SHEFFIELD SIGNS TAURUS DEBT FACILITY AND EPC CONTRACT

Similar documents
SHEFFIELD SUCCESSFULLY COMPLETES INSTITUTIONAL PLACEMENT TO PROGRESS THE THUNDERBIRD MINERAL SANDS PROJECT

ABN Interim Financial Report

ABN Interim Financial Report

A$74 Million Loan Package from NAIF

Thunderbird a World Class Mineral Sands Project Filling the supply gap. Ruidow Zircon and TiO 2 Conference May 2018 Ningbo, China ASX:SFX

Thunderbird The Emerging Force in Mineral Sands. TZMI Presentation November 2017 ASX : SFX

For personal use only

Thunderbird The Emerging Force in Mineral Sands. Investor Presentation Global Roadshow Mines and Money April 2017 ASX : SFX

Thunderbird The Emerging Force in Mineral Sands. Investor, Mines and Money New York May 2017 ASX : SFX

Pre-Feasibility Study Demonstrates Significant Potential of the Riversdale Anthracite Project

For personal use only

MD&A. All dollar amounts contained in this MD&A are expressed in United States dollars, unless otherwise stated.

BUY SHARE PRICE CHART FORECAST OPERATING CASHFLOW COMPANY DATA & RATIOS. A$m - CY20 CY21 CY22 CY23 CY24 CY25

Thunderbird The Emerging Force in Mineral Sands. Mineral Sands Conference Presentation March Perth ASX : SFX

BUILDING A TIER 1 MINERAL SANDS COMPANY. Africa Downunder Conference August 2012 BRUCE GRIFFIN CEO

Glencore Finances Matrix into Copper Production Summary

For personal use only

TUNKILLIA GOLD PROJECT

PRESS RELEASE. Banro Files NI Technical Report on Namoya Project, Democratic Republic of the Congo

JAMBREIRO IRON ORE PROJECT SET TO DELIVER STRONG CASH FLOWS AND RETURNS: PRE-FEASIBILITY STUDY

SHEFFIELD RESOURCES LTD (SFX AU, $0.67)

BALAMA PROJECT UPDATE

Battery Minerals agrees terms of US$30m debt & equity funding package with RCF

MD&A. All dollar amounts contained in this MD&A are expressed in United States dollars, unless otherwise stated.

For personal use only

For personal use only

QUARTERLY ACTIVITIES REPORT September 2017

BUILDING A TIER 1 MINERAL SANDS COMPANY. TZMI Congress November 2012 Bruce Griffin CEO

TAMPIA GOLD PROJECT FEASIBILITY STUDY

For personal use only

WODGINA ORE RESERVE COMMENTARY

Board approves Kwale Phase 2 mine optimisation project to deliver enhanced economics 1

March 2018 Quarterly Report 17 April Summary

SAVANNAH RESOURCES PLC AIM: SAV

AZUMAH MINING LEASES GRANTED

Strong progress on construction at Montepuez

For personal use only. ASX Code: GMM

Strong progress on construction and supply contracts puts Battery Minerals on track for commissioning in November

PILBARA MAINTAINS GROWTH MOMENTUM WITH STRONG CUSTOMER SUPPORT TO UNDERPIN FUNDING PACKAGE FOR STAGE 2 PILGANGOORA EXPANSION

For personal use only

MOUNT GIBSON IRON LIMITED QUARTERLY REPORT FOR THE PERIOD ENDED 31 DECEMBER January 2016

For personal use only

For personal use only

MAHENGE BEST IN CLASS GRAPHITE PROJECT. 121 Mining Investment Cape Town

Positive Pre-Feasibility at Borborema

SARACEN MINERAL HOLDINGS LIMITED QUARTERLY REPORT: DECEMBER Corporate Details: Sustainability

GALAXY RESOURCES LIMITED

June 2018 Quarterly Report

MDL UPDATE ASX: MDL. Investor Presentation September 2017

Quarterly Activities Report For the Three Months Ended 31 March 2018

Half Year Financial Results to 31 December 2017

ALLIED GOLD MINING PLC ALLIED GOLD REPORT FOR QUARTER AND HALF YEAR 30 JUNE

Nominal NPV 10, 2% escalation applied to operating costs and revenues

20% Increase in T3 Feasibility Study Plant Throughput to 3Mtpa

Heron Secures Complete A$240 Million Funding Package for Development of its Woodlawn Zinc-Copper Project 1

For personal use only

Quarterly Activities Report for the period ended 30 September 2018

QUARTERLY ACTIVITY STATEMENT

Aries Project Prefeasibility Study Optimization Report

Aeon Metals Limited. Quarterly Report For the three months ending 30 June ASX Announcement 31 July 2018

PROSPECT ANNOUNCES SIGNIFICANT VALUE UPGRADE OF ARCADIA LITHIUM PROJECT FOLLOWING UPDATED PRE-FEASIBILITY STUDY

QUARTERLY ACTIVITIES REPORT PERIOD ENDING 30 SEPTEMBER 2015

Western Australia Iron Ore Overview. Michael Bailey General Manager, Port Operations

2017 Half Year Results Tom O Leary, Managing Director Doug Warden, Chief Financial Officer and Head of Strategy and Planning.

Kenmare Resources plc Past, present & future. TZMI Congress, Hong Kong 2016

For personal use only

MANAGING DIRECTOR PRESENTATION 30 November 2016

Low capital development cost and high grades maximise free cash flow

ASX Code: THR THOR MINING PLC LETTER TO SHAREHOLDERS. 19 June 2018

For personal use only

2009 AGM SHAREHOLDER QUESTIONS & ANSWERS

Market Release 24 February Executive Summary

Media Announcement (For Immediate Release)

Presentation August ASX Code: TNG

Quarterly Activities Report September 2018

SCOTGOLD RESOURCES LIMITED

Qube delivers another solid financial performance Further progress on Moorebank Project with strong tenant interest

For personal use only

March. Report. Highlights. expected. Full Cash. Wodgina

Quarterly Report for Shareholders Period Ending 31 March 2014

SEPTEMBER QUARTERLY REPORT TUCANO TURNAROUND CONTINUES TO DELIVER

ELGIN MINING PROVIDES STRONG FOURTH QUARTER CASH COSTS AND POSITIVE 2014 OUTLOOK

Cleveland Completes Royalty Note Issue and Gold Refining Pre-Payment Agreement to Grow Gold Production and Cash-Flow in Brazil

H i g h l i g h t s. Metro Mining Limited (ASX:MMI) MoU Signed with SPIC. Bauxite Hills Construction Largely Complete

MDL INVESTOR PRESENTATION

SEPTEMBER 2018 QUARTERLY ACTIVITIES REPORT

6 September 2017 AFRICA DOWN UNDER AMENDED PRESENTATION

NOLANS RARE EARTHS A MAJOR PROJECT FOR THE TERRITORY

For personal use only

MDL UPDATE. Investor Presentation February 2018 ASX: MDL

H Results Presentation

JUNE 18 QUARTERLY PRODUCTION REPORT

LionGold s Bolivia Gold Project delivers a 40% increase in its Mineral Resource estimate to now contain a total of 1.79 million ounces of gold

Managing Director s Review of Operations

Key Highlights. Significant Events Post Quarter End. Outlook

Positioned for Growth. TZMI Congress 2016, Hong Kong 8 th November 2016

Straits Asia Resources Limited

Straits Resources Debt Restructure A New Beginning

WEST AFRICAN SCOPING STUDY DELIVERS HIGH MARGIN, LOW CAPITAL COST STAGE 1 GOLD PROJECT

For personal use only

Transcription:

SHEFFIELD SIGNS TAURUS DEBT FACILITY AND EPC CONTRACT Sheffield Resources Limited ( Sheffield, the Company ) (ASX: SFX) is pleased to announce the signing of two key commercial agreements ( Agreements ) that will substantially advance and de-risk development of the world class Thunderbird Mineral Sands Project ( Thunderbird or the Project ) in northern Western Australia. These Agreements include: A$366m fixed price, lump sum engineering, procurement and construction (EPC) contract with GR Engineering Services Limited (GRES) (ASX: GNG) for the design and construction of the Thunderbird mineral processing plant, supporting infrastructure and associated facilities (EPC Contract); and US$175m (A$240m 1 ) fully underwritten, syndicated facility agreement with Taurus Mining Finance Fund and Taurus Mining Finance Annex Fund (Taurus) for a seven-year term loan (Facility Agreement). The Agreements provide significant certainty of funding, execution and delivery of Thunderbird. Sheffield Managing Director, Bruce McFadzean said: These Agreements are a tremendous result for Sheffield shareholders as they substantially de-risk Thunderbird and put the Company in a strong position to move into construction. We now have a full EPC contract with one of Australia s leading process engineering companies, with extensive experience in Western Australia and in the delivery of mineral sands projects. Additionally, we have executed US$175 million of senior debt financing with Taurus, one of the world s premier mining finance funds. The Taurus Facility Agreement has provided certainty of funding for the development of Thunderbird and now includes the expanded Northern Australia Infrastructure Facility (NAIF) loan facilities. The addition of the Federal Government support through the A$95 million NAIF funding, provides financial assistance to toward the development of key infrastructure including power generation, roads and port facilities associated with Thunderbird. We acknowledge and appreciate the collaborative manner in which both Taurus and NAIF have enabled funding for Thunderbird. The NAIF loan facilities are very competitive, with long dated tenor enabling Sheffield to own strategic infrastructure and significantly reduce our operating costs by a minimum of A$7.5 million per annum over the 42-year life of mine. The NAIF loan facilities comprise a A$30 million Project Development Facility that sits alongside the Taurus facilities and a A$65 million Infrastructure Development Facility. The A$30 million facility (15-year tenor) enables improvements in throughput, material handling and operability of the Thunderbird processing plant. The A$65 million facility (20-year tenor) will allow the ownership of key non-processing infrastructure that will significantly enhance long-term financial metrics via a substantial reduction in operating costs to Sheffield. Thunderbird has now secured A$335 million of loan facilities to enable the Project to proceed, including long tenor infrastructure loans from the Federal Government. Securing the loan facilities, combined with finalisation of the fixed price, lump sum EPC contract, in conjunction with completion of permitting, collectively build on the recent milestones achieved by Sheffield and pave the way for construction of Thunderbird to commence in the new year, following the wet season. As we close in on development of Thunderbird, we will continue to progress all funding options including ongoing discussions with potential strategic partners. Mr McFadzean concluded. 1 Assumes AUD: USD exchange rate of $0.73 : $1.00 2 As set out in Sheffield s announcement on 19 October 2018, current estimate of total development capital expenditure for Stage 1 is approximately A$463m, excludes working capital, corporate overheads, cost overrun provisions and financing fees

Taurus Chief Investment Officer Michael Davies commented, We are delighted to be a part of the development of this important Australian project that will see benefits particularly to the people of the State of Western Australia and the Kimberley communities for decades to come. EPC Contract Under the EPC Contract, GRES will design and construct a 7.5 million tonne per annum (Mtpa) Stage 1 mineral processing plant and supporting infrastructure. The EPC Contract is a fixed price, lump sum arrangement of approximately A$366 million and covers approximately 80% of Thunderbird s estimated total Stage 1 capital cost of A$463 2. The EPC contract provides for the turnkey delivery of the Project s processing infrastructure, including process design engineering, procurement, construction, commissioning and performance testing of the facilities over a construction and commissioning period of approximately two years, with anticipated commencement in Q2 calendar 2019. Engineering and design activities undertaken by GRES throughout 2018 and reviewed by Taurus and its nominated Independent Technical Expert, has enabled Sheffield to assess several design developments focussed on increasing throughput, operational efficiencies and the functionality of the processing plant, substantially de-risking metallurgical performance and overall project execution. Figure 1: Thunderbird Stage 1 Capital Expenditure As at the end of September 2018, approximately 30% of design and engineering work has been completed, representing substantial progress in advance of formal execution of the EPC Contract. The

level of engineering is extremely well advanced for this stage of the Project, allowing plant design to progress beyond plant layout, with structural engineering nearing completion and detailed engineering well underway. Based on the construction and commissioning schedule, first zircon products will be delivered during commissioning in the last quarter of calendar 2020, and first ilmenite products are expected during Q2 of calendar 2021. The EPC contract now includes the following items: Plant area civils and process water Wet concentrator plant Concentrate upgrade plant Zircon processing plant Ilmenite processing plant Low temperature roast plant (ilmenite upgrade) Hot acid leach Site administration complex, stores and process workshops Bore field headworks and high voltage (HV) distribution Internal roads, hardstand and other infrastructure to support the processing operations Operational support during the first six months of ramp-up Figure 2: Wet Concentrator design and layout

The remaining capital and infrastructure, (majority funded via NAIF loan facilities) including management costs comprise: Power station and gas storage Village, road and port Potable water supply Waste water treatment All site clearing and preparation Pre-strip and trial mining Communications network Sheffield management and labour costs Taurus Syndicated Facility Agreement Under the terms of the Facility Agreement, Taurus will arrange and fully underwrite US$175 million of senior loan facilities, which will be used to partially fund the construction of Thunderbird. Execution of the Facility Agreement follows thorough technical, financial and legal due diligence by Taurus and significantly de-risks the delivery of Thunderbird for Sheffield shareholders. The due diligence process was led by Taurus nominated independent technical expert, Metifex Pty Ltd (Metifex), in collaboration with Taurus, Sheffield and GRES. This process has enabled improvements in throughput, material handling and operability of the Thunderbird processing plant and an increase in mineral sands recovery equipment, leading to a more robust and flexible Project. These improvements include: Inclusion of filter belts and direct forward feed of products by conveyor. The BFS assumed the use of drain pad and the forward feed of products by loader; Increase in consumables storage from 5 days to 10 days; Installation of lift bays in dry buildings; Optimised thickener size for tailings material, improving water recovery; Improvements in Wet Concentrator Plant capacity and additional cleaner scavenger spiral bank, reducing circulating load; Installation of additional High Tension Roll and Induced Roll Separators, increasing recovery capacity for Valuable Heavy Minerals in the dry plant. The detailed and extensive technical due diligence has allowed Sheffield to spend 12 months with industry experts Metifex and GRES focusing on optimising the process plant design and functionality to further de-risk the construction execution and commissioning of the project. Importantly, the majority of the additional capital expenditure to optimise and improve the plant has been funded by the NAIF project debt facility (A$30 million) minimising the impact on shareholder equity required. The key terms of the Facility Agreement are summarised in Schedule 1. Sheffield has completed a number of the conditions precedent to drawdown under the Facility Agreement, including those relating to offtake agreements, environmental approval and the granting of the Mining Lease. Sheffield is working closely with Taurus to satisfy the remaining conditions with financial close currently anticipated in early 2019. As a result of the recently announced NAIF investment decision (refer to ASX announcement dated 19 September 2018), Sheffield will not require the previously announced Taurus US$25 million Contingent Instrument Facility. This Facility was solicited for bonding requirements for key third party-owned infrastructure that will now be insourced with owned infrastructure by Sheffield.

ENDS For further information please contact: Bruce McFadzean Managing Director Tel: 08 6555 8777 info@sheffieldresources.com.au Website: www.sheffieldresources.com.au Follow us: @Sheffield_ASX LinkedIn Media: Yvonne Ball Citadel-MAGNUS Tel: +61 8 6160 4900 yball@citadelmagnus.com ADDITIONAL INFORMATION PREVIOUSLY REPORTED INFORMATION The information was extracted from the Company s previous ASX announcements as follows FEDERAL ENVIRONMENTAL APPROVAL GRANTED FOR THUNDERBIRD 28 September 2018 MINING LEASE GRANTED OVER THUNDERBIRD MINERAL SANDS PROJECT 26 September 2018 NAIF APPROVES LOAN FACILITIES TOTALLING A$95M 19 September 2018 STATE MINISTER FOR ENVIRONMENT APPROVES THUNDERBIRD MINERAL SANDS PROJECT 13 August 2018 SHEFFIELD ANNOUNCES EPC PREFERRED CONTRACTOR 19 October 2017 SHEFFIELD MANDATES TAURUS FOR US$200M DEBT FACILITY 18 October 2017 EPA RECOMMENDS APPROVAL OF THUNDERBIRD 9 October 2017 THUNDERBIRD BFS DELIVERS OUTSTANDING RESULTS 24 March 2017 FORWARD LOOKING AND CAUTIONARY STATEMENTS Some statements in this report regarding estimates or future events are forward-looking statements. They involve risk and uncertainties that could cause actual results to differ from estimated results. Forward-looking statements include, but are not limited to, statements concerning the Company s expected production dates, Stage 1 capital expenditure estimates, exploration programme, outlook, construction and commissioning dates, target sizes and mineralised material estimates. They include statements preceded by words such as anticipated, expected, targeting, likely, scheduled, intends, potential, prospective and similar expressions. ABOUT SHEFFIELD RESOURCES Sheffield Resources Limited is focused on developing its 100% owned, world class Thunderbird Mineral Sands Project, located in north-west Western Australia. Sheffield continues to also assess other regional exploration opportunities. THUNDERBIRD MINERAL SANDS Thunderbird is one of the largest and highest-grade mineral sands discoveries in the last 30 years. Sheffield s Bankable Feasibility Study shows Thunderbird is a technically low risk, modest capex project that is positioned to generate strong cash margins from globally significant levels of production over an exceptionally long mine life of 42 years.

Thunderbird will generate a high-quality suite of mineral sands products with specifications suited to market requirements. These products include Premium Zircon suitable for the ceramic sector and LTR Ilmenite which will be one of the highest-grade sulfate feedstocks available globally. Thunderbird is located in one of the world s most attractive mining investment jurisdictions and is well placed to deliver long term, secure supply of high-quality products to a range of potential customers. The Company is targeting initial production in Q4 of 2020. The initial planned production profile is aligned with expected emerging supply gaps in global mineral sands markets. ASX Code: SFX Market Capitalisation: A$184m Issued shares: 230.5m Cash (unaudited, 30 Sep 2018): A$13.7m

SCHEDULE 1: KEY TERMS OF TAURUS FACILITY AGREEMENT Facility Amount Tenor Security Availability Interest Rate Term Loan: US$175 million Tranche A: US$75 million Tranche B: US$100 million Approximately 7 years. The termination date is 30 September 2025, subject to a 6 month extension (if approved by Taurus) Senior secured facility From satisfaction of Conditions Precedent until 3.5 years after signing Tranche A: USD Libor + 4.5%p.a Tranche B: 8.5% p.a. Upfront Fee Commitment fee on undrawn amounts Royalty Conditions Precedent to drawdown Customary for a facility of this nature (50% due upon signing and the balance due on satisfaction of certain conditions precedent to drawdown of the facility) Tranches A and B: Commitment fees on undrawn amounts: 2.0% p.a. Revenue royalty (FOB basis) of: 0.50% (years 1 4, starting on first sale of product from the Project) 0.75% (years 5 22.5) The royalty is documented under a separate royalty deed. Generally customary for a facility of this nature, but include completion of due diligence, approval from the State of Western Australia and entry into documentation for the A$95 million NAIF facilities, execution of other finance and project documents and raising of the required minimum equity Repayment Schedule Tranches A and B both interest only for 3.5 years Tranche A repayable between Year 3.5 and Year 7 Tranche B repayable at end of Year 7 Additional sweep of available cashflow in certain circumstances