OFFICIAL DOCUMENTS. Project Agreement. Public Disclosure Authorized. GRANT NUMBER D336-GN CREDIT NUMBER 6261-GN Public Disclosure Authorized

Similar documents
Project Agreement. (WEST AFRICA REGIONAL FISHERIES PROGRAM REPUBLIC OF LIBERIA (Phase I)) between INTERNATIONAL DEVELOPMENT ASSOCIATION.

Southern African Power Market Program Project Agreement. (Mozambique Component Mozambique-Malawi Transmission Interconnection Project) between

Project Agreement OFFICIAL DOCUMENTS. Public Disclosure Authorized LOAN NUMBER 8457-CN. Public Disclosure Authorized. (Zhengzhou Urban Rail Project)

Project Agreement OFFICIAL DOCUMENTS. Public Disclosure Authorized. Public Disclosure Authorized CREDIT NUMBER 5127-UG

(Punjab Barrages Improvement Phase-II Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT. and PROVINCE OF PUNJAB

Project Agreement. (Private Sector Development Support Project) between INTERNATIONAL DEVELOPMENT ASSOCIATION. and

Haiti Education for All Multi-donor Trust Fund Grant Agreement

Project Agreement. (Zanzibar Basic Education Improvement Project) between INTERNATIONAL DEVELOPMENT ASSOCIATION. and

Ebola Recovery and Reconstruction Trust Fund Grant Agreement

OFFICIAL DOCUMENTS. Project Agreement LOAN NUMBER 8655-YF. (Additional Financing for Corridor X Highway Project) between

OFFICIAL MDTF-HRI GRANT NUMBER TF between REPUBLIC OF CAMEROON. and

Financing Agreement OFFICIAL DOCUMENTS GRANT NUMBER D004-FM FEDERATED STATES OF MICRONESIA INTERNATIONAL DEVELOPMENT ASSOCIATION

OFFICIAL DOCUMENTS. Financing Agreement. Public Disclosure Authorized CREDIT NUMBER 6343-RW. Public Disclosure Authorized. (Housing Finance Project)

Multi Donor Trust Fund for the Zimbabwe Reconstruction Fund Project Agreement

Project Agreement. (West Beka a Emergency Water Supply Project) between

INTERNATIONAL DEVELOPMENT ASSOCIATION

Financing Agreement. (Uganda Public Service Performance Enhancement Project) between THE REPUBLIC OF UGANDA. and

Tamil Nadu Project Agreement

Financing Agreement OFFICIAL DOCUMENTS 1. (Amending and Restating the Development Credit Agreement) Public Disclosure Authorized

Multi-Donor Trust Fund for the Malawi Public Finance and Economic Management Reform Program Grant Agreement

between Republic of The Gambia and

Restated and Amended Project Agreement

DOCUMENTS OFFICIAL. Financing Agroement. Public Disclosure Authorized CREDIT NUMBER 6122-GH. Public Disclosure Authorized

Financing Agreement,.

Loan Agreement DMIUMTS OFFICIAL LOAN NUMBER 8131-CN PEOPLE'S REPUBLIC OF CHINA INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

OFFICIAL DOCUMENTS. Loan Agreement LOAN NUMBER 8734-GD. (OECS Regional Tourism Competitiveness Project) between GRENADA

Project Agreement OFFICIAL DOCUMENTS LOAN NUMBER 8391-UA. Second Urban Infrastructure Project (Urban Infrastructure Project - 2) between

OFFICIAL DOCUMENTS. Loan Agreement

(Taunsa Barrage Emergency Rehabilitation and Modernization Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT.

Multi-Donor Trust Fund for the Sahel Adaptive Social Protection Program Grant Agreement

OFFICIAL DOCUMENTS ZW4

Project Agreement CONFORMED COPY CREDIT NUMBER 4191-TA. (Financial Sector Support Project) between INTERNATIONAL DEVELOPMENT ASSOCIATION.

Loan Agreement. (Power System Improvement Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT. and ELECTROSTOPANSTVO NA MAKEDONIJA

Development Credit Agreement

Project Agreement CONFORMED COPY LOAN NUMBER CHA. (Hubei Shiman Highway Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

OFFICIAL DOCt HMENTS

Project Agreement. (Indonesia Infrastructure Finance Facility Project) among INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT.

Prqject Agreement. Public Disclosure Authorized. CREDIT NUMBER 2634 KG Public Disclosure Authorized. (Telecommunications Project)

PROJECT AGREEMENT. (Power Distribution Enhancement Investment Program Tranche 1, Investment Project and Support Project) between

Financing Agreement CREDIT NUMBER 5816-ET. (Transport Systems Improvement Project) between FEDERAL DEMOCRATIC REPUBLIC OF ETHIOPIA.

Nile Basin Trust Fund Grant Agreement

Loan Agreement OFFICIAL DOCUMENTS LOAN NUMBER 8658-CM. (Electricity Transmission and Reform Project) between. REPUBLIC OF CAMEROON and

Global Environment Facility Trust Fund Grant Agreement

Financing Agreement CONFORMED COPY GRANT NUMBER H732 -AF. (Financial Sector Rapid Response Project) between ISLAMIC REPUBLIC OF AFGHANISTAN.

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Global Environment Facility Grant Agreement

Financing Agreement OFFICIM. DOCUMENTS1 CREDIT NUMBER 5283-IN. (Low Income Housing Finance Project) between INDIA. and

Project Agreement. (Shanghai Urban Environment Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT. and SHANGHAI MUNICIPALITY

Loan Agreement. (Institutional Development and Agriculture Strengthening Project) between MONTENEGRO. and

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Financing Agreement CREDIT NUMBER VN. (Ho Chi Minh City Green Transport Development Project) between SOCIALIST REPUBLIC OF VIETNAM.

RS Project Agreement. (Second Local Initiatives (Microfinance) Project) between INTERNATIONAL DEVELOPMENT ASSOCIATION. and REPUBLIKA SRPSKA

Loan Agreement. Public Disclosure Authorized LOAN NUMBER 8599-GE. Public Disclosure Authorized. (Secondary Road Asset Management Project)

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized CONFORMED COPY

OFFICIAL DOCUMENTS. Project Agreement LOAN NUMBER 8715-ID

Financing Agreement CREDIT NUMBER 5404-PG CREDIT NUMBER 4931-PG INDEPENDENT STATE OF PAPUA NEW GUINEA INTERNATIONAL DEVELOPMENT ASSOCIATION

Financing Agreement. Public Disclosure Authorized CREDIT NUMBER 5181-KE. Public Disclosure Authorized. (Judicial Performance Improvement Project)

ECG Project Agreement

Financing Agreement CONFORMED COPY IDA CREDIT NUMBER 4825-KG IDA GRANT NUMBER H618-KG. (Emergency Recovery Project) between KYRGYZ REPUBLIC.

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized CONFORMED COPY

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized CONFORMED COPY

, Honorable Tendai Biti Minister of Finance Ministry of Finance

Project Agreement. Public Disclosure Authorized OFFICIAL DOCUMENTS LOAN NUMBER 7792-IN. Public Disclosure Authorized

Development Financing Agreement

Multi-Donor Health Results Innovation Trust Fund Grant Agreement

Financing Agreement. (Strengthening Regional Cooperation for Wildlife Protection in Asia Project) between NEPAL. and

Global Environment Facility Trust Fund Grant Agreement

Loan Agreement OFFICIAL 90CUMENTS1. Public Disclosure Authorized LOAN NUMBER 8263-GE. Public Disclosure Authorized

Project Agreement CREDIT NUMBER 3991 MOZ. (Beira Railway Project) between INTERNATIONAL DEVELOPMENT ASSOCIATION. and

Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized. Public Disclosure Authorized CONFORMED COPY

Project Agreement. (Energy Efficiency Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Republic of Senegal: Advance Agreement for the Preparation of the Proposed Casamance Development Pole Project Project Preparation Advance No.

PAD Project Agreement. (Second Transport Sector Project) between INTERNATIONAL DEVELOPMENT ASSOCIATION. and PORT AUTONOME DE DAKAR. Dated May 13, 1999

Project Agreement. Public Disclosure Authorized CONFORMED COPY LOAN NUMBER 2224 BR. Public Disclosure Authorized. (Third Feeder Roads Project)

Project Agreement REPUBLIKA SRPSKA CREDIT NUMBER 4912-BA. (Additional Financing for Health Sector Enhancement Project) between

Project Agreement. Public Disclosure Authorized CONFORMED COPY LOAN NUMBER 1674 PA. Public Disclosure Authorized

Tazama Project Agreement

PROJECT AGREEMENT. (Sindh Cities Improvement Investment Program Project 1) between ASIAN DEVELOPMENT BANK. and PROVINCE OF SINDH

Financing Agreement. (Additional Financing for Village Communities Support Program (Phase I)) between REPUBLIC OF GUINEA. and

Financing Agreement OFFICIAL OCUMENTS. Public Disclosure Authorized CREDIT NUMBER 5152-UZ. Public Disclosure Authorized

Global Environment Facility Trust Fund Grant Agreement

cocumeasn Loan Agreement OFFICIAL LOAN NUMBER 8095-BR

Loan Agreement. (Real Property Registration and Cadastre Project) between REPUBLIC OF CROATIA. and

Loan Agreement. (Indonesia Infrastructure Finance Facility Project) between REPUBLIC OF INDONESIA. and

1. Paragraph (D) of the Preamble to the GEF Grant Agreement is deleted and the succeeding paragraph re-numbered accordingly.

Financing Agreement. (Environmental and Social Capacity Building for the Energy Sector Project) between THE REPUBLIC OF CAMEROON.

Liaoning Project Agreement

Loan Agreement (Real Estate Management Project)

(Third Integrated Financial Management Technical Assistance Project) between REPUBLIC OF GUATEMALA. and

Loan Assumption Agreement

Section (a) ADB and Uzbekenergo shall cooperate fully to ensure that the purposes of the Loan will be accomplished.

INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Development Credit Agreement. (Basic Health Project) between BOSNIA AND HERZEGOVINA. and INTERNATIONAL DEVELOPMENT ASSOCIATION

Ondo Projeet Agreement

Project Agreement. (Orissa Socio-Economic Development Program) among INTERNATIONAL DEVELOPMENT ASSOCIATION. and

Agreement Amending Project Agreement

Project Agreement LOAN NUMBER CN. (Second Liuzhou Environment Management Project) between INTERNATIONAL BANK FOR RECONSTRUCTION AND DEVELOPMENT

Development Credit Agreement

PEOPLE S REPUBLIC OF CHINA

Transcription:

Public Disclosure Authorized OFFICIAL DOCUMENTS GRANT NUMBER D336-GN CREDIT NUMBER 6261-GN Public Disclosure Authorized Project Agreement (Guinea - Mali Interconnection Project) Public Disclosure Authorized between INTERNATIONAL DEVELOPMENT ASSOCIATION and ELECTRICITt DE GUINEE Public Disclosure Authorized

PROJECT AGREEMENT GRANT NUMBER D336-GN CREDIT NUMBER 6261-GN AGREEMENT between the INTERNATIONAL DEVELOPMENT ASSOCIATION ("Association") and ELECTRICITE DE GUINEE ("EDG" or "Project Implementing Entity") ("Project Agreement"), in connection with the Financing Agreement ("Financing Agreement") of the Signature Date between the Republic of Guinea ("Recipient) and the Association, concerning Grant No. D336-GN and Credit No. 626 1-GN. The Association and EDG hereby agree as follows: ARTICLE I - GENERAL CONDITIONS; DEFINITIONS 1.01. The General Conditions (as defined in the Appendix to the Financing Agreement) apply to and form part of this Agreement. 1.02. Unless the context requires otherwise, the capitalized terms used in this Agreement have the meanings ascribed to them in the Financing Agreement or the General Conditions. ARTICLE II - PROJECT 2.01. EDG declares its commitment to the objectives of the Project and the Program. To this end, EDG shall carry out Parts 1.A.1, 1.A.2, I.A.3, 1.B and 2 of the Project in accordance with the provisions of Article V of the General Conditions and the Schedule to this Agreement, and shall provide promptly as needed, the funds, facilities, services and other resources required for Parts I.A.1, 1.A.2, 1.A.3, L.B and 2 of the Project. ARTICLE III - TERMINATION 3.01. For purposes of Section 10.05(c) of the General Conditions, the date on which the provisions of this Agreement shall terminate is twenty (20) years after the Signature Date. ARTICLE IV - REPRESENTATIVE; ADDRESSES 4.01. EDG's Representative is its General Administrator (Administrateur Gjnrale).

-2-4.02. For purposes of Section 11.01 of the General Conditions: the Association's address is: International Development Association 1818 H Street, NW Washington, DC 20433 United States of America; and the Association's Electronic Address is: Telex: Facsimile: 248423(MCI) or 1-202-477-6391 4.03. For purposes of Section 11.01 of the General Conditions: EDG's address is: Immeuble EDG Cit6 Chemin de Fer B.P. 1463 Conakry Republic of Guinea

-3 - AGREED as of the later of the two dates written below. INTERNATIONAL DEVELOPMENT ASSOCIATION By: Authorized Representative Name: 4 Title: _C_ Date: ( By: Authorized Representative Name: Lo L % AjK Title: IL 4 Date: V)O )

-4- SCHEDULE Execution of Parts 1.A.1, 1.A.2, 1.A.3, 1.B and 2 of the Project Section I. Implementation Arrangements A. Institutional Arrangements 1. Project Implementation Unit EDG shall maintain throughout Project implementation, at all times under terms of reference and with a composition satisfactory to the Association, the Project Implementation Unit vested with responsibility for, inter alia: (i) carrying out the bidding process for the works to be financed under the Project; (ii) supervising the implementation of the Project; (iii) coordinating the activities of the various stakeholders, including consultants, manufacturers, installers, inspection services and all the public services concerned; (iv) approving technical documents; (v) ensuring sound financial management of the Project; (vi) preparing Project and Completion Reports; (vii) coordinating the commissioning of the Project once completed; (viii) ensuring the smooth handing over of its facilities to the utility that shall, upon Project completion, be in charge of operating and maintaining them; and (ix) preparing and participating in, as secretary, the meeting of the Joint Implementation Steering Committee. For such purposes, the PIU shall be headed by the Project Coordinator and its composition shall include existing staff of EDG, consultants, and the following specialists to be employed by the EDG: (A) not later than two (2) months after the Effective Date, one (1) accountant; and (B) not later than three (3) months after the Effective Date: one (1) senior environmental specialist, one (1) social development specialist, one (1) electrical engineer specialized in power transmission substations, and one (1) electrical engineer specialized in power transmission lines, all with experience and qualifications satisfactory to the Association. B. Safeguards 1. EDG shall implement the Project in accordance with the provisions of the Environmental and Social Management Plan (ESMP) and the Resettlement Action Plan (RAP), all in a manner satisfactory to the Association. 2. Without limitation upon the provisions of the precedent paragraph 1, EDG shall take all required measures to ensure, through its own staff and/or existing environmental/social institutions, that no works are commenced under the Project until and unless all Project Affected Persons have been properly compensated in accordance with the provisions and procedures set forth in the RAP, including an up-to-date census which adequately identifies all such Project Affected Persons,

-5 - and in compliance with the requirements of appropriate national and/or local authorities. 3. Without limitation upon its other reporting obligations under this Agreement, EDG shall collect, compile and furnish to the Association on a quarterly basis, or promptly whenever the circumstances warrant, reports on the status of compliance with the Environmental and Social Management Plan (ESMP) and the Resettlement Action Plan (RAP), giving details of: (c) measures taken in furtherance of the ESMP and the RAP; conditions, if any, which interfere or threaten to interfere with the smooth implementation of the ESMP and the RAP; and remedial measures taken or required to be taken to address such conditions. 4. EDG shall promptly take all remedial measures referred to in paragraph 3 of this Section C as shall have been agreed by the Association. C. Project Implementation Manual EDG shall: take all action required to carry out the Project in accordance with the provisions and requirements set forth or referred to in the Project Implementation Manual; submit recommendations to the Association for its consideration for changes and further updates of the Project Implementation Manual as they may become necessary or advisable during Project implementation in order to achieve the objectives of the Project; and (c) not assign, amend, abrogate or waive the Project Implementation Manual or any of its provisions without the prior approval of the Association. Notwithstanding the foregoing, if any of the provisions of the Project Implementation Manual is inconsistent with the provisions of this Agreement, the provisions of this Agreement shall prevail and govern. D. Annual Work Plan and Budget (AWP&B) EDG shall: prepare a draft AWP&B for each Fiscal Year, setting forth, inter alia: (i) a detailed description of planned Project activities for the following Fiscal Year; (ii) the sources and uses of funds therefor; and (iii) responsibility for execution of said Project activities, budgets, start and completion date, outputs, and monitoring indicators to track progress of each activity; on or about November 30 of each Fiscal Year and after considering the comments provided by the Joint Implementation Steering Committee,

-6- furnish to the Association for its comments and approval, the draft AWP&B and, promptly thereafter, finalize the AWP&B taking into account the Association's views and recommendations thereon; and (c) adopt and sign the final version of the AWP&B in the form approved by the Association not later than December 31 of such Fiscal Year. E. Training For the purposes of the training to be provided under Parts I.A. 1, I.A.2, 1.A.3, 1.13 and 2 of the Project and to be delivered through study tours, workshops and conferences, EDG shall: (c) furnish to the Association for its approval, not later than November 30 of each year, a training program including an explanation of how such training is consistent and conducive to the objectives of the Project and whether it offers the best price/quality ratio, as well as the schedule for its implementation; select the trainees in accordance with a transparent process and criteria satisfactory to the Association; and furnish to the Association a report of such scope and detail as the Association shall reasonably request, on the results of each training and the benefits to be derived therefrom. F. Commercial Terms for Future Energy Exchange EDG shall, not later than three (3) months after the Effective Date, sign with EDM a term sheet, upon conditions deemed satisfactory to the Association, describing broadly the commercial terms of the energy exchange between the two utilities, including a commitment on a range of quantity and price of energy, which shall govern the negotiation of a future power purchase agreement between EDG and EDM. G. Complaint Handling Mechanism EDG shall, not later than three (3) months after the Effective Date establish, and thereafter maintain and operate, a functional complaint handling mechanism for the Project, with adequate staffing and processes for registering complaints and acceptable to the Association, thereby ensuring the ongoing improvement on service delivery under the Project.

-7- H. Accounting Systems and Auditing EDG shall: not later than two (2) months after the Effective Date: (i) update its fiduciary procedures manual; and (ii) customize its existing accounting software version to make it suitable for the Project and reflect the Project specificities, thereby allowing the Recipient to comply with its obligations under this Agreement; and not later than five (5) months after the Effective Date, recruit an external auditor under terms of reference and with qualifications and experience satisfactory to the Association. Section II. Project Monitoring, Reporting and Evaluation A. Project Reports 1. EDG shall monitor and evaluate the progress of Parts 1.A. 1, 1.A.2, 1.A.3, 1.B and 2 the Project and prepare Project Reports for Parts I.A. 1, I.A.2, I.A.3, 1.B and 2 of the Project in accordance with the provisions of Section 5.08 of the General Conditions and on the basis of the Monitoring and Evaluation Indicators. Each such Project Report shall cover the period of one calendar quarter, and shall be furnished to the Recipient and the Association not later than forty-five (45) days after the end of each calendar quarter, covering the calendar quarter. 2. EDG shall provide to the Recipient and the Association not later than six (6) months after the Closing Date, the report referred to in Section 5.08(c) of the General Conditions. B. Mid-Term Review EDG shall: (c) maintain policies and procedures adequate to enable it to monitor and evaluate on an ongoing basis, in accordance with the Monitoring and Evaluation Indicators, the carrying out of Parts 1.A.1, 1.A.2, 1.A.3, 1.B and 2 of the Project and the achievement of the objectives thereof; prepare, under terms of reference satisfactory to the Association, and furnish to the Association, on or about April 30, 2022, a report integrating the results of the monitoring and evaluation activities and setting out the measures recommended to ensure the efficient carrying out of Parts 1.A. 1, 1.A.2, I.A.3, 1.B and 2 of the Project and the achievement of the objectives thereof during the period following such date; and review with the Association, on or about June 30, 2022, or such later date as the Association shall request, the report referred to in the preceding paragraph, and, thereafter, take all measures required to ensure the efficient completion of Parts 1.A.1, 1.A.2, 1.A.3, 1.B and 2 of the Project

-8- and the achievement of the objectives thereof, based on the conclusions and recommendations of the said report and the Association's views on the matter.