Perspective on Financing Wind Energy Projects. June 16, 2016

Similar documents
Rating Methodology for Wind Power Producers

RATING METHODOLOGY June Rating Methodology for Solar Power Producers. ICRA Rating Feature. Overview

Wind Project Financing. Targets, Barriers & Challenges, Elements of Financing, Recommendations for Financing

F. No. 53/15/2016 -WE Ministry of New & Renewable Energy. Evaluation of Generation Based Incentives Scheme for Wind Power Projects

Green Day Ahead Market (Petition no. 187/MP/2016) CERC Hearing I December 1, 2016

M.P. Electricity Regulatory Commission Bhopal

REC Market. Business Development March 14

Case No. 85 of Coram. Shri Azeez M. Khan, Member Shri Deepak Lad, Member. Maharashtra State Electricity Distribution Co. Ltd.

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI

ORIENT GREEN POWER Leading Diversified Renewable Energy Generator

Suzlon Energy Limited H1 FY November 2017

Agenda. Enel: Introduction Auctions: Enel experience and key factors Case study: India Closing remarks

Compendium of State Government Policies on Renewable Energy Sector in India ARUNACHAL PRADESH

Enabling Low Cost Financing to Renewable Energy in India

ROBUST OPERATIONAL PERFORMANCE

Regional Power Market Challenges and Opportunities from Nepalese perspective

Leading Diversified Renewable Energy Generation Company

Suzlon Energy Limited. Q1 FY16 Earnings Presentation

KErala StatE ElECtriCity regulatory CommiSSion (Renewable Energy) Regulations, 2015.

Suzlon Energy Limited Q1 FY August 2017

HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION, SHIMLA. (Date of Order: )

March 8, Power Exchange India Limited

Tidal financing Lessons from offshore wind

Suzlon Energy Limited. H1 FY16 Earnings Presentation

CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3rd & 4th Floor, Chandralok Building, 36, Janpath, New Delhi : /

June 08, 2017 Ratings

Implementation of Solar Based Projects in MP Dated 20 July, 2012

BIHAR ELECTRICITY REGULATORY COMMISSION PATNA

Competitive bidding set to transform wind power market

Solar development & rooftop solutions BOO/BOOT

TAMIL NADU ELECTRICITY REGULATORY COMMISSION. Tariff Order No 1 of 2010 dated

Consultant report on EBITDA projections prepared by Greenko

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. No. UPERC/Secy/Regulation/ Lucknow : Dated, 17 th August, 2010

We guide companies leading the electricity transformation

PPAs and Tariff Design

JSW Energy Limited Investor Presentation May 2015

Leading Diversified Renewable Energy Generation Company

INOX WIND LIMITED QUARTERLY INVESTOR UPDATE Q4 & FY16

GOVERNMENT OF MADHYA PRADESH

Result Presentation Q1 FY11 13th August 2010

Draft MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION

Raising Equity for large biomass to power projects

EXTRA ORDINARY 13 SHRAVANA (S) BIHAR ELECTRICITY REGULATORY COMMISSION

The Role of Commercial Banks and Private Sector in NAMA Design and Implementation. Rodrigo Violic Head of Project Finance, Banco BICE

GOVERNMENT OF KERALA

Second Quarter 2018 Ended September 30, 2017 Earnings Presentation

Chhattisgarh State Electricity Regulatory Commission

Uttar Pradesh Electricity Regulatory Commission

9M FY16 Results. Leading Diversified Renewable Energy Generation Company

Morocco s experience in financing solar projects

Meghalaya State Electricity Regulatory Commission

PORTFOLIO OPTIMIZATION FOR OPEN ACCESS CONSUMERS/DISCOMS

Reaching India s Renewable Energy Targets: The Role of Institutional Investors

Anti-dumping duty on PV cells and modules November 2017

SunEdison s Comments on NERSA REFIT 2011 Consultation Paper

Cross Border Electricity Trade

Comments on proposed amendments in Electricity Rules (with respect to Captive Power Plants) issued by Ministry of Power on 22 nd May 2018

Regional Liquidity Support Facility Mitigating risks for private investments in Renewable Energy in Sub-Sahara Africa.

The Potential of Institutional Investors to Help Meet India s Renewable Energy Targets

THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY

Minutes of Pre-bid meeting held on 29th June 2017 at GETRI, Vadodara with prospective bidders for Solar and Wind power tenders floated by GUVNL.

Criteria for rating wind power projects

Back stop of performance guarantees in solar and storage

INVESTMENT OPPORTUNITIES in Central Asia Power Sector

Developing the Power Sector through Private Investment in Mongolia. Edgar Saravia Program Manager

BEFORE THE KARNATAKA ELECTRICITY REGULATORY COMMISSION, BENGALURU. Dated 16 th, May,2018

Leading Renewable Energy Generation Company

INDEPENDENT POWER PRODUCERS

FINANCIAL ANALYSIS: PROJECT 1

SJVN Q3 and 9M FY 2016 Results Conference Call. February 4, 2016

Financing Offshore wind farms. Financing offshore wind farms: How banks view risks and what they can do

NHPC Limited. March 29, 2018

@5}; i i,, DeeffiflE anga Comp ny Secretary. 07thAugust, 2018

1.1 These regulations shall extend to whole of the State of Punjab.

Fourth Quarter & Full Year Ended March 31, 2018 Earnings Presentation

Electricity Market. July 15.

Ratings. August 2, Synopsis

EPC CONTRACTS FOR WIND ENERGY PROJECTS - SOUTH AFRICAN RE IPP PROGRAMME - LESSONS LEARNED FROM PHASES 1 AND 2 (OCTOBER 2012)

Certified Expert in Climate & Renewable Energy Finance. Module 7: Renewable Energy Finance and the Role of Project Finance

Petronet LNG Limited A Case Study. Mohit Saraf Senior Partner Luthra & Luthra Law Offices 1

RENEWABLE ENERGY PROJECT FINANCING

INOX WIND LIMITED Q2FY18 INVESTOR UPDATE

Rakesh Jha. Role of Credit Risk Guarantee Facility in Result Based Incentive model for Distributed Generation Projects

GROWING OUR INDUSTRY-LEADING POSITION

INTERNATIONAL CONFERENCE ON HYDRO POWER FOR SUSTAINABLE DEVELOPMENT FEB , 2015 DEHRADUN. Small Hydro Power Presentation by Arun Sharma President

Sustainable Energy Handbook

PTC India Financial Services Limited. July 2011

Nigeria Power Series - Part 2: Unlocking Financing for Developing Independent Power Projects in Nigeria

IPP s Project Risk Classification

Project Finance and Debt Equity Solar Thermal Projects

IN THE JHARKHAND STATE ELECTRICITY REGULATORY COMMISSION AT RANCHI. Case No. 12 of 2018, 13 of 2018, 14 of 2018 & 15 of 2018

JSW Energy Limited. Q2 FY 2016 Results Presentation October 28, 2015

FINANCIAL ANALYSIS A. Introduction

IL&FS Energy Development Company Limited September 25, Rating 9. CARE BB- [Double B Minus] (credit watch under negative implications)

REC Genesis: Separating green attribute from electricity

Electricity trading and risk management in liberalised market

POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT. Energy Department Government of Bihar

Global Project Finance Alert

The policy and regulatory aspects of a bankable solar power project. Uzbekistan Energy Forum, London 18 April 2018 Louis Skyner Partner

NIGERIAN POWER SECTOR REFORMS AND PRIVATISATION. By Bolanle Onagoruwa Director General, Bureau of Public Enterprises

Transcription:

Perspective on Financing Wind Energy Projects June 16, 2016

Agenda 2 1 Risk Matrix 3 Context Setting Way Forward KEY SEGMENTS IN THIS PRESENTATION

3

Indian Energy Sector Landscape Bank Lending Sector wise (Nov 2015) Other 74.5% Steel & Mining, 5.8% Infrastructure 15.0% Textiles 3.4% Power Projects - Capacity Mix (Mar 2016) Thermal 210.67GW Nuclear 5.78 GW Hydro 42.78 GW Renewable 42.73 GW 58% Energy 21% Transport 10% Telecom 11% Other 26.73 GW Wind 6.76 GW Solar 4.27 GW SHP 4.83 GW Biomass Lending to Infrastructure accounts for the single largest sectoral exposure for Banks with the energy sector on stand alone basis contributing to ~60% Installed capacity of Renewable Energy Projects ~14% of total installed capacity in Power sector Share of capacity addition under Renewable Energy is ~28% of total power projects capacity addition in FY16 India added 6,937 MW of grid-connected wind and solar energy during FY2015 16. This is one and a half times more than the target of 4,460 MW set at the start of the financial year by MNRE

Global Wind Energy Sector Evolution Global - Installed Wind Capacity (GW) 121 94 74 17 24 31 39 48 59 159 198 238 283 319 370 432 11 GW 14 GW 23GW 26 GW 45 GW 74 GW 145 GW Canada UK Spain India Germany US China 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 Wind as % of Total Energy Generation (2014) Declining Cost of Energy 2015 3% 7% 34% 17% 6% 2% 3% 2% T E C H N O L O G Y 1 V100(1800W) G97(2000W) GE116(2300W) S97(2100W) E 53 (800W) G58 (850W) WWD 60 (1000W) S52 (650W) TIME 2 3 Rotor Dia Hub Height V82(1650W) GE 82.5(1500W) V77(1500W) S82 (1500W)

Indian Wind Energy Sector Evolution Path WIND CAPACITY GROWTH - INDIA 2011 2012 14,155 MW 17,352 MW L&T INFRA FINANCE POWER PROJECTS MIX 2013 19,051 MW 12% 26% 62% 2014 21,177 MW 15% 26% 59% 2015 23,444 MW 36% 24% 40% 2016 26,743 MW 49% 32% 19% Wind Other Renewable Thermal Tax incentive focussed developers. Primarily balance sheet funding. Serious IPP players. Non-recourse project financing. 2003-2008 2009 2010 2011 2012 2013 2016 2017 Accelerated Depreciation Benefits Introduction of Generation Based Incentive Introduction of REC Mechanism Accelerated Depreciation and GBI withdrawn GBI benefit reintroduced AD reduced to 40% after reintroducing in 2014

Deal Origination Filter Technical Framework Filter Financial Framework Filter Sanction

Risk Perception Wind Energy Project Sponsor Risk Implementation Risk Technology Risk Operation Risk Market Risk 2010 2015 Financing risk Foreign Exchange Risk High Risk Medium Risk Low Risk

Risk Matrix Promoter Risk Assessment Sponsor Risk Relatively less dependent on promoter strength considering the nature of non-recourse funding and sustainability of project on its cash flows Construction Phase Dealing with promoters with prior experience in similar sector Short construction period 100% Equity upfront unless backed by strong promoter Fixed price EPC Cost overrun if any is primarily due to Interest during construction (IDC). However low gestation period, financing structure, contract LDs create buffer for IDC Operation Phase Long term comprehensive O&M contract with OEM/EPC Nature of O&M amenable to management using contractual/ professional assistance Proper project appraisal is critical for right selection of projects 9

Risk Matrix Implementation Risk Assessment Low degree of intricacy & modularity of implementation supports a reasonably high probability of on-time/on-budget completion. Construction Risk Simple Construction Turnkey solution offered by OEM players/epc players 100% land acquisition as Pre Disbursement Condition Low-complexity civil work & low dependence on labour Modularity allowing for activities to be carried out in parallel than in sequence allowing flexibility of isolating & fixing errors in one segment of the project before affecting the overall critical path Mitigants inbuilt in Fixed Time Fixed Price EPC contract Events Liquidated Damages Cost Overrun Delays Force Majeure Contingencies Selection of Right OEMs /Module Supplier is essential Insurance 10

Risk Matrix - MRT Framework Ability to Differentiate enables Disciplined Origination Market Risk Assessment Evaluating Business Models Mitigating Counterparty Risk Regulatory Risk Assessment Assessment of PPA execution risk Insights into Regulatory/ Policy framework of states or Centre Technical Risk Assessment Selection of Equipment Supplier Critical examination of technical elements of Project site & Grid 11

Risk Matrix - Market Risk Assessment Fixed price PPA for 25 years Cash flow certainty Hedge against rising cost of thermal Unit for State Discoms With each passing year PPA reneging risk by Discoms for renewable project reduces 7.00 6.00 5.00 4.00 3.00 Yr 1 Yr 2 Yr 3 Yr 4 Yearly tariff per Unit Yr 5 Yr 6 Yr 7 Yr 8 Yr 9 Thermal Tariff overtaking Renewable 4.83 Yr Yr Yr Yr Yr Yr Yr Yr Yr Yr Yr Yr Yr Yr Yr Yr 10111213141516171819202122232425 THERMAL RENEWABLE Counter party Risk Provision of sufficient cushion in terms of working capital and DSRA for projects having PPAs with relatively weaker Discoms Periodic monitoring of Discoms operational and financial health and our indirect exposure Stringent Group Captive Financing Framework Petition by GUVNL to revisit solar tariff under solar PPAs on retrospective basis quashed by APTEL No event of reneging of PPAs by State Discom on account of high cost of procurement (under the PPA) COUNTERPARTY RISK DEFAULT RISK... But... COUNTERPARTY RISK = DELAY RISK 12

Risk Matrix Evaluating Market Risk in Revenue Models REVENUE MODEL STATE DISCOMS PRIVATE PARTIES FEED IN TARIFF + GBI APPC+ REC+GBI GROUP CAPTIVE THIRD PARTY FIT CERC/ SERC guidelines (3.20 to 5.92 Rs / kwh) GBI Rs. 0.50 / kwh APPC Filed by Discoms (2.70 to 3.90 Rs / kwh) GBI Rs. 0.50 / kwh Benchmarked with higher Tariff commercial & industrial consumers (5 to 7 Rs / kwh) Exempted from Cross subsidy surcharge Benchmarked with higher Tariff commercial & industrial consumers (5 to 7 Rs / kwh) Moderate project IRRs Credit worthiness of DISCOMs Fixed revenue profile till the tenor of Power Purchase Agreement with Discoms Low project IRRs Credit worthiness of DISCOMs Illiquid REC market Min requirements on shareholding and off-take Credit Risk of off-takers Subject to Open access approval Subject to Banking & Wheeling charges Credit Risk of off-takers Subject to Open access approval Subject to Cross subsidy charges in addition to wheeling and banking charges - impact net realization

Risk Matrix Group Captive Model Alt. Source of Cheap energy Idle Merchant Capacity Evacuation Constraint Technology Disruption Solar Module Efficiency Solar Capex per MW Insight Timing the Point of Inflection Making the project competitive beyond Point of Inflection Tools/ Strategy Option 1 Option 2 Concessional Open Access charges Continuity of Cross subsidy Continuity of Favourable Regulatory Regime 14

Risk Matrix - Regulatory Risk Assessment Regulatory Risk Measurement Clearances to Project Good/Established track-record for grant of clearances Single window mechanism for granting clearance evolving in several states PPA Tie up PPA signing (Upfront/post COD) for Wind projects is as per state specific policy PPA Execution Risk Assessing RPO Compliance Status Assessing Energy Deficit/Surplus Status Political Will / Track record of OUR APPROACH meeting / exceeding RPO target Financial health of Discoms /Ability for RPO Compliance Current pooled power purchase cost & economic rationale of procuring high cost RE Upcoming fossil fuel based power capacities & likely tariff 15

MP & Rajasthan - In a difficult spot Difference between Wind FIT and APPC Agriculture & Domestic Customers (%) 3.50 Low APPC Raj 62% 3.00 2.50 2.00 1.50 1.00 0.50 0.00-8% -7% -6% -5% -4% -3% -2% -1% 0% TN, 0.13 Kar -6.70% Mah -1.80% Guj, 0.86 Kar, 1.44 AP, 1.43 Power Surplus/ Deficit (%) Guj & TN -0.30% Raj, 2.34 Mah, 2.01 MP, Raj, AP 0% MP, 3.13 MP Kar TN AP Mah Guj TN Kar Raj Guj Mah AP MP 18% 40% 43% 31% 30% 34% 51% 54% 57% 48% 59% 30% 40% 50% 60% 70% RE as a % of Peak Demand 51% 63% 15% 25% 35% 45% 55% 65%

Risk Matrix Insurance as Mitigant ALOP : Does not cover normal delay only insurable perils Stand alone MBD program where maintenance/operation are warranted by third party not allowed Computation of Annual Gross profit /Timelines for loss computation Customer Premise Extension for MLOP and FLOP Availability & Applicability 17

Risk Matrix Operational Risk Assessment Operation Risk Perceived Risks Resource Variability Performance risk- turbines/not functioning properly or technical problem in gear box / inverters Grid curtailment/ Unavailability of electrical lines Mitigants Resource assessment done by Lender s Engineer and conservative debt sizing based on P90 Established track record of stable and predictable operating regime for power plants Comprehensive O&M services (replacement of spare parts) provided by turbine manufacturers in wind sector with guaranteed machine availability (usually 95% - 97%) Black Box Future wake effect O&M reserve for 20 years operational life Economic/Technical Curtailment Selection of Right OEMs is essential 18

Way forward : Sustainable Wind Energy Target 60 GW Structural Reforms for Addressing Discom Health & RPO Enforcement Affordable Energy Storage Technologies Scheduling & Forecasting, TOD tariff Design for Grid Management, Green Transmission Corridor Competitive bidding Route

THANK YOU