Plant Vogtle Additional Units 3 and 4 (Project) Amended and Restated Power Purchase Agreement Between MEAG and JEA (PPA)

Similar documents
Responses to Investor Questions - September 24, 2018

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Washington, D. C FORM 8-K CURRENT REPORT

BEFORE THE FLORIDA PUBLIC SERVICE COMMISSION. The following Commissioners participated in the disposition of this matter:

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Washington, D. C FORM 8-K CURRENT REPORT

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Washington, D. C FORM 8-K CURRENT REPORT

UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 8-K

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Washington, D. C FORM 8-K CURRENT REPORT

SOUTHERN CO FORM 8-K. (Current report filing) Filed 01/29/15 for the Period Ending 01/29/15

Regardless of the ownership model, however, the costs of providing service, with only a few exceptions, are covered by the customer.

Information Regarding Status of Construction of Plant Vogtle Units 3 and 4 June 12, 2017

Information Regarding Status of Construction of Plant Vogtle Units 3 and 4 September 1, 2017

UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C FORM 10-Q

RE: Reply Brief of the Sierra Club in Case No E-ENEC

Recommended. Operating and Capital Budget As Adopted June 19, 2018 JE<1 FOR THE YEAR OCTOBER 1, SEPTEMBER 30, Building Community*

asset management group

DIRECT TESTIMONY OF STEVEN D. ROETGER, WILLIAM R. JACOBS, JR PH.D, MARK D. RAUCKHORST AND DAVID P. POROCH,

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Washington, D. C FORM 8-K CURRENT REPORT

UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C FORM 10-Q

IN THE COURT OF APPEALS OF THE STATE OF MISSISSIPPI CAUSE NO CA APPEAL FROM THE CIRCUIT COURT OF ATTALA COUNTY, MISSISSIPPI

UNITED STATES SECURITIES AND EXCHANGE COMMISSION Washington, D.C FORM 10-Q

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Washington, D. C FORM 8-K CURRENT REPORT

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Washington, D. C FORM 8-K CURRENT REPORT

Mr Martin, Sincerely yours, Anton Affentranger Chief Executive officer Implenia AG Industriestrasse Dietlikon Switzerland

UNITED STATES SECURITIES AND EXCHANGE COMMISSION WASHINGTON, D.C FORM 8-K

Questions and Answers regarding MEAG Power s Vogtle 3 & 4 Project after the crisis in Japan

STATE OF NEW YORK DEPARTMENT OF PUBLIC SERVICE THREE EMPIRE STATE PLAZA, ALBANY, NY

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Washington, D. C FORM 8-K CURRENT REPORT

MEMORANDUM FROM: Jacqueline M. Kovilaritch, Assistant City Attorney ' DATE: April 26, 2007 RE: Retention of Outside Counsel

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) PJM Interconnection, L.L.C. ) Docket No. ER )

UNITED STATES SECURITIES AND EXCHANGE COMMISSION. Washington, D. C FORM 8-K CURRENT REPORT

BEFORE THE GEORGIA PUBLIC SERVICE COMMISSION STATE OF GEORGIA

UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF GEORGIA ATLANTA DIVISION

IN THE HIGH COURT OF NEW ZEALAND AUCKLAND REGISTRY CIV [2015] NZHC KIWIBANK LIMITED Defendant

Grady Electric Membership Corporation

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. ) ISO New England Inc. ) Docket No. ER )

Case MFW Doc Filed 12/03/18 Page 1 of 4 KYLE LAW CORPORATION. San Francisco, California December 3, 2018

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION

October 20, VIA ELECTRONIC FILING-

Southern Company Conference Call. May 21, 2018

JEA BOARD AGENDA. DATE: February 20, 2018 TIME: 12:00 PM PLACE:

My recommendation includes a protection product for which I will receive a commission directly from the product provider.

IN THE COURT OF SPECIAL APPEALS OF MARYLAND. September Term, No MARYLAND OFFICE OF PEOPLE S COUNSEL, et al.,

February 26, VIA ELECTRONIC FILING -

Management s Discussion and Analysis of Financial Performance for the Quarter Ended December 31, 2018

A. LLC Recordkeeping and Member Access to Records

Dear Members and Staff of the Public Company Accounting Oversight Board:

PUBLIC SERVICE COMMISSION OF WEST VIRGINIA CHARLESTON * * * * * * * * * BLUESTONE INDUSTRIES, INC. * COAL-SC-GI * * * * * * * * *

BENEFITING FROM PROFESSIONAL TRUST SERVICES

NCOIL EXPRESSES RENEWED CONCERNS ABOUT ALI RESTATEMENT OF THE LAW OF LIABILITY INSURANCE

No. 47. An act relating to the Vermont Energy Act of (H.56) It is hereby enacted by the General Assembly of the State of Vermont:

THE SCHWAB BUILDING 101 MONTGOMERY STREET SAN FRANCISCO, CA (415)

South Carolina Electric & Gas Company ("SCE&G" or the "Company") hereby

ORAL STATEMENT. July 15, 2004

Information & Instructions: Demand letter opportunity to cure and intent to accelerate the note

mew Doc 912 Filed 07/14/17 Entered 07/14/17 17:13:46 Main Document Pg 1 of 7

A MESSAGE FROM. Our Chairman DEAR SHAREHOLDERS, NET INCOME: RETURN ON AVERAGE ASSETS:

SECURITIES TRADING MEMORANDUM

OFFICE OF THE CITY COUNCIL

Duke Energy Corporation

October 4, 2013 VIA ELECTRONIC FILING

IN THE UNITED STATES BANKRUPTCY COURT IN AND FOR THE SOUTHERN DISTRICT OF FLORIDA WEST PALM BEACH DIVISION

Equifax Inc. (Exact Name of Registrant as Specified in Charter)

UNITED STATES DISTRICT COURT DISTRICT OF MINNESOTA. v. MEMORANDUM OF LAW & ORDER Civil File No (MJD/JSM)

Telephone Fax

Financial Contents. Southern Company 2017 Annual Report

~e5i= ~ GUNSTER FLORIDA'S LAW FIRM FOR BUSINESS. November 2, 2017 E-PORTAL FILING

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION. Meridian Energy USA, Inc. ) Docket No. ER

Municipal Electric Authority of Georgia

Proposed Rules on Proxy Voting by Investment Advisers and Registered Management Investment Companies (File No. S )

4025 Chestnut St Chestnut St. Philadelphia, PA, Philadelphia, PA, 19104

FINRA Regulatory Notice Extension of FINRA Rule 5122 to All Private Offerings

February 20, National Grid Renewable Energy Standard Procurement Plan Docket No. 3765

IN THE CIRCUIT COURT OF THE FIFTEENTH JUDICIAL CIRCUIT, IN AND FOR PALM BEACH COUNTY, FLORIDA. v. CASE NO AH

April 28, Re: File Nos. SR-NYSE and SR-NYSE ; Release No : NYSE OpenBook Proposal 1

PRESERVING YOUR LEGACY

PartnerRe Board of Directors Issues Letter to Shareholders

NOTICE OF PROPOSED CLASS ACTION SETTLEMENT AND SETTLEMENT HEARING

POLICE AND FIRE PENSION FUND ONE WEST ADAMS STREET, SUITE 100 JACKSONVILLE, FLORIDA

Filing # E-Filed 02/14/ :18:22 PM

AGREE New York. December 22, 2014

UNITED STATES OF AMERICA DEPARTMENT OF ENERGY BEFORE THE BONNEVILLE POWER ADMINISTRATION

Southern Company. 2nd Quarter 2018 Earnings. June 30, 2018

DEPARTMENITT~~;J~~~~~~--

From Article at GetOutOfDebt.org

Notes for Menifee CCA Hearing

Georgia Power Company s Qualifying Facilities (QF) Fundamentals

October 30, 2017 File No VIA ELECTRONIC SUBMISSION

Appellant, Lower Court Case No.: CC O

Re: Basel Standardized Proposal and Improvements to U.S. Process for International Standards

Southern Company. 4th Quarter 2009 Earnings. December 31, 2009

AUSLEY MCMULLEN ATTORNEYS AND COUNSELORS AT LAW 123 SOUTH CALHOUN STREET. P.O. BOX 391 (zip 32302) TALLAHASSEE, FLORIDA 32301

Submission Data File General Information Subject-Company File Number Subject-Company CIK Subject-Company Name Subject-Company IRS Number

February 16, Hon. Sheldon Silver Speaker New York State Assembly Legislative Office Building 932 Albany, NY

file:///i /...20Received/2011/October/Objection%20to%20Integration%20-Sec.%2011%20T4N-R32W%20Sebastian%20County%20AR.htm[10/20/2011 2:40:48 PM]

SUPREME COURT OF FLORIDA. v. Lower Tribunal No.: 2D RESPONDENTS AMENDED RESPONSE TO PETITIONERS JURISDICTIONAL BRIEF

IN THE SUPREME COURT OF FLORIDA TALLAHASSEE, FLORIDA. Petitioner, S.C. Case No.: SC DCA Case No.: 5D v. L.T. Case No.

Re: Proposed Statement of Financial Accounting Standards, Disclosure of Certain Loss Contingencies

Revenue Procedure , Changes in Methods of Accounting

ARMED SERVICES BOARD OF CONTRACT APPEALS

Chase Tower, Eighth Floor. P.O. Box July 13,2018

Transcription:

E L E C T R I C W A T E R S E W E R September 18, 2018 Via E-mail Gregory P. Thompson Chairman of the Board MEAG Power 1470 Riveredge Parkway, N.W. Atlanta, GA 30328-4640 Re: Plant Vogtle Additional Units 3 and 4 (Project) Amended and Restated Power Purchase Agreement Between MEAG and JEA (PPA) Dear Mr. Thompson: I am writing to you in my capacity as Chairman of the Board of JEA. As public power entities, JEA and MEAG Power are uniquely positioned among the Vogtle parties to make decisions that are purely in the best interest of our customers and the communities we serve. We are not inherently conflicted by delivering investor returns to our shareholders. Instead, we can focus solely on delivering reliable, affordable essential services, particularly to those least able to afford them. We appreciate the magnitude and difficulty of the decision before the MEAG Power Board, especially in light of how much time and money has already been poured into Plant Vogtle. But we in Jacksonville have 50,000 families that live at or below the poverty line to protect, making affordability an essential priority for us and our community. And for the vast majority of our customers, their monthly utility bill is a significant expense. JEA and MEAG Power have a responsibility to make decisions in the financial best interest of the communities we serve, even when those decisions are hard. And this decision is crystal clear: if MEAG Power s Board votes not to proceed with this Project, communities across Georgia, Alabama, and Florida could save at least $2.5 billion when compared to at least one alternative power option we have identified: money that makes a meaningful difference in the lives of the people we serve. The choices made this week will endure long past our own lifetimes. These are choices with which our children and our grandchildren will have to live. Choose affordability; vote no. To better inform your vote, allow me to share the following facts which inform JEA s position that the Project should not proceed. First, JEA has secured a firm term sheet for 206MW of energy and capacity at a fixed price through 2042 ( JEA Replacement Offer ) that, if JEA were to accept the offer, would save JEA customers over $1.1 billion if the Project is abandoned and those savings include JEA continuing to pay for

Gregory P. Thompson September 18, 2018 Page 2 of 4 Project sunk costs. The JEA Replacement Offer, the mismanagement of the Project, and the state of the current technology and generation market are three major points of consideration JEA s Board has utilized to cement our current position on the Project. Second, in the spirit of partnership and for the benefit of MEAG s ratepayers, JEA has also secured a term sheet offer for 294MW of energy and capacity at a fixed price through 2042 ( MEAG Replacement Offer ). The capacity and energy under the JEA Replacement Offer and MEAG Replacement Offer is to be supplied by a proven and fully operational generating facility located in Georgia with full standby redundancy. It does not depend on unproven technology and is not subject to construction completion risk. Based upon the MEAG Replacement Offer and MEAG s financial projections provided to JEA on August 31, 2018, cancellation of the Project, repayment of the sunk Project costs and acceptance of the JEA Replacement Offer and the MEAG Replacement Offer would result in savings in excess of $2.5 billion to MEAG, JEA and PowerSouth Energy Cooperative. MEAG alone would save more than $800 million over the initial 20-year life of the PPA. These savings assume the payment of scheduled debt service requirements by MEAG, PowerSouth, and JEA on all Project J and Project P borrowings to date. To illustrate the value of the savings under the MEAG Replacement Offer, MEAG s fixed contractual rate would have to exceed $133 per MWh over the remaining 20 years for the MEAG Replacement Offer to be uneconomical relative to proceeding with the completion of the Project. This represents a greater than 350% increase to current market rates in an environment where numerous forces, including advancements in renewables and storage, are driving prices down. Please note these savings assume the Project is completed in 2021/2022 at a total cost of more than $30 billion (based on JEA s estimate from information provided by MEAG on August 31, 2018), a questionable assumption given that cost and schedule estimates for the Project to date have been and continue to be incorrect. One additional fact that MEAG s Board should consider is the current 2018 cost of utility scale solar of approximately $30 per MWh 1. The current 2018 cost of utility scale storage is approximately $85 per MWh 2. The aggregate, carbon-free cost of energy, based on storing half the output of the solar, is estimated at $73 per MWh. Costs for both solar and storage have dropped significantly over recent years and prices are expected to continue to drop, a fact that is in stark contrast to the megawatt price that will result from the Project. The $800 million saved by MEAG with the MEAG Replacement Offer, over the initial 20-year period, would provide more than enough capital to pay for more future annual solar generation at utility scale than the annual output of MEAG s current entire system. Any argument that carbon free energy and capacity in 2042 would not otherwise be available or cost justifiable is without merit. 1 Based on JEA s actual solar pricing plus land and interconnect costs, including investment tax credit awarded in March 2018. 2 Based on GTM Research US Energy Storage Monitor: Q3 2018 Executive Summary - $225/kWh cost of 4-hour storage, assuming 80% depth of discharge, 90 percent efficiency, and a 20-year battery life. 2

Gregory P. Thompson September 18, 2018 Page 3 of 4 This MEAG Replacement Offer eliminates any doubt for MEAG and its Board of Directors as to the appropriateness of voting to abandon the Project. A decision to continue with the Project is a decision to impose at least $2.5 billion of unnecessary costs on MEAG s Participants and their customers, PowerSouth and JEA, and is contrary to prudent utility practice. Moreover, JEA believes a decision to proceed in the face of this MEAG Replacement Offer would be a breach of the MEAG Board s duties to its Participants and their customers and a breach of MEAG s duties to JEA under the PPA. In light of the foregoing, I would respectfully ask that you and your fellow directors on the MEAG Board carefully consider your vote on whether to continue the Project. The duties you owe to your Participants and their respective customers parallel the duties owed by JEA to its customers. JEA believes it would be a breach of your duty to your Participants and their customers to vote in favor of continuing construction of the Project based on the following facts: Estimated costs of the Project have increased from $14.5 billion to over $30 billion (based on JEA s estimates) in 18 months and there is no guarantee the Project costs will not continue to increase; The lack of Project controls as demonstrated by the additional $2.3 billion in cost overruns announced only six months after the Owners expressed confidence regard completion costs and timing to the Georgia PSC and the public; JEA has obtained formal term sheets for the JEA Replacement Power and the MEAG Replacement Offer that could save over $2.5 billion for MEAG, JEA and PowerSouth as opposed to the cost of completing the Project; and, The cost of carbon free and renewable power in the 2018 market is, and in 2042 will more than likely be, at or below the current cost of the Project and continuing to decline on an annual basis. You are no doubt aware of the lawsuits filed by each of JEA and MEAG against the other. JEA does not take the decision to litigate lightly. However, after receiving zero responses from any of the Project Owners to two separate written requests attached hereto, we felt compelled to act to safeguard the interests of our customers and investors. I am hopeful that a commercial solution can yet be reached that will bring a swift end to the pending litigation. Finally, JEA filed a petition today with the Federal Energy Regulatory Commission (FERC) for FERC to assert jurisdiction over the PPA. We have asked FERC to find that MEAG was obligated under the Federal Power Act (FPA) to submit the PPA to the Commission for review upon execution and to direct MEAG to promptly make a filing under Section 205 of the FPA seeking approval of the PPA. MEAG will then have the burden of proving that the terms, conditions and rates in the PPA are just and reasonable. We do not believe MEAG can meet this burden. 3

Gregory P. Thompson September 18, 2018 Page 4 of 4 I am happy to answer any questions you have regarding the foregoing and will make myself available to speak with you directly prior to MEAG Power voting on the Project. Further, if requested, JEA will provide MEAG a formal term sheet for the MEAG Replacement Offer at or prior to the MEAG Board meeting where it intends to take action related to voting on proceeding with the Project. It is my understanding that the MEAG Board plans to vote on this matter at its meeting on September 20, 2018. Please let me know of your availability for a meeting or call prior to the MEAG Power Board voting on this Project. Sincerely, G. Alan Howard JEA Chairman of the Board Cc: Attached: MEAG Board of Directors Gary Smith, PowerSouth CEO PowerSouth Board of Directors Hon. Lenny Curry, Mayor, City of Jacksonville Jacksonville City Council JEA Board of Directors Mr. Aaron Zahn, Interim Managing Director and CEO of JEA First Letter Request Second Letter Request 4

First Letter Request from September 5, 2018 5

21 West Church Street Jacksonville, FL 32202 September 5, 2018 Via E-mail or Fascimile E L E C T R I C W A T E R S E W E R Georgia Power Company Paul Bowers, President and CEO 241 Ralph McGill Boulevard Atlanta, GA 30308 Oglethorpe Power Corporation Michael L. Smith, President and CEO 2100 East Exchange Place Tucker, GA 30084-5336 Municipal Electric Authority of Georgia James E. Fuller, President and CEO 1470 Riveredge Parkway, NW Atlanta, GA 30328-4686 City of Dalton Georgia Don Cope 1200 V.D. Parrott, Jr. Parkway Dalton, GA 30721 Re: Plant Alvin W. Vogtle Additional Units 3 and 4 Request to Extend Participating Parties Vote to Continue to October 31, 2018 Dear Mr. Bowers, Mr. Smith, Mr. Fuller and Mr. Cope: As you are aware, JEA and Municipal Electric Authority of Georgia ( MEAG ) are parties to an Amended and Restated Power Purchase Agreement related to Plant Vogtle Units 3 & 4 ( Project ). As such, JEA has a significant interest in this Project and ensuring all interested parties reach an amicable and mutually agreeable resolution.

It is our understanding that the owners, Georgia Power, Oglethorpe Power Corporation, MEAG and City of Dalton ( Owners ) are to vote on whether to continue with the Project on or before September 21, 2018 and that this date was selected primarily due to the timing of the U.S. Department of Energy s ( DOE ) amended and restated loan guarantee (DOE Loan Guarantee). It is also JEA s understanding that DOE is willing to extend the date of the DOE Loan Guarantee closing consistent with an extension of the vote of the Owners. JEA hereby requests that the Owners extend the formal vote, in accordance with Section 2.0 of the Agreement Regarding Additional Participating Party Rights, Amendment No. 3 to the Plant Alvin W. Vogtle Additional Units Ownership Agreement and Amendment No. 4 to the Plant Vogtle Owners Agreement Authorizing Development, Construction, Licensing and Operation of Additional Generating Units ( Owners Agreement ) dated November 2, 2017, on whether to continue the Project, on or after October 31, 2018. JEA believes this postponement may provide sufficient time for all parties to have reasonable conversations and potentially reach a mutually agreeable resolution that benefits all of our interests. Please acknowledge receipt of this request and indicate the willingness of the Owners to agree to the requested extension within 48 hours of receipt. Very Truly Yours, Aaron Zahn, Interim Managing Director and CEO Cc: John Sneed, DOE Executive Director/Loan Programs Office Dong K. Kim, DOE COO/Loan Programs Office Peter M. Degnan, Esq., MEAG Senior VP & General Counsel G. Alan Howard, Esq., JEA Chair Allen Maines, Esq. Jody L. Brooks, Esq., JEA Chief Legal Officer

Second Letter Request from September 8, 2018 6

September 8, 2018 Via E-mail Georgia Power Company Paul Bowers, President and CEO 241 Ralph McGill Boulevard Atlanta, GA 30308 Oglethorpe Power Corporation Michael L. Smith, President and CEO 2100 East Exchange Place Tucker, GA 30084-5336 Municipal Electric Authority of Georgia James E. Fuller, President and CEO 1470 Riveredge Parkway, NW Atlanta, GA 30328-4686 City of Dalton Georgia Tom Bundros, CEO 1200 V.D. Parrott, Jr. Parkway Dalton, GA 30721 Re: Plant Alvin W. Vogtle Additional Units 3 and 4 Second Request to Extend Vote to Continue Project Dear Mr. Bowers, Mr. Smith, Mr. Fuller and Mr. Bundros: JEA and Municipal Electric Authority of Georgia ( MEAG ) are parties to an Amended and Restated Power Purchase Agreement relating to Plant Vogtle Units 3 & 4 ( Project ). On August 17, 2018, JEA notified MEAG of its formal position that, due to the significant cost and schedule overruns, it was neighter financially responsible nor consistent with prudent utility practice that the Project proceed. As such, JEA demanded MEAG use its ~23% position to vote no to proceeding with the Project. Our position on voting no to continuation of the Project remains consistent. JEA has a significant interest in this Project and in protecting the interest of its rate payers and investors. We want to ensure all interested parties reach an amicable and mutually agreeable resolution on the decision of whether to proceed with the Project. On September 5, 2018, I wrote to you and requested that your respective organizations, as the Owners of the Project, extend the scheduled vote to continue the Project from September 21, 2018 to October 31, 2018 ( Extension ). I requested the Extension in order to provide sufficient time

for all parties to discuss a reasonable commercial agreement. My letter on September 5, 2018, requested a response by end of business on September 7, 2018. As of today, September 8, 2018, JEA has not received a response to that correspondence from a single Owner. This letter is a second request to the Owners to extend the vote to continue the Project. JEA requests that the Owners confirm their agreement to extend the vote to continue the Project by 5:00 pm, September 11, 2018. Very Truly Yours, Aaron Zahn, Interim Managing Director and CEO Cc: Brian McCormack, U.S. Departement of Energy Chief of Staff John Sneed, DOE Executive Director/Loan Programs Office Dong K. Kim, DOE COO/Loan Programs Office Peter M. Degnan, Esq., MEAG Senior VP & General Counsel G. Alan Howard, Esq., JEA Chair Allen Maines, Esq. Jody L. Brooks, Esq., JEA Chief Legal Officer