Logan River Water Supply Scheme

Similar documents
Cedar Pocket Water Supply Scheme

Mary Valley Water Supply Scheme

Central Lockyer Valley Water Supply Scheme

Central Lockyer Valley Water Supply Scheme

Lower Lockyer Valley Water Supply Scheme

Warrill Valley Water Supply Scheme. Annual Network Service Plan

Logan River Water Supply Scheme

Mary Valley Water Supply Scheme. Network Service Plan

Central Brisbane River Water Supply Scheme

Bowen Broken Rivers Bulk Water Service Contract

Proserpine River Bulk Water Service Contract

Burdekin-Haughton Water supply Scheme Submission Sunwater irrigation price review Volumes 1&2.

I appreciate the Authority's continued involvement in ensuring rural irrigation prices have effective regulatory oversight.

Background paper QCA review of irrigation prices. Expenditure update Changed regulatory period

Referral Notice for the Review of South East Queensland Bulk Water Prices

Final Report. Seqwater Bulk Water Price Review

Ref CTS 06610/11 Minister for Energy and Water Utilities

QCA review of irrigation prices Renewals annuity Background Paper

Review of irrigation prices

QCA Pricing Practices Recommendations April 2014 Update on SunWater Implementation Plan

Lower Lockyer Valley Water Supply Scheme

Department of Energy and Water Supply

2015 Price Monitoring Investigation. Submission to the Queensland Competition Authority APPENDICES Volume One

Background paper. Cost forecasting assumptions

SEQWATER PORTFOLIO RISK ASSESSMENT AND MANAGEMENT

Submission to the Queensland Competition Authority (QCA) Gladstone Area Water Board 2015 Price Monitoring Investigation

DELIVERING WATER FOR LIFE

ANNUAL REPORT. Transformation in action

Seqwater Bulk Water Prices 2015 to 2018

WATER BALANCE SHEET ACTUAL AND ASSUMPTION DATA

SUBMISSION QUEENSLAND COMPETITION AUTHORITY ASSESSMENT OF PRICING MATTERS FOR BURDEKIN HAUGHTON WATER SUPPLY SCHEME

vision service success

Operational Plan SUPPLY

achieving results in the public sector Kāpiti Coast District Council Financial Investigation of a Kāpiti Coast Unitary April 2013

HORIZON ENERGY DISTRIBUTION LIMITED

Final Report Inquiry on Harvey Water Bulk Water Pricing

Consultation paper. Review of Guaranteed Service Levels to apply in Queensland from 1 July 2020

Financial Accounts & Reports. For the Year Ended 30 June Schedule of Donations

SEQ Interim Price Monitoring

Precinct Acceleration Protocol Funding. Draft guidelines for application of commercial principles

TABLE OF CONTENTS. Notes to the Financial Statements Directors Declaration Independent Auditor s Report CORPORATE GOVERNANCE...

RE:EX Toronto Water CAPITAL BUDGET NOTES CONTENTS CONTACTS CAPITAL BUDGET AND PLAN OVERVIEW. Overview

SEQ Interim Price Monitoring. Guideline for Templates for 2010/11

Area of Service Slides 3-6. Financials : 2009/2010 Financial Year Slides Strategic Objectives 2011/2012 Slides 11-12

SEQ Interim Price Monitoring Information Requirements for 2010/11

Cave Creek and Desert Hills Master Plan. Master Plan Cost Estimate. Cave Creek and Desert Hills, AZ BASIS OF ESTIMATE

RISK ADVISORY AURIZON NETWORK PTY LTD. Cost Review of 2017 Flood Claim Tropical Cyclone Debbie

Forecast Expenditure Summary Operating Costs

6.0 INFRASTRUCTURE MAINTENANCE PROGRAM (IMP)

Richard Pearson, Community Development Director Tim Tucker, City Engineer

RESERVOIR LEGISLATION IN WALES

DATE: September 12, 2017 REPORT NO. PW Chair and Members Committee of the Whole Operations and Administration

Te Anau Basin Water Supply Subcommittee Agenda OPEN

The QCA reviews the Gazetted Tariffs each year and the revised tariffs are applied from 1 July 2014.

This page intentionally left blank

Allocating capital costs of bulk water supply assets. An Issues Paper prepared for the Queensland Competition Authority by PricewaterhouseCoopers

Performance Management. Framework

Seqwater Response to Draft Queensland Competition Authority Report SEQ bulk water price path

Final Report. Burdekin Haughton Water Supply Scheme: Assessment of Certain Pricing Matters relating to the Burdekin River Irrigation Area

SEQ Water Grid Manager Annual Report

Toronto Water Budget BU Recommended Operating Budget Recommended Capital Plan 2017 Recommended Water Rate

McKenzie Surface Water Source Alternatives

9. RELATIONSHIP BETWEEN ISO AND PARTICIPATING TOs. Each Participating TO shall enter into a Transmission Control Agreement with the

SOLICITATION ADDENDUM

Mandatory Explanatory Notes

PRESENTATION BY OPW TO JOINT OIREACHTAS COMMITTEE ON CULTURE, HERITAGE, AND THE GAELTACHT

Irish Water 2019 Revenue Control

Dunblane and Bridge of Allan (Potentially Vulnerable Area 09/03) Local Plan District Local authority Main catchment Forth Stirling Council Allan Water

PORTLAND WATER DISTRICT BOARD OF TRUSTEES. Policy 675 INFRASTRUCTURE SURCHARGE AND CAPITAL RESERVE ACCOUNTS

Transpower capex input methodology review

Girl Guides of Canada, Ontario Council - LPESC Role and Responsibilities

CITY OF PENTICTON UTILITY RATE REVIEW

Attachment B. King County Flood Control Zone District Work Program

Draft Decision on Maximum Allowable Revenue Aurizon Network s 2014 Draft Access Undertaking. 30 September 2014

Your guide to reading your customer tax invoice

Public Disclosure Copy

It is essential that the QCA reality checks its assumptions and calculations prior to making its final Determination.

Information Paper. Proposal for Recovery of Full Retail Contestability Costs for the Mid-West and South-West Gas Distribution Networks

Statement of Regulatory Pricing Principles for the Water Sector

QUARTERLY UPDATE. Realm Resources Ltd (ASX: RRP) ( Realm or the Company ) is pleased to provide an update on activities during the quarter.

FORTISALBERTA INC. MANAGEMENT S DISCUSSION AND ANALYSIS

PUBLIC FACILITIES ELEMENT

Marin County Flood Control & Water Conservation District. Zone No. 3 Advisory Board Meeting

23 May Mr Charles Millsteed Chief Executive Officer Queensland Competition Authority. Dear Mr Millsteed. DBCT Incremental Expansion Study

PR19 Business Plan. Water Resources RCV Allocation Submission January 2018

Third Quarter Report FRESHWATER FISH MARKETING CORPORATION

GOLDFIELDS GAS PIPELINE. Proposed Revised Access Arrangement Information

Natural Hazards Mitigation Plan Kankakee County, Illinois Executive Summary

Decision on the Maximum Reserve Capacity Price proposed by the Independent Market Operator for the 2015/16 Capacity Year

~-~ ~(ij~~) TREASURY CORPORATION. 30 March Mr EJ Hall Chief Executive Queensland Competition Authority GPO Box 2257 Brisbane QLD 4001

EXPLAINED. Your Rates

Stirling (Cornton and Causewayhead) (Potentially Vulnerable Area 09/05) Local Plan District Forth Local authority Clackmannanshire Council, Stirling C

Thurston County, WA Flood Hazard Mitigation Plan Annual Progress Report CRS Activity 510

CEO S PRESENTATION. WestSide 2012 Annual General Meeting 22 November 2012

TRANSMISSION CHARGING STATEMENT

Impacts from the July 8, 2013 Storm Event on the City of Toronto

NCVER AUSTRALIAN VOCATIONAL EDUCATION AND TRAINING STATISTICS. Financial information 2002

Request for Advice on Cost Recovery for Mandated Smart Metering Infrastructure

Appendix 7. Final Report DORC Valuation Calliope Shire Council Water Supply Infrastructure (Davwil Designs and Management Services Pty Ltd)

Draft Strategic Asset Management Plan

Transcription:

Logan River Water Supply Scheme Annual Network Service Plan 2017-18 Published: September 2017

Contents Section Title Page 1. Introduction... 3 2. Scheme Details... 3 2.1 Scheme background and context... 3 2.2 Infrastructure details... 3 2.3 Customers and water entitlements serviced... 4 2.4 Water availability and use... 4 2.4.1 Water availability... 4 2.4.2 Water use... 5 2.5 Water trading... 5 2.6 Irrigation Customer Consultation... 6 2.7 Customer service standards... 6 3. Financial Performance... 7 3.1 Tariffs... 7 3.2 Operating expenditure... 7 3.3 Renewals... 8 3.3.1 Asset Restoration Reserve... 8 3.3.2 Renewals expenditure... 9 3.3.2.1 2016-17 renewals... 9 3.3.2.2 2017-18 forecast renewals... 10 3.3.2.3 Asset management plan... 10 3.3.2.4 Material planning period renewals... 10

1. Introduction This Network Service Plan (NSP) is a key component of Seqwater s consultation with its customers and is intended to provide useful and helpful information. Seqwater invites comments and suggestions on the content of this NSP. All submissions will be published on the Seqwater website along with Seqwater s responses. Customers may provide feedback via email or post at the following addresses: Email: irrigators@seqwater.com.au Post: NSP Comments Seqwater PO Box 16146 City East QLD 4002 2. Scheme Details 2.1 Scheme background and context The Scheme is located in the Logan River Basin and supplies bulk raw water to water allocation holders in the nine zones that comprise the Scheme. The scheme stretches along a 101.4 km length of the Logan River and along 27 km of Burnett Creek. It was designed to supplement natural flows for the fertile alluvial areas along Burnett Creek and the Logan River. The Scheme is regulated under the Logan Basin Resource Operations Plan (ROP) first issued in December 2009. The ROP was amended to include Wyaralong Dam as part of the Scheme in December, 2012. A further amendment in March 2014 included Christmas Creek and Running Creek under the ROP. However, these two creeks, which are not supplemented by Seqwater s infrastructure, do not form part of the Scheme. The water year runs from 1 July to 30 June. The Scheme consists of one tariff group, Logan River. 2.2 Infrastructure details The table below sets out the bulk water assets, owned and operated by Seqwater, that comprise the scheme.

Table 1: Bulk water assets Dams/ Weirs Off-stream storages Other bulk water assets Maroon Dam Wyaralong Dam Cedar Grove Weir Bromelton Weir South Maclean Weir Bromelton Off-Stream Storage Gauging stations Customer water meters 2.3 Customers and water entitlements serviced The following table sets out the distribution of water allocations amongst classes of customers. Table 2: Ownership of water allocations Customer type Number of customers Medium priority volume (ML) High priority volume (ML) Irrigation 131 13,552 - MP Industrial 1 2.5 - HP Industrial 5-936 Seqwater 7-8,920 Totals 145 13,554.5 9,856 Source: Moreton Resource Operations Plan June 2014; Seqwater (2017) 2.4 Water availability and use 2.4.1 Water availability The announced allocation determines the percentage of nominal water allocation volume that is available in each water year. The following table sets out the announced allocations for both medium priority and high priority water allocations for the current year plus the historical position for the previous ten years. Table 3: Announced allocations history Year MP % HP % 2007-08 0-90 0-100 2008-09 95-100 100 2009-10 100 100 2010-11 100 100 2011-12 100 100 2012-13 100 100 Table 3: Announced allocations history (continued)

Year MP % HP % 2013-14 100 100 2014-15 100 100 2015-16 100 100 2016-17 100 100 2017-18 100 100 2.4.2 Water use Figure 1 below shows the actual medium priority water usage per year from 2002-03 to 2016-17. Also shown is the medium priority usage assumption adopted by the Queensland Competition Authority (QCA) for the 2013-17 price path (extended to 2019) which is 10,881ML or 80% of the nominal volume. The current usage assumption has been extrapolated to prior years for comparison purposes only. The previous 2006-11 irrigation price path (extended to 31 December 2013) adopted a usage forecast of 5,421 ML or 40% of the nominal water allocation volumes. Figure 1: Annual Scheme water usage for years ending 30 June 2003 to 30 June 2017 ML 12000 Logan River WSS Annual Water Use 1 July 2002-30 June 2017 10000 8000 6000 4000 2000 0 Jun-03 Jun-04 Jun-05 Jun-06 Jun-07 Jun-08 Jun-09 Jun-10 Jun-11 Jun-12 Jun-13 Jun-14 Jun-15 Jun-16 Jun-17 Year ended Annual Actual Usage Forecast Usage Average Actual Usage 2.5 Water trading Figure 2 sets out the volumes of temporary transfers by year from 1July 2008.

Figure 2: Temporary transfers 2009-17 Medium priority temporary transfers (ML) 567 395 302 317 305 201 127 2 2 2008-09 2009-10 2010-11 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 2.6 Irrigation Customer Consultation Seqwater is committed to customer engagement as required under its Statement of Obligations. Customer engagement includes customer forums and web-based information. On 5 June 2017, Seqwater held a scheme consultation forum for the Logan River WSS. The 2016-17 renewals and the future renewals programs were discussed. The meeting summary has been published on the Logan River WSS page on Seqwater s website. The next customer forum is expected to be held in May/June 2017 unless matters arise that require consultation prior to that date. Seqwater will be holding customer forums at least annually for the purpose of consulting on the NSP and other Scheme issues that may arise from time to time. Attendance at customer forums is open to all irrigation customers of the Scheme and other stakeholders. All customer or stakeholder submissions in relation to the NSP will be published on Seqwater s website along with Seqwater s responses and decisions. 2.7 Customer service standards The service standards are published on the Logan River WSS web page on Seqwater s website. In 2016-17 Seqwater met all of its service targets. The performance report was published on the Logan River WSS page on Seqwater s website.

3. Financial Performance 3.1 Tariffs In June, 2017, Seqwater s responsible Ministers issued the Seqwater Rural Water Pricing Direction Notice (No. 1) 2017 which extends the 2013-17 irrigation water price path by two years to 2019. The Direction Notice was published in the Queensland Government Gazette on 9 June 2017. Table 4: Water prices (Nominal $/ML) Tariff 2017-18 2018-19 Fixed (Part A) 30.02 30.77 Variable (Part B) 11.02 11.29 3.2 Operating expenditure The forecast operating costs set as a target by the QCA for the 2013-17 regulatory period have been extended for the additional two years of the price path and are set out in the tables below. The 2017-18 forecast costs were calculated by applying the QCA s escalation rates to the 2016-17 forecast operating costs. The 2018-19 forecast operating costs were calculated by applying the QCA s escalation rates to the 2017-18 forecast costs. Some base costs have changed since the cost estimates were initially compiled for the QCA review in 2012. In these cases, Seqwater has amended the 2016-17 forecast base costs before applying the QCA s escalation rates. Any adjustments have been explained by way of notes in table 6 below. These costs include both fixed and variable operating costs. Table 5: Forecast operating costs for 2017-19 ($Nominal) Operating cost item 2017-18 2018-19 Direct operations 492,635 509,394 Repairs and maintenance 115,875 120,511 Dam safety Rates 39,629 40,620 Consultation costs 7,920 8,118 Non-direct costs 483,065 496,744 Total operating costs 1,139,124 1,175,387 The following table sets out Seqwater s detailed actual expenditure compared to the QCA s target budget for 2016-17 and the detailed QCA budget for 2017-18. Explanations of material variations are set out below the table.

Table 6: Operating expenditure for 2016-17 and operating budget 2017-18 ($Nominal) Operating cost item QCA Budget 2016-17 2017-16 Actual Extended QCA Budget Direct operating costs Labour 331,492 242,615 (1) 343,426 Electricity 8,043 4,276 8,244 Other 136,903 98,064 (2) 140,966 Repairs and maintenance 111,419 153,406 (3) 115,875 Dam safety 24,643 (4) Rates 62,053 38,662 (5) 39,629 (9) Consultation costs 7,727 (6) 7,920 Total direct operating costs 682,280 537,023 656,060 Non-direct costs (indicative) Operations 282,395 367,296 (7) 291,009 Non-infrastructure 28,306 32,315 (7) 29,015 Insurance 159,066 89,264 (8) 163,043 Total non-direct costs 469,767 488,875 483,067 Total operating costs 1,152,047 1,025,898 1,139,127 ; QCA Final Report, Seqwater Irrigation Price Review 2013-17 (April 2013) Notes: (1) Labour costs were less than budget because less staff time was required to operate the scheme. (2) Costs were less than budget mainly because water quality monitoring costs were much lower than expected. (3) Repairs and maintenance costs were higher than budget because additional costs were incurred to repair damage following ex-tropical cyclone Debbie. (4) The planning work for the dam safety upgrade at Maroon Dam included the elements of the scheduled dam safety inspection and obviated the need for the inspection. (5) The budgeted costs for rates included property associated with Wyaralong Dam which does not form part of the scheme cost base. (6) Consultation costs are included in non-direct operations and are not accounted for separately. (7) Higher corporate and indirect operating costs resulted in a higher indicative allocation of costs to the scheme. (8) Seqwater negotiated lower insurance premiums in 2016-17 resulting in savings in insurance costs for the Scheme. (9) The QCA s forecast rates budget has been reduced by $23,976 to account for rates not associated with the Scheme. 3.3 Renewals 3.3.1 Asset Restoration Reserve The balance of the renewal annuity funds are recorded in the Asset Restoration Reserve (ARR). Seqwater has reported the ARR in Table 7 below for 2016-17.

Table 7: Logan River WSS Asset Restoration Reserve ($Nominal) Asset Restoration Reserve 2016-17 Opening Balance 1 July 2016-1,134,099 (1) Revenue irrigation 41,506 Revenue other 77,484 Expenditure for year -66,834 Interest for year* -71,841 Closing Balance 30 June 2017-1,153,783 * The interest rate is based on the Queensland Competition Authority s recommended weighted average cost of capital (WACC) of 6.2% post-tax nominal. Seqwater has adopted the equivalent pre-tax nominal WACC rate of 6.64% (previously 6.22%). Interest has been applied to the balance at 30 June 2016 and adjustments were applied to prior years. (1) A net adjustment of $219,825 was applied to the published 2015-16 closing balance of -$1,353,924 to account for the flood repairs costs incurred in 2013-14 that were not reimbursed under Seqwater s insurance policies amounting to -$111,192 offset by other adjustments to interest, revenue and expenditure of $331,018. 3.3.2 Renewals expenditure 3.3.2.1 2016-17 renewals The following table sets out the renewals projects that were undertaken in 2016-17. Table 8: Renewals projects for 2016-17 Asset Project scope Budget ($ 000) Customer water meters Replace 10 customer water meters carried over from 2015-16 Actual ($ 000) 20 23 Maroon Dam Public toilet amenity renewal 1 Maroon Dam water treatment plant Replace exposed section of main inlet chamber lid 20 Replace treated water pump no. 2 29 * (1) Install shading for clarifier carried over from 2015-16 11 13 Cedar Grove Weir Install safe access to fishway entrance 29 29 * Expenditure less than $500 Notes: (1) Project commenced in 2016-17 and will be finalised in 2017-18.

3.3.2.2 2017-18 forecast renewals Forecast renewals expenditure for 2017-18 is provided in table 9 below. Table 9: Renewals by project for 2017-18 ($Nominal) Asset Project scope Forecast ($ 000) Customer water meters Replace minimum 10 flow meters 180 Maroon Dam Replace reticulation pipework 84 Maroon Dam water treatment plant Replace treated water pump no. 2 29 3.3.2.3 Asset management plan Seqwater has developed an Asset Portfolio Master Plan (APMP). The APMP is considered to be leading practice within the water industry. All of Seqwater s future capital expenditure is considered within the APMP framework. The long-term renewals program developed for the Scheme s assets by Seqwater s Asset Capability Team using the Asset Lifecycle Management Plan is included in the APMP. 3.3.2.4 Material planning period renewals During the extended price path, Seqwater will adopt a rolling 20 year planning horizon until a new planning time frame is settled for the upcoming price review. Material renewals projects that fall in the rolling renewals planning time frame, which is 2019-39 for this network service plan, are set out below. A material renewal project is defined as one which accounts for 10% or more in present value terms of the total forecast renewals expenditure for the 20 year planning period. The 10% threshold, in present value terms, is $406,586. Table 10: Material renewals projects 2019-39 ($Real) Asset Project scope Year Forecast ($ 000) Maroon Dam Water Treatment Plant Top up filter media 2025-26 611 Complete refurbish of filter media 2035-36 967