CHAPTER I: PRELIMINARY Short title, commencement and interpretation

Similar documents
AGREEMENT FOR SYNCHRONOUS OPERATION OF CAPTIVE POWER PLANTS OF.. WITH JHARKHAND STATE ELECTRICITY BOARD SYSTEM

THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY

Bhopal: Dated 5 th May 2006

Uttar Pradesh Electricity Regulatory Commission

THE JHARKHAND GAZETTE EXTRAORDINARY PUBLISHED BY AUTHORITY

UTTAR PRADESH ELECTRICITY REGULATORY COMMISSION. No. UPERC/Secy/Regulation/ Lucknow : Dated, 17 th August, 2010

GUJARAT ELECTRICITY REGULATORY COMMISSION. Notification No. 13 of 2005

Bhopal Dated : 5th October 2004

Meghalaya State Electricity Regulatory Commission

Draft MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION

GOVERNMENT OF MADHYA PRADESH

Electricity (Net-Metering) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 45 and 46) THE ELECTRICITY (NET-METERING) RULES, 2018

Implementation of Solar Based Projects in MP Dated 20 July, 2012

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION MUMBAI

ELECTRICITY ACT, 2005

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION

New and Renewable Energy Department Vallabh Bhavan, Bhopal

MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI Maharashtra Electricity Regulatory Commission (Fees and Charges) Regulations, 2017

Uttarakhand Electricity Regulatory Commission

Power Purchase Obligation (Compliance by purchase of Renewable Energy/Renewable Energy Certificates) Regulations, 2012 (Regulation No. 1 of 2012).

Draft Consultative Paper on. Captive Generating Plants

STANDARD IMPLEMENTATION AND SERVICE AGREEMENT FOR DEVELOPMENT AND OPERATION OF INTRA-STATE TRANSMISSION SYSTEM

DRAFT (To be signed on Non-judicial stamp paper of Rs.100/-)

GOVERNMENT OF PUNJAB DEPARTMENT OF POWER (Power Reforms Wing) NOTIFICATION The 21 st June, 2010

Expression of Interest. Procurement of Renewable Energy Under Short Term basis. Reliance Industries Limited In Gujarat and Maharashtra

Notified on : 22 January 2010 Bhopal, Dated: 9 th December, 2009

Rate Code: L L-16 SOUTH CAROLINA PUBLIC SERVICE AUTHORITY (SANTEE COOPER) LARGE LIGHT AND POWER SCHEDULE L-16

Uttar Pradesh Electricity Regulatory Commission

1.1 These regulations shall extend to whole of the State of Punjab.

JHARKHAND BIJLI VITRAN NIGAM LIMITED

AGREEMENT FOR NEW TRANSMISSION SERVICE CUSTOMERS WITH AN INDIRECT INTERCONNECTION TO THE BC HYDRO SYSTEM

Rajasthan Electricity Regulatory Commission

BEFORE THE MAHARASHTRA ELECTRICITY REGULATORY COMMISSION, MUMBAI JAIGAD POWERTRANSCO LIMITED (JPTL)

Jammu and Kashmir State Electricity Regulatory Commission (J&K SERC) (Security Deposit) Regulation, 2008.

BRIEF ANALYSIS ON NEW OPEN ACCESS REGULATIONS IN THE STATE OF MAHARASHTRA

KOSCIUSKO REMC AGREEMENT FOR INTERCONNECTION OF DISTRIBUTED GENERATION

Bhopal, Dated:

(Collective Transaction) Procedure for Scheduling

STANDARD TERMS AND CONDITIONS

New and Renewable Energy Department Vallabh Bhavan, Bhopal

SMP-10/2016 M.P. Electricity Regulatory Commission Bhopal

Comments on proposed amendments in Electricity Rules (with respect to Captive Power Plants) issued by Ministry of Power on 22 nd May 2018

RATE 833 RATE FOR ELECTRIC SERVICE INDUSTRIAL POWER SERVICE No. 1 of 12 Sheets

GOVERNMENT OF KERALA

Chhattisgarh State Electricity Regulatory Commission

THE HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA. NOTIFICATION Shimla, the 22 nd November, 2018

CUSC - SECTION 3 USE OF SYSTEM CONTENTS

M.P. Electricity Regulatory Commission Bhopal

Preamble : Policy Frame Work :

NIE Transmission Licence Consolidated Document see notes at the end of the document Northern Ireland Electricity Ltd

ELECTRIC UTILITY RATES

The Brihan Mumbai Electric Supply & Transport Undertaking

BIHAR ELECTRICITY REGULATORY COMMISSION

Procedure for Scheduling

Revised Policy on Collection of Cheques/ Instruments ( )

GUJARAT ELECTRICITY REGULATORY COMMISSION No. ---/---/---/GERC Dated: 13/01/2017. NOTIFICATION No. of 2017

RATE 832 RATE FOR ELECTRIC SERVICE INDUSTRIAL POWER SERVICE

DRAFT LICENCE CONDITIONS

PRELIMINARY. (2) These Regulations shall come into force from the date of their publication in the Official Gazette.

LIMITED TENDER NOTICE

Feed in Tariff (FIT) Terms and Conditions

MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION BHOPAL

HIMACHAL PRADESH ELECTRICITY REGULATORY COMMISSION SHIMLA NOTIFICATION. Shimla, the 26 th May, 2010 REGULATIONS

Request for Proposal For Consultant for availing the Duty Credit scrip- under Foreign Trade Policy ( )

The South African Grid Code. Transmission Tariff Code. Version 9.0

The Brihan Mumbai Electric Supply & Transport Undertaking

CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI NOTIFICATION (DRAFT)

Order on. Petition No. 21/2014

GENERAL TERMS AND CONDITIONS OF PURCHASE GENERAL TERMS AND CONDITIONS OF PURCHASE

Phone Office: /89 Maulana Azad Campus, Chelmsford Road New Delhi

GUAM POWER AUTHORITY SCHEDULE "M" Standby, Auxiliary, Supplementary or Breakdown Service for Customers with Demands of 200 Kilowatts or More

COMPETITIVE BIDDING FRAMEWORK IN INDIA MOHAN MENON

CHAPTER 25. SUBSTANTIVE RULES APPLICABLE TO ELECTRIC SERVICE PROVIDERS.

APPLICATION FOR STANDARD CONTRACT BY A QUALIFYING COGENERATOR OR SMALL POWER PRODUCER

DUKE ENERGY OHIO REQUEST FOR PROPOSALS FOR PEAKING/INTERMEDIATE POWER SUPPLY IN RESPONSE TO OHIO SENATE BILL 221

CONSEQUENTIAL LOSS (FIRE) POLICY

EMP Commercial Terms and Conditions AS AT DECEMBER 2015 ENERGY DONE BRIGHT

Electricity (Development of Small Power Projects) GN. No. 77 (contd.) THE ELECTRICITY ACT (CAP.131) RULES. (Made under sections 18(5), 45 and 46))

Domestic Feed in Tariff (FIT) Terms and Conditions

CENTRAL ELECTRICITY REGULATORY COMMISSION (CERC) 3rd & 4th Floor, Chandralok Building, 36, Janpath, New Delhi : /

UNIFIED CARRIER LICENCE TELECOMMUNICATIONS ORDINANCE (Chapter 106)

Irish Life Assurance plc (Incorporated in the Republic of Ireland) CHIEF OFFICE IRISH LIFE CENTRE LOWER ABBEY STREET DUBLIN 1 RETIREMENT EXTRA PLAN

Customer s Name: Address: Contact Person: Telephone Number: Service Point Address: (Name and Address) Signature

PTC INDIA LIMITED NEW DELHI

REQUEST FOR PROPOSAL (RfP) ASSAM POWER DISTRIBUTION COMPANY LTD

MODEL DISTRIBUTION COOPERATIVE AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION LONG FORM CONTRACT

The Victory Electric Cooperative Association, Inc. Schedule of Tariffs Table of Contents

SECTION III RATE SCHEDULES Page 14.1

TELANGANA STATE POWER COORDINATION COMMITTEE Request for Proposal (RfP) NOTICE No. TSPCC (Commercial)/02/15-16

EOI DOCUMENTS FOR PROJECT THERMAL

POLICY ON DEVELOPMENT OF HYDRO POWER PROJECT. Energy Department Government of Bihar

Frequently Asked Questions on Companies (Cost Audit Report) Rules, 2011

CENTRAL ELECTRICITY REGULATORY COMMISSION New Delhi NOTIFICATION

Tender For. Supply, Installation & commissioning APC/HITACHI MAKE UPS. SLDC-Vadodara

UNION TERRITORY GOODS AND SERVICES TAX ACT, 2017

ENTERGY LOUISIANA, LLC

INDUSTRIAL DEVELOPMENT (INCOME TAX RELIEF) ACT

ORISSA ELECTRICITY REGULATORY COMMISSION BIDYUT NIYAMAK BHAWAN UNIT-VIII, BHUBANESWAR ************

Tampa Electric Company FERC Electric Tariff First Revised Service Agreement No. 5

4.2 Definitions In this Clause 4 and Schedule E the following terms shall have the meanings ascribed to them below:-

Transcription:

Notification dated 20.2.2009 Bhopal: dated 31 st January, 2009 No. 254-MPERC-2009. In exercise of the powers conferred by Section 181 read with Subsection (b) of Section 86 of the Electricity Act 2003 (36 of 2003) and all powers enabling it in that behalf, the Madhya Pradesh Electricity Regulatory Commission hereby revises the Madhya Pradesh Electricity Regulation Commission (Power Purchase and other matters with respect to conventional fuel based captive power plants) Regulations, 2006 notified on 29.9.2006 to harness the surplus generation capacity of captive power units and to reduce peak time shortages in the system. MADHYA PRADESH ELECTRICITY REGULATORY COMMISSION (POWER PURCHASE AND OTHER MATTERS WITH RESPECT TO CONVENTIONAL FUEL BASED CAPTIVE POWER PLANTS) REGULATIONS, (Revision-I) 2009 {RG-30(I) of 2009} PREAMBLE Whereas the Commission had notified Madhya Pradesh Electricity Regulatory Commission (Power Purchase and Other Matters with respect to conventional fuel based Captive Power Plants) Regulation, 2006 (G-30 of 2006) on 29.9.06 and whereas certain changes are necessary in these Regulations to align them with the Tariff Policy notified by the Ministry of Power, Government of India on 6 th January 2006, therefore these Regulations are being notified. CHAPTER I: PRELIMINARY Short title, commencement and interpretation 1.1 These Regulations may be called the Madhya Pradesh Electricity Regulatory Commission (Power Purchase and Other Matters with respect to conventional fuel based Captive Power Plants) Regulations, (Revision-I) 2009 {RG-30 (I) of 2009}. 1.2 These Regulations shall extend to the whole of Madhya Pradesh and shall apply only to the Captive Power Plants using conventional fuels. 1.3 These Regulations shall come into force on the date of their publication in the official gazette of the Government of Madhya Pradesh. Definitions 1.4 In these Regulations, unless the context otherwise requires, (a) Act shall mean the Electricity Act, 2003 (36 of 2003); (b) (c) (d) Authority means the Central Electricity Authority referred to in Subsection(1) of Section 70 of the Act; Billing cycle means the period between two consecutive meter readings for billing purposes; Captive Power Plant (CPP) shall have the meaning assigned to the term under clause 1.5 of these Regulations;

(e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r) (s) CPP Holder shall mean an individual, company or a body corporate being the owner of the Captive Power Plant; Captive User(s) shall have the meaning assigned to these Users under clause 1.5 of these Regulations; Commission shall mean the Madhya Pradesh Electricity Regulatory Commission (MPERC); Conventional Fuel shall mean any of the fossil fuels such as coal, lignite etc. Day shall mean a period from 00.00 hours to 24.00 hours. Firm Power shall mean the power agreed for supply by a CPP holder to a Licensee in the Power Purchase Agreement (PPA) executed between the Licensee and the CPP Holder. The variation up to plus or minus 15% from the agreed capacity will be treated as firm power; Firm Energy corresponds to Firm Power. In-firm Power shall mean the power supplied by a CPP holder to a Licensee if it is less than 85% or more than 115 % of the firm power defined above; In-firm Energy corresponds to In-firm Power. Licensee shall mean a Distribution Licensee; Stand-by period shall mean a period worked out by the Licensee as per the procedure for requisitioning stand-by support as provided in these Regulations; Stand-by support shall mean the contractual arrangement between the CPP Holder and the Distribution Licensee of his area of supply to provide power in case of planned or forced outage of the CPP; State Transmission Utility means the Licensee or the Government Company specified as such by the State Government under Sub-section (1) of Section 39 of the Act; User means the Captive User; Words and expressions used and not defined in these Regulations but defined in the Act shall have the meanings as assigned to them in the Act, or in absence thereof, shall have the same meaning as commonly understood in the electricity supply industry. Definition of a CPP with respect to own consumption versus sales mix 1.5 A power plant shall be identified as a Captive Power Plant only if it satisfies the conditions contained in clause 3 (1) (a) and (b) of the Electricity Rules, 2005 notified by the Ministry of Power, Government of India, on 8 th June 2005, reproduced here for ready reference: 3(1)No power plant shall qualify as a captive generating plant under section 9 read with clause (8) of section 2 of the Act unless- (a) in case of a power plant- (i) not less than twenty six percent of the ownership is held by the captive User(s), and (ii) not less than fifty one percent of the aggregate electricity generated in such plant, determined on an annual basis, is consumed for the captive use 2

(b) Provided that in case of power plant set up by registered cooperative society, the conditions mentioned under paragraphs at (i) and (ii) above shall be satisfied collectively by the members of the cooperative society: Provided further that in case of association of persons, the captive User(s) shall hold not less than twenty six percent of the ownership of the plant in aggregate and such captive User(s) shall consume not less than fifty one percent of the electricity generated, determined on an annual basis, in proportion to their shares in ownership of the power plant within a variation not exceeding ten percent; in case of a generating station owned by a company formed as special purpose vehicle for such generating station, a unit or units of such generating station identified for captive use and not the entire generating station satisfy(s) the conditions contained in paragraphs (i) and (ii) of sub-clause (a) above including- Explanation: - (1) The electricity required to be consumed by captive Users shall be determined with reference to such generating unit or units in aggregate identified for captive use and not with reference to generating station as a whole; and (2) The equity shares to be held by the captive User (s) in the generating station shall not be less than twenty six percent of the proportionate of the equity of the company related to the generating unit or units identified as the captive generating plant. 1.6 If in any financial year, the conditions contained in the above mentioned Electricity Rules, 2005 are not satisfied by the Captive User(s), then as per clause 3 (2) of the Electricity Rules, 2005 (reproduced below), the entire electricity (generated from the captive power plant) consumed by Captive Users in the year shall be treated as if it is supply of electricity by a generating company and shall be liable to all the charges as recoverable from an Open Access User. In such an eventuality, the Captive User shall have the right to represent before the Commission if he is not satisfied with the claim made by the Distribution Licensee. 3(2) It shall be the obligation of the Captive Users to ensure that the consumption by the Captive Users at the percentages mentioned in sub-clauses (a) and (b) of sub-rule (1) above is maintained and in case the minimum percentage of captive use is not complied with in any year, the entire electricity generated shall be treated as if it is a supply of electricity by a generating company. Explanation: (1) For the purpose of this rule- (a) Annual Basis shall be determined based on a financial year; (b) (c) Captive User shall mean the end User of the electricity generated in a Captive Generating Plant and the term Captive Use shall be construed accordingly; Ownership in relation to a generating station or power plant set up by a company or any other body corporate shall mean the equity share capital with voting rights. In other cases ownership shall mean proprietary interest and control over the generating station or power plant; 3

(d) Special Purpose Vehicle shall mean a legal entity owning, operating and maintaining a generating station and with no other business or activity to be engaged in by the legal entity. CHAPTER II: GENERAL AND TECHNICAL CONDITIONS IN CASE OF INTERCONNECTION WITH GRID 2.1 The Captive Power Plant (hereafter in these Regulations refers to as CPP) and dedicated transmission/distribution lines and substations shall be established, operated and maintained, as per the technical, safety and grid standards specified by the Authority or State Transmission Utility or the Commission. 2.2 As per proviso to Section 9(i) of the Act, the supply of electricity from a CPP through the grid shall be regulated in the same manner as that of the generating station of a generating company. For this purpose, the CPP Holder at 132 kv shall be required to comply with the directions issued by the State Load Despatch Centre (SLDC) for exercising supervision and control as may be necessary for ensuring integrated grid operations and for achieving the maximum safety, economy and efficiency in the operation of power system in the state. Similarly for supply at 33/11 kv, the CPP holder shall be required to comply with the directions issued by the Distribution Licensee s Control Centre (DLCC) for exercising necessary supervision and control. Provided that if any dispute arises with reference to the quality of electricity or safe, secure and integrated operation of the State grid or in relation to any direction issued by SLDC it shall be referred to the Commission for decision. However, pending the decision of the Commission, the CPP Holder shall comply with the direction issued by the SLDC/DLCC, as the case may be. 2.3 CPP Holder shall ensure the compliance of Madhya Pradesh Electricity Grid Code, the Indian Electricity Grid Code or the Regulations issued by the Authority as amended from time to time. The connectivity to the grid shall be provided by the Licensee only after the CPP Holder completes all formalities as prescribed by the Licensee for seeking connection of his CPP to the grid, including submission of all statutory clearances from the Pollution Control Board, Chief Electrical Inspector etc. The CPP Holder shall also ensure that the statutory clearances so obtained remain valid and are in force throughout the term of connectivity of his CPP with the grid. The coordination authority for 132 kv/ below 132 kv level shall be the Transmission Company and concerned Distribution Licensee respectively. 2.4 For the CPPs covered under these Regulations, the CPP Holders shall pay all such charges as are specified in these regulations, and any other charges as may be specified by the Commission from time to time. 2.5 The CPP Holder shall submit such technical details concerning generation and transmission to the concerned Licensee, as may be specified by the Authority or the Commission from time to time. 4

2.6 The CPP Holder shall provide the infrastructure for connecting the generating plant (if not existing earlier) to the network of the Transmission/Distribution Licensee, as the case may be. If the CPP Holder requires the Transmission Licensee/Distribution Licensee to build the infrastructure to connect his CPP with the Licensee s network, then the CPP Holder shall bear the cost of interconnection equipment and associated facilities including those necessary for network protection and metering. 2.7 The scheme of synchronising the CPP with the concerned Licensee s network shall be approved by the Officer designated by the concerned transmission/distribution licensee for such purpose. CHAPTER III: CONDITIONS FOR SALE OF CPP POWER TO A DISTRIBUTION LICENSEE 3.1 Any CPP Holder shall be entitled to sell surplus power to that Distribution Licensee in whose area of supply CPP is located. 3.2 The maximum rate of purchase of power from a CPP Holder by the Distribution Licensee shall be as determined by the Commission in its tariff order issued from time to time. However, the concerned Distribution Licensee shall have the option of procuring short-term / long-term power from any CPP Holder based on competitive bidding, using the guidelines specified by the Ministry of Power, Government of India in this regard but not exceeding the rates as determined by the Commission. In such an event, the Commission shall adopt the rate for power purchase as decided through such competitive bidding. In all such cases, the agreement shall be executed by M.P. Power Trading Co. Ltd. on behalf of the Distribution Licensee. 3.3 In view of the Govt. of M.P. notification dated 3 rd June, 2006 and allocation of power amongst three Distribution Licensees vide notification dated 14 th March, 2007 wherein Madhya Pradesh Power Trading Company Limited has been made the nodal agency for procurement of power on behalf of the Distribution Licensees, the applicability of these Regulations is extended to Madhya Pradesh Power Trading Company Limited. 3.4 Any CPP Holder with any exportable surplus power and who is willing to sell such surplus power to a Licensee, shall be required to enter into a Power Purchase Agreement (PPA) with such Licensee. The Licensee shall prepare and submit to the Commission a standard Power Purchase Agreement (hereinafter in these Regulations referred to as PPA) to be signed with CPP Holder for the Commission s approval, within one month of notification of these Regulations. 3.5 For CPP Holders having a PPA with the Licensee, energy for each time block of 15 minutes equivalent to Firm Power declared in the PPA shall be worked out as under: D * 1000 5

Where, FE = -------------------------- 4 FE = Firm Energy (in kwh) D = Firm Power (in MW ) Rates of Firm Power and In-firm Power rates for power purchase by Licensee from CPP : 3.6 The rate of purchase of Firm Power shall be differentiated between power purchased during normal time (between 0600 Hrs. to 1800 Hrs.), peak-time ( between 1800 Hrs. to 2200 Hrs.) and off-peak time (between 2200 Hrs. to 0600 Hrs. of next day). 3.7 For CPP Holder having PPA with a Licensee, the rate of purchase of Firm Power during normal time shall be as approved by the Commission in its Tariff Order for the financial year in question. The rate of purchase of Firm Power during peak time and off-peak time shall be 110 % and 90 % of the rate for normal time respectively. 3.8 The rate of purchase of In-Firm Power shall be 85% of the rate specified for Firm Power, for respective time periods. 3.9 The energy delivered shall be measured at the interface point of the Distribution or Transmission Licensee and the CPP, as the case may be. The Current Transformer (CT) of the synchronising breaker installed at sub-station of CPP shall be considered as the commercial interface for this purpose. Scheduling, Balancing and Settlement 3.10 CPPs shall be required to provide injection schedules for Firm Power as per Madhya Pradesh Electricity Grid Code, dated 24 th October, 2005 and subsequent amendments thereof. Provided that injection schedule for Firm Power during peak time shall not be less than the injection schedule for normal/off-peak time for the same day. Such CPPs shall also be bound by appropriate provisions of Scheduling and Balancing and Settlement Code as and when notified. The CPPs injecting In-Firm Power are not required to provide injection schedule. 3.11 No deemed generation shall be allowed. All payments for Firm and In-firm energy shall be done as per the following methodology: (a) (b) Step-1: Energy, for each time-block of 15-minutes shall be recorded by the export/import energy meter installed at the interface point of CPP holder and the licensee. Step-2: At the end of a billing cycle, the data downloaded from the interface meters shall be used to compute Firm and In-Firm Energy. The actual energy delivered to the Licensee shall be determined after deducting any third party shares and energy allocated to own consumers, if any, from the total net exported energy as recorded at the CPP premises. 6

(c ) Step-3:Payment settlement for Firm and In-Firm Energy: For each time block of 15 minutes, the data downloaded from the said energy meter representing actual export/import shall be compared with the injection schedule for each corresponding time block of 15 minutes and payment shall be made on the following basis:- If the actual energy is equal to or more than the Firm Energy, then the entire actual energy shall be paid at the rate of Firm Energy at the rate applicable for the particular period of time. In case the actual energy is found to be less than the scheduled energy, then the entire actual energy will be treated as In-Firm Energy and paid at the applicable rate. 3.12 The Commission prescribes a settlement period of 30 days from the date of submission of the bill to the concerned Distribution Licensee where the power is injected. The bills shall be submitted to the concerned distribution licensee, who shall then verify the bills and send the same within seven days of receipt of bills to M.P. Power Trading Co. Ltd. for making payment to the developer. In case of delay, M. P. Power Trading Co. Ltd. will pay penal interest on outstanding amount at the rate of 1% per month or part thereof. In case M.P. Power Trading Co. Ltd. makes payment within 15 days from the date of submission of bill, a rebate of 1% of billed amount shall be allowed by the CPP holder. 7

CHAPTER IV: OTHER MATTERS Stand-by support 4.1 The Stand-by support shall be provided to the following types of captive generators/ Users [hereinafter is referred to as User(s) ] with a minimum capacity of 1 MW : (a) CPP and User are located in the same premises but the CPP is not connected to the grid (operating in an islanded mode) and thus the User is not a consumer of the Distribution Licensee; (b) CPP and User (s) are in the same premises and CPP is connected to the grid, but the User does not have any external source of supply other than the Licensee of User s area of supply; and (c) CPP is located at one premises and the User is located at other premises. Also, the User is availing additional supply from licensee only and there are no other supply arrangements. 4.2 The Stand-by support shall not be allowed to any consumer who has arrangement for availing supply from a source other than the Licensee of his area of supply and his own captive generation. 4.3 The following table lays down the different types of transactions involving Captive Power Plants and its Users, and the applicability of stand-by support in each situation: Part CPP type / location A B C Islanded CPPs (physical connection to grid required if CPP User requests Stand-by support) CPP and User located in same premises and connected to Grid CPP located at premises A and user located at premises B Arrangement for availing additional supply by Captive User No arrangement From Licensee only Stand-by support Allowed Allowed From Licensee only Allowed subject to the terms and conditions under Balancing and Settlement Code. 8

Part CPP type / location D CPP and User located in same premises and connected to Grid Arrangement for availing additional supply by Captive User From Licensee and also from other sources Stand-by support Not allowed E CPP located at premises A and user located at premises B From Licensee and also from other sources Not allowed 4.4 User who is allowed Stand-by support as per the table above may request for Stand-by support from the Distribution Licensee of his area of supply and the Distribution Licensee shall be obliged to provide such support to the User. 4.5 Users existing on the date of notification of these regulations and requiring Stand-by support shall be required to execute supplementary agreement within 30 days of notification of these regulations to abide by the rules under these Regulations applicable from the date of notification. The prospective Users shall disclose their willingness to avail of stand-by support at the time of submitting their application for connection / open access. 4.6 For the purpose of Stand-by support, such User and the Distribution Licensee or M.P. Power Trading Co. on behalf of the Distribution Licensee shall have to enter into an agreement for such support. The Distribution Licensee/ M.P. Power Trading Co., as the case may be, shall prepare a model agreement within one (1) month of notification of these regulations and shall take Commission s approval for the same. 4.7 The User shall normally not avail Stand-by support more than the contracted stand-by demand. 4.8 The following Sections of the Regulations describe the conditions for provision of stand-by support applicable on each Part or type of transaction described in the table above, which are allowed the facility of Stand-by support from the Licensee (i.e. Parts A, B and C). PART A: Conditions for availing Stand-by support 4.9 Such Users, if requiring Stand-by support, shall have to procure required interconnecting infrastructure at their cost. The Interconnecting breaker on the User s end shall be kept open, and shall be charged by the Licensee only when the requirement of Stand-by support is informed by the User in writing to the Licensee as per clause 4.10 below. 9

4.10 Such Users shall request the Distribution Licensee of his area of supply in writing about the requirement of Stand-by support. It shall be the responsibility of the Distribution Licensee to maintain the interconnecting line in charged condition with the interconnecting breaker in open position. The Distribution Licensee shall arrange to close the interconnecting breaker on User s end within a period of 2 hours from the time of receipt of such request. When the User ceases to require Stand-by support from the Licensee, it shall again inform the Licensee in writing about the same. The Licensee, on receiving such request, shall re-open the Interconnecting breaker on the User s end within 2 hours. 4.11 User s request to the Licensee shall indicate the amount of Stand-by demand the User wishes to requisition against his total Stand-by Contracted Demand for daily scheduling purposes by the Distribution Licensee. 4.12 The total period for the purpose of billing for stand-by support shall be from the time the Licensee closes the interconnecting breaker in the premises of the User in presence of its representative for the availability of stand-by support up to the time the interconnecting breaker is re-opened for disconnection of stand-by supply in presence of user s representative pursuant to communication of the User and subject to provisions in Clause 4.10 above. 4.13 The request from the User shall be sent to the Superintending Engineer of the concerned Circle, or any other authorised officer as designated by the Licensee. The detailed process of sending and acknowledgements of these requests shall be worked out between the Licensee and the User and shall be stated in the Stand-by agreement. Charges for Stand-by support 4.14 In case of such Users, the maximum demand that can be contracted under Stand-by support cannot be more than the total rated capacity of all the captive generating units of the CPP holder. 4.15 Wherever an agreement for Stand-by support exists between the User and the Licensee of his area of supply, the User shall be required to pay to the Licensee a charge equal to Rs. 31 per kva per month or part thereof towards commitment charges applied on the capacity (in kva) contracted on 33 kv and Rs. 25 per kva per month or part thereof towards commitment charges applied on the capacity (in kva) contracted on 132kV as Stand-by support from the Distribution Licensee. Provided that the charges referred to above shall apply uniformly every month commencing from the date of applicability of the stand-by agreement, irrespective of whether the User avails stand-by support or not. Provided further that the above commitment charges are applicable up to the control period ending on 31.3.2012, and shall be reviewed thereafter. 4.16 In addition to above commitment charges, the User shall also be required to bear energy charges and fixed charges for the power consumed during period of Stand-by support which shall be same as applicable for temporary connection as approved by the Commission for corresponding category in its tariff orders from time to time. 4.17 The fixed charges shall be applied on the maximum demand at any 15 minutes time block covered under stand-by period subject to minimum of 90 % of the contract demand. The standby period for this purpose shall be reckoned maximum up to 30 continuous days. The energy charges shall be applied on the total energy consumed across all time-blocks covered under stand-by period. 10

4.18 In case the recorded maximum demand at the CPP premises exceeds the Stand-by contract demand, the excess demand recorded shall be billed for at 2 times the fixed charges arrived at from Clause 4.17. 4.19 The Stand-by support availed by the User shall be entitled for power factor incentives and penalties as approved by the Commission for retail supply consumers in its Tariff Order. However, the load factor concession shall not be applicable. 4.20 There shall be no minimum energy charges on power consumed under Stand-by support for such Users. 4.21 In case the stand-by support is availed by the User for more than one time in a particular month, the fixed charges shall be billed for the first time only. PART B: Conditions for availing Stand-by support 4.22 The User shall request the Distribution Licensee of his area of supply about the requirement of stand-by support at least two (2) hours before the time the captive consumer intends to avail power from the Distribution Licensee. The User shall inform the Distribution Licensee with the date and time of the stoppage of its captive power plant. When the User s CPP starts functioning again, the User shall, within a period of one (1) hour, inform the Distribution Licensee about the same duly giving the actual date and time since the plant started functioning again. However, where modification in metering is required while affording standby supply, the User shall request for standby support twelve (12) hours in advance and for withdrawal of support, the Distribution Licensee shall stop the standby support within twelve (12) hours of receipt of such request. The total period of stand-by support shall be worked out accordingly. Provided that the Distribution Licensee may verify the actual date and time of both commencement and ending of the Stand-by period, as provided by the User, with the actual meter readings, and other records as may be necessary, at the CPP / Captive User s premises. 4.23 User s request to the Licensee shall indicate the amount of Stand-by demand the consumer wishes to requisition against his total Stand-by Contracted Demand for the purpose of daily scheduling by the Distribution Licensee. 4.24 The request from the User shall be sent to the Superintending Engineer of the concerned Circle, or any other authorised officer as designated by the Licensee. The detailed process of sending and acknowledgements of these requests shall be worked out between the Licensee and the User and shall be stated in the Stand-by contract. Charges for Stand-by support 4.25 The maximum demand that can be contracted under Stand-by support cannot be more than the total rated capacity of all the generating units of the User s CPP. 4.26 Wherever an agreement for Stand-by support exists between such User and the Distribution Licensee of his area of supply, the User shall be required to pay to the Distribution Licensee, the charges as per clause 4.15 and 4.16 of these Regulations. 4.27 The billing for Stand-by charges shall be done in the manner as prescribed in clause 1.18 (g) of the tariff order dated 29.3.08. 11

4.28 Other terms and conditions shall be as per clause 4.17 to 4.21 of these Regulations. PART C: Conditions for availing Stand-by support 4.29 The facility for standby support shall be available for such Users subject to the terms and conditions under Balancing and Settlement Code, which shall be notified by the Commission. Charges for Stand-by support 4.30 The maximum demand that can be contracted under Stand-by support cannot be more than the total rated capacity of all the generating units of the User s CPP. 4.31 Wherever an agreement for Stand-by support exists between such User and the Distribution Licensee of his area of supply, the User shall be required to pay to the Distribution Licensee, the charges as per clause 4.15 and 4.16 of these Regulations. 4.32 The billing for Stand-by charges shall be done in the manner as prescribed in clause 1.18 (g) of the tariff order dated 29.3.08. 4.33 Other terms and conditions shall be as per clause 4.17 to 4.21 of these Regulations. Miscellaneous Provisions (applicable to all parts) Matters related to metering, meter reading and energy billing 4.34 CPP Holders / Captive Users involved either in sale of power to the Distribution Licensee of its area of supply or seeking Stand-by support from the Licensee shall be required to install at their premises, main and check import/export ABT compliant Energy Meters capable of time differentiated measurements (15 minutes) of active and reactive energy. A request for stand-by support to eligible captive Users as per these Regulations shall be entertained by the Licensee only after the captive User has installed the required meters at their premises. Such meters and related equipments shall be got tested by Licensee or in presence of Licensee s representative at an accredited laboratory at the cost of CPP holder/captive User. Such tested meter and related equipments shall be duly sealed by the Licensee. 4.35 Meter reading, energy accounting and settlement of charges at the CPP interface point shall be the responsibility of the concerned Distribution Licensee in whose area of supply the CPP is located. In case of captive Users contained in Part C of these Regulations, the procedures for meter reading, energy accounting and settlement of charges, the entities involved and their individual responsibilities shall be as per the Balancing and Settlement Code. 4.36 The Invoice for power purchased by M.P. Power Trading Co. on behalf of a Licensee shall be raised by the CPP Holder based on the meter readings at the interface point within a period of one week from the date of meter reading. The M.P. Power Trading Company on behalf of the concerned Licensee shall be responsible for making payment against the invoice within 30 days of receipt of bill. In case of delay, M. P. Power Trading Co. Ltd. will pay penal interest on outstanding amount at the rate 1% per month or part thereof. In case M.P. Power Trading Co. Ltd. makes payment within 15 days from the date of submission of bill, a rebate of 1% of billed amount shall be allowed by the CPP holder. 12

4.37 In case the Distribution Licensee is not in a position to supply the standby contract demand on the request of User on the terms and conditions provided in these Regulations, the Distribution Licensee shall pay to the User by way of penalty at two times the commitment charges prescribed in these Regulations for the period supply is not made available. However, any party shall not be liable for any claim for loss / damage or compensation whatsoever arising out of failure of supply when such failure of supply is due to, either directly or indirectly, to Force Majure conditions such as war, mutiny, Civil commotion, riot, terrorist attack, Fire, Flood, Strike (Subject to certification by Labour Commissioner), Lock out (subject to certification by Labour Commissioner) Cyclone, Tempest, Lightening, Earthquake or act of God. But in such events, the period of discontinuance shall be added to the said period of the agreement. Power to remove difficulties 4.38 If any difficulty arises in giving effect to any of the provisions of these regulations, the Commission may, by general or special order undertake steps or direct the licensees to undertake steps, which in the opinion of the Commission are necessary or expedient for the purpose of removing difficulties. Power to Amend 4.39 The Commission may, at any time add, vary, alter, modify or amend any provisions of these regulations. If clarification of any of the provisions included in these regulations is required, the concerned person may approach the Commission for seeking such clarification. Savings 4.40 Nothing in these Regulations shall be deemed to limit or otherwise affect the inherent power of the Commission to make such orders as may be necessary for ends of justice to meet or to prevent abuses of the process of the Commission. 4.41 Nothing in these Regulations shall bar the Commission from adopting, in conformity with the provisions of the Act, a procedure, which is at variance with any of the provisions of this Code, if the Commission, in view of the special circumstances of a matter or class of matters and for reasons to be recorded in writing, deems it necessary or expedient for dealing with such a matter or class of matters. 4.42 Nothing in these Regulations shall, expressly or impliedly, bar the Commission dealing with any matter or exercising any power under the Act for which no Codes have been framed, and the Commission may deal with such matters, powers and functions in a manner it thinks fit. By order of the Commission (Ashok Sharma) 13

Commission Secretary Calculation sheet for working out the Commitment charges (A) For EHT consumers CPP with standby contract demand = 20 MVA The Licensee has to keep reserve the capacity of 20 MVA. Therefore, the expenditure to be incurred for this shall have to be recovered from the CPP towards commitment charges (besides temporary tariff for fixed charges and energy charges) as under :-- On account of No Load Losses Assuming no load losses as 20 kw, the amount of energy lost in a month = No load losses X no. of hours in a month = 20 X 730 = 14,600 units Cost of energy lost based on average cost of supply = Rs. 3.69 X 14,600 = Rs. 53,874 Interest on investment on 20 MVA transformer(including accessories) Cost of transformer (including accessories) = Rs. 3.25 Crores Amount of interest @ 1% p.m. on cost of transformer = Rs. 3,25,00,000 X 0.01 = Rs. 3,25,000 O&M Charges for maintenance of transformer O&M charges = 0.5 % per month of cost of transformer = 0.5 X 32500000/100 = 1,62,500 14

O&M Charges for maintenance of lines O&M charges = 0.5 % per month of cost of line (max. 10 Kms.) = 0.5 X 32,50,000 X 10/100 = Rs.1,62,500 Therefore, Commitment charges per month = Rs. 53,874 + Rs. 3,25,000 + Rs. 1,62,500 + Rs. 1,62,500 = Rs. 7,03,000 and Commitment Charges per kva per month = Rs. 7,03,000 /20000 = Rs. 35.15 say Rs. 35 15