER FINANCIAL RESULTS

Canadian Environmental Assessment Agency

TLA AMIN NATION TAX TREATMENT AGREEMENT

Pipelines: Government Decision-Making

Reference Guide on Environmental and Social Impact Assessment Procedures Applicable in Nunavik

Whole-Site Risk Considerations for Nuclear Power Plants

SUPPORTING EVIDENCE FOR ENTRIES INTO NUCLEAR ACCOUNTS

Cameco reports fourth quarter and 2017 financial results

NB Power Licence Renewal Intervention CNSC Hearing Notice No H-02

Dr. Wang Wenying Secretary General of CIETAC Hong Kong Arbitration Center

PROJECT AGREEMENT FOR THE HAMMOND REEF GOLD MINE IN ONTARIO

Ontario Power Generation 2017 Investor Call. March 9, 2018

Evaluation of the Canadian Nuclear Safety Commission s Contribution to the Canadian Standards Association s Nuclear Standards Program

Regulatory Approval and Expediency

THE ONTARIO NFWA TRUST

Contents. Application. What is the difference between a Technical Interpretation and a Ruling? INCOME TAX INFORMATION CIRCULAR

The Regulatory Roadmaps Project

OPG REPORTS 2016 SECOND QUARTER FINANCIAL RESULTS

Broadcasting Decision CRTC

Visit and subscribe to our alert service to receive the latest Province of Ontario updates:

C A N A D I A N E N V I R O N M E N TA L A S S E S S M E N T A C T & R E V I E W P R O C E S S

Re: Consultation on the Draft Directive NO. 1R4, Counselling in Insolvency Matters

THE ONTARIO NFWA TRUST

Enhancing Canada s International Tax Advantage Submission to the Advisory Panel on Canada s System of International Taxation

Transcription:

Canadian Nuclear Safety Commission Commission canadienne de sorete nucleaire Record of Proceedings, Including Reasons for Decision Applicant Cameco Corp_o_ra_ti_o_n _ Subject Application to Amend the Blind River Fuel Facility Operating Licence Hearing Date June 9,2011 Canada

RECORD OF PROCEEDINGS Applicant: Address/Location: Purpose: Cameco Corporation 205 Peter Street, Port Hope, Ontario L1A 3V6 Application to amend the Blind River Facility Operating Licence Application received: August 18, 2011 Date of hearing: June 9, 2011 Location: Members present: Secretary: Recording Secretary: Canadian Nuclear Safety Commission (CNSC) 280 Slater St., Ottawa, Ontario M. Binder, Chair M. Leblanc S. Gingras Licence: Amended

i Table of Contents Introduction... 1 Decision... 1 Issues and Commission Findings... 2 Qualifications and Protection Measures... 2 Application of the Canadian Environmental Assessment Act... 2 Conclusion... 3

Introduction 1. Cameco Corporation (Cameco) has applied to the Canadian Nuclear Safety Commission 1 (CNSC) for an amendment to the operating licence for its Blind River Facility located in Blind River, Ontario. The current licence, FFOL-3632.1/2012, expires on February 29, 2012. 2. Cameco requested to amend the licence to remove an ambiguous statement in Appendices C and F and clarify that the incinerator may be operated 24 hours per day. 3. The Blind River incinerator has been operating since the facility was licensed to operate in 1984. In February 2007, Cameco requested a licence amendment to permit the installation of new emission control equipment to meet the Ontario Ministry of the Environment s (MOE) emission guidelines. Issue 4. In considering the application, the Commission was required to decide, pursuant to subsection 24(4) of the Nuclear Safety and Control Act 2 (NSCA): a) if Cameco is qualified to carry on the activity that the amended licences would authorize; and b) if in carrying on that activity, Cameco would make adequate provision for the protection of the environment, the health and safety of persons and the maintenance of national security and measures required to implement international obligations to which Canada has agreed. Hearing 5. Pursuant to section 22 of the NSCA, the President of the Commission established a Panel of the Commission to review the application. The Commission, in making its decision, considered information presented for a hearing held on June 9, 2011 in Ottawa, Ontario. During the hearing, the Commission considered written submissions from CNSC staff (CMD 11-H108) and Cameco (CMD 11-H108.1). Decision 6. Based on its consideration of the matter, as described in more detail in the following sections of this Record of Proceedings, the Commission concludes that Cameco has met the conditions of subsection 24(4) of the NSCA. Therefore, 1 The Canadian Nuclear Safety Commission is referred to as the CNSC when referring to the organization and its staff in general, and as the Commission when referring to the tribunal component. 2 Statutes of Canada (S.C.) 1997, chapter (c.) 9.

- 2 - the Commission, pursuant to section 24 of the Nuclear Safety and Control Act, amends the Nuclear Fuel Facility Operating Licence FFOL-3632.1/2012 issued to Cameco Corporation for its Blind River Facility located in Blind River, Ontario. The amended licence, FFOL-3632.2/2012, is valid until February 29, 2012. 7. The Commission includes in the licence the conditions as recommended by CNSC staff in CMD 11-H108. Issues and Commission Findings Qualifications and Protection Measures 8. Cameco has applied for an amendment to a note under Table 2 of Appendix C and F of its operating licence to remove the reference to the operation of the incinerator for up to 12 hours per day. Cameco has requested to increase the operation of the incinerator to allow flexibility in operations without exceeding the maximum weekly feed rate of 18 540 kg/week. 9. CNSC staff is of the opinion that the note referred to in Table 2 was only meant to calculate the daily emission rate based on 12 instead of 24 hours averaging time. CNSC staff added that accepting the requested change will clarify the note and will not change the emissions to the environment, the daily uranium emissions being well below the action level and the maximum amount of waste to be incinerated per week remaining the same. The action levels and the emission limits will also remain the same. 10. CNSC staff has determined that the licence amendment requested is minor in nature and that the requested changes will have no adverse impacts on the Aboriginal rights or Treaty rights of Aboriginal groups. Therefore, the Duty to consult did not arise in relation to the proposed licence amendment. Application of the Canadian Environmental Assessment Act 11. Before making a licensing decision, the Commission must be satisfied that all applicable requirements of the Canadian Environmental Assessment Act 3 (CEAA) have been fulfilled. 12. CNSC staff reported that it had completed an Environmental Assessment (EA) determination. CNSC staff stated that there was no requirement for an EA pursuant to subsection 5(1) of the CEAA as the bounding factors of the previous EA conducted for this project in 2006 are still valid. 3 S.C. 1992, c. 37.

13. The Commission has considered the information and submissions of CNSC staff and Cameco and is satisfied that the requested amendments are administrative in nature and will not adversely impact the safety of the Blind River facility operations. The Commission is also satisfied that aboriginal consultation is not necessary in relation to the proposed amendments. 14. The Commission is also satisfied that all applicable requirements of the CEAA have been fulfilled. d-'~ Michael Binder President, Canadian Nuclear Safety Commission