SECTION GENERAL CONTRACTOR/CONSTRUCTION MANAGER (GC/CM) AGREEMENT TABLE OF CONTENTS ARTICLE 1 DEFINITIONS... 2

Similar documents
Terre View Research Facility Relocation Washington State University Pullman, WA Project Manual

OREGON STATE UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)

Tri-Cities Academic Building Washington State University Richland, WA Project Manual

Document A133 TM. AGREEMENT made as of the day of in the year Two Thousand and Sixteen. BETWEEN the Owner:

Document A133 TM. AGREEMENT made as of the day of in the year 20 (In words, indicate day, month and year.)

EASTERN OREGON UNIVERSITY CM/GC CONTRACT. (Construction Manager/General Contractor)

Construction Management-at-Risk Agreement

AIA Document A133 TM 2009

CONSTRUCTION MANAGER AGREEMENT BETWEEN THE UNIVERSITY OF ROCHESTER AND. Insert CM Firm. Insert Name of Project. Insert Project Number

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER PRE-CONSTRUCTION AND CONSTRUCTION SERVICES

AIA Document A201 TM 1997

AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND SPAWGLASS CONSTRUCTION CORP., CONSTRUCTION MANAGER-AT-RISK

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER. Pre-Construction and Construction Phase Services

CONSTRUCTION MANAGEMENT-AT-RISK AGREEMENT

Document A133 TM. AGREEMENT made as of the day of in the year 20 (In words, indicate day, month and year.)

AIA Document A133 TM 2009

STANDARD FORM OF CONTRACT FOR CONSTRUCTION MANAGEMENT SERVICES INCLUDING CONSTRUCTION FOR A GUARANTEED MAXIMUM PRICE BETWEEN

Document A General Conditions of the Contract for Construction, Construction Manager as Adviser Edition

General Conditions for Construction GCC201. Contract Type: Document No. for the following PROJECT: (Name and location or address) EXAMPLE

AIA Document A133 TM 2009

MARION COUNTY HEALTH SERVICES BUILDING RENOVATION PUBLIC IMPROVEMENT AGREEMENT

AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN the Owner: (Name, legal status and address)

Document C132 TM. Standard Form of Agreement Between Owner and Construction Manager as Adviser

Document A Standard Abbreviated Form of Agreement Between Owner and Contractor

AIA Document A133 TM 2009

Document C132 TM. Standard Form of Agreement Between Owner and Construction Manager as Adviser

Standard Form of Agreement Between Owner and Contractor for a Residential or Small Commercial Project

AGREEMENT BETWEEN THE BOARD OF REGENTS OF THE TEXAS A&M UNIVERSITY SYSTEM AND J.T. VAUGHN CONSTRUCTION, LLC DESIGN-BUILD CONTRACTOR

AIA Document A201 TM 1997

Document A201 TM 2007 SP

Request For Proposal. For Construction Management Services. For The. Benton County Jail and Sheriff s Office

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER-AT-RISK

Document A SP General Conditions of the Contract for Construction, for use on a Sustainable Project, Construction Manager as Adviser Edition

Document A133 TM. AGREEMENT made effective as of the day of in the year (In words, indicate day, month and year.)

STATE OF VERMONT STANDARD FORM. GENERAL CONDITIONS FOR F P R DESIGN BUILD CONTRACTS (March 2017)

Document A201 TM. General Conditions of the Contract for Construction. (Name and location or address)

STANDARD FORM OF AGREEMENT BETWEEN DESIGN-BUILDER AND GENERAL CONTRACTOR - LUMP SUM

itaia..." Document A

2. Do you have any final geotechnical report for the proposed property? Yes, See attached. More to come.

Request for Fee Proposals (RFFP) Progressive Design-Build Services. New High School

THE CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA, INC. CMAA Document CMAR-1 (2004 Edition)

Standard Form of Agreement between Owner and Construction Manager

SAN DIEGO CONVENTION CENTER CORPORATION

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager At-Risk

BUILDING CONSTRUCTION AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER

Document A Exhibit A Determination of the Cost of the Work

GENERAL CONDITIONS BETWEEN OWNER AND DESIGN-BUILDER

GENERAL CONDITIONS of the CONTRACT FOR CONSTRUCTION for the ARCHDIOCESE OF CHICAGO (2004 Archdiocese Edition)

AIA Document A201 TM 2007

AIA Document A103 TM 2007

Standard Form of Agreement Between Owner and Architect for a Federally Funded or Federally Insured Project

ARTICLE 8: BASIC SERVICES

Document A201/CMa. General Conditions of the Contract for Construction where the Construction Manager is NOT a Constructor

AIA Document A133 TM 2009

AIA Document A201 TM 2007

Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.

Document A201 TM. General Conditions of the Contract for Construction

MASTER AGREEMENT BETWEEN OWNER AND ARCHITECT/ENGINEER Contract No.

Document A201 TM. General Conditions of the Contract for Construction

Educational Use Only S A M P L E S A M P L E

THE BIDDING AND CONTRACT PROVISIONS Document Section General Conditions (Standard Multiple and Single Contract Sets)

OWNER/PROFESSIONAL SERVICES CONSULTANT AGREEMENT PROJECT TITLE UNIVERSITY OF ILLINOIS

Reviewed/Updated: 9/24/2010 1

AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES

CONSULTANT S AGREEMENT

STANDARD FORM OF AGREEMENT BETWEEN DESIGN-BUILDER AND GENERAL CONTRACTOR - COST PLUS FEE WITH AN OPTION FOR A GUARANTEED MAXIMUM PRICE

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

EXHIBIT "A" RESPONSIBILITIES AND SERVICES OF PROGRAM MANAGER 1. BASIC SERVICES A-1 2. GENERAL PROGRAM SERVICES A-6

BUILDING CONSTRUCTION AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER

{Company.Name} {ToContact.DisplayAddress} {Projects.Name}

STATE OF COLORADO OFFICE OF THE STATE ARCHITECT STATE BUILDINGS PROGRAM DESIGN/BUILD LUMP SUM (LS) AGREEMENT (STATE FORM SC-8.

AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES FOR

Standard Form of Agreement Between OWNER AND CONSTRUCTION MANAGER Construction Manager as Owner s Agent

Educational Use Only S A M P L E S A M P L E

Subcontract Agreement

CITY OF EAST POINT BID NO BID TITLE: CONTRACT FOR CONSTRUCTION AND INCORPORATED GENERAL CONDITIONS

Educational Use Only S A M P L E S A M P L E

Educational Use Only S A M P L E S A M P L E

Standard Form of Agreement Between. Owner and Design-Builder Cost Plus Fee with an Option for a Guaranteed Maximum Price

C R D A Capital Region Development Authority

GENERAL CONDITIONS TABLE OF CONTENTS

Standard Form of Agreement Between Design-Builder and Contractor. The Design-Builder has entered into a Design-Build Contract with the Owner dated:

GENERAL CONDITIONS. of the CONTRACT FOR CONSTRUCTION. for the ARCHDIOCESE OF CHICAGO. for SOLE SOURCE CONTRACTS. (2004 Archdiocese Edition)

CONSTRUCTION MANAGEMENT/GENERAL CONTRACTOR AGREEMENT

203(K) STANDARD OWNER/CONTRACTOR AGREEMENT

General Conditions of the Contract for Construction

Document A104 TM. Standard Abbreviated Form of Agreement Between Owner and Contractor

CONSTRUCTION MANAGEMENT AGREEMENT. between WEST VILLAGES IMPROVEMENT DISTRICT. and. for the construction of the

Document A Exhibit A

STANDARD FORM OF AGREEMENT BETWEEN DESIGN CONSULTANT AND DESIGN SUB-CONSULTANT

FIXED PRICE CONSTRUCTION CONTRACT BETWEEN OWNER AND CONTRACTOR

ANNEX A Standard Special Conditions For The Salvation Army

Instructions to Bidders Page 1

WASHTENAW COMMUNITY COLLEGE CONSTRUCTION CONTRACT - GC

Agreement. Preconstruction Services

STANDARD CONSTRUCTION MANAGEMENT CONTRACT BETWEEN THE SCHOOL BOARD OF ORANGE COUNTY, FLORIDA AND FOR CONTRACT NO.

AIA Document A133 TM 2009

GUARANTEED MAXIMUM PRICE AGREEMENT

AGREEMENT BETWEEN OWNER AND CONSTRUCTION MANAGER

LEGAL ADVERTISEMENT CITY OF WINTER GARDEN REQUEST FOR QUALIFICATIONS (RFQ) RFQ #EN DESIGN CRITERIA PROFESSIONAL SERVICES

Transcription:

SECTION 00 50 00 GENERAL CONTRACTOR/CONSTRUCTION MANAGER (GC/CM) AGREEMENT TABLE OF CONTENTS ARTICLE 1 DEFINITIONS... 2 ARTICLE 2 THE CONTRACT DOCUMENTS... 3 ARTICLE 3 WORK OF THIS CONTRACT... 4 ARTICLE 4 RELATIONSHIP OF THE PARTIES... 12 ARTICLE 5 DATE OF COMMENCEMENT, TIME OF COMPLETION, LIQUIDATED DAMAGES... 13 ARTICLE 6 TOTAL CONTRACT COST... 14 ARTICLE 7 SUBCONTRACTING... 23 ARTICLE 8 COMPENSATION... 25 ARTICLE 9 MISCELLANEOUS... 27 RSD 2017 Bond Projects 00 50 00-i December 2016

SECTION 00 50 00 GENERAL CONTRACTOR/CONSTRUCTION MANAGER (GC/CM) AGREEMENT PROJECT: RSD 2017 Bond Projects This AGREEMENT is made and entered into by and between No. 122, a Washington quasi-municipal corporation (Owner), and (Contractor) hereinafter referred to as the Parties. This Agreement will be effective on the last date set forth on the signature page. This Agreement will be the agreed basis of performing, and compensating for, all work identified herein. In consideration of the mutual covenants and agreements of the Parties herein contained, the Contractor agrees to furnish all material, labor, tools, equipment, apparatus, facilities, and other services necessary to perform and complete in an acceptable manner all general contractor and construction management services and the Work called for in the Contract Documents for a total not to exceed Total Contract Cost (TCC) of ($ ). Costs to be paid to Contractor are summarized below: Maximum Allowable Construction Cost (MACC) $ Percent Fee of the MACC ( %) $ Fixed Amount for Specified General Conditions $ Total Contract Cost:$ Preconstruction Services $ Total Contract Cost plus Preconstruction Services:$ This Agreement is entered into pursuant to the provisions of RCW 39.10.200-.210 and RCW 39.10.340-.410. Contractor agrees, as required by RCW 39.10.350, that if the Work cannot be completed for the agreed Maximum Allowable Construction Cost (MACC), excepting increases due to Owner-directed changes, regulatory changes, design errors or omissions, or unforeseen site conditions, as described in Section 6.4.3, any and all additional costs will be the sole responsibility of the Contractor, and Contractor hereby assumes liability for such costs without reimbursement by the Owner. In executing this Agreement, the Parties acknowledge that the scope of the Work and TCC provided herein do not represent the complete scope of Work and cost for the entire Project as described in the RFP and documents, which includes three Components: (1) the new 5-6/7-8 schools complex; (2) expansion of Ridgefield High School; and (3) repurposing the existing View Ridge Middle School into school district offices and community spaces and making minor security upgrades at Union Ridge and South Ridge elementary schools. The MACC stated above and elsewhere herein is for the scope of Work on Component(s), as indicated in Attachment 3 to this Agreement. The Parties agree to negotiate regarding additions to the MACC based on the Drawings and Specifications for the remaining Components, as set forth in Section 6.8. The TCC listed above and elsewhere herein includes the amounts for the Fixed Amount for Specified General Conditions and Preconstruction Services applicable to Component(s). RSD 2017 Bond Projects 00 50 00-Page 1 of 30 December 2016

Upon successful negotiation for additions to the MACC based on the Drawings and Specifications for the remaining Components (i.e, portion(s) of the Work), the Parties will execute an addendum amending the appropriate portions of this Agreement, including, but not limited to, those discussing the MACC and TCC. The Percent Fee for Work on any additional Components will be the same as that stated above and in Section 6.5. ARTICLE 1 DEFINITIONS In addition to the definitions set forth in the General Conditions for GC/CM Projects, the following definitions will apply to this Agreement. 1.1 Architect. Architect or A/E refers to LSW Architects, PC. 1.2 Construction Work. The term Construction Work will mean all Work performed during the Construction Phase of the Project. 1.3 Component. Component means one of the three major portions of the Project: (1) the new 5-6/7-8 schools complex; (2) expansion of Ridgefield High School; and (3) repurposing the existing View Ridge Middle School into school district offices and community spaces and making minor security upgrades at Union Ridge and South Ridge elementary schools 1.4 Contract Documents. The Contract Documents consist of the following: 1.4.1 This General Contractor/Construction Manager Agreement; 1.4.2 Any documents referenced herein or attached to this Agreement, including but not limited, to the following: Attachment 1 ( Matrix of Cost Allocation ) (in the event of a conflict or inconsistency between Attachment 1 and this Agreement, Division 00, and Division 01, then this Agreement, Division 00, and Division 01 will take precedence over Attachment 1); Attachment 2 ( Form of Construction Cost Estimate ); Attachment 3 ( Construction Cost Summary ); Attachment 4 ( List of Contract Documents ); and Attachment 5 ( List of Negotiated Support Services ); and 1.4.3 The following documents are incorporated herein by reference, as if set forth herein in full: (1) General Conditions for GC/CM Projects; (2) any Modifications and Supplemental Conditions to the General Conditions; (3) Drawings and Specifications with all addenda and modifications thereof; (4) Change Orders issued after execution of this Agreement; (4) the RFP document for selection of the GC/CM and the Contractor s Response to Request for Proposals; (4) the Request For Final Proposals for GC/CM Services () issued by the Owner and its addenda and the Contractor s written response to the, including Contractor s Percent Fee bid and Fixed Amount for Specified General Conditions Work; and (5) other documents listed in this Agreement or the General Conditions for GC/CM Projects. RSD 2017 Bond Projects 00 50 00-Page 2 of 30 December 2016

1.5 Construction Management Consultant. The Construction Management Consultant (CM Consultant) is a contractor providing construction management services to the Owner throughout the Project, other than the GC/CM, and acting as Owner s project manager. The CM Consultant will generally act as the point of contact for communication between the Contractor, Architect, and their consultants. The CM Consultant for the Project is R&C Management, LLC. 1.6 General Contractor/Construction Manager. General Contractor/Construction Manager (GC/CM) means a firm with which the Owner has negotiated a Maximum Allowable Construction Cost and selected to provide services during the design phase and to act as general contractor and construction manager during the Construction Phase pursuant to this Agreement. The terms GC/CM and Contractor are used interchangeably in this Contract. The Contractor is. 1.7 Maximum Allowable Construction Cost. The Maximum Allowable Construction Cost (MACC) means the maximum cost of the Work to construct the Project, including a percentage for risk contingency, an amount for Negotiated Support Services, and an amount for approved Change Orders. 1.8 Negotiated Support Services. Negotiated Support Services means services that the GC/CM would normally manage or perform on a construction project including, but not limited to, surveying, hoisting, safety enforcement, provision of toilet facilities, temporary heat, cleanup, and trash removal. Negotiated Support Services are listed in Attachments 1 and 5. 1.9 Owner. Owner refers to No. 122, as represented by the Owner s Representative. 1.10 Percent Fee. Percent Fee means the percentage amount on the MACC to be earned by the GC/CM as overhead and profit and as further defined in Section 6.5 of this GC/CM Agreement. 1.11 Project Team. The Project Team consists of the Construction Manager, the Owner, the CM Consultant, and the Architect, and all consultants and Subcontractors of any tier employed or retained by each of them. 1.12 Total Contract Cost. Total Contract Cost (TCC) means the fixed amount for the detailed Specified General Conditions Work, the negotiated MACC, and the Percent Fee on the negotiated MACC. ARTICLE 2 THE CONTRACT DOCUMENTS 2.1 Contract Documents. The Contract Documents, as defined in Article 1 of this Contract, form the complete agreement between the Parties and are as fully a part of this Agreement as if attached to this Agreement or repeated herein. The Contract Documents represent the entire and integrated agreement between the Parties and supersede prior negotiations, representations, or agreements, either written or oral, including, but not limited to, the Agreement for Preconstruction Services. In the event of any inconsistencies between the component parts of the Contract Documents, the order of precedence of the documents will be as stated in Section 1.2 of the General Conditions for GC/CM Projects. RSD 2017 Bond Projects 00 50 00-Page 3 of 30 December 2016

ARTICLE 3 WORK OF THIS CONTRACT 3.1 General. The Contractor will work collaboratively and proactively with the Owner, Architect, and CM Consultant to proceed with the planning, design, and development of the Work in a manner that supports the Owner s efforts to keep costs within the Owner s budget and overall objectives for the Project. The Contractor will provide Construction Management (CM) and General Contractor (GC) services throughout all phases of the Project. 3.1.1 Components. To expedite the Project, the development of the Project will be composed of various Components, each with its own scope of Work, including design, construction documentation, permitting, construction, and commissioning. To the extent possible, work during the Preconstruction Phase will be synchronized to allow construction cost estimating and coordination reviews to occur simultaneously for each Component. 3.1.2 Construction Cost Estimates. The Contractor will prepare construction cost estimates in the format provided in Attachment 2 ( Form of Construction Cost Estimate ) to this Agreement for each Component at every Phase and for the MACC negotiations, unless otherwise approved by the Owner. 3.1.3 WSSP. The Parties acknowledge and agree that to the extent this Project receives Washington State funds for school construction, design and construction of the Project must meet at least the Washington Sustainable Schools Protocol (WSSP) requirements in accordance with Chapter 39.35D RCW. Contractor will provide all CM and GC services, including, but not limited to, labor and materials, required to construct all Components of the Project such that the Project fully meets all WSSP requirements in effect at the time the Project, or any Component thereof, is completed. Such services will be accounted for in the MACC (or, for Preconstruction Phase services, in any amount agreed to herein for Preconstruction Services), unless otherwise specified. Contractor will fully participate in any and all activities required by state law or regulations or the WSSP to achieve WSSP compliance and approval, including, but not limited to, providing all applications, documentation, and reports (annual or otherwise) requested by Owner or mandated by the WSSP. The Contractor will manage environmental issues and implement and document the Project s WSSP requirements, including but not limited to: (1) outlining Subcontractor requirements for WSSP in the subcontract bid documents; (2) monitoring the submittal process to ensure WSSP compliance; (3) training Subcontractors in WSSP requirements; (4) reviewing design changes during construction for WSSP impacts and informing Owner of said impacts; (5) ensuring installed products are WSSP compliant; and (6) assembling, maintaining, and submitting all records to document WSSP compliance, including but not limited to annual reports. 3.1.4 Other Sustainable Design. In addition, Contractor will assist the Owner and Architect in identifying and implementing sustainable design opportunities that are practicable for the Project. The Architect will track the implemented sustainable design elements for the Project and provide a summary report for the Owner at the conclusion of the Project. RSD 2017 Bond Projects 00 50 00-Page 4 of 30 December 2016

3.1.5 CPARB Reporting. Contractor will promptly provide the Owner any project information required to be submitted by the Contractor in accordance with the provisions of Chapter 39.10 RCW and the requirements of the Capital Projects Advisory Review Board (CPARB) or otherwise requested by the Owner for purposes of receiving approval for the GC/CM alternative public works contracting procedure under Washington State law. Any and all agreements between Contractor and Subcontractors of any tier will contain this provision requiring the Subcontractor to submit project information required by the CPARB or requested by the Owner. 3.2 Contractor s Responsibilities. 3.2.1 Contractor will perform the Preconstruction Services, will be responsible for coordinating the activities of construction during the Construction Phase, will be fully responsible for discharging all of the Contractor s obligations under the Contract Documents, and, during the Preconstruction and Construction Phases, will advise and work with the Owner, Architect, CM Consultant, Owner s other consultants, and Subcontractors to make recommendations for alternate or substitute products and technologies, construction techniques, methods, and practices based on maintainability and durability as well as cost savings, time savings, and/or other related efficiencies. The Owner or its designee will be responsible for coordinating the activities of the Project Team during the Preconstruction Phase. 3.2.2 The Contractor s Preconstruction Phase responsibilities are set forth in Section 3.3. The Contractor s Construction Phase responsibilities are set forth in Section 3.4. The Owner and Contractor may agree, in consultation with the Architect, for the Construction Phase to commence prior to completion of the Preconstruction Phase, in which case, both phases will proceed concurrently. 3.2.3 The Contractor will identify a representative authorized to act on behalf of the Contractor with respect to the Project. Contractor will provide recommendations regarding accelerated or fast-track scheduling, procurement, or phased construction. Contractor will take into consideration occupancy needs, site logistics, utilities, cost reductions, cost information, constructability, provisions for temporary facilities, and procurement- and construction-scheduling issues. 3.3 Work During Design (Preconstruction Phase). 3.3.1 During the Design Development Phase of the Project, the Contractor will actively participate in the Project as a member of the Project Team. Contractor will also cooperate with other Project Team members to provide a preliminary evaluation of the Owner s program, schedule, and construction budget requirements, each in terms of the other. The Contractor will provide the services and will support the key principles and approaches described in Contractor s proposal submitted in response to the RFP/. In doing so, the Contractor will assign to the Project those professional personnel named in its proposal and will meet its commitments made therein. RSD 2017 Bond Projects 00 50 00-Page 5 of 30 December 2016

3.3.2 Prior to execution of this Agreement, the Parties entered into an Agreement for Preconstruction Services. Upon execution of this Agreement, that Agreement for Preconstruction Services will be superseded by the terms and conditions set forth in this Agreement, except that the following provisions from that Agreement for Preconstruction Services are still in effect and are incorporated into this Agreement: Section 6 on prevailing wages and Attachments A and C. In the event the services to be provided under the Agreement for Preconstruction Services, and any amendments thereto, are not fully performed when this Agreement is executed, then such services will be delivered under the terms of this Agreement on a time and materials basis, up to and not more than the lump sum agreed to in the Agreement for Preconstruction Services and any amendments thereto; provided, however, that if the cost of Preconstruction Services exceeds said lump sum, Contractor will be solely responsible for the excess cost. 3.3.3 Coordination. The Contractor will jointly schedule and conduct meetings with the Architect, Owner, and CM consultant on a weekly basis during the Design Development Phase and the Construction Document Phase to discuss such matters as procedures, progress, coordination, and scheduling of the Work. The Contractor will actively and cooperatively advise the Owner and the Architect on proposed site use and improvements, selection of materials, and building systems and equipment. The Contractor will also actively and collaboratively provide recommendations consistent with the Project requirements to the Owner and Architect on constructability; availability of materials and labor; time requirements; phasing and site work planning; sequencing and scheduling for procurement, installation, and construction; traffic planning; factors related to construction quality, local market trends, bidding strategies, maintainability, and durability; and factors related to construction cost including, but not limited to, costs of alternative designs or materials, preliminary budgets, life-cycle data, and value engineering. 3.3.4 Design Review. The Contractor will review the Schematic Design documents, Design Development Documents, Construction Documents, Drawings, Specifications, and other Contract Documents as they are developed and completed. These documents will include those prepared by the Contractor s design-build Subcontractors, if any, and may be developed at different rates and for different Components of the Project. 3.3.4.1 The Contractor will report in writing to the Owner and the Architect any errors, inconsistencies, incomplete information, or other questions or deficiencies that the Contractor has discovered and that need to be resolved for the successful completion of the Work, paying particular attention to coordination issues. 3.3.4.2 Design review activities are to be a cooperative and collaborative effort with the Architect, the Owner, the CM Consultant, and their consultants. 3.3.4.3 The Contractor will recommend changes and alternatives to the Architect, without, however, assuming any of the Architect s design responsibilities, except to the extent the Contractor or a Subcontractor performs designbuild Work. RSD 2017 Bond Projects 00 50 00-Page 6 of 30 December 2016

3.3.4.4 The Contractor is not responsible to ascertain that the Drawings and Specifications prepared by the Architect are in accordance with applicable laws, statutes, ordinances, building codes, rules, and regulations. However, if the Contractor recognizes that portions of the Drawings and Specifications vary from the requirements of applicable laws, statutes, ordinances, building codes, rules, and regulations, the Contractor will promptly notify the Architect, Owner, and CM Consultant in writing. 3.3.5 Constructability. 3.3.5.1 The Contractor will work with the Owner, Architect, and CM Consultant to prepare a constructability plan for the Project to reduce cost, save time, improve quality, reduce risk, and improve the overall process of Project delivery. Key objectives of the constructability program will include creation and maintenance of a well-planned, safe, effective, cooperative, and mutually beneficial work environment for all participants. A primary objective of these efforts will be to assist the Owner to ensure that the final TCC does not exceed the Owner s budget and the Project is completed on time. 3.3.5.2 The Contractor will perform actions designed to minimize adverse effects of labor or material shortages or delays; time requirements for procurement, installation, and construction completion; and factors related to construction cost. As part of this effort, the Contractor will participate in and provide written comments appropriate to the Design Development Phase as a part of formal constructability analysis following completion of the Design Development Documents for each Component and when the Construction Documents are ninety percent (90%) complete for each Component. Contractor will confirm, prior to solicitation of the first subcontract bid package, that a constructability analysis has been performed. 3.3.6 Value Engineering. Contractor will participate in value engineering throughout the Project. At minimum, the Contractor will participate in value engineering the Design Development Documents at fifty percent (50%) of the Design Development Phase and on a continuing basis with the Architect in subsequent phases up to ninety percent (90%) Construction Drawings. At the completion of each of its reviews, the Contractor will provide the Owner and Architect with a formal record of its findings and recommendations. The Architect and the Contractor will brief the Owner and any value engineers and answer their questions to determine the advisability of changes in the Design Development Documents. Value engineering will include selecting building systems, with final selection of systems to occur prior to the start of the Construction Documents Phase. 3.3.7 Contractor will not incur any cost to be reimbursed as part of the cost of the Work prior to the commencement of the Construction Phase except for authorized Preconstruction Services unless the Owner provides prior written authorization for such costs. RSD 2017 Bond Projects 00 50 00-Page 7 of 30 December 2016

3.3.8 Long-Lead Time Procurement. The Contractor will prepare, for the Architect s, Owner s, and CM Consultant s review and the Owner s acceptance, and will update at least monthly, a procurement schedule for items that must be ordered well in advance of construction. The Contractor will expedite and coordinate the ordering and delivery of these items and/or services. The Contractor ordinarily will contract directly for these items and/or services. The Contractor will update the schedule of all long-lead-time items at least monthly. If the Owner so requests in writing, the Contractor will purchase, expedite, and complete the procurement of long-lead-time items to effectuate their delivery by the required dates. The Owner will be responsible for the cost of the Work relating to long-lead-time items it directs the Contractor to purchase, whether or not the Construction Phase commences. The Contractor will promptly notify the Owner of any anticipated delay with respect to long-lead-time items. The Contractor will identify and estimate the value of any items that require off-site storage. The Contractor will also identify proposed locations for storage during the course of the Work acceptable to Owner. These locations will be selected to provide a maximum of protection and minimum of cost and delay associated with delivery to the site. 3.4 Work During Construction (Construction Phase). 3.4.1 General. During the Construction Phase, the Contractor will provide all services required of a general contractor and construction manager to execute the Work. Some details of Contractor s work are provided below, but this list will in no way limit the Contractor s overall duty to provide GC/CM services as needed to complete the Project as described in the Contract Documents. 3.4.2 Meetings and Tours. The Contractor will conduct weekly construction progress meetings and provide all schedules, logs, and other information regarding construction activities to support such meetings. The CM Consultant will record and distribute meetings minutes for the same. The Contractor will also: conduct separate weekly safety and Subcontractor meeting(s) and maintain minutes for same; and attend Project Team core meetings with representatives from the Owner and the A/E on a monthly basis until Final Completion is achieved, or as otherwise specified by Owner. Upon advance notice, the Contractor will conduct site tours for the Owner and other officials as required by any public body or requested by Owner consistent with the terms of the Contract Documents. 3.4.3 Superintendence/Coordination. The Contractor will be responsible for: superintendence; providing ongoing coordination between crafts; job site safety; housekeeping; quality control; settling disputes between Subcontractors; negotiating any Change Orders with the Subcontractors (Owner expects the Contractor to negotiate with Subcontractors but reserves the right to reject any Subcontractor proposal); negotiating Change Orders with the Owner; reviewing, coordinating, and forwarding submittals, substitution requests, and Requests for Information (RFIs) to the Owner s Representative for action; and responding to all correspondence related to the effort required for any procurement activities that arise from a Subcontractor s inability or unwillingness to perform. 3.4.4 Planning and Layout. The Contractor will be responsible for the planning and layout of the Work, and for the coordination of layout work provided by separate RSD 2017 Bond Projects 00 50 00-Page 8 of 30 December 2016

trades for their own work, to ensure that no conflict exists with the work of other trades. 3.4.5 Staffing. The Contractor will provide sufficient and experienced staff, consistent with or in excess of that specified in its response to the RFP. Such staff will include, but not be limited to, project managers, field engineers, superintendents, surveyors, Health and Safety Officers, CQC representatives, testing engineers, scheduling engineers, quality control specialists, cost engineers, data processing personnel, clerical and accounting personnel, and others to ensure that: 3.4.5.1 The Work is performed and coordinated in a timely manner in compliance with the Contract Documents. 3.4.5.2 Change Order proposals are submitted to the Owner within seven (7) calendar days of the receipt by the Contractor of the Subcontractor s proposal; only proposals for changes negotiated between Contractor and Subcontractor are acceptable proposals to the Owner. 3.4.5.3 RFIs are reviewed and forwarded to the Owner s Representative as expeditiously as possible so as to not cause delay to the Project. 3.4.5.4 Submittals are reviewed for completeness and forwarded to the Owner s Representative within five (5) days of receipt. 3.4.5.5 Replies to correspondence from Subcontractor, Owner, and third parties (including, but not limited to, public bodies) are provided within seven (7) calendar days. 3.4.5.6 For a minimum of ninety (90) calendar days after Substantial Completion or until Final Completion is achieved, whichever is later, provide adequate qualified on-site personnel who are authorized to act on behalf of the Contractor to coordinate and ensure that any outstanding work items, punch lists, testing, and commissioning are completed, all at no additional cost to the Owner. 3.4.5.7 All requirements of the Contract Documents are satisfied. 3.4.6 Inspections. Inspections required by the appropriate building officials and regulatory agencies will be provided by the Owner per the Contract Documents. The Contractor will be responsible for ensuring that the Owner s inspectors are given notice and are afforded timely and appropriate access to the Work to make their inspections. 3.4.7 Building Permit Changes. The Contractor will perform all work required to make Building Permit changes and updates. Building Permit changes and updates will be, if approved by Owner, incorporated into the appropriate subcontract package(s) and the Contract Documents by Change Order. 3.4.8 Certificate of Occupancy. The Contractor will obtain a Certificate of Occupancy and the required operating permits necessary for the Owner to take beneficial RSD 2017 Bond Projects 00 50 00-Page 9 of 30 December 2016

occupancy of the Project or any partially completed portion of the Project when notified in writing by the Owner of its desire to so occupy said portion. 3.4.9 Substantial Completion. Substantial Completion, for purposes of Section 6.7 of the General Conditions for GC/CM Projects and Article 5 of this Contract, will include those activities necessary to: (1) obtain a Certificate of Occupancy; and (2) comply with the requirements listed in Section 01 7800, Closeout Submittals, and elsewhere in the Contract Documents. 3.4.10 Schedule. The Contractor will prepare and submit to the Owner, Architect, and CM Consultant a schedule for the Work and submittal schedule in accordance with Section 3.2 of the General Conditions for GC/CM Projects. The Contractor will provide regular monitoring and will update monthly (or sooner in the event of a substantial change) the construction schedule as Work progresses. 3.4.11 Progress Reporting. The Contractor will record the progress of the Project. On a monthly basis, or otherwise as agreed to by the Owner, the Contractor will submit written progress reports to the Owner, Architect, and the CM Consultant showing percentages of completion and other information required by the Owner, broken down by Component as appropriate. The reports will: 3.4.11.1 Include information concerning both the entire Project and each subcontract bid package. 3.4.11.2 Identify variances between scheduled and probable completion dates, and recommend action required to meet scheduled completion dates. 3.4.11.3 Review the schedule for portions of the Project not started or incomplete and, as appropriate, recommend to the Owner alternate procedures or adjustments to meet the scheduled completion dates. 3.4.11.4 Provide summary reports of each schedule update. 3.4.11.5 Document all significant changes in the schedule and any Owner s approval of them and reflect the reasons for them. 3.4.11.6 Record in writing and by photographs the progress of the Project. 3.4.11.7 Identify significant problems in scheduling together with recommended corrective action. 3.4.11.8 Contain a QC log. 3.4.11.9 Document any outstanding RFIs and risks associated with delayed responses. 3.4.11.10 List outstanding submittals and risks associated with delayed responses. 3.4.11.11 Document any outstanding Change Orders and any risks associated with delayed responses. RSD 2017 Bond Projects 00 50 00-Page 10 of 30 December 2016

3.4.11.12 Discuss the status of permits that the Contractor is required to obtain. The Contractor will also keep, and make available to the Owner, Architect, and CM Consultant, with its monthly Application for Payment or more often as requested by the Owner, a daily log containing a record for each day of weather, Subcontractors working on the site, deliveries, Work accomplished, portions of the Work in progress, number of workers on site, identification of equipment on site, problems that might affect progress of the Work, accidents, injuries, and other information required by the Owner. The information on the log does not constitute notice of a potential or actual Claim to the Owner. 3.4.12 Cost Control. The Contractor will develop a system of cost control for the Work, including regular monitoring of actual costs for activities in progress and estimates for uncompleted tasks and proposed changes. The Contractor will identify variances between actual and estimated costs and report the variances to the Owner, Architect, and CM Consultant, and will provide this information in its monthly reports to the Owner, Architect, and CM Consultant, in accordance with Section 3.4.11, above. The Contractor will include a Project status report in a format acceptable to the Owner and listing: (1) all pending and/or approved Change Orders and Construction Change Directives (including amounts); (2) an analysis of the Specified General Conditions and Negotiated Support Services budget with an explanation of substantial variances from previous budgets; (3) projected cash flow of construction costs; (4) an allocation by subcontract bid package and schedule-of-values line item; (5) expenditures to date; (6) estimates to complete; (7) forecast at completion;(8) variances with budget and commitment; and (9) the items for which the Owner has authorized the Contractor to use Contingency, the cost of those approved items, and the balance of funds remaining in the Contingency account. 3.4.13 Review and Inspection. The Contractor will review and inspect the Work of the Subcontractors on a regular basis (at least as often as described in the Contractor s approved quality-management plan) for defects and deficiencies in their Work and for conformance with the Drawings, Specifications, and other Contract Documents, and will stop the Work of Subcontractors if necessary. The Contractor will provide notification at regularly scheduled progress meetings of any significant defects or deficiencies and recommend remedial action. The Contractor will take the lead role in negotiating and resolving any disputes with Subcontractors and obtain the Owner s concurrence or approval of all settlements that may affect the MACC before Change Orders are executed with Subcontractors. 3.4.14 Recordkeeping. The Contractor will maintain, in good order, on a current basis, and as part of Specified General Conditions, a record copy of all subcontracts, purchase orders, Drawings marked to record all changes made during construction, Specifications, addenda, Change Orders, and other modifications; shop drawings; product data; samples; submittals; inspection reports; purchases; materials; equipment; applicable handbooks; maintenance and operating manuals and instructions; other related documents and revisions which arise out of subcontracts or Work. These records will be available to the Owner, and, at completion of the Project, delivered to the Owner. RSD 2017 Bond Projects 00 50 00-Page 11 of 30 December 2016

3.4.15 Apprenticeship. Pursuant to RCW 39.04.320, the Contractor will achieve apprentice participation of at least fifteen percent (15%) of the total construction labor hours, as set forth in Section 10.11 of the General Conditions for GC/CM Projects 3.5 Work During Commissioning. The Owner will hire an independent Commissioning Authority. The Contractor will provide a Test Engineer and all support activities required by Division 01 of the Specifications or as necessary to complete the commissioning process. 4.1 General. ARTICLE 4 RELATIONSHIP OF THE PARTIES 4.1.1 The Contractor accepts the relationship of trust and confidence established by this Agreement and covenants with the Owner to: cooperate with the Project Team throughout every Phase of the Work; utilize the Contractor s best skill, efforts, and judgment in furthering the interests of the Owner; furnish efficient business administration and supervision; make best efforts to furnish at all times an adequate supply of workers and materials; and perform the Work in the best way and most expeditious and economical manner consistent with the interests of the Owner. The Contractor recognizes that the Owner has a separate agreement with the Architect to design the Project and to provide certain construction administration services necessary to ensure that the construction is in accordance with the Contract Documents. The Contractor further recognizes that the Owner has a separate agreement with a consultant to perform additional construction management services throughout all phases of the Project, and that said CM Consultant will coordinate communication between the Owner, the Architect, the Contractor, and any other consultants performing services in furtherance of the Project. The Contractor further recognizes that in order for the Project to be completed on time and within budget, the Contractor, Architect, Owner, and CM Consultant will have to closely cooperate on a regular basis to revise plans, Drawings, Specifications, materials, methods, estimates, schedules, and budgets as necessary to meet the Owner s financial constraints. 4.1.2 The Owner agrees to assist the Contractor to perform the Work in the best way and most expeditious manner by timely furnishing and approving information required by the Contractor and making payments to the Contractor in accordance with the requirements of the Contract Documents. 4.1.3 The Contractor will provide the Owner and Architect access to the Work wherever it is in preparation or progress. 4.2 RORC. Contractor acknowledges that the Owner intends to enter into an agreement with the City of Ridgefield to build sports fields and other amenities adjacent to the site of the 5-6/7-8 schools complex, to be known as the Ridgefield Outdoor Recreation Complex (RORC). Although Contractor is not expected to perform Construction Work on the RORC as part of the Project pursuant to this Agreement, Contractor acknowledges that full coordination and cooperation with the City, its contractor and subcontractors, architect(s), and consultants, and any of their employees and personnel (collectively, the City RSD 2017 Bond Projects 00 50 00-Page 12 of 30 December 2016

Representatives ), is critical to successful completion of the RORC as a complement to the Work of the Project. Therefore, Contractor agrees to fully coordinate and cooperate with the City Representatives as directed by Owner through actions, including, but not limited to, coordinating staging, traffic management, and site cleanup. Any services provided by Contractor in furtherance of the RORC will be included as part of the Negotiated Support Services and compensated as such. ARTICLE 5 DATE OF COMMENCEMENT, TIME OF COMPLETION, LIQUIDATED DAMAGES 5.1 Subject to Funding. If the Owner determines, in its sole discretion, that sufficient funds are not available for the Project or one or more Components thereof, the Owner will have the right to immediately terminate this Agreement for its convenience at any time during the Preconstruction Phase (i.e., before commencement of the Construction Work under this Agreement as authorized in a Notice to Proceed) for the Component(s) at issue. In that event, Owner will compensate the Contractor for the value of the Preconstruction Services it has performed, if any, and the costs already incurred for Construction Work on any other Component, if any. However, the Contractor will not be entitled to any compensation for damages, lost profits, or payment of any other kind. 5.2 Time is of the Essence. It is understood that time is of the essence in performing each phase of the Work on each Component of the Project, including any Milestones identified in the Contract Documents, including, but not limited to, in specification Section 00 11 01, Milestone Schedule. The Contractor will provide the necessary equipment, personnel, and services to commence Work on the date this Agreement is executed (or at such other time as provided for in the Contract Documents), and for the Work to be substantially complete within the time periods set forth in the Contract Documents. 5.3 Date of Commencement. The date of commencement of the Preconstruction Services set forth in Section 3.3 herein will be issuance of the Agreement for Preconstruction Services. The date of commencement of all other Work for each Component, including the Construction Work, will be by a Notice to Proceed letter to the Contractor specifying the Work that is being authorized. Any Work performed prior to issuance of this Agreement or a relevant Notice to Proceed will be at the Contractor s sole risk and expense. 5.4 Substantial Completion. 5.4.1 Owner anticipates issuing a Notice to Proceed regarding the Construction Work for Component 1 on or around. This Notice to Proceed will allow the Contractor to begin site mobilization and then begin construction. All Work delineated for Component 1 in the Contract Documents, not including Preconstruction Services, will be substantially complete no later than, or if the Notice to Proceed is delayed beyond the date listed above, no later than ( ) calendar days after Contractor s receipt of such Notice to Proceed. 5.4.2 Owner anticipates issuing a Notice to Proceed regarding the Construction Work for Component 2 on or around. This Notice to Proceed will allow the Contractor to begin site mobilization and then begin construction. All Work delineated for Component 2 in the Contract Documents, not including Preconstruction Services, will be substantially complete no later than, or if RSD 2017 Bond Projects 00 50 00-Page 13 of 30 December 2016

the Notice to Proceed is delayed beyond the date listed above, no later than ( ) calendar days after Contractor s receipt of such Notice to Proceed. 5.4.3 Owner anticipates issuing a Notice to Proceed regarding the Construction Work for the Component 3 on or around. This Notice to Proceed will allow the Contractor to begin site mobilization and then begin construction. All Work delineated for Component 3 in the Contract Documents, not including Preconstruction Services, will be substantially complete no later than, or if the Notice to Proceed is delayed beyond the date listed above, no later than ( ) calendar days after Contractor s receipt of such Notice to Proceed. 5.5 Substantial Completion Liquidated Damages. For failure to achieve Substantial Completion for a given Component by the time specified for the Work as required by Section 5.4, Contractor will pay Owner liquidated damages as specified in Section 3.7 of the General Conditions for GC/CM Projects for each and every calendar day from the date when Substantial Completion for that Component was due under Section 5.4 to the date Substantial Completion for that Component is effectively achieved. ARTICLE 6 TOTAL CONTRACT COST 6.1 General. The TCC has been mutually negotiated and agreed to by the Parties. The Contractor agrees that the Project is adequately defined and that Construction Documents are at least ninety percent (90%) complete for those Components of the Project included in the MACC at the time of execution of this Agreement. Further, the Contractor has determined that the Project is sufficiently clear and understandable for the Contractor to agree to the TCC set forth herein. The TCC is defined in Article 1 herein. 6.1.1 This Contract is entered into pursuant to the provisions of RCW 39.10.210 and 39.10.340 through 39.10.410. Contractor agrees, as required by RCW 39.10.350, that if the Work cannot be completed for the agreed MACC, any additional costs, except as provided below, will be the responsibility of the Contractor and Contractor hereby assumes liability for such costs without reimbursement by the Owner. Owner agrees that cost increases due to Owner-directed changes, regulatory changes, design errors or omissions, and unforeseen site conditions are the Owner s responsibility, as provided in Section 6.4.3. 6.1.2 To the extent that the Drawings and Specifications are anticipated to require further development by the Architect, the Contractor will provide in the TCC for such further development consistent with the Contract Documents and reasonably inferable therefrom, and will also provide for market conditions at the time of bidding and possible estimating inaccuracies. Such further development does not include such things as change in scope, systems, kinds and quality of materials, finishes, or equipment, all of which, if required, will be incorporated by Change Order. A change in the Work will not be warranted if the Work in question was reasonably inferable from or contemplated by, or a prudent contractor should have realized that the Work was necessary and appropriate under, the Contract Documents. 6.2 Determination. The TCC was determined through a negotiation of the MACC conducted prior to execution of this Agreement. The MACC negotiations are separate from and not RSD 2017 Bond Projects 00 50 00-Page 14 of 30 December 2016

part of the services under the Agreement for Preconstruction Services. The Contractor will not be reimbursed for MACC negotiations work. 6.3 Preconstruction Services. Prior to execution of this Agreement, Preconstruction Services were provided pursuant to an Agreement for Preconstruction Services. Upon execution of this Agreement, this Agreement replaces and supersedes said Agreement and all work will be performed in accordance with this Agreement. Total compensation for Preconstruction Services, excluding Washington State sales tax, is identified on the first page of this Agreement, where said amount includes Preconstruction Services performed both under the Agreement for Preconstruction Services and this Agreement. The cost for this Preconstruction Services work is not included in the TCC. Any amount that exceeds the total compensation agreed to for Preconstruction Services will be at the Contractor s sole cost and expense unless there are scope changes in the Preconstruction Services authorized by Change Order or amendment of the Contract Documents. 6.4 Maximum Allowable Construction Cost (MACC). 6.4.1 Calculation. The MACC is the amount, mutually agreed to between the Owner and Contractor, that is required to complete all Work as described in the Contract Documents. The MACC will include all Subcontractor scope of work by bid package consistent with the Subcontract Plan, as discussed in Section 6.6, including Work the Construction Manager will self-perform through the Subcontractor bidding process, except the Specified General Conditions Work. The MACC will include funds for all costs through the life of the Project, except those required for: 6.4.1.1 Preconstruction Services work, whether under the Agreement for Preconstruction Services or this Agreement. 6.4.1.2 Percent Fee. 6.4.1.3 Fixed Amount of Specified General Conditions Work. 6.4.1.4 Owner-directed changes. 6.4.1.5 Other changes due to: (1) Design errors or omissions; (2) Unforeseen physical conditions; and (3) Regulatory changes at variance with the Contract Documents. 6.4.1.6 Washington State sales tax. 6.4.2 Upon completion of the buyout of subcontract bid packages, the Contractor will ascertain whether any scope changes beyond those specified in Section 6.1.2 have occurred in the subcontract bidding documents as a result of completion of the Construction Documents to the one-hundred percent (100%) level. In the event that any such scope changes were required for the Project and approved by both RSD 2017 Bond Projects 00 50 00-Page 15 of 30 December 2016

the Contractor and the Owner, any balance in the MACC may be accessed. Any amounts remaining in the MACC when all the subcontract bid packages have been awarded will be added to the Owner s Contingency. 6.4.3 The Parties agree that when the MACC was set, the Contractor had participated in and was aware of the existing conditions and proposed design for the Project. It is further intended that the MACC will include all elements necessary to complete the Work in accordance with the Contract Documents, and that Change Orders adjusting the MACC (and thus the Percent Fee on the MACC) will therefore not be necessary except in limited circumstances as set forth below. Accordingly, the MACC will be adjusted principally for the following events: 6.4.3.1 Scope Changes. Owner revisions on scope items previously approved by the Owner and incorporated in the pricing of the MACC. 6.4.3.2 Design Errors or Omissions. Generally, errors or omissions in the Drawings or Specifications that could not reasonably have been anticipated or discovered by the Contractor before the MACC was established. However, design errors and omissions do not include, for example: (1) failure to coordinate between trades; (2) requirements of the Specifications that are not specifically shown in Drawings; (3) requirements of the Drawings that are not specifically described in the Specifications; or (4) design changes made at the request of the Contractor in order to facilitate the constructability of the Project. The failure of the Architect to specify every detail in the Construction Documents does not eliminate the requirement for the Contractor to provide at least a standard commercially available detail that can serve the basic functions of the design. 6.4.3.3 Unforeseen Physical Conditions. Such conditions are as described in Section 5.10 of the General Conditions for GC/CM Projects. 6.4.3.4 Regulatory Agency Changes. Costs incurred as a result of changes in regulatory requirements, but only where such requirements change after agreement on the MACC. This will not include costs incurred as a result of inspections or other enforcement that are based upon preexisting requirements of the building permit(s). This provision includes changes required by the inspector of a governmental authority having jurisdiction beyond those contained in regulations or previously communicated. 6.4.4 Examples of events for which the MACC will not be adjusted include, but are not limited to: 6.4.4.1 Subcontractor gaps. Gaps in scope coverage between Subcontractors, including self-performed Work, that occur after the MACC is negotiated. 6.4.4.2 Scope gaps. An item indicated in the Drawings or Specifications that was not picked up in the MACC. RSD 2017 Bond Projects 00 50 00-Page 16 of 30 December 2016

6.4.4.3 Ambiguities in the Construction Documents that the Contractor knew of or that a reasonable contractor would have identified and raised with the Owner prior to establishing the MACC. 6.4.4.4 Interdisciplinary Coordination. Coordination inconsistencies and errors between design disciplines that the Contractor knew of, caused or contributed to, or reasonably should have known of. 6.4.4.5 Subcontractor Failure. A Subcontractor fails to perform or goes bankrupt. 6.4.5 In accordance with RCW 39.10.350, if Construction Work is completed for less than the MACC, any savings will accrue to the Owner. If the Construction Work is completed for more than the MACC, excepting increases due to Owner-directed changes, regulatory changes, design errors or omissions, or unforeseen site conditions, the additional cost is the responsibility of the Contractor. 6.4.6 Pursuant to RCW 39.10.370, the Owner may authorize the Contractor to proceed with bidding and award of bid packages and construction before receipt of complete Project plans and specifications. Any contracts so awarded by Contractor will be incorporated into the negotiated MACC. 6.4.7 Contractor Responsibility: The Contractor will be responsible for: (1) all costs related to Subcontractor claims or charges that result from mistakes or omissions in the subcontract buyout; (2) coordination errors and coordination omissions related to the Coordinated Shop Drawings work of specification Section 01 6000, Product Requirements; (3) interference between Subcontractor(s) and the GC/CM; (4) interference between Subcontractors; (5) the Contractor s failure to coordinate the Work it self-performs with Work of other Subcontractors; and (6) all costs related to damage or loss of the Work, materials, or equipment, except damage or loss caused by the sole acts or omissions of the Owner. 6.4.8 Construction Cost Summary: As part of the MACC negotiations, a complete construction cost summary will be provided by the Contractor at execution of this Agreement and at execution of any amendment to the Contract Documents that modifies the MACC. The construction cost summary will be in the format provided in Attachment 3, herein, and will cover any applicable Component(s) for which Work will be performed under that MACC. 6.4.9 Risk Contingency Account: A Risk Contingency Account has been established in the amount of three percent (3%) of the Total for subcontract costs as identified in Attachment 3 ( Construction Cost Summary ). The Risk Contingency Account is included in the MACC. The Contractor may utilize the Risk Contingency Account established herein to pay for items for which it is responsible, as defined in Section 6.4.7 herein, provided Contractor may only utilize the Risk Contingency Account to cover costs related to damage or loss to the Work, materials, or equipment when: (1) the Risk Contingency Account has not already been expended; (2) the loss occurs prior to Substantial Completion; (3) it cannot be determined which Subcontractor or Contractor may have caused the damage or loss; and (4) the Owner agrees to waive the provisions of Paragraph 5.8(F) of the General Conditions and authorizes the use of the Risk Contingency Account for RSD 2017 Bond Projects 00 50 00-Page 17 of 30 December 2016